PORTHOS Basis of completion design

ECM Number #: 196564

TAQA Energy B.V. Kruseman van Eltenweg 1,  1817BC Alkmaar,  The Netherlands  Date:    August 8th, 2019 Issue No.:  Version 2.0   

 

Page 2: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 2 of 22

DOCUMENT CONTROL

Authorization

Activity  Name  Function  Date  Signature 

Prepared   Hein van Heekeren  Senior Well Engineer     

Reviewed  Tim‐Tijn Scherpenhuijsen  Geologist / CCS Project 

Manager    

Reviewed  Willem‐Jan Plug  Subsurface Manager      

Reviewed  Reinout Storm  Manager Drilling & Wells     

Approved  Isabelle de Vos Drilling & Completions expert, EBN 

   

Revision record

Version  Date  Status / Changes 

0, Draft  27‐2  For review 

0.1 Draft  28‐2  Incorporated comments from TTS, WJP & RS 

0.2  28‐2  For approval 

0.3  5‐3  Incorporated comments Jan‐Thijs Keijser 

1.0  25‐3  Incorporated comments IdV 

1.1  12‐6  Added wells optional wells P18‐2A6 & P18‐6a7, for review. 

1.2  19‐6  Included comments of reviewers, for approval. 

2.0  8‐8  Included comments IdV and updated to follow ISO specification 

   

   

Page 3: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 3 of 22

TABLE OF CONTENTS 

DOCUMENT CONTROL .................................................................................................................. 2 

Authorization ................................................................................................................................... 2 

Revision record ................................................................................................................................. 2 

1.  INTRODUCTION .................................................................................................................... 4 

2.  DESIGN ASSUMPTIONS ......................................................................................................... 5 

2.1.  Reservoir .............................................................................................................................. 5 

2.2.  Regional pore pressure and fracture gradient profiles ....................................................... 5 

2.3.  CO2 delivery specifications ................................................................................................... 6 

2.4.  Normal operational parameters and input from the flow assurance study ....................... 7 

2.5.  Well integrity ........................................................................................................................ 8 

3.  DESIGN REQUIREMENTS ..................................................................................................... 10 

3.1.  Completion configuration .................................................................................................. 10 

3.2.  Materials ............................................................................................................................ 11 

3.3.  Annulus fluids ..................................................................................................................... 12 

3.4.  Production Liner & Casing cement .................................................................................... 12 

3.5.  Logging requirements ........................................................................................................ 12 

3.6.  Clean‐out ............................................................................................................................ 13 

4.  CONCLUSIONS AND RECOMMENDATIONS .......................................................................... 14 

5.  APPENDICES ....................................................................................................................... 15 

5.1.  Appendix A: generalized stratigraphy of the P18 area ...................................................... 15 

5.2.  Appendix B: Static wellhead and reservoir pressures for CO2 injection well ................... 17 

5.3.  Appendix C: Example CO2 injection completion P18‐4A2 well .......................................... 18 

5.4.  Appendix D: Example CO2 injection completion P18‐2A3 well ......................................... 19 

5.5.  Appendix E: Wellhead and Tree ......................................................................................... 20 

Page 4: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 4 of 22

1. INTRODUCTION

As part of the Porthos CCS project it is planned to inject CO2 in the depleted P18‐2 and P18‐4 Bunter 

gas reservoirs. A multidisciplinary well selection workshop* has been held on the 31st of January in the 

EBN office to select the candidate wells for injection based on reservoir properties and well integrity 

status. All planned injection wells are located on the normally unmanned P18/A platform and are 

currently producing gas that is evacuated through the P15/D platform. The below table lists all wells 

that were selected to serve as an injection well: 

 

Well Name:  Well type  Well type 

P18‐2A1  P18‐A platform  Injector 

P18‐2A3  P18‐A platform  Injector 

P18‐2A5  P18‐A platform  Injector 

P18‐4A2  P18‐A platform  Injector 

P18‐2A6  P18‐A platform  Optional injector*

P18‐6A7  P18‐A platform  Optional injector*

*The mother bore of P18‐2A6 well and the P18‐6A7 well have been added as optional injection 

candidates to the basis of completion design in a later phase because the flow assurance study 

indicated that there may be a benefit in using these wells as “start‐up” wells and to increase the total 

storage capacity. 

 

The purpose of this document is to prepare a basis of design for re‐completion of the wells to make 

them suitable for CO2 injection based on current known requirements for the wells. The design will 

follow ISO standard 27914 “Carbon dioxide capture, transportation and geological storage ‐ Geological 

storage”. 

 

Page 5: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 5 of 22

2. DESIGN ASSUMPTIONS

2.1. Reservoir 

CO2 is planned to be injected in the Bunter reservoir at a depth of around 3200 m TVD. The caprock consists of the Solling Claystone Member and an >500m TVD thick sequence consisting of the Rot, Muschelkalk, Keuper and various Altena shales. A generalised stratigraphy of the P18 wells can be found in appendix A. 

2.2. Regional pore pressure and fracture gradient profiles 

The pore pressures and formation fracture pressures are displayed in the figure below; 

The minimum fracture gradient is based on P18 limit and leak‐off test results, indicated by a Green dot. The Green line connects these dots and is indicative of the formation strength. 

The Blue line shows the hydrostatic pressure line of the formations 

The Red line shows the pressure profile in case the well would be fully filled with CO2 at the final planned reservoir pressure of 345 bar 

   

Page 6: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 6 of 22

2.3. CO2 delivery specifications 

Component Concentration* Based on

CO2  ≥ 95% ISO-27913

H2O  ≤ 40 ppmv OCAP ≤40ppmv / Technical Operation ≤50 ppmvNote 1

Sum [H2+N2+Ar+CH4+CO+O2]  ≤ 4% ISO-27913Note 2

H2  ≤ 0.75% ISO-27913Note 2

N2  ≤ 2% ISO-27913

Ar  ≤ 1% ISO-27913

CH4  ≤ 1% ISO-27913

CO  ≤ 750 ppmv Note 3 OCAP

O2 ≤ 40 ppmv Note 4 Storage license P18-4

H2S ≤ 5 ppmv Note 5 OCAP

SOx ≤ 50 ppmv ISO-27913

NO  ≤ 2.5 ppmv OCAP (emitters do not require additional purification)

NO2  ≤ 2.5 ppmv Note 6 OCAP (emitters do not require additional purification)

NOx  ≤ 5 ppmv Note 6 OCAP NO+NO2

C2+ (hydrocarbons) ≤ 1200 ppmv Note 7 OCAP (emitters do not require additional purification)

Aromatic hydrocarbons (incl.BTEXNote8) 

≤ 0.1 ppm OCAP (emitters do not require additional purification)

Total volatile organic compoundsNote 9  ≤ 350 ppm Already being sent to OCAP Note 10

Ethylene (Etheen)(C2H4)  ≤ 1 ppmv OCAP (emitters do not require additional purification)

H-cyanide (HCN)  ≤ 20 ppmv OCAP (emitters do not require additional purification)

Carbonyl Sulfide  ≤ 0.1 ppmv OCAP (emitters do not require additional purification)

Dimethyl Sulfide  ≤ 1.1 ppmv OCAP (emitters do not require additional purification)

*All percentages are mole %. Note: 1 % (mole) = 10 000 ppmvNote 1: A study of the phase diagram with CO2 and H2O vs. the Porthos operating regimes indicated that solids may form at 100ppm H2O, but not at 50ppm. Optimization between these steps has not been done to determine the maximum amount of H2O that could be allowed to prevent solid formation. Note 2: Components lighter than CO2 shift the phase diagram upwards. This increases the operating costs for compression, but also increases the 2-phase zone which must be avoided in the offshore pipeline. Crossing the 2-phase zone from high pressure to low pressure causes significant temperature drops by the Joule Thompson effect. Hydrogen is the lightest of these components and should therefore be allowed with caution. Note 3: Next limit: ISO-27913 CO < 0.2%. Note 4: ISO-27913 stipulates O2 < 10 ppmv (Petroleum Industry Standard w.r.t. well integrity), although recommendation from material specialist to avoid corrosion is 100ppm. Also, for wells in stainless steel, low levels of O2 is actually required to form an oxidation layer. Therefore, the specification was slightly relaxed to OCAP composition. Note 5: Next limit: ISO-27913 and specialist recommendation to avoid corrosion and: H2S < 200ppmv. Note 6: Next limit: ISO-27913 NO2 < 50 ppmv Note 7: Next limit: ISO-27913 C2+ < 2.5% Note 8: BTEX = benzene, toluene, ethylbenzene, xylene Note 9: Total volatile organic compounds = ethanol, acetaldehyde, ethyl acetaat, traces of n-propanol, isobutanol, acetone, dimethyl ether, propanal, 2-butanol, methanol, n-butanol and isoamyl acetaat Note 10: OCAP specification on Total volatile organic compounds < 1.2 ppm

Page 7: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 7 of 22

2.4. Normal operational parameters and input from the flow assurance study 

For the flow assurance study (Flow assurance study presentation January 31th 2019, Stefan Belfroid, TNO) the following parameters have been taken into account for steady state injection: 

Temperatures: 

Compressor outlet temperature 35 < T < 80 °C 

Downhole temperature T > 15 °C 

Topside piping T > ‐10 °C 

Flowrates: 

Desired flow rates 15 – 170 kg/s, (through pipeline) with an objective of 70 kg/s per well 

4 wells available for injection (1 well in P18‐4; 3 wells in P18‐2). The optional injection wells P18‐2A6 and P18‐6A7 were added in the final stage of this study, hence no detailed FAS modelling has been done for these two wells. Therefore, the generalized completion and well design have been applied for both the P18‐2A6 and P18‐6A7. The recommendation is to update the flow assurance study including these two additional wells to understand the impact on completion and well design due to differences in reservoir properties and injectivity. 

Pressure: 

Reservoir pressure prior to start of CO2 injection: 20 bar (note: The P18‐2 and P18‐4 reservoir pressures are now around 22 bar and the P18‐6 reservoir pressure is around 46 bar)  

Reservoir pressure end of CO2 injection: 340 bar 

Minimum pipeline pressure 60 bar (minimum discharge pressure compressor) 

Other constraints such as tubing vibrations; thermal/mass flow rate constraints for reservoir, thermal gradients in well (radial and axial) 

 In order to stay within the above operating boundaries, the flow assurance study has shown that a completion with primarily 5 1/2" tubing is the most optimal. When using a smaller diameter tubing it will be easier to meet the temperature constraints at the topside. On the other hand, it will lead to higher wellhead pressures which implicates that at the final reservoir pressure the desired injection rates cannot be met. When modelling the larger diameter tubing it became apparent that it will be very difficult to meet the temperature requirements at low reservoir temperatures. (Flow assurance study presentation January 31th 2019, Stefan Belfroid, TNO) 

During start‐up and shut‐in, the temperatures of the CO2 in the well can drop even further. The worst case that is modelled for the flow assurance study is an Emergency Shut Down (ESD) with 20 bar reservoir pressure, below is a graph with the resulting minimum temperature and lowest mean temperature of the CO2. When the reservoir pressure increases with injection this temperature effect will reduce and the well will stay at higher temperatures.  

Page 8: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 8 of 22

Figure 1 Static temperature and CO2 temperature profiles during an ESD 

Downhole monitoring The flow assurance modelling has shown that the wellhead pressure will vary very little with increasing reservoir pressure, refer to appendix B for a graph (Flow assurance study presentation January 31th 2019, Stefan Belfroid, TNO). It is therefore recommended to install a downhole pressure gauge to allow for accurate monitoring of the reservoir pressure. Given the large expected temperature variations and the big impact that this will have on the completion it is recommended to install a continuous array of temperature measurements over the tubing to confirm the results of modelling and aid in operating the well in the design envelope. The data gathered in the Porthos project may also be beneficial for future CO2 storage projects.  

2.5. Well integrity 

A well integrity review has been performed by TNO (Well integrity study presentation January 31th 2019, Paul Hopmans, TNO NB: This review did not consider the P18‐6A7 well as a potential injector). The currently installed completions have a retrievable packer which is not deemed suitable for the expected temperature variations and will therefore need to be replaced. The main conclusion of this review, on the well materials that will stay in the well, were: 

No major operational issues during cementing of the production casings and liners which are located at the proposed packer setting area. 

Most of the cement bond logs that were run over the production liners showed poor bonding.  

No annular pressures have been observed during the productive life of the wells except for the P18‐2A5 well where there is a sustained pressure slowly building on the A‐annulus. 

The formation integrity tests done after cementing show competent casing shoes whereby all casing shoes from the 13 3/8” down can cope with the anticipated maximum CO2 pressure. 

Page 9: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 9 of 22

The P18‐2A6 well is a multilateral well, consisting of a lateral which will need to be decommissioned and a mother bore which could be considered as an injection candidate, this will involve retrieving a whipstock and isolation of the lateral section.  

 A Taqa quick scan of the P18‐6A7 well integrity has revealed the following: 

The completion has a permanent packer, in the define phase it could be considered to perform a detailed assessment including a flow assurance study to check whether the completion could be used as is including potential temperature limitations. 

FIT’s of the 9 5/8” casing (Holland Marl) down are of sufficient strength to cope with anticipated maximum CO2 pressure. 

There are no abnormal annular pressures recorded.  No CBL’s were run, the 13 3/8” primary cement job failed due to a blocked bottom plug / float 

collar, the result of subsequent squeeze jobs was poor. Losses were observed during the 9 5/8” casing cement job, the calculated top of cement is 

inside the 13 3/8” shoe.

Losses were observed during the 7” liner cement job, the theoretical top of cement was estimated at 118 m below the TOL (spacer returns observed), the liner was rotated during the first part of the displacement. 

During the 5” liner cement job the top wiper plug was bumped 2.2 m3 early, it was thought that cement had bypassed the wiper plug, therefore only spacer and no cement was observed above the TOL, rotation not reported. 

 When the annular cement of a production liner is deemed inadequate it could be considered to place the packer above the liner across a caprock in an area with good annulus cement. It is therefore not expected that the current cement status will be an issue for CO2 injection. However, the prognosed quite extreme temperature cycles may influence the cement bond quality during the well life. A study is being performed by TNO on the effect of the temperature cycles on the cement bond quality, it is advised to take the study results along in the define phase. Remediation for a poor annulus cement is discussed in the design requirements section (section 3.4). 

Page 10: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 10 of 22

3. DESIGN REQUIREMENTS

3.1. Completion configuration 

The Flow assurance study shows that 5 1/2" is the optimal tubing size for the injection wells. This will fit in the top part of all injection wells since the top part of the wells consist of 9 5/8” casing. Three of the wells have a 7” liner above the reservoir, 2 wells have a 5” liner over the reservoir and the P18‐6A7 has a predrilled 3 1/2” liner over the reservoir. The P18‐2A6 well will require decommissioning of the lateral and isolation of the lateral from the motherbore. Various solutions exist which could be used, this is not expected to lead to a reduction in ID smaller than that of the ID of a 7” liner. In the define phase the benefits of using a system with a larger ID which could enable using a larger tubing to deeper in the well could be weighed against potential downsides of such a solution including potential extra cost. Below is a table with the depth of the Top Of Liners (TOL) and the top of the perforations.  

  P18‐2A1  P18‐2A3  P18‐2A5  P18‐4A2  P18‐2A6  P18‐6A7 

7” TOL [m]  3405  2672 3594 3924 *2200  2435

5” TOL [m]  N/A  3785 4402 N/A N/A  3761

4 1/2" TOL [m]  N/A  N/A N/A N/A N/A  N/A

Top of perforations [m] 

3575  4070 4796 4083 4488  **4953

* Estimated top of a to be installed scab liner over the window, this could be 7” scab liner or a different size scab liner/patch, this will be decided on in the define phase ** Predrilled holes in 3 1/2” liner  For the wells with a 7” liner over the reservoir there is an opportunity to install the packer across the caprock just above the perforations in case the annulus cement at that level is deemed competent (refer to appendix C for an example completion diagram). This will reduce the amount of liner and casing that is in contact with CO2. It will also facilitate the final decommissioning of the well as the packer with a plug installed can be used to isolate the upper part of the well from the reservoir and it can serve as a base for the cement plug. This will reduce decommissioning risks and cost whilst still allowing to set a full‐bore cement plug against the caprock (for more details on the decommissioning please refer to the Porthos basis of decommissioning design). The maximum tubing size that will fit in a 7” liner is 4 1/2” when a pressure/temperature monitoring cable is run with the tubing.  For the wells with a 5” liner the packer will need to be installed as deep as possible in the 7” liner across a suitable caprock (refer to appendix D for an example completion diagram). For the P18‐6A7 well this means that the packer will be installed just above the caprock (Altena shales). This is not the preferred place since it could allow leakage above the caprock without a possibility to monitor it. However, it could be considered to stab the tailpipe of the completion into the 5” TOL to add an additional barrier to the 7” liner and to monitor the condition of the barrier by regular risk based corrosion logs. Installing a packer in the 5” liner will result in a too small tubing size to allow for the required injection rates. This means that the 5” liners will be exposed to CO2. For the P18‐6A7 well it may be preferred to install a deeper packer and to accept a reduced injection capacity. In the define phase, it should be confirmed with Flow Assurance calculations that the depth of the packers will not form a too big restriction for injection, this will be an iterative process. Next to pressure and temperature effects, the maximum allowed velocity in the well components to avoid erosion should be considered.  An example of the proposed configurations with a 7” liner and with a 7” & 5” liner can be found in appendix C and D.  Packer It is preferred to install a completion whereby the tubing is fixated to a packer. Given the relatively large impact of pressure fluctuations on well temperatures in CO2 injection wells it is advised to perform flow assurance calculations based on the final injection parameters for the operating envelope of each specific well. The outcome from the flow assurance study can be used as input to calculate the 

Page 11: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 11 of 22

loads on the packer and as such to validate the final packer design. For the wells where the packer can be placed just above the perforations permanent packers may be used since these can be left downhole during decommissioning of the wells. However, in case of an unexpected workover due to issues with the new completion this would lead to extra workover cost compared to a retrievable packer.  For wells where the packers cannot be set close enough to the caprock for instance due to poor casing quality, poor annulus cement or unsuitable production liner size it is advised to source retrievable packers with a cut to retrieve option for ease of later decommissioning. In case no retrievable packers of sufficient strength can be sourced, a permanent packer can be installed but this will lead to extra time spend on milling of the packer during the final decommissioning of the wells.  The extreme temperature variations that are modelled in the Flow Assurance study will lead to very high loads on the tubing and packer and will lead to strict specifications for the packer and tubing.   In case the detailed modelling shows that the use of a standard packer completion is not an option it could be considered to select a system where the tubing is allowed to slide in a sealbore. The downside of this option is that given the frequent movement past the seals this is more susceptible to leakages.  Subsurface safety valve The use of a Surface Controlled SubSurface Safety Valve (TRSCSSSV) is mandatory for self‐flowing wells. This safetyvalve should be suitable for the low anticipated temperatures in the well, it is however expected to be difficult to find a standard safetyvalve in the market that fulfils this requirement, especially in the top section which is expected to cool down the most, it could be considered to place the safteyvalve deep in the well where the temperatures will be higher. Next to that the control line fluid may be susceptible to freezing which will hamper the functionality of the TRSCSSSV. Therefore, it could be considered to use an injection valve rather than a TRSCSSSV or a combination of both. An injection valve will always close directly in case of an uncontrolled release whereas a TRSCSSSV closes after a sequence of valves is closed or hydraulic pressure is lost. A downside of injection valves is that they may be more susceptible to erosion and that they are not controllable from surface. A dispensation will need to be requested from the regulator for not installing a TRSCSSSV. The pro’s and cons of both options and the effect of the low CO2 temperature on the control line fluid needs to be investigated in the define phase. A deep‐set injection valve which gives backpressure to the system may aid in reducing the ESD loads on the well, this should be investigated in the Flow Assurance study.  Downhole monitoring In order to get the full temperature profile of the wells a fibre optic Distributed Temperature Sensor (DTS) system could be installed in combination with a downhole pressure gauge. This will lead to restrictions on the tubing size at the bottom of the wells compared to a design where no downhole monitoring is required. 

3.2. Materials 

Tubulars For the flow wet tubulars Cr13 material will be required to cope with the proposed CO2 specification, higher quality super Cr13 variants could be required to cope with the very low temperature requirements. In the define phase this should be discussed with OCTG (tubing) suppliers in order to prepare the material specification.  Casing & Liners The casing designs of the injector wells will need to be checked against the CO2 injection load cases. As part of this wellhead movement should be assessed and checked for interference with the platform structure and facilities.  Wellhead & X‐tree The existing wellhead and tree have not been designed (Temperature class PU ‐20°C to 121 °C) to cope 

Page 12: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 12 of 22

with the very low expected temperatures. The flow wet components such as the tubing hanger and the X‐tree can be changed out, the new equipment will need to be ordered to artic specification (API temperature class KU ‐60°C to 121 °C). It will be very difficult to change out the wellhead equipment of the casings, it should however be checked what the temperature effect will be on this equipment and whether the equipment is suitable for this. Also the use of heat tracing could be considered. Refer to Appendix E for wellhead and tree setup for the P18‐A wells. Please note that the wellhead & tree of the P18‐6A7 well is different than that of the other P18 wellhead and trees.  Elastomers If elastomers are used in the packer, wellhead or subsurface safety valve these need to be checked against compatibility with the CO2 specification

3.3. Annulus fluids 

Standard oil and gas wells in the Netherlands are completed with a completion brine in the A‐annulus, 

however in these wells the expected low temperatures may lead to freezing of the brine. Also, the 

outer annuli could be exposed to freezing conditions. In the define phase, the temperature effects on 

the annulus fluids should be modelled. In case it is apparent that the A‐annulus will freeze it should be 

considered to add anti‐freezing agents, use an oil‐based annulus fluid and/or nitrogen blanket in the 

annulus. The use of a nitrogen blanket in the annulus may have the additional benefit of insulation to 

the outer casing strings and will lead to a continuous overpressure which will allow continuously 

verification of the barrier envelope. This could be an option in case modelling shows that the outer 

annuli will be susceptible to freezing conditions since it is not possible to change‐out the fluids that are 

present in the outer annuli. Alternatively, the operating envelope would need to be reduced in order to 

keep the temperatures of the annuli within acceptable boundaries. Introducing a nitrogen blanket will 

however make the completion installation a bit more complex and may introduce a potential leak path 

in the completion.  

3.4. Production Liner & Casing cement 

The preferred setting depth of the production packer is as close to the perforations as possible where 

the well geometry allows this. This means that the production liners and the annulus cement will be 

part of the primary barrier envelope. The CBL’s that were done on the production liners just after 

installation showed poor bonding for most of the wells. However, the isolation of the liner cement is 

believed to be sufficient for CO2 injection when the cement job parameters were good and no annulus 

pressures have been observed during the producing life of the wells. It could be considered to 

reinterpret the existing CBL’s to gain extra confidence in the cement bond logs. 

Alternatively the production packer could be installed in the production casing when the cement job parameters were good, a FIT/LOT showed that the shoe is of sufficient strength to cope with the maximum anticipated pressure and no annulus pressures have been observed during the producing life of the wells. In case that no isolation is present remedial actions could be considered. The best way to remediate a poor cement job would be to decommission the existing production liner with a Full‐bore Formation Plug against the caprock and sidetrack back into the reservoir to install a new production liner, this will be an expensive solution.  

3.5. Logging requirements 

Several logs could be run before running the new completion to verify the condition of the well. During the injection phase production logging may be required to assess the well and the injection performance. As per ISO 27914:2017 standard prior to conversion for CO2 storage, the long‐string casing shall be inspected and tested for integrity over its full length by obtaining and evaluating cement integrity logs and running and evaluating a casing inspection log for casing corrosion or damage.  

Page 13: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 13 of 22

Cement bond logs A cement bond is typically used during the construction of a new well when there were operational issues with the cementation to check if there is a cement bond behind the casing. Please note however that it is the experience of Taqa that CBL results can be misleading, we have had examples of well sections with poor CBL’s and good isolation and well sections with good CBL’s where there was an obvious leak path. It is therefore of importance to ensure that the planned cement evaluation tool is suitable for the specific cement/casing situation and that prior to running the tool the evaluation and decision criteria are established.    Corrosion logs Corrosion logs will be run as per the ISO standard. It is important to ensure that the minimum required wall thickness is known prior to running the tools and that the evaluation and decision criteria are established.  Special focus areas of the corrosion logs are the proposed packer setting area in the production liner since in cases where this area was exposed to well fluids containing a minor amount of CO2 during the production life and the P18‐2A5 well where irregular A‐annulus behaviour has been observed during its productive life.  Production logs When for some wells there are doubts on reservoir performance (injectivity) a production log like an (M)PLT could be considered. The CCS ISO standards also mentions that a baseline saturation log should be obtained to establish gas saturations near the wellbore, the benefits of such a log should be discussed with the subsurface team in the define phase. 

3.6. Clean‐out  

Before running a new completion and potentially some logs it is advised to perform a clean‐out run with casing scrapers to remove scales, debris and plugging material from the well kill from the casing walls. 

   

Page 14: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 14 of 22

 

4. CONCLUSIONS AND RECOMMENDATIONS

The 4 initially proposed P18‐2 and P18‐4 gas wells are suitable to convert to CO2 injection wells. 

The P18‐2A6 well is a multilateral well, consisting of a lateral which will need to be decommissioned and a mother bore which could be considered as an injection candidate, this will involve retrieving a whipstock and isolation of the lateral section.  

The P18‐6A7 well could be considered as an injection candidate, it does have a different well architecture and wellhead system than the other P18‐A wells which will lead to variations in the design. 

For P18‐2A6 and P18‐6A7 a flow assurance study needs to be done to understand the impact on completion and well design due to differences in reservoir properties and injectivity. 

The large variation in modelled injection temperature profiles will lead to large loads on the tubing and packer and will require strict specifications and lead to extra cost and longer lead times 

The expected extreme low temperatures will lead to strict specifications for materials and lead to extra cost and longer lead times 

The cyclic temperature loading on the existing cement should be taken into account in the detailed design. 

It is recommended to review options to reduce the temperature loads in order to be able to use a more cost‐effective design. 

It is recommended to prepare a flow assurance model for the detailed completion of each well and to update this model with the actual planned start and end reservoir pressures.  

The completions should cater for production logging during the operational stage 

The casing designs of the injector wells will need to be checked against the CO2 injection load cases. 

Temperature limitations of well elements that cannot be changed‐out during a workover such as annulus fluids and wellhead seals must be evaluated as they might impact the operational boundary conditions. 

Wellhead movement should be assessed and checked for interference with the platform structure and facilities. 

In the define phase start engaging equipment vendors for completion items & wellhead / xmas tree to share the project requirements and issue statement of requirements allowing for expert input on dedicated equipment specifications. 

For time and cost estimates please refer to the separate “Porthos CCS P18‐2 well options cost estimates” document (ECM#198432) 

   

Page 15: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 15 of 22

 

5. APPENDICES

5.1. Appendix A: generalized stratigraphy of the P18 area 

The Mainbuntsandstein formation “Bunter” in Taqa nomenclature is the only stratigraphic interval in the P18a,c area  that has producing gas fields. In the nearby P15 production license, the Rijswijk member “Rijn” in Taqa nomenclature and Delft sandstone member “Delfland” in Taqa nomenclature may contain oil.    Generalised Stratigraphy of the P18 wells (based on the vertical P18‐2 well): 

M TVDSS (+‐) 

Tertiary 

Upper North Sea 

Undifferentiated  0  The North Sea Group, which consists of siliciclastic sediments. Three major aquifers cam be distinguish; the Dongen sand, a basal transgressive sandstone, and the marine Brussels sand and the Berg sand  

Middle North Sea 

Boom Clay  417

Berg Sand  456 

Lower North Sea 

Asse Clay  465 

Brussel sand  489 

Ieper Clay  530 

Dongen sand  637 

Landen Clay  870

Upper 

Cretaceous

Chalk 

Ommelanden Formation  920  Upper Cretaceous Chalk Group, which consist at the base of the formation of sands and marls and a thick layer (900 m) of limestones (Chalk). The distribution of the basal Texel Greensand is limited to the southern basin margin. 

Texel Marlstone Member  1785 

Texel Greensand Member  1828 

Lower Cretaceous  

Rijn

land 

Holland 

Upper Holland Marl Member  1876  Lower Cretaceous Rijnland Group, which consist of marine sandstones, shales and marls. At the base of the Rijnland Group, the Rijn / Rijswijk sandstone is present. This sandstone is widely distributed in the P18 area. It is also known for its oil (P15) and gas (onshore) accumulations within the West Netherlands Basin. The Rijnland sandstones are interpreted as transgressive sheet sands, with good lateral continuity. The Berkel and IJsselmonde are interpreted as coastal barriers with less lateral continuity. It must be assumed that the Berkel Sand is in connection with the Rijswijk/Rijn member. The IJsselmonde, Berkel and Rijswijk/ Rijn share the same seal which is the Vlieland Claystone and Lower Holland Marl Member. In the upper part of the Rijnland succession, the Holland Greensand is present. It consists of argillaceous sands and silts. The distribution is limited to the southern margin of the West Netherlands Basin. Although the Holland Greensand has good lateral continuity, permeability is in general low 

Middle Holland Claystone Member  1996 

Holland Greensand Member 2056

Lower Holland Marl Member  2078 

Vlieland 

Vlieland Claystone Formation  2190 

IJsselmonde Sandstone Member  2416 

IJsselmonde Claystone Member  2436 

Berkel Sandstone Member  2486 

Berkel Sand‐Claystone Member 2496

Rijswijk Sandstone Member (Rijn in TAQA Nomenclature) 

2529 

Jurassic 

Schieland 

Delflan

d  Rodenrijs Claystone Member 2544 The Schieland Group, which consists of shales and 

(stacked) channel sands of the Nieuwekerk Fm. (Delft sandstone equivalent). The lateral continuity of the individual sandbodies (thickness 2‐5m) is probably very limited.  

Delft Sandstone Member (“Delfland” in Taqa nomenclature) 

2562 

Altena 

Alblasserdam Member  2567  Directly above the primary seal, a thick succession of marine claystones, siltstones and marls is present. These sediments have excellent sealing quality and belong the Altena Group (Jurassic age). 

Lower Werkendam Member  2573 

Page 16: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 16 of 22

Posidonia Shale Formation  2747  In the P18‐02 well, the Altena Group has a thickness of approx. 500 m. 

Aalburg Formation  2778 

Sleen Formation  3036 

Upper Triassic 

Upper Germanic Triassic 

Upper Keuper Claystone Member  3077  The primary seal to the P18 reservoirs is formed by siltstones, claystones, evaporites and dolostones of the Solling Claystone Member, the Röt Formation, the Muschelkalk Formation, and the Keuper Formation that discomformably overlie the reservoir. The Solling Claystone Member consists of red, green and locally grey claystones that where deposited in a lacustrine setting just after the tectonic movements of Hardegsen phase during a major transgression (Geluk et al., 1996). It is the first laterally extensive claystone above the reservoir rocks of the Main Buntsandstein. In well P18‐02, it has a thickness of approx. 5 m (Fig. 11). The Röt Formation consists of thin‐bedded claystones, and is approx. 40 m thick. The Muschelkalk Formation consists of claystones, dolomites, and evaporates, and is approx. 70 m thick. All these rocks contain variable amounts of nodular anhydrite cementation (Spain and Conrad, 1997). The Keuper Formation consists of claystones intercalated with zones of anhydrite and gypsum, and is approx. 40 m thick. In total, the thickness of the primary seal in well P18‐02 is approx. 155 m. 

Dolomitic Keuper Member 3086

Red Keuper Claystone Member 3111

Upper Muschelkalk Member  3123 

Middle Muschelkalk Marl Member  3145 

Muschelkalk Evaporite Member  3158 

Lower Muschelkalk Member  3165 

Röt Claystone Member  3208

Solling Claystone Member 3228

Rot Sandstone / Basal Solling Sandstone 

3226   Sandstone 

Lower Triassic 

Lower Germanic Triassic  M

ain Buntsan

dstein 

“Bunter” 

Hardegsen Formation 3239 Dominated by reservoir‐quality sandstones, depleted gas accumulation 

Detfurth Claystone Member 

3308 

Lower Detfurth Sandstone Member 

3338 

Volpriehausen Clay‐Siltstone Member 

3349 

Lower Volpriehausen Sandstone Member 

3404 

Rogenstein Member  3454 

Main Claystone Member  3547

Permian 

Zechstein 

Zechstein Upper Claystone Formation 

3595    

Z1 Fringe Sandstone Member  3605    

Z1 Middle Claystone Member  3618    

Rotliegend Slochteren Formation  3622    

Caboniferous Ruurlo Formation  3645    

    

Page 17: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 17 of 22

 

5.2. Appendix B: Static wellhead and reservoir pressures for CO2 injection well 

 

 Source Flow assurance study presentation January 31th 2019, Stefan Belfroid, TNO   

Page 18: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 18 of 22

5.3. Appendix C: Example CO2 injection completion P18‐4A2 well 

 

 

Page 19: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 19 of 22

5.4. Appendix D: Example CO2 injection completion P18‐2A3 well 

 

 

Page 20: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 20 of 22

5.5. Appendix E: Wellhead and Tree  

Generic setup P18‐A wells 

  

Page 21: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 21 of 22

Part  Connection  Rating (psi) 

Cameron 5 1/8” 5000psi Production tree with manual swab upper and lower master valves and hydraulically actuated wing valve 

9” FMC Speedloc  5000 

FMC Spacer Spool  13 5/8 FMC Speedloc x  9”   FMC Speedloc 

5000 

FMC 13 5/8” x 13 5/8” Tubing Head Spool  13 5/8” FMC Speedloc x 13 5/8” FMC Speedloc 

5000 

FMC 20 ¾” x 13 5/8” Intermediate Casing Head Housing 

20 ¾” FMC Speedloc x 13 5/8” FMC Speedloc  5000 

FMC  Sliploc type casing head  20 ¾” FMC Speedloc  3000  

 

   

Page 22: PORTHOS Basis of completion design - Commissiemer.nl

 

Page 22 of 22

P18‐6A7 wellhead and tree   

  

Part  Connection  Rating (psi) 

Cameron 4 1/16” 6500psi production tree with manual swab upper and lower master valves and hydraulically actuated wing valve 

13 5/8” Cameron Fastlock  6500 

Cameron Spacer Spool  13 5/8” Fastlock x 13 5/8” Fastlock  6500 

Cameron 13 5/8” x 13 5/8” SSMC dual stage wellhead 

13 5/8” Cameron Fastlock x 20 3/4” Cameron Fastlock 

5000 

X‐over from Cameron to FMC  20 ¾” FMC Speedloc x 20 3/4” FMC Speedloc  3000 

FMC Sliploc type casing head  20 ¾” FMC Speedloc  3000