Upload
vuongdat
View
214
Download
0
Embed Size (px)
Citation preview
Outline of the Presentation:
• Salient geographical features of Bhutan
• Hydropower Development in Bhutan
• Power Supply & Demand
• Transmission Network
• Present Transmission Works
• Future Transmission Works
• Other Projects
• Other Issues
Salient geographical features of Bhutan:
• Located in the Eastern
Himalayas
• Area – 38,394 sq. km
• Forest cover – 80.89%
(Excluding Shrubs: 70.46%)
• Population – 6,34,982 (2005
Census) (700,000 by 2011)
• Altitude range from 100 –7500
meters above mean sea level
• Stretch of 170 km north to
south and 300 km east to west
• Climate – generally 4 seasons
(Spring, Summer, Autumn, and
Winter)
• Religions: Buddhism, Hinduism
Hydropower Development in Bhutan:
• Total Hydro Power Potential = 30,000 MW (Techno-
Economically Feasible : 24,000 MW)
• Total Installed Hydro Generation Capacity = 1488
MW (from 28 power plants sizes ranging 8 kW to
1020 MW)
• First hydropower plant of 360 kW built in 1967 in
Thimphu (Capital)
Hydropower Development in Bhutan (Contd.):
• First CDM (Clean Development Mechanism) micro
hydro (Chendebji) – 70 kW commissioned in August
2005
• Remaining to be developed = 71 large sites that have
been identified ( 22,280 MW)
• 10,000 MW hydropower generation capacities to be
developed by 2020.
Power Supply & Demand:
• Electricity export - About 75% of the generation
• Annual export estimate = 7,216.53 MU (2010)
• Revenue from sale of electricity contributes to 40%
of national revenue.
• Bhutan’s consumption + losses = 1,628.03 MU (2010)
Sl.
No.
Name of
Hydropower Plant
(HP)
Year of
commissioning
Installed
Capacity
(MW)
Average
Annual
Generation
in MU1 Chhukha HP 1986-1988 336 2,024
2 Basochhu HP - Upper
Stage
1999 22 105
3 Kurichhu 2000- 2001 60 400
4 Basochhu HP - Lower
Stage
2004 40 291
5 Tala HP 2006-2007 1,020 4,865
Total 1,478 7,865
Existing Major Hydropower Plants (HP):
Power plants in pipeline:Sl.
No. River Basin Project Name
Installed
Capacity (MW)
Construction
Period
1. Punatsangchhu Punatsangchhu-I 1200 2007 – 2014
2. Mangdechhu Mangdechhu 770 2009 – 2016
3. Punatsangchhu Punatsangchhu-II 990 2009 – 2016
4. Bumthangchhu Chamkharchhu-I &II 670/570=1240 2014 – 2020
5. Drangmechu Kuri Gongri 1800
6. Drangmechhu Kholongchhu 485 2020 – 2024
7. Amochhu Amochhu (Dorokha) 500
8. Nikachhu Nikachhu 210
9. Kurichhu Rothpashong 400
10. Dagachhu Dagachhu CDM 114 2007 - 2011
11. Punatsangchhu Sunkosh 2500
Total MW 10,064
• Length of 400 kV D/C lines 74.143 km
• Length of 220 kV D/C lines 35.780 km
• Length of 220 kV S/C lines 183.739 km
• Length of 132 kV S/C lines 379.484 km
• Length of 66 kV S/C lines 267.196 km
• Length of 66 kV D/C lines 5.960 km
• Length of 66 kV M/C lines 3.405 km
Total Transmission Line Length 949.707 km
Existing Transmission Network in Bhutan
Existing Transmission Substation in Bhutan
Sl.
No.
Substation Qty (Nos.) Capacity
(MVA)
1 400 /220/66kV substation 1 200
2 220 /66kV substation 2 160
3 132kV substations 7 102
4 66kV substations 11 199.5
5 33kV substations 1 3
6 66kV Switching Station 1 -
Total 23 664.5
Transmission works completed recently:
• 220 kV S/C from Rurichhu to Tsirang-47.50 km
• 132 kV S/C line from Tingtibi to Yurmoo- 32.60 km
• 132kV S/C from Deothang to Rangia - 56.46 km
• 66 kV Yurmoo to Trongsa- 20.3 km and 66 kV Yurmooto Bumthang- 34.70 km
Present Transmission Works:
Transmission Lines under construction:
• 400kV D/C Transmission line from Punatshangchhu toLhamoizingkha- 2 x 86 km
• 220kV D/C Transmission line from Dagachhu, Tsirang to Jigmeling -48. 2 km
• 220kV D/C Transmission Line from Malbase-Samtse- 43kms
• 132 kV D/C East-West Link from Lodrai to Jigmeling – 12 km
• 66kV S/C Transmission Line from Samtse to Sipsu- 35km
• 66kV S/C Transmission Line from Samtse to Gomtu- 15km
Present Transmission Works(Contd.):
Present Transmission Works(Contd.):
Substations under construction:
• 220/132kV substation at Jigmeling
• 220/66kV substation at Tsirang
Present Transmission Works(Contd.):
Transmission Line & substation construction under
NIT/Limited bidding:
• 132/33kV substation at Yurmoo (Trongsa)
• 400 kV line from Mangdechhu to Jigmeling via Goling poolingstation
• 400 kV line from Punatshangchhu-II to Jigmeling
• 66kV line from Pangrizampa,Thimphu to Damji,Gasa
Future Transmission Works:
• 400 kV lines from 2500 MW Sunkosh HEP to Alipore
• 400 kV line from Amochhu/Torsa Projects to Siliguri (newBinnaguri) pooling station
• 220/66/33 kV substation at Dhamdhum Industrial Estate(Samtse)
• 66/33 kV substation at Sipsu (Samtse)
Future Transmission Works (Contd.):
• OPGW & ADSS Interlinking
- Live line replacement of existing ground wire with OPGW in 220kV Transmission
Lines between Thimphu and Phuentsholing: 86kms (completed)
- Live line replacement of existing groundwife with OPGW in 132kV & 66kV
Transmission Lines: 394.58 kms (completed)
- All Dielectric Self Supporting (ADSS) Optical fibre cables on BPC distribution poles
at 33kV & below: 1290 kms (ongoing)
• National Load Dispatch Centre
• ERP Implementation
Other Projects:
Other Projects (Contd.) :• BPC plans to replace all the ground wire of 66 kV and above
lines with OPGW.
Other possible Business Associations :
• Mini/Micro Hydro project
• Long Term Turn-key Project Association
• Long Term O&M association – Live Line and Technical Know-how Transfer
• Continuous need-based Personnel Interaction / Training
Other Issues: