Upload
vuongminh
View
215
Download
0
Embed Size (px)
Citation preview
Decision 21394-D01-2017
Power Renewable Energy Corporation Facility Applications
Alberta Electric System Operator Needs Identification Document Application AltaLink Management Ltd. Facility Application
Jenner Wind Power Plant and Interconnection June 16, 2017
Alberta Utilities Commission
Decision 21394-D01-2017: Jenner Wind Power Plant and Interconnection
Power Renewable Energy Corporation
Facility Applications
Applications 21394-A001, 21394-A002, 21394-A004, and 21394-A006
Alberta Electric System Operator
Needs Identification Document Application
Application 21394-A003
AltaLink Management Ltd.
Facility Application
Application 21394-A005
Proceeding 21394
June 16, 2017
Published by the:
Alberta Utilities Commission
Fifth Avenue Place, Fourth Floor, 425 First Street S.W.
Calgary, Alberta
T2P 3L8
Telephone: 403-592-8845
Fax: 403-592-4406
Website: www.auc.ab.ca
Contents
1 Decision summary ................................................................................................................. 1
2 Introduction and background .............................................................................................. 1
3 Legislative scheme ................................................................................................................. 4 3.1 Power plant .................................................................................................................... 4 3.2 New transmission facilities ............................................................................................ 6
3.2.1 AESO NID applications .................................................................................... 6 3.2.2 Transmission facility applications .................................................................... 7
4 AESO needs identification document .................................................................................. 7 4.1 Commission findings ..................................................................................................... 8
5 Jenner 122.4-MW power plant ............................................................................................ 8 5.1 Introduction .................................................................................................................... 8
5.2 Environment ................................................................................................................. 10 5.2.1 Overhead collector lines ................................................................................. 11
5.3 Noise ............................................................................................................................ 15
5.3.1 Noise impact assessment................................................................................. 15 5.3.2 Class C2 adjustment ........................................................................................ 17
5.4 Commission findings ................................................................................................... 21 5.4.1 Environmental issues ...................................................................................... 21 5.4.2 Noise ............................................................................................................... 24
5.4.3 Conclusion ...................................................................................................... 25
6 Halsbury 306S Substation and transmission line 949L ................................................... 26 6.1 Halsbury 306S Substation ............................................................................................ 26 6.2 Transmission line 949L ................................................................................................ 26
6.3 Commission findings ................................................................................................... 30
7 AltaLink Jenner 275S Substation alterations ................................................................... 31 7.1 Commission findings ................................................................................................... 32
8 Decision ................................................................................................................................ 32
Appendix A – Abbreviations ...................................................................................................... 34
Decision 21394-D01-2017 (June 16, 2017) • 1
Alberta Utilities Commission
Calgary, Alberta
Power Renewable Energy Corporation
Facility Applications
Alberta Electric System Operator
Needs Identification Document Application
AltaLink Management Ltd. Decision 21394-D01-2017
Facility Application Proceeding 21394
Jenner Wind Power Plant and Interconnection Applications 21394-A001 to 21394-A006
1 Decision summary
1. In this decision, the Alberta Utilities Commission must decide whether to approve
applications to construct and operate the Jenner Wind Power Plant and its interconnection to the
Alberta Interconnected Electric System. These applications include a needs identification
document application from the Alberta Electric System Operator, facility applications from
Power Renewable Energy Corporation to construct and operate the 120-megawatt Jenner Wind
Power Plant, the Halsbury 306S Substation and transmission line 949L, and a facility application
from AltaLink Management Ltd. to alter the Jenner 275S Substation. This proceeding was the
first in which applications utilizing market participant choice (for the approval and construction
of transmission facilities) and a Class C2 adjustment (to address noise issues related to wind
masking) were considered by the Commission.
2. After consideration of the record of the proceeding, and for the reasons outlined in this
decision, the Commission finds the AESO’s assessment of the need to be correct and that
approval of the proposed developments, including the Preferred Route of transmission line 949L,
is in the public interest, having regard to the social and economic effects of the project and its
effect on the environment.
2 Introduction and background
3. Power Renewable Energy Corporation (PRE) filed an application with the Commission
for approval of a phase 1 buildable area for a 120-megawatt (MW) wind project designated as
the Jenner Wind Power Plant. The application, filed pursuant to Section 11 of the Hydro and
Electric Energy Act, was registered on March 3, 2016 as Application 21394-A001.
4. On May 13, 2016, PRE filed Application 21394-A002 with the Commission for approval
to construct and operate the Halsbury 306S Substation pursuant to sections 14, 15 and 18 of the
Hydro and Electric Energy Act. On May 19, 2016, PRE filed Application 21394-A004 for
approval to construct and temporarily operate transmission line 949L pursuant to sections 14, 15
and 18 of the Hydro and Electric Energy Act and Section 5 of the Transmission Deficiency
Regulation.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
2 • Decision 21394-D01-2017 (June 16, 2017)
5. The Alberta Electric System Operator (AESO) filed an application with the Commission,
pursuant to Section 34 of the Electric Utilities Act, seeking approval of a needs identification
document (NID) to interconnect the Jenner Wind Power Plant to the Alberta Interconnected
Electric System. The application was registered on May 17, 2016 as Application 21394-A003.
6. AltaLink Management Ltd. (AltaLink) filed a facility application with the Commission
for approval to alter the Jenner 275S Substation. The application was filed pursuant to
sections 14, 15 and 18 of the Hydro and Electric Energy Act and was registered on
May 24, 2016, as Application 21394-A005.
7. Pursuant to Section 15.4 of the Hydro and Electric Energy Act, PRE, the AESO and
AltaLink requested that the Commission consider the NID application and the facility
applications jointly. The Commission granted the request and advised parties that the
applications would be considered in Proceeding 21394.
8. The Commission issued a notice of application for the Jenner Wind Power Plant,
Application 21394-A001 on April 18, 2016. The notice was sent directly to potentially impacted
stakeholders within 2,000 metres of the project. It was also published on the AUC website and
notification was automatically emailed to eFiling System users who had chosen to be notified
of notices of application issued by the Commission. The notice was also published in the
Brooks Bulletin and the Medicine Hat News.
9. In response to the notice, the Commission received four statements of intent to
participate: from Carmen Stopanski, the Alberta Wilderness Association, the Friends of Science
Society, and Rylee Osadczuk.
10. On June 22, 2016, the Commission issued a notice of applications for the related
interconnection applications, applications 21394-A002 to 21394-A005. The notice was sent
directly to potentially impacted stakeholders within 2,000 metres of the proposed power plant
and within 800 metres of the proposed transmission line and substations. It was also published on
the AUC website and notification was automatically emailed to eFiling System users who had
chosen to be notified of notices of application issued by the Commission. The notice was also
published in the Brooks Bulletin and the Medicine Hat News.
11. No additional statements of intent to participate were received in response to the notice of
applications.
12. The Commission issued its ruling on standing on September 21, 2016, in which it denied
standing to the four parties that had sought to participate in the proceeding.1
13. On October 7, 2016, the AESO filed a letter requesting that the Commission suspend
further process and withhold from issuing a decision on its NID application, until PRE filed a
phase 2 application for its Jenner Wind Power Plant. The AESO submitted that:
… the AESO files a connection NID with the Commission only after the “required
deliverables” for Stage 3 of the Connection Process have been satisfied. In the case of a
proposed generating facility, these deliverables include the filing by a project proponent
1 Exhibit 21394-X0127, AUC Ruling on standing, September 21, 2016.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 3
of a power plant application, pursuant to Section 11 of the Hydro and Electric Energy
Act, with the Commission.2
14. The AESO stated that it is the filing of a phase 2 application that satisfies the AESO’s
Stage 3 Connection Process requirement and that the AESO had filed its NID application
prematurely by filing the application after PRE filed its phase 1 application.3
15. In response to the AESO’s request, PRE filed a letter on October 11, 2016, in which it
requested to file a phase 2 buildable area application prior to the phase 1 application being
approved in order to limit the time the AESO’s NID application, and the interconnection
applications associated with it, would be suspended.4
16. The Commission granted the AESO’s request to suspend the processing of the NID
application and also suspended the processing of the associated interconnection applications, i.e.,
PRE’s applications for the new Halsbury 306S Substation and transmission line 949L and
AltaLink’s application to alter the Jenner 275S Substation, so that the AESO NID application
may be considered with the associated transmission applications in a single process.5
17. In response to PRE’s request to file a phase 2 buildable area application, the Commission
stated:
the buildable area approval process is progressive in nature. A phase 1 approval
delineates the area within which a project can be built and phase 2 addresses specific
turbine specifications and siting issues. It is also anticipated that a phase 2 application
will address any conditions attached to a phase 1 approval and will likewise be
responsive to any concerns identified by the Commission in its phase 1 decision. Implicit
in the process is that approval of phase 1 is necessary to proceed to phase 2.6
18. The Commission stated that it could not begin processing PRE’s phase 2 application until
it decided whether to approve phase 1. If PRE filed its phase 2 application, the Commission
would hold it in abeyance until it ruled on the phase 1 application and would also hold the
AESO NID and the related interconnection applications in abeyance.
19. The Commission offered an alternative to PRE. PRE could file the portions of its phase 2
application necessary to form a complete power plant application when combined with its
phase 1 application, in essence abandoning the buildable area application type, and instead apply
for the wind farm as a typical power plant application.
20. PRE decided to combine its applications and requested that the power plant applications
be considered in a separate proceeding to allow the interconnection applications to continue to be
processed. Alternatively, it requested that the Commission “issue a ruling on the [interconnection
applications] and to not withhold any such ruling pending the ongoing processing of the [power
plant application]”. PRE argued that “the issues arising from the [power plant application] will
2 Exhibit 21394-X0128, AESO LT AUC request to suspend proceedings 2016-10-07.
3 Exhibit 21394-X0128, AESO LT AUC request to suspend proceedings 2016-10-07.
4 Exhibit 21394-X0129, PREC request to AUC to file Phase 2 Application.
5 Exhibit 21394-X0130, AUC Letter to Parties - 2016-10-17.
6 Exhibit 21394-X0130, AUC Letter to Parties - 2016-10-17.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
4 • Decision 21394-D01-2017 (June 16, 2017)
be different than those associated with the [interconnection applications] and that the timing of a
decision on one should not be dependent on the other.”7
21. PRE filed the second portion of its power plant application on November 1, 2016. This
application was registered as Application 21394-A006.
22. On December 16, 2016, the Commission issued a notice of applications for the
Jenner Wind Power Plant, applications 21394-A001 and 21394-A006. The notice was sent
directly to potentially affected stakeholders within 2,000 metres of the project. It was also
published on the AUC website and notification was automatically emailed to eFiling System
users who had chosen to be notified of notices of application issued by the Commission. The
notice was also published in the Brooks Bulletin and the Medicine Hat News. No additional
statements of intent to participate were received in response to this notice.
3 Legislative scheme
3.1 Power plant
23. The Commission regulates the construction and operation of power plants in Alberta.
The wind farm proposed by the applicant, including the associated collector system, is a “power
plant” as that term is defined in Subsection 1(k) of the Hydro and Electric Energy Act.
Section 11 of the Hydro and Electric Energy Act states that no person may construct or operate a
power plant without prior Commission approval. In addition, sections 14 and 15 of the
Hydro and Electric Energy Act direct that Commission approval is necessary before the
construction or operation of a substation or a transmission line.8
24. When considering an application for a power plant and associated infrastructure, the
Commission is directed by sections 2 and 3 of the Hydro and Electric Energy Act, and
Section 17 of the Alberta Utilities Commission Act.
25. Section 2 lists the purposes of the Hydro and Electric Energy Act. Those purposes
include:
To provide for the economic, orderly and efficient development and operation, in the
public interest, of the generation of electric energy in Alberta.
To secure the observance of safe and efficient practices in the public interest in the
generation of electric energy in Alberta.
To assist the government in controlling pollution and ensuring environment conservation
in the generation of electric energy in Alberta.
26. Section 3 of the Hydro and Electric Energy Act requires the Commission to have regard
for the purposes of the Electric Utilities Act when assessing whether a proposed power plant is in
the public interest under Section 17 of the Alberta Utilities Commission Act. The purposes of the
7 Exhibit 21394-X0131, PREC Letter re Response to AUC Oct 17 Letter.
8 Defined in Section 1(1)(o)(iii) of the Hydro and Electric Energy Act, “transmission line” includes substations.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 5
Electric Utilities Act include the development of a fair, efficient and openly competitive electric
industry structure and the development of an electric generation sector guided by competitive
market forces.9 Section 3 of the Hydro and Electric Energy Act also directs that the Commission
shall not have regard to whether the proposed power plant “…is an economic source of electric
energy in Alberta or to whether there is a need for the electric energy to be produced by such a
facility in meeting the requirements for electric energy in Alberta or outside of Alberta.”
27. The Commission’s public interest mandate is expressed in Section 17 of the
Alberta Utilities Commission Act, which states:
Public interest
17(1) Where the Commission conducts a hearing or other proceeding on an application to
construct or operate a hydro development, power plant or transmission line under the
Hydro and Electric Energy Act or a gas utility pipeline under the Gas Utilities Act, it
shall, in addition to any other matters it may or must consider in conducting the hearing
or other proceeding, give consideration to whether construction or operation of the
proposed hydro development, power plant, transmission line or gas utility pipeline is in
the public interest, having regard to the social and economic effects of the development,
plant, line or pipeline and the effects of the development, plant, line or pipeline on the
environment.
28. In Decision 2001-111, the AUC’s predecessor, the Alberta Energy and Utilities Board
(EUB or the Board) explained how it assesses whether the approval of a power plant is in the
public interest:
The determination of whether a project is in the public interest requires the Board [the
Commission’s predecessor] to assess and balance the negative and beneficial impacts of
the specific project before it. Benefits to the public as well as negative impacts on the
public must be acknowledged in this analysis. The existence of regulatory standards and
guidelines and a proponent’s adherence to these standards are important elements in
deciding whether potential adverse impacts are acceptable. Where such thresholds do not
exist, the Board must be satisfied that reasonable mitigative measures are in place to
address the impacts. In many cases, the Board may also approve an application subject to
specific conditions that are designed to enhance the effectiveness of mitigative plans. The
conditions become an essential part of the approval, and breach of them may result in
suspension or rescission of the approval.
In the Board’s view, the public interest will be largely met if applications are shown to be
in compliance with existing provincial health, environmental, and other regulatory
standards in addition to the public benefits outweighing negative impacts.10
9 Electric Utilities Act, Section 5.
10 EUB Decision 2001-111: EPCOR Generation Inc. and EPCOR Power Development Corporation, - 490-MW
Genesee Power Plant Expansion, Application 2001173, December 2001, page 4.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
6 • Decision 21394-D01-2017 (June 16, 2017)
29. In Decision 2014-040,11 the AUC applied the above principles to its assessment of the
Bull Creek Wind Project. The Commission considers the above approach to be consistent with
the purpose and intent of the statutory scheme and is satisfied that it continues to provide an
effective framework for the assessment of wind energy projects.
30. Rule 007: Applications for Power Plants, Substations, Transmission Lines, Industrial
System Designations and Hydro Developments applies for the construction and operation of
power plants, substations and transmission lines, which are governed by the Hydro and Electric
Energy Act. The application must meet the informational and other requirements set out in
Rule 007. Specifically, an applicant must provide technical and functional specifications,
information on public consultation, environmental and land-use information including a
noise impact assessment. The application must also meet the requirements set out in
Rule 012: Noise Control.
31. Further, an applicant must obtain all approvals under other applicable provincial or
federal legislation.
3.2 New transmission facilities
32. Except in the case of critical transmission infrastructure, two approvals from the
Commission are required to build new transmission capacity in Alberta. First, an approval of the
need to expand or enhance the Alberta Interconnected Electric System, pursuant to Section 34 of
the Electric Utilities Act, is required. Second, a permit to construct and a licence to operate a
transmission facility, pursuant to sections 14 and 15 of the Hydro and Electric Energy Act, must
be obtained.
3.2.1 AESO NID applications
33. The AESO is Alberta’s independent system operator established under the
Electric Utilities Act, and is responsible for preparing a NID and filing it with the Commission
for approval pursuant to Section 34 of the Electric Utilities Act.
34. In Decision 2004-087, the Commission’s predecessor, the EUB, described the NID
process as follows:
It is the Board’s view that section 34 contemplates a two-stage consideration of an NID.
In the first stage, the Board must determine whether an expansion or enhancement of the
capability of the transmission system is necessary to alleviate constraint, improve
efficiency, or respond to a request for system access… If it is determined that expansion
or enhancement of the system is required to address constraint, inefficiency, system
access requests, or any combination thereof, the Board must then assess, in the second
stage, whether enhancement or expansion measures proposed by AESO are reasonable
and in the public interest.12
11
Decision 2014-040: 1646658 Alberta Ltd. – Bull Creek Wind Project, Proceeding 1955, Application 1608556,
February 20, 2014. Errata issued on March 10, 2014. 12
EUB Decision 2004-087: Alberta Electric System Operator Needs Identification Document – Southwest Alberta
240-kV Transmission System Development Pincher Creek – Lethbridge Area, Addendum to Decision 2004-075,
Application 1340849, October 14, 2004, page 12.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 7
3.2.2 Transmission facility applications
35. Applications for new transmission facilities designed to serve the Alberta Interconnected
Electric System are generally prepared by a transmission facility owner (TFO) in accordance
with directions from the AESO. However, under the Transmission Deficiency Regulation, a
market participant that requires a transmission facility to provide system access service may
make a proposal to the AESO to construct and temporarily operate a transmission line. If the
AESO accepts the proposal and the Commission approves the transmission line, the market
participant is required to transfer ownership of the transmission line to a TFO following its
construction.
36. As noted above, Section 17 of the Alberta Utilities Commission Act sets out the
Commission’s public interest test for new utility infrastructure. In Decision 2009-028, the
Commission explained how it applied that test when considering an application for new
transmission facilities.
In the Commission’s view, assessment of the public interest requires it to balance the
benefits associated with upgrades to the transmission system with the associated impacts,
having regard to the legislative framework for transmission development in Alberta. This
exercise necessarily requires the Commission to weigh impacts that will be experienced
on a provincial basis, such as improved system performance, reliability, and access, with
specific routing impacts upon those individuals or families that reside or own land along
a proposed transmission route as well as other users of the land that may be affected.13
37. The Commission confirms that this approach applies equally to all applications for new
transmission facilities regardless of whether the application is made by a TFO on the direction of
the AESO, or by a market participant under the Transmission Deficiency Regulation.
4 AESO needs identification document
38. The AESO explained in its application that PRE requested system access service for a
wind power plant designated as the Jenner Wind Power Plant, with a capacity of 120 MW. The
AESO submitted that the need could be met by adding a new 240-kilovolt (kV) transmission line
to connect PRE’s proposed Halsbury 306S Substation to the existing Jenner 275S Substation and
modifying Jenner 275S Substation by adding one 240-kV circuit breaker.
39. The AESO indicated that PRE submitted a proposal for the construction and temporary
operation of transmission line 949L pursuant to Section 5 of the Transmission Deficiency
Regulation. It explained that, in accordance with the process set out in that regulation, PRE
would be responsible for the design and construction of transmission line 949L and for operating
the transmission line for a short period of time before transferring operating responsibility to
AltaLink. It also confirmed that AltaLink would be responsible for the design, construction and
operations related to the alterations to Jenner 275S Substation.
13
AUC Decision 2009-028: AltaLink Management Ltd., Transmission Line from Pincher Creek to Lethbridge,
Proceeding 19, Application 1521942, paragraph 33.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
8 • Decision 21394-D01-2017 (June 16, 2017)
40. The AESO conducted power flow, transient stability, and short-circuit analyses to assess
the effects that the project would have on the transmission system. The AESO stated that
post-connection assessments identified system performance issues, some of which also exist in
the pre-connection assessments, that could be largely mitigated through real-time operational
practices and remedial action schemes. The AESO stated that the remaining thermal criteria
violations could be resolved by restoring the seasonal continuous thermal ratings of transmission
lines 7L159 and 7L16. The AESO stated it plans to direct the transmission facilities owners of
transmission lines 7L159 and 7L16 to restore the seasonal continuous thermal ratings and that
these restorations will have to occur prior to the energization of the proposed development.
41. The AESO directed PRE and AltaLink to file facility applications with the AUC for the
facilities to meet the need identified and to assist the AESO in conducting a participant
involvement program for its NID application. The AESO submitted that no concerns or
objections have been raised regarding the need for the proposed transmission development.
4.1 Commission findings
42. The Commission finds that the NID application filed by the AESO contains all the
information required by the Electric Utilities Act, the Transmission Regulation and Rule 007.
43. No interested party demonstrated that the AESO’s assessment of the need to interconnect
the Jenner Wind Power Plant is technically deficient or that approval of the NID application is
not in the public interest. Therefore, the Commission considers the AESO’s assessment of the
need to be correct, in accordance with Subsection 38(e) of the Transmission Regulation, and
approves the AESO’s NID application.
5 Jenner 122.4-MW power plant
5.1 Introduction
44. PRE requested approval to construct and operate the 122.4-MW Jenner Wind Power
Plant in Application 21394-A006. The power plant would consist of 36 turbines, each with a
capability of 3.4 MW. The power plant would be located in townships 21 and 22, ranges 8 and 9,
west of the Fourth Meridian, approximately 3.5 kilometres east of Jenner, Alberta.
45. The locations of the turbines are shown in the following map:
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 9
Figure 1: Jenner Wind Power Plant proposed location
46. The power plant would also include a 34.5-kV collector system consisting of
underground and overhead power lines. The turbines would be 110 metres tall and have a rotor
diameter of 140 metres. The maximum height at the tip of blade would be 180 metres.
47. PRE submitted that it had notified and obtained the necessary approvals from
Transport Canada, Alberta Transportation and Environment Canada. PRE also provided an
evaluation from NAV Canada which concluded that it had no objection to the project.
48. PRE consulted with the Special Areas Board and stated that it would apply for a
development permit upon receiving approval from the AUC.
49. PRE applied to Alberta Culture and Tourism for Historical Resources Act clearance for
the project. Alberta Culture and Tourism required that PRE conduct a historical resources impact
RED
DEER
R.
884
555
RA
NG
E R
D. 9
1
R.9 R.8W.4M.
T.22
T.21
T.20
WIND FARM PROJECT BOUNDARYWIND TURBINES
N.T.S.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
10 • Decision 21394-D01-2017 (June 16, 2017)
assessment for archaeological resources. PRE confirmed that it would conduct the assessment
field studies prior to construction and provided a summary of its initial findings.
50. PRE conducted a participant involvement program with the goal of ensuring that all
potentially-affected stakeholders have the necessary information regarding the project and the
ability to ask questions and express their concerns and suggestions. The program involved
notifying parties within 2,000 metres of the project boundary and conducting consultations with
stakeholders within 800 metres of the project. PRE also held open houses on November 24, 2015
and June 21, 2016 in Jenner. PRE submitted that it would continue to consult with stakeholders
as the project progresses.
5.2 Environment
51. PRE retained McCallum Environmental Ltd. (McCallum) to prepare an environmental
evaluation of the project. McCallum prepared an initial environmental assessment for phase 1 of
the buildable area process; it then provided a second report in PRE’s subsequent power plant
application that included the locations of turbines, access roads, and collector lines.14
52. In its second report, McCallum acknowledged that the project will result in increased
fragmentation of wildlife habitat but contended that the use of cultivated lands and paralleling
linear infrastructure will reduce these impacts. McCallum submitted that the project’s
environmental impacts will be minimized through the mitigation measures it proposed and that
standard and best practice construction mitigation methods will be implemented to ensure there
are no significant impacts on valued ecosystem components.
53. In the Alberta Environment and Parks-Wildlife Management’s (AEP WM) Renewable
Energy Referral Report dated March 12, 2015,15 AEP WM identified the project site as having a
potential high risk for wildlife with concerns primarily related to the proximity to valley and
coulee breaks of the Red Deer River and the inclusion of areas of native grassland within the
buildable area. In response to these concerns, PRE agreed to implement a 500-metre setback
from valley and coulee breaks of the Red Deer River in order to mitigate risks associated with
the presence of birds and bats along the Red Deer River corridor.
54. PRE submitted an updated Renewable Energy Referral Report (dated October 7, 2016),16
which covered both application phases 1 and 2, including the locations of turbines, access roads,
and collector lines.
55. PRE submitted that all pre-development wildlife monitoring had been conducted, and
AEP WM’s Renewable Energy Referral Report and subsequent correspondence confirmed that
the pre-construction wildlife monitoring met AEP WM’s requirements. PRE confirmed that in
the event of delays to the project it would work with AEP and update any studies if necessary.
56. The environmental report stated that four of the proposed turbines would be located
within native grassland and that the remaining 32 turbines would be located on cultivated land.
The total disturbance to native grassland would be approximately 11.51 hectares. PRE submitted
14
Exhibit 21394-X0134, Attachment 10: JWPP Environmental Effects Assessment. 15
Exhibit 21394-X0006, Attachment 6 - Alberta Environment and Parks Consultation. 16
Exhibit 21394-X0138, Attachment 6: AEP Consultation.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 11
that it would restore the 8.33 hectares of native grasslands that would be temporarily disturbed
by construction and would pursue compensation for the 3.18 hectares of native grasslands that
would be permanently disturbed. PRE stated it would investigate at least the following three
options associated with compensation for the permanent disturbance: (i) reclaiming previously
disturbed native grassland; (ii) creating protection offsets through conservation easements; or
(iii) contributing to conservation groups that are completing habitat restoration projects. PRE
stated it would continue to consult with AEP with respect to the restoration and compensation
plan for native grasslands.
57. PRE submitted that in order to mitigate the effects to native grassland, it would construct
during dry/frozen ground conditions outside of AEP’s recommended minimum setbacks and
restricted activity periods for sensitive wildlife species, and it would locate all temporary
components, such as storage areas and operational trailers, on cultivated land.
58. PRE provided a project-specific environmental protection plan (EPP) that outlined the
practices to be used to ensure successful conservation and reclamation of valued ecosystem
components in the area. AEP WM reviewed the EPP and found it met the current policy of
minimizing disturbance on native grasslands.17
59. PRE proposed a post-construction wildlife monitoring program that was reviewed and
confirmed by AEP WM, that it would meet its requirements. Given the assessment of high risk to
wildlife for the project, AEP WM recommended that the post-construction mortality monitoring
occur for a minimum of three years.18
5.2.1 Overhead collector lines
60. AEP WM raised concerns about the project’s use of overhead collector lines that transfer
electricity from individual turbines to the substation. AEP released a new version of
Wildlife Directive for Alberta Wind Energy Projects19 that came into effect on January 27, 2017.
However, the directive makes it clear that the earlier version of the Policy - Wildlife Guidelines
for Alberta Wind Energy Projects – 201120 will apply to applications filed with the AUC before
the directive came into force. The new directive states as follows with respect to collector lines:
Wind energy project collection lines must be placed underground using minimal
disturbance construction techniques unless there are significant landscape constraints
(Bradley and Neville 2011). Where aboveground power lines are required due to
17
Exhibit 21394-X0138, Attachment 6: AEP Consultation, PDF page 10. 18
Exhibit 21394-X0138, Attachment 6: AEP Consultation, PDF page 11. 19
Government of Alberta, Wildlife Directive for Alberta Wind Energy Projects, Fish and Wildlife Policy, Alberta
Environment and Parks, AEP Fish and Wildlife 2016 No. 6, April 7, 2017. Retrieved from
http://aep.alberta.ca/fish-wildlife/wildlife-land-use-guidelines/documents/WildlifeWindEnergyDirective-Apr07-
2017.pdf. 20
Alberta Government, Wildlife Guidelines for Alberta Wind Energy Projects, Fish and Wildlife Division,
Sustainable Resource Development, September 19, 2011. Retrieved from
https://open.alberta.ca/dataset/249abbdc-444a-4bd5-97b6-64374624acf1/resource/987fea0d-75a6-4bef-9e82-
344367a5dae3/download/2011-WildlifeGuidelines-AlbertaWindEnergyProjects-Sep19-2011.pdf.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
12 • Decision 21394-D01-2017 (June 16, 2017)
landscape constraints these lines must be designed and constructed to avoid collision and
electrocution of birds.21
61. AEP WM acknowledged that the Jenner project should not be held to the new standard
but noted that the 2011 guidelines also recommend the reduction of above ground power lines
and, where that is not possible, above ground lines should be designed to avoid strikes and
electrocution of birds. AEP WM requested that PRE use underground collector lines on native
grassland and within wildlife and/or wetland setbacks.
62. AEP WM indicated that the project is sited in “an area with considerable wildlife
sensitivity” and that “the overall sensitivity of the Project area” also contributed to the
recommendation to bury all collector lines on native grassland and within wildlife and/or
wetland setbacks.22 Below is a map of PRE’s proposed collector routes overlaid on the area’s
vegetation use.
21
Government of Alberta, Wildlife Directive for Alberta Wind Energy Projects, Fish and Wildlife Policy, Alberta
Environment and Parks, AEP Fish and Wildlife 2016 No. 6, April 7, 2017, PDF page 10. 22
Exhibit 21394-X0138, Attachment 6: AEP Consultation, PDF page 19.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 13
Figure 2 –Proposed collector routes23
63. PRE stated that all individual turbine connections on native grassland would be buried
and that overhead lines are only proposed for the longer distance backbone collector system.
PRE stated that the collector lines follow linear developments to the greatest extent possible. In
particular, the north/south overhead collector lines are sited parallel to the Preferred Route of the
proposed 240-kV transmission line to minimize the area of disturbance and keep the majority of
the overhead lines in the same corridor.
64. PRE confirmed that all overhead collector lines would meet AEP’s recommended
setbacks for wildlife species.
23
Exhibit 21394-X0138, Attachment 6: AEP Consultation, PDF page 17.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
14 • Decision 21394-D01-2017 (June 16, 2017)
65. PRE utilized a wetland classification system that classify wetlands as follows:
Class I – Ephemeral wetlands
Class II – Temporary wetlands
Class III – Seasonal ponds and lakes
Class IV – Semi-permanent ponds and lakes
Class V – Permanent ponds and lakes
Class VI – Alkali ponds and lakes
Class VII – Fen Pond
66. PRE stated that wetlands with higher classifications typically support a higher abundance
and diversity of wildlife and vegetation. PRE stated that the overhead collector lines would cross
four Class I wetlands in cultivated land that have no wildlife habitat, and would cross five Class I
wetlands in native grassland. PRE stated that it would position poles at least 15 metres from the
wetland boundaries and that it does not expect any effects on the wetlands.
67. PRE argued that burying the collector lines would disturb significantly more native
grassland and estimated that burying all the collector lines on native grassland would disturb
approximately 16.5 hectares of native grassland. It contended that using above ground lines
would limit the extent of the project’s disturbance to the footprint of the pole and support
locations, as compared to underground lines which would have a much larger footprint. In
addition, PRE noted that any maintenance issues with collector lines would require that buried
lines be excavated.
68. PRE argued that overhead distribution lines are an approved method of development for
serving oil and gas facilities in the local area and stated that it attempted to parallel existing
distribution lines with its proposed collector lines where possible.
69. PRE committed to installing bird marking devices on the collector lines that are
within 100 metres of Class III wetlands, Class IV wetlands, and Class V wetlands and within
100 metres of any open water body’s high water mark.
70. PRE stated it is planning a second phase for the Jenner wind farm with an additional
180 MW of capacity. PRE committed to enhancing pole structures to support its future
expansion so that future collector lines could be understrung on the existing poles to avoid future
ground disturbance.
71. PRE submitted that burying all of the collector system on native grassland would add
approximately $9 million to the capital costs of this project and would add an additional
$9 million for its 180-MW expansion.
72. The Commission issued information requests to clarify which portions of the collector
lines paralleled linear infrastructure and whether PRE would be amenable to burying the
single-circuit collector lines that do not parallel the Preferred Route of the transmission line. PRE
responded as follows:
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 15
PRE has considered buried lines, but to avoid crossing pipelines with buried cables and
for cost reasons, PRE strongly prefers overhead collector lines in the referenced areas due
to the abundance of oil and gas activities in the region and the associated below-ground
and surface infrastructure. PRE also notes the extensive network of overhead collection
lines that are already installed in the area for the oil and gas industry.
However, in order to address proliferation concerns on native prairie, PRE would be
amenable to burying the line segments on native prairie, as identified in IR5-002 (b) and
(c) that do not parallel disturbances, if so directed by the AUC. A potential revision to the
collector system is shown in the red ovals marked IR5-002(d) on page 4 in Attachment
IR5-002-1. This change would reduce the total length of overhead collector lines on
native prairie by approximately three kilometres, and in total by 4.3 kilometres, and
would increase the number of buried pipeline crossings by approximately 11.24
73. PRE submitted that if significant bird collisions are identified along the collector system,
it would consult with AEP WM and would install line modifications, such as additional
bird-marking devices on segments of the collector system that lack markers.
5.3 Noise
5.3.1 Noise impact assessment
74. PRE retained RWDI Consulting Engineers & Scientists (RWDI) to prepare a noise
impact assessment (NIA) for the project. PRE submitted updated NIAs in support of
supplementary information request responses. The initial NIA was dated October 31, 2016,25 the
second NIA was dated January 24, 2017,26 and the third, and most up-to-date NIA, was dated
March 17, 2017 (the Project NIA).27
75. The Project NIA indicated that the project would utilize 36 Senvion 3.4-MW wind
turbines with hub height of 110 metres with 3,600 kilovolt-ampere (kVA) pad-mounted
transformers. The sound data for the proposed wind turbines were provided in Senvion’s
acoustics specifications. The Project NIA also included the proposed Halsbury 306S Substation.
The sound data for the proposed substation equipment was provided in the Halsbury 306S
Substation NIA, also prepared by RWDI.
76. The Project NIA identified and included the sound level contribution of existing
energy-related facilities, including six multi-well batteries.
77. The October 2016 and January 2017 NIAs identified 10 residential receptor locations in
the project study area. However, in response to information requests, the applicant confirmed
that based on the most recent site visit, one of these receptor locations was no longer considered
a receptor. As such, the March 2017 Project NIA identified nine residential receptor locations
within the noise study area.
24
Exhibit 21394-X0178, JWPP_Information Request 5 Response, PDF page 6. 25
Exhibit 21394-X0132, Attachment 11: Noise Impact Assessment. 26
Exhibit 21394-X0157, Attachment IR4-008-1 Revised NIA Report. 27
Exhibit 21394-X0170, IR5-006-02_Revised_NIA March 2017.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
16 • Decision 21394-D01-2017 (June 16, 2017)
78. RWDI submitted that the permissible sound level (PSL) values determined in accordance
with Rule 012 are 40 dBA Leq nighttime and 50 dBA Leq daytime for all residential receptor
locations, with the exception of receptor R1. Receptor R1 is a Hutterite colony and has a
dwelling density of nine to 160 dwellings per quarter sections resulting in a PSL of 43 dBA Leq
nighttime and 53 dBA Leq daytime.
79. RWDI set out the predicted cumulative sound level of the project compared with the
PSLs as outlined in Rule 012. The results of the cumulative sound level assessment indicate that
the project is predicted to be in compliance with Rule 012 PSL values at all receptor locations
assessed.
Table 1. Cumulative sound level assessment28
Notes: 1 - Ambient sound level as outlined by AUC Rule 012, Table 1. 2 - The cumulative sound level is the logarithmic sum of AUC ambient sound level and Existing Oil and Gas Facilities contributions and the project contribution. 3 - PSL as outlined by AUC Rule 012.
28
Exhibit 170, IR5-006-02_Revised_NIA March 2017, PDF page 21.
Receptor ID Ambient sound
level1 (dBA)
Existing oil and gas facilities contribution
(dBA)
Project contribution
(dBA)
Cumulative sound level2
(dBA)
PSL3 (dBA)
Nighttime (22:00 – 07:00)
R1 38 19.5 26.2 38.3 43
R2 35 16.6 34.2 37.7 40
R3 35 16.2 34.1 37.6 40
R4 35 9.7 31.0 36.5 40
R6 35 11.5 32.1 36.8 40
R7 35 25.0 31.8 37.0 40
R8 35 20.3 29.3 36.1 40
R9 35 19.9 29.3 36.1 40
R10 35 19.2 28.9 36.0 40
Daytime (07:00 – 22:00)
R1 48 19.5 26.2 48.0 53
R2 45 16.6 34.2 45.4 50
R3 45 16.2 34.1 45.3 50
R4 45 9.7 31.0 45.2 50
R6 45 11.5 32.1 45.2 50
R7 45 25.0 31.8 45.2 50
R8 45 20.3 29.3 45.1 50
R9 45 19.9 29.3 45.1 50
R10 45 19.2 28.9 45.1 50
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 17
80. The Project NIA evaluated the potential for a low frequency noise contribution from the
project. RWDI included the C-Weighted sound level (dBC) minus the A-Weighted sound level
(dBA) for the project sound contributions and existing energy-related facilities. RWDI stated it
considered the potential for a low frequency noise issue to be low because the C-weighted values
are below 60 dBC and the specification for the turbine states that tonality will not occur.
5.3.2 Class C2 adjustment
81. The Project NIA included an application for a nighttime Class C2 adjustment at receptors
R2, R3 and R4.
82. PRE included the request for a Class C2 adjustment to the PSL in its public consultation
program and a sound specialist was available to answer questions on the subject at the Jenner
open house in June 2016. PRE submitted that stakeholders expressed no concerns on the topic.
83. Rule 012 allows project proponents to apply for a Class C2 adjustment to the PSL at a
residence if the proponent can demonstrate that the ambient wind sound level (AWSL) at a
particular dwelling is higher than an assumed ambient sound level based on Table 1 of Rule 012.
In other words, the Class C2 adjustment accounts for “wind masking” which can occur when the
sound of the wind at a residence “drowns out” the sound of the wind turbine. The maximum
available Class C2 adjustment under Rule 012 is 10 dB.
84. To qualify for a Class C2 adjustment, the project proponent must complete an AWSL
survey to determine the difference between the ambient sound level found in Table 1 of Rule 12
and the measured AWSL. Such survey must include, for each (group of acoustically comparable)
dwelling(s), the measurement of the available wind noise masking for each wind speed of at least
three metres per second (m/s) in each wind direction that is downwind from dominant wind
turbines toward the most exposed side of that dwelling.
85. RWDI conducted an AWSL survey at two receptor locations (dwellings), receptor R3
and receptor R7, over a 17-day monitoring period from May 20 to June 6, 2016.
86. The results of the AWSL survey indicated greater than assumed ambient rural sound
levels of 45 dBA and 35 dBA for the daytime and nighttime period respectively. Based on the
review of the audio recording, RWDI determined the elevated levels were due to the influence of
wind on the surrounding structures and vegetation.
87. PRE stated that the AWSL survey verified the presence of wind masking in the project
area and requested a Class C2 adjustment to the PSL to inform future compliance testing. PRE
submitted that the Class C2 adjustment to the PSL accounts for the wind generated sound, which
would allow future compliance testing to discern between sound generated by the project and
normal wind-generated sound levels in the area.
88. A record of wind speeds was collected from a weather tower at the project site and
averaged in 10-minute intervals. From these records, an average site wind shear was calculated
using standard meteorological formulae and a relative wind profile was generated to obtain the
ground level (1.5 metres) and hub height (110 metres) wind speeds.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
18 • Decision 21394-D01-2017 (June 16, 2017)
89. RWDI submitted that the Senvion 3.4-MW wind turbines reach maximum noise output of
104 dBA when winds reach 7.5 metres per second (m/s) at hub height. Based on wind shear
calculations, RWDI determined the maximum turbine sound emissions will occur during 4 to
4.5 m/s ground level wind speeds.
90. The monitoring results were executed in 10-minute intervals and for each interval, the
L9029 sound level was extracted and the wind speed and wind direction were averaged. Records
were grouped into 12 wind direction bins, from zero degrees and comprised of +/- 15 degree
groupings. Groups were further subdivided into integer wind speed bins of
+/- 0.5 m/s starting at 3 m/s.
91. For each wind speed and bin direction, the standard deviation for the L90 records was
determined and the minimum number of valid samples required for a +/- 3 dB confidence level
was determined. The AWSL was calculated for each receptor, wind direction and wind speed
bins.
92. RWDI assigned each receptor an AWSL for a wind speed bin and wind direction bin
based on the location of the nearest turbine and the relative type of dwelling. Receptors R2 and
R3 used the measurement record from receptor R3, while the remaining receptors used the
measurement record from receptor R7. If a wind speed and wind direction bin combination
resulted in no valid measured AWSL, the second nearest turbine direction was used. This was
the case for receptor R4.
93. As third party energy-related facilities were operational during the measurement period,
the modelled contributions of those facilities were subtracted from the AWSL prior to
calculation of the PSL resulting in an ambient sound level without the influence of
energy-related facilities.
94. Using the AWSL at each receptor location and methodology outlined in Rule 012, RWDI
determined the Class C2 adjustment to the daytime and nighttime PSL for each receptor location.
95. RWDI determined that no receptors qualify for a Class C2 adjustment to the daytime
PSL, but some receptors would qualify for a Class C2 adjustment to the nighttime PSL.
96. RWDI requested Class C2 adjustments to the nighttime PSL for receptors R2, R3 and R4.
The determination of the Class C2 adjustment to the nighttime PSL results for those receptors is
summarized below.
29
The sound level that is exceeded 90 per cent of the time. This parameter is used to assess the AWSL in 10-minute
intervals, to account for lulls in wind speed and will consequently represent the quietest 10 per cent of the time in
a 10-minute interval.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 19
Table 2. Determination of adjusted nighttime PSL from the valid AWSL30
Receptor ID
Angle to nearest turbine
(0⁰ as North)
Wind direction
bins ± 15⁰
Valid AWSL (dBA) for Ground Wind Speed Bin (Hub Height Wind Speed)
(m/s)
Class C2 Adjusted PSL (dBA) for wind speed bin (hub height wind
speed) (m/s)
Final PSL (dBA)
3 (5) 4 (7) 5 (9) 3 (5) 4 (7) 5 (9)
R2 1 156 150 36.7 39.2 - 42 44 - 44
R3 1 152 150 36.7 39.2 - 42 44 - 44
R4 2, 3 347 330 37.2 37.2 37.3 42 42 42 42
Notes: 1 - Values based on measurement results from R3 ambient survey, third party facilities removed. 2 - Values based on measurement results from R7 ambient survey, third party facilities removed. 3 - Second nearest turbine used to determine wind bin, as nearest turbine resulted in minimal L90 data for day and night. -' indicates no valid L90 measurements for the wind speed.
97. RWDI submitted a summary table that included a comparison of the Rule 012 nighttime
PSL to the requested Class C2 adjusted nighttime PSL at receptors R2, R3 and R4 summarized
in Table 3 below.
Table 3. Class C2 adjustments requested
Receptor ID
AUC Rule 012 nighttime PSL (dBA)
Class C2 Adjusted nighttime PSL (dBA)
R2 40 44
R3 40 44
R4 40 42
98. A summary of the predicted cumulative sound level compared with the Class C2 adjusted
nighttime PSL for receptors R2, R3 and R4 is presented in Table 4. This assessment shows that
the project will comply with the Class C2 adjusted PSL at receptors R2, R3 and R4.
Table 4. Assessment of compliance with Class C2 adjusted PSLs31
Receptor ID C2 adjusted ambient
sound level (dBA)
Existing oil and gas facilities
contribution (dBA)
Proposed project contribution (dBA)
Predicted cumulative sound level
(dBA)
C2 adjusted nighttime PSL
(dBA)
R2 39 16.6 34.2 41.3 44
R3 39 16.2 34.1 41.3 44
R4 37 9.7 31.0 38.9 42
99. In accordance with Rule 012, a Class C2 adjustment may only be requested if the
operation of the wind turbines can be adjusted for the variability of the wind speed and direction
to maintain compliance with the PSL. In response to information requests, the applicant stated
30
Exhibit 21394-X0170, IR5-006-02_Revised_NIA March 2017, PDF page 18, Table 11. 31
Exhibit 21394-X0170, IR5-006-02_Revised_NIA March 2017, PDF page 22, Table 15.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
20 • Decision 21394-D01-2017 (June 16, 2017)
there are a variety of operating modes available with the Senvion wind turbine that include the
normal operating mode and three sound reduced modes. PRE confirmed the Senvion wind
turbine normal and sound reduced operating modes can be triggered by wind speed and wind
direction measured at the nacelle-mounted instrumentation on the turbine and that, in the event
of a complaint, specific atmospheric conditions can be preprogrammed into the turbine to engage
the reduced noise operating modes.
100. Rule 012 states that a Class C2 adjustment for one dwelling may be applied to other
dwellings within the same project study area that have a similar acoustical environment and
ambient wind sound level.
101. Specifically, Rule 012 states:
For a dwelling to be deemed similar, justification must be provided demonstrating that
the difference in daytime and nighttime ambient wind sound level at the dwelling(s) is no
greater than plus or minus three dB from the measured wind ambient sound level at the
similar dwelling.
102. PRE submitted that receptors R2 and R3 are similar because of their proximity to each
other and their similar site conditions.
103. PRE submitted that receptor R7 was chosen as the most representative of wind conditions
at receptor R4 for wind masking for the following reasons:
The orientation of R4 to the Jenner Wind Power Plant is similar, with both receptors
located east of the project, with R4 only southeast of turbines while R7 is east, southeast
and northeast of turbines.
Both locations are single family farms.
Wind-generated sound would be influenced by structures more than vegetation.
There are structures between the turbines and the residences.32
104. In order to demonstrate the requirement for acoustic similarity between receptors, PRE
submitted that “measured AWSLs are more dependent on wind speed than the number of
structures, or orientation of structures to the microphone or the density of vegetation.”33
PRE submitted that receptors R3 and R7 have less than 3 dBA variation in the directions for
which valid data for use in a Class C2 adjustment is available. It provided a table, reproduced in
Table 5, to demonstrate this point:
32
Exhibit 21394-X0169, IR5-006-1_C2 Adjustment, Detailed Analysis_R7, page 4. 33
Exhibit 21394-X0169, IR5-006-1_C2 Adjustment, Detailed Analysis_R7, page 1.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 21
Table 5. Measured AWSL for 4 m/s wind speed at R3 and R734
Receptor Wind Direction Bins
+/- 15 degrees
Wind Speed Bin
(m/s)
AWSL
(dBA)
R3 150 4.0 39
180 39
300 37
330 39
R7 150 4.0 37
300 40
330 37
105. PRE submitted that there is less than a 3 dBA variation between receptors R3 and R7
despite the fact that the “general layout, number of structures and trees varied between the two
sites, with fewer structures on the R3 location compared to R7, particularly for wind from the
300⁰ and 330⁰ directions.”35
5.4 Commission findings
5.4.1 Environmental issues
106. The Commission recognizes PRE’s attempts to locate infrastructure on cultivated land
and to parallel linear disturbances to mitigate the environmental effects of the project.
107. The AEP WM Wind Energy Referral Report indicates that with the exception of
overhead collector lines on native grassland, the project’s impact to the environment is
acceptable to AEP WM. AEP WM’s review and sign off on PRE’s pre-development wildlife
surveys, environmental protection plan, and post-construction monitoring program is an
important factor in the Commission’s consideration of the environmental effects of the project.
The Commission recognizes PRE’s commitments to update any wildlife studies in the event of
delays to the project.
108. The Commission also recognizes PRE’s commitments to develop a plan to compensate
for the 3.18 hectares of native grasslands that would be permanently disturbed by the project and
to continue to consult with AEP to develop this plan. Further, PRE committed to reclaiming
8.33 hectares of native grasslands that would be temporarily disturbed during construction and to
using best practices for native grassland reclamation.
109. The Commission recognizes that burying collector lines is an important tool to mitigate
incremental impacts to wildlife, in particular bird and bat mortalities from collisions with wind
turbines and related infrastructure, and observes that most of the approved wind energy
developments in Alberta have utilized underground collector lines. However, the Commission
also recognizes that there could be instances where the use of overhead connector lines may be
required. In such circumstances, the Commission finds that routing overhead collector lines
34
Exhibit 21394-X0169, IR5-006-1_C2 Adjustment, Detailed Analysis_R7, page 2, Table 1. 35
Exhibit 21394-X0169, IR5-006-1_C2 Adjustment, Detailed Analysis_R7, page 2.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
22 • Decision 21394-D01-2017 (June 16, 2017)
parallel to linear disturbances such as transmission and distribution lines will mitigate the impact
of the collector lines.
110. The Commission acknowledges that PRE’s attempts to site the turbines on cultivated
land, as opposed to native grasslands, will result in the distribution of the turbines to be more
widely spread out into groupings or clusters rather than a single contiguous area. Connecting
these clusters necessitates a lengthier collector system and requires that the collector system
traverse native grassland. The Commission is satisfied that the impacts of the overhead portion
of PRE’s proposed collector system will be mitigated in part by routing the collector lines
parallel to existing and proposed linear infrastructure, such as distribution lines and the
Preferred Route of the proposed 949L Transmission Line, should the Commission approve that
route.
111. The Commission considers PRE’s amendment to its collector system to bury additional
lines on native grassland that do not parallel linear disturbances to be an important measure that
demonstrates PRE’s commitment to mitigating the environmental impacts of the project. While
AEP WM has not had an opportunity to review and comment on this amendment, the
Commission finds that it is a material improvement over the earlier collector system layout and
appears to be more consistent with the goals and objectives of AEP WM, set out in its most
recent directive.
112. The Commission finds that given PRE’s proposal to parallel linear disturbances,
including transmission and distribution lines, the use of overhead collector lines on native
grassland is acceptable in these circumstances.
113. Should the Commission approve the project, it will direct PRE to bury the collector
lines on native grassland in sections 4, 5, 8 and 9 of Township 21, Range 8, west of the
Fourth Meridian that do not parallel linear disturbances and for which PRE has provided an
underground option.36
114. Having regard to the recommendations in AEP WM’s signed October 7, 2016 Renewable
Energy Referral Report and the environmental commitments of PRE, should the Commission
approve the project, it would include the following conditions in the approval:
a. PRE shall keep the project’s wildlife data current (i.e., no more than two years old) until
the project is commissioned by updating the wildlife field surveys as necessary.
b. PRE shall implement any additional mitigation measures recommended by AEP WM
should any new wildlife features or issues be identified during completion of updated
wildlife surveys.
c. PRE shall complete a minimum of three years of post-construction bat and
bird mortality surveys, and submit the results of the surveys yearly to AEP WM.
PRE’s post-construction bird mortality surveys must include surveying along any
36
As shown in Exhibit 21394-X0168, IR5-002-1 Jenner Wind Power Project Proposed Collector Detailed Map
Book.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 23
above-ground segments of its collector line system located on native grasslands. PRE
shall provide yearly confirmation to the Commission that it has conducted this work.
d. PRE shall implement mitigation measures as directed by AEP WM if the
post-construction wildlife mortality surveys indicate levels of bat or bird mortalities in
the vicinity of any of the turbines or any of the above-ground collector lines that are
unacceptable to AEP WM.
115. The reclamation obligations for certain power generation facilities in Alberta, including
wind power generating facilities, are set out in the Environmental Protection and Enhancement
Act, which is administered and enforced by Alberta Environment and Parks.
116. Under the Environmental Protection and Enhancement Act, an operator carrying out an
“activity” (as defined in the act and/or its regulations) has a duty to reclaim specified land and
obtain a reclamation certificate from Alberta Environment and Parks. To obtain a reclamation
certificate an operator must reclaim the land in accordance with the standards set out in
the Environmental Protection and Enhancement Act or as otherwise directed by
Alberta Environment and Parks.
117. Until recently, the definition of “activity” under the Environmental Protection and
Enhancement Act did not include wind power generation projects and, therefore, the duty to
reclaim did not apply to the operators of such projects. However, on March 31, 2017, the
Renewable Electricity Act came into force and amended the Environmental Protection and
Enhancement Act by adding “the generating of wind electric power” to its Schedule of Activities.
118. As a result of this amendment, it is the Commission’s view that wind power generation
projects now fall within the definition of an “activity” in the Environmental Protection and
Enhancement Act and that the operators of such projects located on specified land are now
required to obtain reclamation certificates from Alberta Environment and Parks.
119. The Commission expects that the applicant will comply with all applicable requirements
for conservation and reclamation of the project site under the Environmental Protection and
Enhancement Act at the end of the project’s life, including the requirement to obtain a
reclamation certificate. However, if for any reason, at the time of decommissioning, there are no
statutory reclamation requirements in place for wind electric power generating facilities, the
applicant will be required to submit a reclamation plan to the Commission for its review and
approval in accordance with the following condition:
The applicant shall comply with current applicable reclamation standards at the time of
decommissioning. If no legislative requirements pertaining to reclamation are in place at
the time of decommissioning, the applicant will submit a reclamation plan to the
Commission for approval.
120. The Commission finds that, with the implementation of the mitigation measures outlined
above, the environmental effects of the project can be adequately mitigated.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
24 • Decision 21394-D01-2017 (June 16, 2017)
5.4.2 Noise
121. The Commission first assessed the noise impact assessment without the request for the
Class C2 adjustment. In that regard, the Commission finds that the March 17, 2017 Project NIA
submitted by PRE meets the requirements of Rule 012 and accepts that the cumulative sound
level of the power plant is predicted to meet the daytime and nighttime PSL at all receptor
locations assessed.
122. The Commission recognizes that PRE’s rationale for applying for a Class C2 adjustment
is driven primarily by concerns about meeting the nighttime PSL when conducting post-
construction noise monitoring. The Commission finds that PRE demonstrated that the wind
resource in the project area, for certain directions and wind speeds, will likely result in an
ambient sound level greater than the assumed ambient sound level (i.e., wind masking) at
receptors R3 and R7. The Commission finds that the methodology RWDI used to conduct the
AWSL survey in aid of its request for a Class C2 adjustment is acceptable and that it meets the
requirements of Rule 012.
123. The Project NIA identified that at receptors R2 and R3, for the wind direction of
150 degrees, +/- 15 degrees, a Class C2 adjustment to the nighttime PSL of 2 dBA and 4 dBA
would be required at ground level wind speeds of 3 m/s and 4 m/s or higher, respectively. The
Project NIA also indicated that for receptor R4, a Class C2 adjustment to the nighttime PSL of
2 dBA would be required for a wind speed of 3 m/s or higher at a wind direction of 330 degrees,
+/- 15 degrees.
124. The NIA then summarized the Class C2 adjustment as a broad adjustment to the
nighttime PSL. The Commission finds this conclusion to be inconsistent with Rule 012,
Section 2.1(24) which provides that a Class C2 adjustment for a wind speed and wind direction
applies to the PSL when that wind speed and direction is present near the dwelling. The
nighttime PSL for remaining wind speed and directions where a Class C2 adjustment was not
applied for remain determined in accordance with Table 1 of Rule 012.
125. RWDI was unable to collect sufficient data for many of the wind directions, in particular
the direction relative to the nearest turbine to receptor R4, based on measurements at receptor
R7. The Commission finds that using a larger wind bin size, e.g. +/- 45 degrees, may have
alleviated some of the problems related to insufficient data.
126. Because PRE is not applying for a Class C2 adjustment at receptor R7, the Commission
considers that it cannot apply for a Class C2 adjustment at receptor R4 based on measurements at
receptor R7. To reiterate, Rule 012 states:
A Class C2 adjustment for one dwelling may be applied to other dwellings within the
same project study area that have a similar acoustical environment and ambient wind
sound level.
127. In the Commission’s view, the clause does not contemplate the use of measurements at
one receptor where no Class C2 adjustment is sought and applying those measurements to
another receptor as is applied for in this case. If receptors R4 and R7 were truly acoustically
similar in the context of a Class C2 adjustment, it would be necessary to apply for the adjustment
at both receptors. Further, the Commission finds that the nature of wind masking is reliant upon
the layout, size and type of structures and vegetation surrounding a residence and, as a result, is
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 25
site dependent. It is also the Commission’s view that the clause regarding dwellings with
acoustically similar environments was intended to refer to groupings of houses, such as receptors
R2 and R3, and was not meant to allow for measurements at two or more receptors that are not
grouped or in immediate proximity to each other.
128. For these reasons, and having regard for the fact that the project will be in compliance
with the PSL without a Class C2 adjustment at receptor R4, the Commission denies the request
for the Class C2 adjustment at receptor R4.
129. The Commission considers that receptors R2 and R3 are in close proximity to each other
and acoustically similar and approves the applied for Class C2 adjustment for these receptors.
The Commission approves a nighttime PSL of 42 dBA for a wind direction of 150 degrees,
+/- 15 degrees at a wind speed of 3 m/s and a nighttime PSL of 44 dBA for a wind direction of
150 degrees, +/- 15 degrees at a wind speed of 4 m/s or higher for receptors R2 and R3. The
nighttime PSL at these receptors for all other wind directions and wind speeds is still considered
to be 40 dBA.
5.4.3 Conclusion
130. As noted in Section 3 above, the Commission is required by Section 17 of the
Alberta Utilities Commission Act to decide if approval of the project is in the public interest
having regard to its social and economic effects and its effects on the environment.
131. The Commission is satisfied that the technical, siting, environmental and noise
requirements for the power plant comply with the requirements prescribed in Rule 007.
132. The Commission finds the participant involvement program undertaken by PRE to be
satisfactory and that it meets the requirements of Rule 007.
133. An important consideration for the Commission with respect to the environmental effects
of the project is the applicant’s compliance with various AEP guidelines applicable to the
project. The Commission regards compliance with the existing regulatory requirements
administered by other public or government departments or agencies to be an important element
when deciding if potential adverse impacts are acceptable. In this case, AEP’s only outstanding
concern related to the use of overhead collector lines for certain portions of the project. The
Commission finds that in these circumstances, PRE’s use of limited above-ground collector lines
is acceptable given the mitigations measures it has proposed and, in particular, the paralleling of
transmission and distribution lines and the use of bird markers.
134. The Commission is satisfied that the applicant’s estimated daytime and nighttime
predicted cumulative sound levels for the project meet the requirements of Rule 012, and that a
Class C2 adjustment is justified for receptors R2 and R3.
135. Having regard to the foregoing, the Commission finds that the adverse effects of the
project, which include noise and impacts to the environment, can be mitigated to an acceptable
degree. The Commission therefore considers the project to be in the public interest in accordance
with Section 17 of the Alberta Utilities Commission Act.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
26 • Decision 21394-D01-2017 (June 16, 2017)
6 Halsbury 306S Substation and transmission line 949L
6.1 Halsbury 306S Substation
136. PRE requested approval to construct and operate the Halsbury 306S Substation, which
would be located on privately owned agricultural land within Special Area No. 2 in the southeast
quarter of Section 32, Township 21, Range 8, west of the Fourth Meridian.
137. PRE proposed that the substation would contain the following major equipment:
two 240/35-kV, 120/160/200-megavolt-ampere (MVA) transformers
one 240-kV circuit breakers
nine 35-kV circuit breakers
associated substation equipment
138. The substation would be surrounded by a chain-link fence approximately 64 metres by
70 metres in dimension.
139. PRE filed a NIA for the Halsbury 306S Substation, prepared by RWDI. The NIA
concluded that the substation would comply with the daytime and nighttime PSLs as outlined in
Rule 012.
6.2 Transmission line 949L
140. PRE also proposed to construct a new single-circuit 240-kV transmission line, designated
as transmission line 949L, that would connect PRE’s Halsbury 306S Substation to AltaLink’s
existing Jenner 275S Substation.
141. PRE submitted that the primary land uses in the study area are ranching and farming, but
that there is also a considerable amount of oil and gas facilities. PRE identified four preliminary
routes for the transmission line and eliminated two of the routes after consultation and
consideration of the route impacts. PRE proposed a Preferred Route and an Alternate Route as
shown in the figure below.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 27
Figure 3: Transmission line 949L proposed routes
JENNER
275S SUBSTATION
PROPOSEDHALSBURY 306S
JENNER
RE
D
DEER
R.
555
884
554
TOWNSHIP RD. 202
RA
NG
E R
D.9
0 T.21
T.22
T.20
R.9 R.8W.4M.
555
884
PROPOSED PREFERRED ROUTEPROPOSED ALTERNATE ROUTE N.T.S.
SUBSTATION
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
28 • Decision 21394-D01-2017 (June 16, 2017)
142. PRE summarized the routes in the following table:
Table 6. Transmission line 949L route comparison
143. PRE submitted that the Preferred Route would have a lower impact on the environment
and infrastructure such as oil and gas facilities and pipelines. It also indicated that the Preferred
Route would reduce overall impacts of the project by paralleling the proposed overhead
collection lines of the wind farm.
144. PRE did not provide the costs of the transmission line because the transmission line is
being constructed as a market participant choice facility and all costs will be incurred by PRE. In
response to information requests from the Commission, PRE estimated that the Alternate Route
would cost approximately three to five per cent more than the Preferred Route.
145. PRE retained McCallum Environmental Ltd. to prepare an environmental summary
report that summarizes the results of pre-construction wildlife field surveys and habitat
evaluations conducted in the project area. The report was intended to identify
potentially-affected valued ecosystem components, determine the project’s impact on those
components, and develop techniques to mitigate any adverse environmental effects.
146. The report indicated that routing adjacent to existing disturbances, such as roads and
power lines, will help reduce wildlife habitat fragmentation. It stated that the Preferred Route
would fall alongside existing disturbances for approximately 75 per cent of its length, while the
Alternate Route would follow existing disturbances for approximately 54 per cent of its length.
147. The report identified that the Jenner 275S Substation is located within the AEP
recommended setback of 1,000 metres for an active ferruginous hawk nest that sits on an existing
37
Exhibit 21394-X0108, PRE Response to Information Request Round 2 for Jenner Wind Interconnection,
page 11, Table 1.
Transmission Line 949L Route Comparison37
Preferred Alternate
Length (km) 13.91 13.65
Pipeline Crossings (total number crossed) 26 (39) 28 (40)
Structures 70 77
Nearby waterbodies 2 6
Wetlands crossed by right-of way 17 17
Distribution Crossings 12 10
Wells in vicinity 16 16
Stakeholders 6 5
Residences within 800 metres 0 0
Cultivated land crossed (m) 825 965
Environmentally Significant Areas crossed (km)
0 4.5
Parallel electric transmission lines (km) 0.7 7.8
Co-location of proposed wind project overheard collector system (km)
48 per cent 0 per cent
Access Good Good
Cost Low Medium
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 29
transmission line structure. The Preferred Route would be located approximately 235 metres
from the nest while the Alternate Route would be located approximately 830 metres away. The
Alternate Route would also be located approximately 430 metres from a sharp-tailed grouse lek.
148. PRE submitted that it assessed an additional route in an attempt to maintain the
1,000-metre setback from the ferruginous hawk nest as much as possible but that it rejected this
route because of additional environmental impacts and engineering difficulties. PRE submitted
that it would install bird makers within an AEP specified distance of the nest and would restrict
construction of the portion of the line within the setback distance to be outside the April 15 to
July 15 breeding period.38
149. McCallum indicated that the Preferred Route would have the least potential impact to
wetland species as it would contain the fewest number of total and permanent wetlands.
150. PRE submitted that the Preferred Route would have lower impacts to wetlands. It stated
that 10 of the 17 wetlands that the Preferred Route would cross are classified as Class III or
higher, while 14 of the 17 wetlands that the Alternate Route would cross are classified as
Class III or higher. PRE submitted that wetlands with higher classifications typically support a
higher abundance and diversity of wildlife and vegetation. In addition, the Alternate Route
would cross four, and be adjacent to an additional two, permanent shallow open water bodies,
while the Preferred Route only crosses one semi-permanent water body.
151. PRE consulted with AEP WM and AltaLink about the use of bird markers on the
transmission line. PRE estimated that it would install bird markers on approximately
4,600 metres of line.
152. PRE also filed correspondence from AEP WM indicating it had reviewed PRE’s
justification for the preferred route and agreed with the rationale and proposed mitigation.39
153. PRE conducted a participant involvement program in conjunction with the participant
involvement program for the Jenner Wind Power Plant. The program included notifying parties
within 2,000 metres of the project boundary and conducting consultations with stakeholders
within 800 metres of the project. PRE also held an open house on November 24, 2015 in Jenner.
154. PRE confirmed that it had executed an Asset Transfer Agreement with AltaLink and that
the Interim Operating Authority Services and Interconnection Agreement had been drafted and
would be in place prior to energization. PRE submitted that the Interim Operating Authority
Services and Interconnection Agreement covers a temporary period that will not exceed six
months following energization subject to extension by the parties’ written agreement.40 AltaLink
indicated that it had worked with PRE to facilitate the temporary operation and eventual transfer
of transmission line 949L to AltaLink. AltaLink stated that it would apply to the Commission to
transfer the necessary approvals to operate transmission line 949L and for an interconnection
order to complete the market participant choice process.
38
Exhibit 21394-X0078, Attachment 7: JWPIP Environmental Summary, PDF pages 62-64. 39
Exhibit 21394-X0078, Attachment 7: JWPIP Environmental Summary, PDF page 61. 40
Exhibit 21394-X0108, PRE Response to Information Request Round 2 for Jenner Wind Interconnection Project,
PDF page 29.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
30 • Decision 21394-D01-2017 (June 16, 2017)
6.3 Commission findings
155. The Commission finds that the applications to construct and operate Halsbury 306S
Substation and transmission line 949L comply with the information requirements prescribed in
Rule 007. The facility applications are also consistent with the need identified in the NID
application.
156. The Commission is also satisfied that the participant involvement program undertaken by
PRE meets the requirements of Rule 007.
157. The Commission finds that the Preferred Route of transmission line 949L will have the
least impacts because it will parallel more linear infrastructure, cross fewer water bodies, and
have less impacts to wetlands than the Alternate Route. The Commission recognizes that
AEP WM agreed with PRE’s justification for the selection of the preferred route. The
Commission is satisfied that with the implementation of appropriate mitigation measures, the
environmental effects of the transmission line and substation will be minimal.
158. The Commission finds that there are no outstanding technical or environmental concerns
associated with the substation or transmission line, nor are there any outstanding public or
industry concerns.
159. Given the considerations discussed above, the Commission finds the construction of the
Halsbury 306S Substation and transmission line 949L to be in the public interest pursuant to
Section 17 of the Alberta Utilities Commission Act.
160. The Commission directs PRE to install bird marking devices on segments of the
transmission line that are:
a. Within 100 metres of Class III, IV and V wetlands.
b. Within 100 metres of the high water mark of open water bodies.
c. Within AEP’s 1,000-metre minimum setback for the existing ferruginous hawk nest.
d. Within AEP’s recommended minimum setbacks for high disturbance level activities for
any bird species at risk that may subsequently be identified during pre-construction
wildlife surveys.
161. The Commission expects that PRE and AltaLink will coordinate their efforts to file an
application to transfer operation of the transmission line to AltaLink after construction is
completed, and anticipates that such application will be filed within six months of the
energization of the transmission line.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 31
7 AltaLink Jenner 275S Substation alterations
162. AltaLink applied pursuant to sections 14 and 15 of the Hydro and Electric Energy Act to
alter and operate Jenner 275S Substation by adding one 240-kV circuit breaker and to install or
modify other associated substation equipment. AltaLink is the owner of the Jenner 275S
Substation pursuant to Permit and Licence 21975-D02-2016.41
163. AltaLink also applied pursuant to Section 18 of the Hydro and Electric Energy Act for an
order to interconnect the Jenner 275S Substation to PRE’s transmission line 949L.
164. The Jenner 275S Substation is located in the southeast quarter of Section 19,
Township 20, Range 8, west of the Fourth Meridian. AltaLink stated that upon completion of the
alterations, the Jenner 275S Substation would contain the following major equipment:
two 240/25-kV, 50/67/83-MVA LTC transformers
one 138/25-kV, 15/20/25-MVA transformer
seven 240-kV circuit breakers
one 138-kV circuit breaker
ten 25-kV circuit breakers
associated substation equipment
165. AltaLink also proposed to expand the fenceline of the substation by approximately
30 metres by 55 metres to the northeast.
166. Subsequent to filing its application, AltaLink filed a separate application and received
approval to install three additional 25-kV circuit breakers at Jenner 275S Substation in
Proceeding 21975, bringing the total number of 25-kV circuit breakers to 13.
167. AltaLink’s participant involvement program consisted of a notification and consultation
process. It provided a project-specific information package to stakeholders within 800 metres of
the substation and conducted consultations with stakeholders directly adjacent to the substation.
AltaLink submitted that there are no outstanding concerns or objections to the substation
alterations.
168. AltaLink submitted that based on the scope of the project and mitigation measures
proposed, it anticipated that the potential environmental effects of the project will be negligible.
169. AltaLink stated that it received Historical Resources Act approval from Alberta Culture
and Tourism for the project on March 3, 2016, and filed a subsequent application for a proposed
temporary workspace for which it received approval on April 14, 2016.
41
Substation Permit and Licence 21975-D02-2016, Proceeding 21975, Application 21975-A001,
September 27, 2016.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
32 • Decision 21394-D01-2017 (June 16, 2017)
170. The cost of the substation project is estimated to be approximately $4,963,000 (within
+20 per cent/-10 per cent accuracy). This cost would be allocated entirely to the customer, PRE.
7.1 Commission findings
171. The Commission finds that the facility application to alter Jenner 275S Substation
complies with the information requirements prescribed in Rule 007, and that it is also consistent
with the need identified in the NID application.
172. The Commission is satisfied that the participant involvement program meets the
requirements of Rule 007.
173. It is also satisfied that there are no outstanding technical or environmental concerns
associated with the substation alterations, nor are there any outstanding public or industry
concerns.
174. Given the considerations discussed above, the Commission finds the alterations to
Jenner 275S Substation to be in the public interest pursuant to Section 17 of the Alberta Utilities
Commission Act.
8 Decision
175. Pursuant to Section 11 of the Hydro and Electric Energy Act, the Commission approves
applications 21394-A001 and 21394-A006 and grants PRE the approval set out in Appendix 1 –
Jenner Wind Power Plant – Approval 21394-D02-2017 – June 16, 2017.
176. Pursuant to Section 34 of the Electric Utilities Act, the Commission approves the need
outlined in NID Application 21394-A003 and grants the AESO the approval set out in
Appendix 2 – Needs Identification Document Approval 21394-D03-2017 – June 16, 2017.
177. Pursuant to sections 14, 15 and 19 of the Hydro and Electric Energy Act, the Commission
approves Application 21394-A002 and grants PRE the approval set out in Appendix 3 – Permit
and Licence 21394-D04-2016 – June 16, 2017, to construct and operate Halsbury 306S
Substation.
178. Pursuant to sections 14, 15 and 19 of the Hydro and Electric Energy Act, the Commission
approves Application 21394-A004 and grants PRE the approval set out in Appendix 4 – Permit
and Licence 21394-D05-2017 – June 16, 2017, to construct and operate transmission line 949L.
179. Pursuant to sections 14, 15 and 19 of the Hydro and Electric Energy Act, the Commission
approves Application 21394-A005 and grants AltaLink the approval set out in Appendix 5 –
Permit and Licence 21394-D06-2017 – June 16, 2017, to alter and operate Jenner 275S
Substation.
180. Pursuant to Section 18 of the Hydro and Electric Energy Act, the Commission approves
Application 21394-A005 and grants AltaLink the approval set out in Appendix 6 – Connection
Order 21394-D07-2017 – June 16, 2017, to connect PRE’s transmission line 949L to AltaLink’s
Jenner 275S Substation.
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
Decision 21394-D01-2017 (June 16, 2017) • 33
181. The appendices will be distributed separately.
Dated on June 16, 2017.
Alberta Utilities Commission
(original signed by)
Anne Michaud
Commission Member
Power Renewable Energy Corporation, Alberta Electric System Operator Jenner Wind Power Plant and Interconnection and AltaLink Management Ltd.
34 • Decision 21394-D01-2017 (June 16, 2017)
Appendix A – Abbreviations
Abbreviation Name in full
AEP Alberta Environment and Parks
AEP WM Alberta Environment and Parks-Wildlife Management
AESO Alberta Electric System Operator
AltaLink AltaLink Management Ltd.
AUC or the
Commission
Alberta Utilities Commission
AWSL ambient wind sound level
EPP environmental protection plan
EUB or the Board Alberta Energy Utilities Board
kV kilovolt
McCallum McCallum Environmental Ltd.
MVA megavolt-ampere
MW megawatt
NIA noise impact assessment
NID needs identification document
PRE Power Renewable Energy Corporation
PSL Permissible Sound Level
Rule 007 Rule 007: Applications for Power Plants, Substations, Transmission
Lines, Industrial System Designations and Hydro Developments
Rule 012 Rule 012: Noise Control
RWDI RWDI Consulting Engineers & Scientists
TFO transmission facility owner