Power PPT Feb14

  • Upload
    inik777

  • View
    25

  • Download
    0

Embed Size (px)

DESCRIPTION

CRISIL Powers ector report

Citation preview

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    Power

    1

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    Key conclusions

    Key reforms introduced to address issues in fuel availability, improve health of discoms and tackle stressed PPAs, however, progress remains slow

    Fuel constraints, weak discom financials, aggressive bidding have adversely impacted returns of many operational projects

    Moreover demand is expected to slowdown to 5.3% CAGR over next 5 years due to weak economic growth

    Slower demand, issues in clearances, and stretched financials of developers to moderate pace of capacity additions to 55 GW over 2013-18 vis--vis 64 GW in past 5 years

    Overall PLFs of coal based plants to remain subdued at 73% in FY18

    - Aggressive bidding and slow demand growth to restrict PLF of new plants to 67% by FY18 which is currently at ~50%

    7 GW domestic coal based projects bid below Rs 3.1 / unit, which is required for equity IRR of 16%, are likely to see severe pressure on their profitability as per existing PPAs

    SEB financials to improve led by FRP implementation, tariff hikes; revenue gap to be eliminated by FY18

    2

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    Source: CEA Source: MoC, MoPNG, Industry sources, CRISIL Research

    3

    Capacity additions have accelerated but PLFs declined

    Source: CEA Source: PFC

    203

    134 9

    11 20

    20 8.7

    0

    50

    100

    150

    200

    250

    FY'09 FY'10 FY'11 FY'12 FY'13 9M FY'14 Dec'13

    Sharp growth in

    capacity additions

    (GW)

    -2%

    0%

    2%

    4%

    6%

    8%

    10%

    12%

    FY

    '09

    FY

    '10

    FY

    '11

    FY

    '12

    FY

    '13

    Coal supply growth

    CAGR: 4.5%

    -40%

    -20%

    0%

    20%

    40%

    60%

    FY

    '09

    FY

    '10

    FY

    '11

    FY

    '12

    FY

    '13

    Gas supply growth

    CAGR: 2.3%

    78 78 75 74

    70

    65

    58

    67 66

    60

    40

    25 20

    30

    40

    50

    60

    70

    80

    FY'09 FY'10 FY'11 FY'12 FY'13 9M'14

    Coal based PLFs Gas based PLFs (%)

    2.93

    3.40 3.55

    3.97

    4.39

    4.71

    2.70

    3.07 3.15 3.33

    3.69

    4.19

    2.5

    2.8

    3.1

    3.4

    3.7

    4.0

    4.3

    4.6

    4.9

    FY'08 FY'09 FY'10 FY'11 FY'12 FY'13E

    ACS ARR (Rs./kwh)

    However, growth in fuel supply lagged capacity additions Sharp growth in installed capacity

    Additionally, financial health of SEBs has worsened Consequently, PLFs have declined

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    Reforms initiated, implementation remains poor

    4

    Compensatory tariff

    In April 2013, CERC ruled that Adani Power and Tata Power be allowed to charge compensatory tariffs

    Committee under Deepak Parekh has submitted recommendations state approval awaited

    PUN, HAR have declined compensatory tariff, MAH has given conditional approval

    Litigations could delay final decision & hurt cash flows

    Power

    Sector

    Reforms

    FSAs with CIL

    CIL mandated to sign FSAs with 78 GW of capacities including cases with tapering linkage

    As of 6th Sep-13, CIL had signed ~140 FSAs

    Tapering linkage for 9 plants extended by 3 years Adani Power, Essar Power, Sterlite Energy to benefit

    Positive move, however, lower ACQ levels would restrict PLFs

    FRP

    Under the FRP, 50% of ST liabilities will be taken over by state and balance restructured with banks for 3 years

    As at December 2013, TN, RAJ, UP and HAR have implemented the FRP. Bihar, Jharkhand and AP to

    implement scheme by Mar13

    ACS-ARR gap to be eliminated by 2017-18; annual tariff hikes of 5-6% critical to ensure cost recovery

    Imported coal cost pass through

    In Jun13, allowed domestic coal linkage based plants to pass on the costs of coal imports to end consumers

    CERC to suggest modalities for implementation of the higher fuel cost pass through to distribution companies

    Delays/Litigations expected; well-structured mechanism is critical

    New SBD for UMPPs

    Fuel cost is a pass through; bidding based on fixed charge for 1st year of operations

    Onus of land acquisition and clearances lies with developer

    Loss on fixed costs due to low PAFs to be shared in 70:30 ratio by developers and SEBs

    New UMPP guidelines de-risk developers but limit returns

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    State Demand

    (BU)

    Supply

    (BU)

    Deficit

    (%)

    Gujarat 67.4 67.4 0

    Madhya Pradesh 36.4 36.4 0

    Rajasthan 42.1 42 0.3

    Haryana 34.6 34.4 0.6

    Maharashtra 93.7 92 1.9

    Tamil Nadu 70 65.5 6.5

    Andhra Pradesh 69.9 64.9 7.1

    Uttar Pradesh 72.3 61.7 14.7

    All India 753.7 720.1 4.5

    Few large states witness decline in deficit Demand growth over FY08-13

    5

    Demand slowdown to add to power sector woes;

    further impact offtake

    Demand growth over FY14-18

    Source: CEA, CRISIL Research

    Weak discom financials & capacity constraints restricted power demand growth to 6.2 per cent over FY08-13

    Power demand growth to slowdown to 5-5.5% CAGR over FY13-18 despite anticipated capacity additions and improvement in financials of state discoms

    Weak GDP growth to restrict power demand growth from industrial and commercial segments,

    Power deficit at near zero levels in Madhya Pradesh, Gujarat, Rajasthan and Haryana due to slowing demand growth

    Southern states to drive demand on higher availability led by capacity additions and inter-regional connectivity

    Demand slowdown to put pressure on PLFs and merchant realisations; also lead to delay in capacity additions

    777 831

    862

    937

    998

    691 747

    788

    858 911

    600

    700

    800

    900

    1000

    1100

    1200

    1300

    1400

    FY'09 FY'10 FY'11 FY'12 FY'13

    (BU)

    Deficit:

    11.1%

    Requirement Availability

    Source: CEA, Note: Data for April-Dec13

    1009 1048

    1116

    1190

    1290

    968 1021

    1095

    1178

    1284

    FY'14P FY'15P FY'16P FY'17P FY'18P

    Deficit:

    0.5%

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    6

    Slowing demand, fuel issues & stretched player financials

    to impact capacity additions

    Source: CRISIL Research

    CRISIL Research expects capacity additions of 55 GW over 2014-18 vis--vis 64 GW over the past 5 years

    Pace of capacity additions to decline with slowdown in demand, delays in clearances, stretched financial position of developers

    Pipeline of projects under construction on a decline as no new projects have been announced in the past 12-18 months

    Coal based capacities to dominate as coal remains the cheapest and most widely available fuel source

    Hydro capacities to account for 9% share; R&R issues and clearance delays to hamper capacity additions

    Private sector to dominate capacity additions at 54 per cent on the back of large expansion plans

    Large conglonmerates such as Adani Power, Reliance Power, Sterlite Energy and Essar Power to lead capacity additions

    Central sector player NTPC to add ~ 9.5 GW of capacities; state sector to lag due to poor financial health

    Project Developer MW

    Nabhinagar NTPC 1000

    Tilaiya UMPP Reliance Power 3960

    Tori TPP Essar Power 1200

    Vidharba TPP Lanco Infratech 1320

    Bara TPP JVPL 1980

    Bhavanupadu PTC 1320

    Tamnar - II Jindal Power 1200

    Source: CRISIL Research

    103 103 106 97 94 92 88

    0

    20

    40

    60

    80

    100

    120

    Jun-1

    2

    Sep-1

    2

    Dec-1

    2

    Mar-

    13

    Jun-1

    3

    Sep-1

    3

    Dec-1

    3

    (GW)

    Source: CEA, CRISIL Research

    21

    15

    12 9 10 9

    0.0

    5.0

    10.0

    15.0

    20.0

    25.0

    FY

    '13

    FY

    '14P

    FY

    '15P

    FY

    '16P

    FY

    '17P

    FY

    '18P

    (GW)

    Total Capacity addition (GW) Trend in projects under construction Projects unlikely to commission by FY18

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    7

    Slowing power demand and limited coal availability to

    restrict PLFs

    Coal PLFs to remain subdued over FY14-FY18

    Slow power demand growth and limited domestic

    coal availability to restrict PLFs

    CIL production to grow at 5.5% CAGR over FY13-

    FY17 against linkage based capacity growth of ~7%

    CIL to supply only 65% of ACQ as per new FSAs

    Additionally, aggressive bidding to limit increase in

    PLFs of post 2009 plants to only 67%

    Share of coal imports to decline over the long term

    Slowdown in capacity additions

    Increase in captive mine production by ~65 mn tonne

    to relieve some pressure

    Imported coal prices to remain range bound at $80-

    $85 over 2013 and 2014

    Source: CEA, CRISIL Research

    Note: Imported coal - 5000 Kcal/kg, Domestic coal - 3500 Kcal/kg

    Source: Ministry of Coal, CRISIL Research

    11%

    14% 16%

    17% 18% 17% 16%

    0%

    5%

    10%

    15%

    20%

    -

    200

    400

    600

    800

    FY'12 FY'13E FY'14P FY'15P FY'16P FY'17P FY'18P

    Domestic Supply Imports Imports to consumption ratio

    (MT

    75%

    70% 66% 67%

    69% 70%

    73%

    51% 54%

    57% 61%

    64% 67%

    40%

    50%

    60%

    70%

    80%

    FY'11 FY'12 FY'13 FY'14 P FY'15 P FY'16 P FY'17 P

    All coal based

    (%)

    Domestic supply and imports of non-coking coal for power

    Average annual PLF of coal based power plants

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    8

    Source: SERCs, CRISIL Research

    (22.3 GW)

    Projects at risk

    4,690

    10,544

    2,000

    4,891

    0

    2,000

    4,000

    6,000

    8,000

    10,000

    12,000

    3.1 and above 2.9-3.1 2.6-2.9 Below 2.6

    (MW)

    7 GW of competitively bid domestic coal projects bid below Rs. 2.9/unit will see pressure on returns

    CCEA has approved pass through of higher cost of imported coal for domestic linkage based plants

    Well structured mechanism for tariff determination

    required to avoid delays/litigations

    GMR Infra has put its 600 MW coal based power plant on block; Adani Power has petitioned for

    compensatory tariff for its Tiroda plant aggressive

    bidding has led to operational losses in these projects

    Tariffs of ~Rs. 3.1 per unit to provide equity

    IRRs of 16% for domestic coal based plants

    In the event of pass-through of imported

    coal costs; levelised tariff required would be

    lower at Rs. 2.9 per unit

    Plant size of 600 MW; Capital cost of Rs 52 mn/MW

    Domestic coal @ Rs. 1,460/tonne Annual cost escalation at ~4%

    PLFs: 58% in Yr 1 ramping up to 70% in Yr 5; 70-75% for balance years

    Imported coal blending at 15% in Year 1 declining to 5% in year 5; 5% blending thereafter

    Debt equity ratio of 70:30

    Source: CRISIL Research

    IRRs sensitive to tariffs a 10 paise change in tariffs will improve IRRs by 150-200 bps

    Domestic coal based plants require tariff of Rs. 3.1/unit to earn healthy

    returns; ~7 GW of capacities at risk due to aggressive bidding

    Competitively bid domestic linkage based projects Domestic Coal - Key Assumptions

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    Weak discoms cater to ~30% of countrys consumption

    9

    Note: ACS ARR Gap is on subsidy booked basis; data as at Mar2012 Source: CRISIL Research

    ACS-ARR Gap

    (Rs./kwh)

    AT&C loss

    (%)

    Accumulated

    losses (Rs. Bn)

    Weak states

    Tamil Nadu (2.06) 19.9 (277.9)

    Punjab (0.11) 20.6 (19.4)

    Rajasthan (4.03) 24.2 (409.4)

    Uttar Pradesh (0.76) 45.1 (301.8)

    Orissa (0.17) 44.7 (54.8)

    Moderate states

    Haryana (0.95) 27.6 (101.4)

    Andhra P 0.0 15.3 1.5

    Madhya P (0.71) 38.3 (144.1)

    Chhattisgarh (0.66) 29.6 (21.9)

    Strong states

    Karnataka (0.02) 24.5 (14.0)

    Maharashtra 0.0 21.6 (46.5)

    Gujarat 0.04 19.3 4.1

    Delhi 0.19 18.6 16.7

    West Bengal 0.03 32.9 (2.1)

    All India (0.70) 27.0 (1,798.7)

    Risk classification on the basis of discom health (financial & operational) as well as state

    governments ability and willingness to support

    Weakest states account for 30% of total power consumption & ~60% of accumulated losses

    Rajasthan has the highest state government support through equity infusions and subsidy

    State government support in Odisha limited due to privatisation of discoms

    Moderate risk states account for 20% of power consumption & 15% of accumulated losses

    MP and Haryanas relatively weak discom scores countered by stronger state support;

    AP enjoys significant subsidy support, however, delays in subsidy payments impact risk profile

    Despite strong financials, state willingness to support low in Chhattisgarh

    Strong states account for 37% of power consumption &

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    ACS-ARR Gap to be eliminated by 2017-18

    10

    8 states have so far approved implementation of FRP; these states account for around 50% of liabilities

    FRP implemented in TN, RAJ, UP and Haryana; to be implemented in Andhra Pradesh Bihar and Jharkhand by

    March14

    Implementation of FRP in FY14 to reduce interest cost to 14p/kwh in FY15 from 34p/kwh in FY13

    Cost reflective annual tariff hikes of 5-6% expected going forward to avoid further operational losses for discoms

    Tariff hike of 6.5% implemented in FY14 following tariff hike of ~13% in FY13

    On a subsidy booked basis, ARR to exceed ACS by 7 p/unit in 2017-18 at a pan-India level

    However, few states such as Tamil Nadu, Madhya Pradesh and Uttar Pradesh to remain stretched due to high level of

    regulatory assets

    ACS: Average cost of supply, ARR: Average revenue realised

    Source: PFC, CRISIL Research

    Note: Revenue is on a subsidy booked basis

    Source: PFC, State SERCs, CRISIL Research

    Particulars FY12A FY13E FY18P

    Revenue 3.69 4.19 5.76

    Less: Expenses 4.39 4.71 5.69

    Power Purchase 3.20 3.47 4.38

    Interest cost 0.32 0.34 0.17

    Other charges 0.87 0.90 1.14

    (Gap) / Surplus (0.70) (0.52) 0.07

    3.4 3.6

    4.0

    4.4 4.7 4.8

    5.1 5.3

    5.5 5.7

    3.1 3.2 3.3

    3.7

    4.2 4.5

    4.8 5.1

    5.5 5.8

    2.5

    3.0

    3.5

    4.0

    4.5

    5.0

    5.5

    6.0

    FY

    '09

    FY

    '10

    FY

    '11

    FY

    '12E

    FY

    '13E

    FY

    '14P

    FY

    '15P

    FY

    '16P

    FY

    '17P

    FY

    '18P

    ACS ARR

    (Rs./kwh) Implementation

    of FRP

    ACS - ARR gap has widened to 70p/unit in FY12 Gap on subsidy booked basis for state utilities (Rs./kwh)

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    11

    About us

    CRISIL Limited

    CRISIL is a global analytical company providing ratings, research, and risk and policy advisory services. We are India's leading ratings agency. We are

    also the foremost provider of high-end research to the world's largest banks and leading corporations.

    CRISIL Research

    CRISIL Research is India's largest independent and integrated research house. We provide insights, opinions, and analysis on the Indian economy,

    industries, capital markets and companies. We are India's most credible provider of economy and industry research. Our industry research covers 70

    sectors and is known for its rich insights and perspectives. Our analysis is supported by inputs from our network of more than 4,500 primary sources,

    including industry experts, industry associations, and trade channels. We play a key role in India's fixed income markets. We are India's largest provider of

    valuations of fixed income securities, serving the mutual fund, insurance, and banking industries. We are the sole provider of debt and hybrid indices to

    India's mutual fund and life insurance industries. We pioneered independent equity research in India, and are today India's largest independent equity

    research house. Our defining trait is the ability to convert information and data into expert judgements and forecasts with complete objectivity. We leverage

    our deep understanding of the macroeconomy and our extensive sector coverage to provide unique insights on micro-macro and cross-sectoral linkages.

    We deliver our research through an innovative web-based research platform. Our talent pool comprises economists, sector experts, company analysts,

    and information management specialists.

    CRISIL Privacy Notice

    CRISIL respects your privacy. We use your contact information, such as your name, address, and email id, to fulfill your request and service your account

    and to provide you with additional information from CRISIL and other parts of The McGraw-Hill Companies, Inc. you may find of interest.

    For further information, or to let us know your preferences with respect to receiving marketing materials, please visit www.crisil.com/privacy. You can view

    McGraw-Hills Customer Privacy Policy at http://www.mcgrawhill.com/site/tools/privacy/privacy_english.

    Last updated: May, 2013

    Disclaimer

    CRISIL Research, a division of CRISIL Limited (CRISIL) has taken due care and caution in preparing this Report based on the information obtained by

    CRISIL from sources which it considers reliable (Data). However, CRISIL does not guarantee the accuracy, adequacy or completeness of the Data /

    Report and is not responsible for any errors or omissions or for the results obtained from the use of Data / Report. This Report is not a recommendation to

    invest / disinvest in any company covered in the Report. CRISIL especially states that it has no financial liability whatsoever to the subscribers/ users/

    transmitters/ distributors of this Report. CRISIL Research operates independently of, and does not have access to information obtained by CRISILs Ratings Division / CRISIL Risk and Infrastructure Solutions Limited (CRIS), which may, in their regular operations, obtain information of a confidential

    nature. The views expressed in this Report are that of CRISIL Research and not of CRISILs Ratings Division / CRIS. No part of this Report may be published / reproduced in any form without CRISILs prior written approval.

  • 2

    013 C

    RIS

    IL L

    td.

    All

    rig

    hts

    reserv

    ed.

    CRISIL Limited

    www.crisil.com