23
Portland Cement NESHAP: PCA Perspectives Andy O’Hare, PCA February 2010

Portland Cement NESHAP: PCA Perspectives

  • Upload
    others

  • View
    7

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Portland Cement NESHAP: PCA Perspectives

Portland Cement NESHAP: PCA Perspectives

Andy O’Hare, PCA

February 2010

Page 2: Portland Cement NESHAP: PCA Perspectives

AgendaOverview of U.S. Cement Industry

Overview of Cement Manufacturing Process

Summary of Concerns

Pollutant Specific Concerns and

Recommendations

Overview of Potential Economic Impacts

Page 3: Portland Cement NESHAP: PCA Perspectives

Overview of U.S. Industry 2008 116 clinker producing plants

167 cement kilns

Average clinker production: 584,000 tons per kiln

Annual clinker capacity: 97.5 million metric tons

Cement imports: 11.5 million metric tons

17,280 cement industry employees

7.2 million construction industry employees

Page 4: Portland Cement NESHAP: PCA Perspectives

U.S. Cement Plants

Page 5: Portland Cement NESHAP: PCA Perspectives

U.S. Cement Consumption (‘000 metric

tons)

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

1998 2000 2002 2004 2006 2008 2010 2012 2015 2017 2019

Page 6: Portland Cement NESHAP: PCA Perspectives

Net U.S. Supply Balance (MMT)

Cement Consumption

Imp

ort

s:

25

.6

MM

T

Cement Production Capacity

Page 7: Portland Cement NESHAP: PCA Perspectives
Page 8: Portland Cement NESHAP: PCA Perspectives

Global Cement Production 2007

Page 9: Portland Cement NESHAP: PCA Perspectives

The Cement Sector is Trade Exposed

Lowest cost building materials are generally sought for construction, including lower cost imported cement

It is relatively inexpensive to ship cement across oceans

U.S. manufacturers compete with imports from China, Colombia, Korea and other developing countries that do not face comparable air emission or potential climate change regulation

Cement producers in these countries therefore have a cost advantage over U.S. manufacturers

Page 10: Portland Cement NESHAP: PCA Perspectives

Timeline for Portland Cement NESHAP March 1998: Initial Proposal

June 1999: Final Rule - particulate matter, dioxin/furan stds and total hydrocarbon (THC) std (greenfield plants only)

August 1999: Challenged by Earthjustice, PCA and NLA

December 2000: D.C. Circuit Decision; Remand back to EPA

April 2002: Final Rule implementing PCA/EPA settlement of litigation

December 2005: Proposed Revisions

December 2006: Revisions Finalized – mercury and total hydrocarbon stds for new and modified facilities; work practices for existing facilities; 112(d)(4) petition granted for HCl

December 2006: December 2006 rule reconsidered

2007: Extensive 114 data request; testing of scrubbers

May 2009: EPA proposes substantial changes

Page 11: Portland Cement NESHAP: PCA Perspectives

Key Concerns with EPA Rule Rule will have significant economic impacts

Mercury and total hydrocarbon (THC) emissions linked primarily to site specific limestone quarries

Use of pollutant-by-pollutant “lowest emitting” methodology with limited data and consideration of variability is inconsistent with Clean Air Act

Standards should reflect full range of emission characteristics of “floor” facilities

Subcategorization and variability methodologies can provide reasonable floors

Emission limits not appropriate for periods of startup, shutdown and malfunction.

Page 12: Portland Cement NESHAP: PCA Perspectives

Pollutant-by-Pollutant Concern Different set of “lowest emitting”(rather than “best

performing”) units used to set “floors” for mercury,

THC, hydrochloric acid (HCl) and particulate matter

(PM)

None of the “floor” facilities capable of complying

with proposed standards without additional controls

EPA approach creates “hypothetical” plant which

does not exist

Best performers should be actual plants capable of

achieving emission standards “in practice” without

add on controls

Page 13: Portland Cement NESHAP: PCA Perspectives

None of the Floor Units Comply with

All of the Proposed Limits

0

5

10

15

20

25

Mercury THC HCl PM

Pollutant

Nu

mb

er

of

Kiln

s

Units that comply (based onlimited stack data)

Units that cannot comply duringmalfunction events

Units with too little information todetermine compliance

Units that cannot comply without limitingmaterials and products, or addingcontrols

Units that cannot comply based on stacktests

Units that do not comply

Page 14: Portland Cement NESHAP: PCA Perspectives

MercuryPollutant/Technology Concern

Mercury comes primarily from plant-specific limestone

Some plants will not be able to achieve the standard even when equipped with technology

Scrubbing efficiency is related to the valence of mercury; only oxidized mercury is captured

Accordingly, scrubber performance will vary by an order of magnitude

Mercury control by cement kiln dust (CKD) removal is very limited

Recommendations

More expansive consideration of variability when determining a specific emission limit

Consider establishing a percent removal as a beyond the floor requirement for selected kilns with elevated mercury limestone concentrations

Subcategorize universe of facilities based on at least the concentration of mercury in limestone

Page 15: Portland Cement NESHAP: PCA Perspectives

Mercury Variability Summary for Best Performers

0

50

100

150

1259 1233 1302 1315 1650 1248 1589 1435 1484 1286 1364 Average

Kiln Code

lb/M

illio

n T

on

Feed

With Additional Consideration of Alternative Local Coal

Adding Statistical Variability in 30 Day Data (2 Std. Dev.)

Adjusting for Alternative Products and/or Alternative Raw Materials

Base Case (30 Days Mass Balance Data)

--- EPA Floor is 26 lbs/Million

ton of feed

Page 16: Portland Cement NESHAP: PCA Perspectives

THCPollutant/Technology Concern

Data set is too limited and of too short a duration

Carbon not effective with light hydrocarbons; THC and mercury carbon systems designed differently

Limitations on the effectiveness of activated carbon will lead to greater use of RTOs; greater greenhouse gas impacts

RTOs have a 5-10 ppm performance limit, restricting emission control capabilities

Many cement plant have limited or no access to natural gas needed for RTOs

THC emissions may be influenced by various plant configurations

Recommendations

Collect additional THC data over much longer period of time to capture natural variability

Subcategorize universe of facilities

Note: THC data collection now ongoing

Page 17: Portland Cement NESHAP: PCA Perspectives

HClPollutant/Technology Concern

EPA has used area source data for a major source standard

Standard based on stack tests; CEMs required for compliance

EPA has overstated the collateral benefit of a wet scrubber for HCl and SO2

High efficiency removal of HCl has not been demonstrated in the presence of SO2

Recommendations

Endorse previously EPA accepted risk based exemption

Page 18: Portland Cement NESHAP: PCA Perspectives

PMPollutant/Technology Concerns

PM data set includes kilns

that were tested for NESHAP

compliance; PCA concerned

with “MACT on MACT”

implications

Recommendations

Remove from PM data set

those kilns which were tested

for NESHAP compliance

Page 19: Portland Cement NESHAP: PCA Perspectives

Technology Requirements of

Proposed MACT Rule

0

20

40

60

80

100

120

140

160

Scrubber ACI with

Baghouse

RTO Baghouse Units at Risk of

Closure

Technology

Nu

mb

er

of

Kil

ns

PCA Estimate

EPA Estimate (Midpoint)

Page 20: Portland Cement NESHAP: PCA Perspectives

Potential Economic Impacts of NESHAP Compliance with the NESHAP as proposed could cost more

than $4.7 billion; add $21 to the cost of cement in 2020 potentially exacerbating leakage of cement production

Limited available capital and market circumstances may make it difficult to comply within the allotted three year timeframe

As many as 30 plants could close, with an additional 12 at high risk of closure

Upwards of 27 million tons of U.S. annual clinker production capacity could be lost

Imports could represent more than 36% of consumption by 2020

Page 21: Portland Cement NESHAP: PCA Perspectives

Potential Economic Impacts

Connect With Concrete

Estimated U.S. Cement Clinker Capacity by ScenarioMillion Metric Tons

0

20

40

60

80

100

120

Baseline Scenario NESHAP Scenario

2007

2013

2015

2020

Page 22: Portland Cement NESHAP: PCA Perspectives

Connect With Concrete

Estimated U.S. Cement Import Shares by ScenarioShare of Total Market (%)

0.00%

5.00%

10.00%

15.00%

20.00%

25.00%

30.00%

35.00%

Baseline Scenario NESHAP Scenario

2007

2013

2015

2020

Page 23: Portland Cement NESHAP: PCA Perspectives

Thank You!

Building Better Outcomes with Concrete