39
POWER GRID CORPORATION OF INDIA LTD SOUTHERN REGIONAL LOAD DESPATCH CENTRE in 3 rd SRPC MEETING 19 TH FEBRUARY 2007 BANGALORE GRID EVENTS AND ISSUES

POWER GRID CORPORATION OF INDIA LTD

Embed Size (px)

DESCRIPTION

POWER GRID CORPORATION OF INDIA LTD. GRID EVENTS AND ISSUES. in 3 rd SRPC MEETING 19 TH FEBRUARY 2007 BANGALORE. SOUTHERN REGIONAL LOAD DESPATCH CENTRE. ISSUES. 3.0 COMPUTATION OF TALCHER STPS-II INJECTION 5.0 AMC FOR SCADA-EMS SYSTEM UNDER SR ULDC SCHEME - PowerPoint PPT Presentation

Citation preview

Page 1: POWER GRID CORPORATION OF INDIA LTD

POWER GRID CORPORATION OF INDIA LTD

SOUTHERN REGIONAL LOAD DESPATCH CENTRE

in

3rd SRPC MEETING

19TH FEBRUARY 2007

BANGALORE

GRID EVENTS AND ISSUES

Page 2: POWER GRID CORPORATION OF INDIA LTD

ISSUES

3.0 COMPUTATION OF TALCHER STPS-II INJECTION

5.0 AMC FOR SCADA-EMS SYSTEM UNDER SR ULDC SCHEME

6.0 WIDE BAND CONNECTIVITY OF PUDUCHERRY

8.0 BACKUP TRANSMISSION SCHEME FOR EVACUATION OF

TALCHER-II GENERATION

10.0 CONCURRENCE FOR AUGMENTATION OF EXISTING ULDC WIDE

BAND NETWORK FOR ENSURING DATA REDUNDANCY

14.0 11TH PLAN CENTRAL SECTOR THERMAL POWER PROJECTS

FOR SR

15.0 OPERATION OF TALCHER-KOLAR HVDC TRANSMISSION

SYSTEM IN GROUND RETURN MODE

16.0 REGIONAL TRANSMISSION SCHEMES FOR EXECUTION BY

POWERGRID

Page 3: POWER GRID CORPORATION OF INDIA LTD

ISSUES

18.0 STATUS OF REGIONAL TRANSMISSION SCHEMES

18.1 UPGRADATION TO 400KV LEVEL OF OPERATION OF KAIGA-

GUTTUR D/C LINE

18.2 SHIFTING OF ONE 315 MVA, 400/220 KV TRANSFORMER AT

TRIVANDRUM

19.0 HANDING OVER OF 220KV KODIKURUCHI-EDAMON LINE

REQUIRED FOR CONSTRUCTION OF 400KV TIRUNELVELI- EDAMON

LINE UNDER KUDUNKULAM EVACUATION SYSTEM

20.0 COMPUTATION OF UI EXCHANGES BETWEEN ER-SR

21.0 SPECIAL PROTECTION SCHEME(SPS) FOR 2X1000 MW

KUDANKULAM ATOMIC POWER PROJECT

23.0 PUMP MODE OPERATION OF KADAMPARAI

Page 4: POWER GRID CORPORATION OF INDIA LTD

ISSUES

25.0 EVACUATION SCHEMES FOR NEW CENTRAL GENERATING

STATIONS

26.0 TERMINATION OF TIRUNELVELI-EDAMON 400KV CIRCUIT

UNDER KUDANKULAM EVACUATION SCHEME AT EDAMON

28.0 REVISED UNIT TRIPPING SCHEME UNDER HVDC POLE

OUTAGES AT TALCHER STAGE-II

29.0 PREPONEMENT OF COMMERCIAL OPERATION OF PGCIL

TRANSMISSION ELEMENTS

30.0 GRID OPERATION

30.1 LOW FREQUENCY OPERATION

30.4 SCHEDULING OF KAYAMKULAM

32.0 CLOSING OF 220KV BALIMELA-UPPER SILERU S/C LINE

29.1.i 29.1.ii

SCM 23rd AGENDA

Page 5: POWER GRID CORPORATION OF INDIA LTD

0

10

20

30

40

50

60

70

80

90

% O

F T

IME

---

>

Aug-06 Sep-06 Oct-06 (upto 20th)

DATE --->

<49.0HZ <49.5HZ <50.0HZ

FREQUENCY SPECTRUM FROM AUGUST 06 TO OCT 06 (UPTO 20TH OCT 06)

  < 49.0 HZ < 49.5 HZ < 50.0 HZ 49 - 50.5 HZ >50.2HZ >50.5 HZ

Aug-06 0.37 6.93 34.82 99.22 22.75 0.41

Sep-06 1.38 29.62 63.95 98.61 12.27 0.02

Oct-06 (upto 20th) 10.54 44.74 83.42 89.47 2.66 0.02

Page 6: POWER GRID CORPORATION OF INDIA LTD

Date: 17th October 2006

PRESS RELEASE

CERC directs PowerGrid to ensure grid stability

1. In order to take action for violating the Indian Electricity Grid Code (IEGC) by drawing electricity in excess of their schedule drawal, the Central Electricity Regulatory Commission (CERC) has directed PowerGrid to furnish the list of States and their quantum of overdrawals in the time-blocks when the frequency in the extended Central Grid was below 49.0 Hz during the period 9th to 15th October 2006.

2. The Commission has further directed all the RLDCs to keep a strict watch over the Grid Code violations, which can possibly endanger the grid stability and promptly inform the Commission about the defaulters with appropriate recommendation regarding remedial action.

3. The maintenance of satisfactory grid frequency has assumed added importance after synchronization of Northern Regional Grid with Central Grid comprising Western, Eastern and North-Eastern Regional Grids. In this context, the IEGC requires that the various beneficiary States shall always endeavor to restrict their net drawal from the grid to their respective drawal schedules, whenever the system frequency is below 49.5 Hz and when the frequency falls below 49.0 Hz, the requisite load shedding shall be carried out by the concerned State to curtail its over drawal.

S. K. ChatterjeeAssistant Secretary

Page 7: POWER GRID CORPORATION OF INDIA LTD

 STATE

No. of Time Blocks for which State

overdrew below 49 Hz.

MWH Overdrawal below 49 Hz

Average MW overdrawn

below 49 Hz

TAMILNADU 110 7146 260

KARNATAKA 70 3351 191

ANDHRA PRADESH 53 1782 134

PUDUCHERRY 109 1439 53

GOA 86 314 15

KERALA 0 0 0

Summary of ODs at Freq. LT 49 HZ. During the week 09-10-06 TO 15-10-06

 STATE

No. of Time Blocks for which State

overdrew below 49 Hz.

MWH Overdrawal below 49 Hz

Average MW overdrawn

below 49 Hz

TAMILNADU 108 2976 110

KARNATAKA 105 2856 109

ANDHRA PRADESH 52 1663 128

PUDUCHERRY 139 1101 32

GOA 107 458 17

KERALA 19 254 53

Summary of ODs at Freq. LT 49 HZ. During the week 16-10-06 TO 22-10-06

Page 8: POWER GRID CORPORATION OF INDIA LTD

Message Type Brief Details

Type A Caution Message when constituent overdraws at frequency <49.2 Hz. (issued in line with IEGC clause 6.4.4)

Type B Violation Message when constituent overdraws at frequency <49 Hz. (issued in line with IEGC clause 6.4.4)

Type C Violation Message when constituent continues to overdraw at frequency <49.0 Hz., in spite of RLDC’s instruction to terminate the over drawal(issued in line with IEGC clause 6.4.9 and Section 29(2) of I.E. Act 2003)

Page 9: POWER GRID CORPORATION OF INDIA LTD

DETAILS OF GRID CODE VIOLATION MESSAGES ISSUED BY SRLDC TO CONSTITUENTS FOR THE MONTH OF OCTIOBER 2006DATE AVG %OFTIME %OFTIME

FRQ FREQUENCY FREQUENCYCAUTION VIOLATION VIOLATION CAUTION VIOLATION VIOLATION CAUTION VIOLATION VIOLATION CAUTION VIOLATION VIOLATION

<49.50hz <49.0hz MESSAGE"A" MESSAGE"B" MESSAGE"C" MESSAGE"A" MESSAGE"B" MESSAGE"C" MESSAGE"A" MESSAGE"B" MESSAGE"C" MESSAGE"A" MESSAGE"B" MESSAGE"C"

05.10.06 1 1

07.10.06 2 1

09.10.06 49.68 17.9 - - - - - - - - - - - - -

10.10.06 49.76 14.7 - - - - - - - - - - - - -

11.10.06 49.69 23.4 - 1 - - - - - 1 - - - - -

12.10.06 49.44 66.4 4.4 - - - 3 1 - 13 4 - - - -

13.10.06 49.15 93.9 21.7 3 - - 2 1 1 8 3 1 - - -

14.10.06 48.96 90.3 60.9 1 1 1 2 3 1 - - -

15.10.06 49.31 76.3 9.1 4 - - 2 - - 4 1 - - - -

16.10.06 49.2 79.1 29 6 3 - 5 2 1 4 1 - - - -

17.10.06 49.23 78.1 25.2 - - - 3 1 1 7 5 3 2 - -

18.10.06 49.16 86.3 31.5 3 8 4 4 3 1

19.10.06 49.2 96.5 15.6 3 6 3 1 1 2

20.10.06 49.19 97.4 11.8 4 2 5 1 1

22.10.06 49.6 33.9 0 2

23.10.06 49.38 68 5.4 8 2 1 1 1

24.10.06 49.38 72.7 2.3 4 1 3 1

25.10.06 49.26 81.3 13.8 7 1 7 4 3 1 1

26.10.06 49.1 95.5 34.1 12 3 13 4 7

60 11 1 60 23 18 47 21 5 4 0 0

ANDHRA PRADESH KARNATAKA TAMILNADU KERALA

Page 10: POWER GRID CORPORATION OF INDIA LTD

SCHEDULE VS DRAWL OF SR STATES FOR 26/10/06

0

500

1000

1500

2000

2500

SC

HE

DU

LE

/DR

AW

AL

IN

MW

AP DRAWAL

AP SCHD

APTRANSCO

0

200

400

600

800

1000

1200

1400

1600

1800

SC

HE

DU

LE

/DR

AW

AL

IN

MW

KAR DRAWAL

KAR SCHDAPTRANSCOKPTCLKPTCL

48.5

49.0

49.5

50.0

50.5

51.0

51.5

0:0

0

1:0

0

2:0

0

3:0

0

4:0

0

5:0

0

6:0

0

7:0

0

8:0

0

9:0

0

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

0:0

0

FR

EQ

UE

NC

Y I

N H

Z

FREQUENCY

0

100

200

300

400

500

600

700

800

900

1000

SC

HE

DU

LE

/DR

AW

AL

IN

MW

KER DRAWAL

KER SCHDKSEB

0

500

1000

1500

2000

2500

SC

HE

DU

LE

/DR

AW

AL

IN

MW

TN DRAWAL

TN SCHDTNEB

Page 11: POWER GRID CORPORATION OF INDIA LTD

FREQUENCY VERSES SR CONSTITUIENTS UI ON 26-10-2006 AT 1200HRS TO 1600 HRS

48.4

48.9

49.4

49.9

50.4

50.9

51.4

12:0

0

12:1

0

12:2

0

12:3

0

12:4

0

12:5

0

13:0

0

13:1

0

13:2

0

13:3

0

13:4

0

13:5

0

14:0

0

14:1

0

14:2

0

14:3

0

14:4

0

14:5

0

15:0

0

15:1

0

15:2

0

15:3

0

15:4

0

15:5

0

16:0

0

TIME

FR

EQ

UE

NC

Y

-600

-400

-200

0

200

400

600

800

FREQ

AP UI

KAR UI

KER UI

TN UI

APTRANSCO'S UI

KPTCL'S UI

TNEB'S UI

KSEB'S UI

FREQUENCY

CHART

Page 12: POWER GRID CORPORATION OF INDIA LTD

STATE UI Vs FREQUENCY FOR 27-OCT-06

48.0

48.5

49.0

49.5

50.0

50.5

51.0

51.5

52.0

10:0

010

:10

10:2

010

:30

10:4

010

:50

11:0

011

:10

11:2

011

:30

11:4

011

:50

12:0

012

:10

12:2

012

:30

12:4

012

:50

13:0

013

:10

13:2

013

:30

13:4

013

:50

14:0

014

:10

14:2

014

:30

14:4

014

:50

15:0

015

:10

15:2

015

:30

15:4

015

:50

16:0

016

:10

16:2

016

:30

16:4

016

:50

17:0

0

TIME --->

FR

EQ

IN H

Z -

-->

-600

-500

-400

-300

-200

-100

0

100

200

300

400

UI I

N M

W -

-->

FREQ AP UI KAR UI KER UI TN UI

KAR UI

AP UI

TN UI

KER UI

FREQ

Page 13: POWER GRID CORPORATION OF INDIA LTD

Computation of Talcher STPS-II Injection

Page 14: POWER GRID CORPORATION OF INDIA LTD

Computation of Talcher STPS-II Injection

• The computation of actual injection of Talcher STPS-II for accounting purposes was done using SEMs installed on the out going feeders till 31.03.2006.

• Clause 7.4.6 of revised IEGC effective from 1st April 2006, provided actual injection of Talcher STPS-II shall be metered on 400 kV side of Generator transformers of Talcher STPS-II units.

• CEA has issued (installation and operation of meters) Regulations, 2006 to become effective from 22.03.06 (came to notice in May, 2005).

NTPC LETTER020806

SRLDC REPLY110806

NTPC LETTER070906

SRLDC REPLY111006

CEA REGUMINUTES OF1st COMM.

AMENDMENTS BY SRLDCIEGC

GT vis a vis Feedres Inj

Page 15: POWER GRID CORPORATION OF INDIA LTD

Computation of UI Exchanges between

ER - SR

Page 16: POWER GRID CORPORATION OF INDIA LTD

The methodology adopted by SRLDC for computation of UI between ER-SR during the period 03.04.06 to 27.08.06 was based on the following stipulations made in IEGC (effective from 1.4.2006):

7.6.1 The regional boundaries for scheduling, metering and UI accounting of inter-regional exchanges between ER & SR shall be as follows:

400 kV Bus couplers between Talcher-I and Talcher-II

400 kV East bus of Gazuwaka HVDC.

7.6.3. No attempt shall be made to split the inter-regional schedules into linkwise schedules (where two regions have two or more interconnections).

Page 17: POWER GRID CORPORATION OF INDIA LTD

As regards to the UI computation of Talcher Stage II, the following provisions as stated in IEGC were also taken into consideration:

7.4.2. For a clear demarcation of responsibilities and minimal to-and-fro coordination, the scheduling of Talcher-II shall be coordinated by SRLDC, and the 400 kV AC bus-couplers between Talcher-I (2x500 MW) and Talcher-II (4x500 MW) shall be treated as the interface between ER and SR.

7.4.6. …… The difference between the actual injection of Talcher II and the dispatch schedule shall constitute the UI of Talcher-II, for which payments shall be made from/into the UI pool account of Southern region operated by SRLDC, but at the UI rate corresponding to ER repeat ER frequency. The energy accounting for Talcher-II STPS shall be carried out by SRLDC.

7.4.7. While the dispatch schedule for Talcher-II shall be as advised by SRLDC, the actual generation at Talcher-II may be varied by station operators depending on ER frequency, as long as the resulting UI does not cause a transmission constraint in ER. In case of a transmission constraint being caused in ER by the UI of Talcher-II, ERLDC may advise Talcher-II to curtail its UI under intimation to SRLDC. Any such advise shall be immediately complied with by Talcher-II.

Page 18: POWER GRID CORPORATION OF INDIA LTD

Specific Issues related to UI exchange between SR & ER vis-à-vis

between Talcher Stage II to ER :

Any UI exchange is carried out with the consent of SRLDC/ERLDC

control rooms to move power mainly from surplus to deficit region

The direction and quantum of UI between would depend on the

generation level maintained by Talcher II - irrespective of regions status

Any UI exchange is carried out depending on the frequency of both the

regions and thereby resulting into positive differential UI

Talcher II may inject UI irrespective of the frequency relationship of the

two regions and thereby at times resulting into negative differential UI

Annexure-I

Any UI exchange gives equitable benefits to the constituents in both the

regions

Injection of UI by Talcher II if clubbed with SR to ER UI, may not result

in such equitable scenario

Annexure-II

Page 19: POWER GRID CORPORATION OF INDIA LTD

It may therefore be seen that in view of the specific location of Talcher II vis-à-vis other ISGSs, the

UI computation in respect of Talcher II is required to be followed in a manner which would be based

on the IEGC provisions as stated above and at the same time it would not defeat the basic UI

philosophy which stipulates that the UI exchange between two agencies/ regions should benefit

both the parties.

In order to achieve this, whenever UI transactions are there in respect of Talcher II with ER, the UI

calculations have to be carried out as per the IEGC provisions (clause 7.4.6 ) i.e. at ER frequency.

However as per this clause, as the payment for this UI to Talcher II has to be made from the UI

pool account operated by SR, it is natural that SR UI pool must be suitably compensated by getting

the equivalent amount from the UI pool operated by ER.

Furthermore by following this methodology as no differential gets generated in SR/ER UI pool on

this account, there cannot be any sharing of accumulated differential UI. therefore the possible

viable approach within the framework of IEGC regulations could be:

--- to treat this transaction as a UI only between Talcher II and ER and

--- while accounting these amounts (as it is) these can be routed through the SR weekly UI

accounts

METHODOLOGY FOR ACCOUNTING OF UI BETWEEN TALCHER II AND ER

Page 20: POWER GRID CORPORATION OF INDIA LTD

TALCHER STAGE II UI & ER AND SR FREQUENCY

-30.00

-20.00

-10.00

0.00

10.00

20.00

30.00

40.00

0000

-001

5

0100

-011

5

0200

-021

5

0300

-031

5

0400

-041

5

0500

-051

5

0600

-061

5

0700

-071

5

0800

-081

5

0900

-091

5

1000

-101

5

1100

-111

5

1200

-121

5

1300

-131

5

1400

-141

5

1500

-151

5

1600

-161

5

1700

-171

5

1800

-181

5

1900

-191

5

2000

-201

5

2100

-211

5

2200

-221

5

2300

-231

5

TIME BLOCK --->

EX

-BU

S I

N M

W -

--->

48.50

49.00

49.50

50.00

50.50

51.00

51.50

52.00

52.50

53.00

53.50

FR

EQ

UE

NC

Y I

N H

Z -

--->

UI SR FREQUENCY ER FREQUENCY 23-May-06 Tuesday

EASTERN REGION

Loss = 2.9 lakhs

Payable by ER RS. 4.3 Lakhs Receivable by SR Rs. 6.2 Lakhs

Negative Differential UI Rs.2.9 Lakhs

Page 21: POWER GRID CORPORATION OF INDIA LTD

TALCHER STAGE II UI & ER AND SR FREQUENCY

-15.00

-10.00

-5.00

0.00

5.00

10.00

15.00

20.00

25.00

30.00

0000

-001

5

0100

-011

5

0200

-021

5

0300

-031

5

0400

-041

5

0500

-051

5

0600

-061

5

0700

-071

5

0800

-081

5

0900

-091

5

1000

-101

5

1100

-111

5

1200

-121

5

1300

-131

5

1400

-141

5

1500

-151

5

1600

-161

5

1700

-171

5

1800

-181

5

1900

-191

5

2000

-201

5

2100

-211

5

2200

-221

5

2300

-231

5

TIME BLOCK --->

EX

-BU

S I

N M

W -

--->

48.50

49.00

49.50

50.00

50.50

51.00

51.50

52.00

52.50

53.00

53.50

FR

EQ

UE

NC

Y I

N H

Z -

--->

UI SR FREQUENCY ER FREQUENCY 10-Jun-06

SaturdayEASTERN REGION

Loss = 3.8 lakhs

Page 22: POWER GRID CORPORATION OF INDIA LTD

SR & ER FREQUENCY AND DIFFERENCE AMOUNT BETWEEN SR-ER UI RATES ON 14-10-2006

-6

-5.465

-4.93

-4.395

-3.86

-3.325

-2.79

-2.255

-1.72

-1.185

-0.65

-0.115

0.42

0.955

1.49

1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85 88 91 94

TIME BLOCKS

DIF

F. A

MO

UN

T B

ET

WE

EN

SR

-E

R U

I RA

TE

S

48.5

48.7

48.9

49.1

49.3

49.5

49.7

49.9

50.1

50.3

50.5

50.7

50.9

51.1

51.3

51.5

SR FREQUENCY

ER FREQUENCY

DIFFERENTIAL AMOUNT

-1.5 lakhs -48.7 lakhs

Page 23: POWER GRID CORPORATION OF INDIA LTD

ERFreq = 49.6 HzUI Rate= Rs.3/

TalcherStage IIGen: 1600Schd: 1600

1600 MWSR

Talcher Stage I & II I/C

SR Freq = 49.16 HzUI Rate= Rs.5/

UI (SR to ER) 0 MW

0 MWER

0 MW UI (from SR to ER)

Annexure -ICASE – 1 UI from Talcher Stage II to ER when SR frequency < ER frequencyBase Case: Talcher Stage II UI =0 MW

Base Case +Talcher Stage II 50 MW UI (Talcher Stage 2 actual Generation = 1650 MW against Schd. of 1600 MW)

ERFreq = 49.6 HzUI Rate= Rs.3/

TalcherStage IIGen: 1650Schd: 1600

1600 MWSR

Talcher Stage I & II I/C

SR Freq = 49.16 HzUI Rate= Rs.5/

UI (SR to ER) 0 MW

50 MWER

0 MW UI (from SR to ER)

Issues

Considering the variable cost of Talcher Stage II as around 80 paisa it would be beneficial for Talcher Stage II to generate positive UI as the ER UI rate is more than its variable cost. For every unit of power exported to ER, Talcher Stage II would get a price of Rs 3/Unit.However if the UI by Talcher Stage II to ER is considered as UI from SR to ER, then it would be a case of –ve UI

For every unit of power exported , SR would expect a price of Rs 5/Unit while ER would be able to give a price of Rs 3/Unit only. Such transactions accumulated during that periods could cause commercial implications.

In order to address this issue ,the UI transactions can be considered between Talcher Stage II and ER, however the accounts can be routed through SR.

Page 24: POWER GRID CORPORATION OF INDIA LTD

BACKUP TRANSMISSION SCHEME FOR EVACUATION OF TALCHER-II GENERATION

Page 25: POWER GRID CORPORATION OF INDIA LTD

BEHRAMPUR

MENDHASAL

OPTION 1

400 KV TSTPP-II- MENDHASAL-BEHRAMPUR-GAZUWAKA.

400 KV TSTPP-II- MENDHASAL IS ORISSA GRIDCO LINE (YET TO BE DECIDED). HENCE LONG TERM STOA HAS TO BE SOUGHT.

STOA WOULD NOT BE LINE WISE BUT FOR ORISSA GRID.

STOA WOULD DEPEND ON THE LINE LOADING. CORRIDOR WOULD NOT BE USED, EXCEPT WHEN POLES ARE OUT

Page 26: POWER GRID CORPORATION OF INDIA LTD

BEHRAMPUR

MENDHASAL

OPTION 2

400 KV TSTPP-II- BEHRAMPUR-GAZUWAKA.

SINCE NO GRIDCO LINE IS INVOLVED, THERE WOULD NOT BE A NEED FOR STOA. HENCE THIS OPTION WOULD BE PREFFERED

Page 27: POWER GRID CORPORATION OF INDIA LTD

REGIONAL TRANSMISSION SCHEMES FOR EXECUTION BY POWERGRID

Page 28: POWER GRID CORPORATION OF INDIA LTD

KRISHNAPATTINAM UMPP

D/C QUAD MOOSE

765 KV

HVDC B2B

TN UMPP

Page 29: POWER GRID CORPORATION OF INDIA LTD

KRISHNAPATTINAM UMPP

D/C QUAD MOOSE

765 KV

HVDC B2B

TN UMPP

Page 30: POWER GRID CORPORATION OF INDIA LTD

COMMENTS ON KRISHNAPATTINAM AND TN UMPP EVACUATION PLAN

• THE FOLLOWING 400 KV LINES WOULD BE STRESSED– CUDDAPAH-KOLAR-SOMANAHALLI– KOLAR - MELKOTTAIYUR– HOSUR-SALEM– RAICHUR EVACUATION BOTTLENECK IN CASE

OF 765 KV LINE TRIPPING– NUNNA-KHAMMAM-N’SAGAR– SRISAILAM-KURNOOL– NUNNA-NELLORE D/C EVACUATION WITH

VEMAGIRI

• HIGH VOLTAGES ARE ALSO A CAUSE OF CONCERN AND ADEQUATE REACTIVE ELEMENTS MAY HAVE TO BE PROVIDED

Page 31: POWER GRID CORPORATION OF INDIA LTD

UMPP EVACUATION BASE CASE

TALCHER-KOLAR NIL

2500 MW EXPORT TO WR ON 765 KV

RAICHUR-SHOLAPUR

Page 32: POWER GRID CORPORATION OF INDIA LTD

KRISHNAPATTINAM UMPP

D/C QUAD MOOSE

765 KV

HVDC B2B

TN UMPP

765 KV RING CONSISTING OF NELLORE, MELKOTTAIYUR, ARASUR, HIRIYUR AND RAICHUR

NAGARJUNA& ONGC PLANT

•CREATE ONE MORE 400 KV STATION NEAR CHENNAI FOR FULL FLEDGED RING MAIN

•400 KV STATION AT DB PURA NEAR BANGALORE AS NELAMANGALA IS TOO CONGESTED

Page 33: POWER GRID CORPORATION OF INDIA LTD

SHIFTING OF ONE 315 MVA, 400/220 KV TRANSFORMER AT TRIVANDRUM

Page 34: POWER GRID CORPORATION OF INDIA LTD

SHIFTING OF 3RD ICT FROM TRIVANDRUM TO MADAKKATHARA

• LOADING OF MADAKKATHARA ICTs ARE AROUND 200-250 MW EACH

• L/C ON ONE ICT TYPICALLY OVERLOADS OTHER ICT– LOAD REARRANGEMENTS AND TRIPPING OF

ONE CKT OF UDUMALPET IS DONE TO CONTROL THE OVERLOAD.

• LOADING OF ABOUT 600 MW IS SEEN IN 2012 CASE

• SHIFTING OF THE ICT IS ADVISABLE

Page 35: POWER GRID CORPORATION OF INDIA LTD

TRIVANDRUM ICTs & TRICHUR ICTs Flows on 05-02-2007

0

100

200

300

400

500

600

00:0

0

01:0

0

02:0

0

03:0

0

04:0

0

05:0

0

06:0

0

07:0

0

08:0

0

09:0

0

10:0

0

11:0

0

12:0

0

13:0

0

14:0

0

15:0

0

16:0

0

17:0

0

18:0

0

19:0

0

20:0

0

21:0

0

22:0

0

23:0

0

00:0

0

Time (In Hrs)--->

MW

--->

TRIV-ICT

TRICH-ICT

MADAKKATHARA ICT TOTAL MW

TRIVANDRUM ICT TOTAL MW

Page 36: POWER GRID CORPORATION OF INDIA LTD

ADVANCED COMMISSIONING OF NARENDRA-GUTTUR D/C

Page 37: POWER GRID CORPORATION OF INDIA LTD

CHARGING OF KAIGA GUTTUR TO 400 KV

PONDA(Goa)

(MAHARASHTRA)

CHIKKODIKARNATAKA

BELGAUM

NARENDRA 220

KADRA

KAIGA

AMBEWADI

XELDEM(GOA)

NAGJHARI

KODASALLI

HUBLI

M.L.PURA

KOLHAPUR

175 KMS

70 KMS

63 KMS

2X100 MVA 220/110

2X100 MVA 220/110

TATA DIESEL80 MW, 593 PS VAR COST

GHATAPRABHA ( 20 MW)

KUDUCHI

TO ALMATTI BAGALKOT,-BBWADI,-LINGSUGUR – Raichur TPS

HAVERI

Page 38: POWER GRID CORPORATION OF INDIA LTD

ADVANTAGES OF NARENDRA GUTTUR LINE

• KAIGA + KALI EVACUATION BECOMES MORE STABLE

• LOOP GETS ADDED AT 400 KV LEVEL• SR GRID LOSSES GET REDUCED BY 6-10

MW• FLOW GETS SHARED BETWEEN KAIGA-

GUTTUR AND NARENDRA-GUTTUR– EVACUATION OF UNIT 3 AND 4

• IMPORT FROM MAHARASHTRA THROUGH 220 KV D/C KOLHAPUR-BELGAUM IS MORE STABLE

Page 39: POWER GRID CORPORATION OF INDIA LTD

CLOSING OF 220KV BALIMELA-UPPER SILERU S/C LINE

GRID MAP OF GRIDCO

GRID MAP OFAP

USL-BLM LETTER

STUDY FOREVACUATION