Upload
jawadazam
View
217
Download
0
Embed Size (px)
Citation preview
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 1/14
Portable and Distributed Power for TelecommunicationsJimmy Godby
Telecom Power Consultants
PO Box 271004
Littleton, CO 80127
1
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 2/14
Portable and Distributed power for Telecommunications
Contents 1. INTRODUCTION ................................................................................................................... 3 2. INTEGRATED POWER ......................................................................................................... 3
A. RECTIFIERS ................................................................................................................... 4 B. BATTERIES .................................................................................................................... 4
3. VOLTAGE CONSIDERATIONS........................................................................................ 5 4. BATTERY RESERVE .......................................................................................................... 5 5. DISTRIBUTION.................................................................................................................... 6 SECTION 2: DISTRIBUTED ARCHITECTURE POWER .......................................................... 6
A. BATTERIES ................................................................................................................... 7 B. LOAD ALGORITHMS ................................................................................................. 7 C. DISTRIBUTED BAY LOAD REQUIREMENTS ...................................................... 8 D. BAYS TO BE FED ......................................................................................................... 8 E. DISTRIBUTION ............................................................................................................ 9 F. RECTIFIERS ............................................................................................................... 10 G. AC CABLE ROUTING ............................................................................................... 11 H. GROUNDING FOR DISTRIBUTED POWER ........................................................ 12 I. CONTROLLER ............................................................................................................... 12
6. DISTRIBUTED POWER CONSIDERATIONS .............................................................. 13
2
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 3/14
1. INTRODUCTION This document discusses distributed power for telecommunications.
In today’s rapidly changing environment, there is an ever increasing need for a
distributed power solution. With today’s available technology in both DC power
plants and batteries, there is a real economical ability to provide these unique
solutions. The implementation of a “Distributed Power Solution” is a solution that
“grows” distributed architecture power as opposed to BDFBs in a traditional
central office. This session will provide insight into the engineering rational behind
this solution. These will include space, capacity, and size considerations for the AC
required, DC plant with distribution, and associated batteries.
This presentation will discuss two aspects of each of the above solutions. The first
aspect is the application. When would you use a distributed architecture bay, where
should you use it, and how would you implement the solution? The second aspect
will tackle design and sizing of that solution.
2. INTEGRATED POWER
Several suppliers have small (one or two shelf switch mode rectifier plants. For the
purpose of this document, the various power systems will be labeled as Micro
Power Systems (MPS) for the duration of this document. The MPS is the heart of
an integrated power solution for distributed architecture. The MPS provides control
and rectification – along with intelligent communication via the customer’s
intranet for the distributed architecture plant.
In keeping with the tradition of all true power engineers and technicians, the load is
just that. It is “something” hanging off the end of the power plant. In these
discussions, the nature of the load is only important as to the answer to these
questions: What is the acceptable voltage range of all of the components of the
load to be fed from this power plant? What are the acceptable parameters of the
DC output (noise, ripple, etc)? What are the acceptable parameters of feedback onthe AC CIRCUITS?
Of course, to be a complete DC power plant, there must be some form of energy
reserve. That reserve will also be discussed.
3
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 4/14
A. RECTIFIERS The heart of a DC plat is the rectifier. As a user, there are several primary
considerations when looking for a rectifier. They include conformation to standard
requirements (NEBS – GR63 CORE from Telcordia), NEC requirements, UL
listing or tested, etc. Exactly which requirements are to be considered and how
they are applied are beyond the scope of this presentation and will not be discussed
further.
The Voltage Requirements are actually on both sides of the rectifier: First, what
AC voltage levels are going to be required? (208, or 240 VAC, and phase – single
or 3 phase AC service.) 480 VAC is not a viable solution for this small
application.
On the output side, do you need 52.08 or 52.80 VDC to match the existingcentralized plant, or can you use a 54 VDC solution as the equipment fed from the
distributed architecture bay is isolated from the central office bulk power supply.
Of course rectifier density is the real key to viability of these applications. When
determining the maximum rectifier size, you must consider whether you have one
or several rectifiers per shelf to be powered from the same AC feed. The two
parameters here are the input circuit breaker size and the ac cable size. Done
incorrectly, the input could call for a non standard AC breaker which will make
your AC feed much more expensive. The second consideration is the AC cablesize. When large AC feeds are required in very limited space, just running the AC
cable can be a real issue. The MPS shelf is designed to eliminate the problems
associated with routing and connecting the AC input cables.
B. BATTERIES
The first technology to be looked at is Valve Regulated Lead Acid (VRLA)
batteries. This is a “known item”. These cells require periodic testing and physical
inspection, they have a much higher energy density that traditional “flooded”
batteries, and have a predictable failure mechanism. (They are prone to thermalrunaway when subjected to high temperatures. This can result in a release of
hydrogen sulfide and be hazardous to people and equipment.)
The real problem with VRLA batteries is that they are not maintenance free, but
maintenance proof. Placing this technology in a distributed architecture bay would
result in an embedded technology that would require quarterly maintenance visits
4
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 5/14
and frequent battery replacement. Furthermore, due to the required maximum bay
width and depth in equipment line-ups, VRLA technology would require the use of
smaller capacity batteries and two bays of these batteries to provide the required
capacity where one bay of lithium batteries would suffice.
NICAD technology is mentioned here just to observe that the technology is not
being ignored. At the same time, the technology is not being considered. Cost and
disposal considerations are the primary reasons that the NICAD technology is not
being discussed.
3. VOLTAGE CONSIDERATIONS
The real issue here is that flooded lead acid batteries that have been traditionally
used in telecommunications float service operate between 52.08 and 52.8 volts per
string. Where VRLA batteries are used in telecommunications, the power plant isdesigned to float at around 54.4 volts.
The concern is not at the minimum volts per string, but the normal float voltage of
the plant. This concern is due solely to the fact that some older equipment will not
work at the 54 volt level... Specifically some of the older switch technologies are
upper voltage level limited at 53 volts.
If all of your equipment is less than 10 years old, the higher voltage is probably not
an issue. However, it is necessary to ensure that all older equipment will function
at these higher voltages before any transition can be considered.
4. BATTERY RESERVE
Battery reserve is mentioned here because it is a critical engineering element. Short
battery reserves can be acceptable with an auto start/auto transfer stand by
engine/alternator for the essential loads at the site.
With an engine/alternator and 3 or 4 hours of battery reserve, we will see that it is
possible to provide all of the power (rectification) needed, the distribution, and thebattery reserve required in a relatively small space. It the case of distributed power,
that would be all of the equipment in a single bay as opposed to a bay for the plant
and an additional bay for batteries.
Reality here is that distributed power is generally not going to be a viable option in
a Community Dial Office (CDO) environment. Due to the small size of CDOs,
5
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 6/14
generally if there is an existing power plant, there are no economics in the
distributed architecture technology because the cost effectiveness of this solution
only comes in to play with long DC cable runs to BDFBs. The solution in a small
site would be to replace the traditional power plant with a one or two bay
distributed architecture plant and “recover” the space currently occupied by the
traditional plant and it’s associated flooded batteries.
5. DISTRIBUTION
The decision to use fuses or breakers is a customer preference. Breakers can be
reset, but over time may weaken and need to be replaced. When a fuse fails it
always needs to be replaced so the “deterioration” clock starts over every time a
fuse is replaced.
Fuse/breaker positions for distributed architecture will be in the 0 to 70 amp range.This will be discussed more thoroughly later.
SECTION 2: DISTRIBUTED ARCHITECTURE POWER Distributed Architecture is essentially a power plant that exists in the equipment
space that a traditional BDFB would. It will have all of the components of a
complete power plant – batteries, distribution, rectifier, and controller.
The following will discuss each of these and develop a “typical size” for the
distributed architecture power bay.
This type of bay was originally proposed by Ed Silverman in the early 1980s.
However, the VRLA batteries available at the time were not reliable enough nor
did they have the power density required for this solution.
The key developments that make this approach practical are the highly dense MPS
rectifier plant, lithium batteries.
The critical physical requirement for this bay is that it be no deeper than 15 inchesso that the bay will fit in a standard relay rack aisle. In addition (for the American
RBOC market), the bay should be 23” wide.
As we develop the distributed architecture model, we need to thank Curtis Ashton
from Qwest Communications who contributed the fact that the “average” transport
equipment bay draws approximately 7.5 amps so that each A or B load to any bay
6
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 7/14
will be approximately 4 amps. (NOTE: This low drain is largely due to the fact that
there are a lot of vacant slots in each bay. If a site has an appreciably higher drain
per bay, a proportionally smaller number of bays will be fed than described below.)
A. BATTERIES
Since the batteries are a critical element, and Lithium batteries are required in
order for this solution to be maintainable, because of rapid technology advances, it
will be necessary for the reader to research lithium battery options.
Because of the circuit density of the rectifier plant used, the distributed architecture
bay will have approximately 2/3s of the frame space available for batteries. The
capacity required will need to fit in this 2/3 of a bay in order for distributed
architecture to be a viable solution.
B. LOAD ALGORITHMS
Earlier I stated that Curtis Ashton of Qwest provided informaiton that the average
load on a typical toll bay in a RBOC central office was 7 ½ amps. This average
was derived across an entire central office where a large number of bays with
various loads are averaged. This accounts for areas where a bay or several bays
may pull 1 amp or less added with bays that draw 40 amps. With a centralized
plant, if the load increases in one are of the building while decreasing in another,
the net result is a wash to the power plant.
With distributed power plant architecture, it is essential to look at a smaller
“universe”. It is also critical to look at growth patterns in the equipment to be
served. If the load in an office moves from one area to another, then one distributed
plant can be essentially deloaded while another is overloaded. By the same token,
if the distributed architecture plant is designed with a 200 amp maximum capacity
and say 20 bays, if 5 bays draw 40 amps each, it will be necessary to place an
additional distributed architecture power plant(s). (More about this later.)
The engineering questions that come out of this situation are: 1) Does bay spaceneed to be reserved for additional distributed architecture power bays? – 2) If so,
how much space should be reserved for additional power?
7
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 8/14
C. DISTRIBUTED BAY LOAD REQUIREMENTS
A key element to the decision of Distributed Power or not is the load that each bay
will draw from the plant. This load can be measured as the Average and Worst
Case drains as shown in the slide. The question that you have to ask yourself is “Is
the drain that I see on this bay now all that I can expect on the bay? Some
“specialized bays are required for certain equipment types. The office might need
only one or two shelves of this equipment, so although the bay has a capacity of 20
or 30 amps the actual load may never exceed 5 amps. Other bays may start with
only one or two amps of load and then eventually blossom to 40 amps. (If a
distribution bay is gong to draw 60 or more amps, it would probably be more
efficient to feed that bay directly from the centralized power plant provided
capacity and distribution fuse/breaker space exists on the centralized plant.
As the decision is made to use distributed power, careful consideration must bemade to determine not only the initial load on the power plant from the bay, but
also the projected load over the life of the plant.
To that end, for this section we will assume that each bay draws a total of 10 amps
– 5 amps each for the A and B feeds. This should be a safe average in the smaller
universe to be served by the distributed power plant.
D. BAYS TO BE FED
The goal of this technology is to provide the most economical power. To that end,
it was first necessary to determine the amount of battery capacity available in 2/3
of a distributed architecture power bay. As the battery technologies being
discussed are still in development, the battery capacity of approximately 200 amps
is available with the lithium batteries that have been researched.
The second step was to determine the amount of current drawn by each bay. Based
on estimates above, for the purpose of this discussion we will use 5 amps each for
the A and B loads on the equipment bays for a total of 10 amps per equipment bay.
W we will use a battery capacity of 200 amps for 4 hours. From the above, we can
calculate that the 200 amps will provide power to 20 bays or to the A or B side of
40 bays.
8
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 9/14
E. DISTRIBUTION
Since this is a single bay solution, there is limited distribution space. In a 7 foot
relay rack, when you remove the top and bottom space for iron work, there are 6 ½
feet of space available for equipment. Reserving 2/3 of that space for batteries and
3 inches for the DC plant leaves approximately 1 ½ feet of space for distribution
The decision to use fuse or circuit breaker distribution again is a decision specific
to the customer. However, the decision can be made easier now because there are
panels available that will accept either.
Distribution fuses and breakers are sized to protect the cable at maximum load to
the bay. These fuse/breakers are generally 0 to 60 amps.
There are several manufacturers that can provide the required distribution. Anacceptable solution will provide a total of 44 zero to seventy amp fuse positions.
NOTE: Distributed architecture provides a significant savings in DC distribution
cable over a centralized power solution. There are two areas of savings. First, the
need for large cables from the centralized power plant to the BDFB does not exist.
Second, and providing an even greater savings, is the cable from the distributed
power plant to the load. As was discussed earlier, there could be as little as a .5 V
drop from the distributed plant to the load. However, this requires relatively large
cable, and is not necessary. Because of the discharge characteristics of the Lithium
battery and the fact that the “load” equipment will work down to 42 volts, it is
possible to use much smaller cable (and smaller fuses) from the distributed
architecture power plant to the load than would allowable from the BDFB solution.
This results in a significant savings in cable with distributed architecture. (Fuse
prices do not generally vary by size so there is no real dollar savings there.
However, care must be taken to correctly size the fuses.)
All traditional BDFBs are rear access. With this configuration, the fuse or breaker
is in the front while cabling is done to the rear. There are three things that happen
with traditional BDFBs. First, the DC feeder cable and all distribution cables areall wired in the back. This can result in cable congestion and routing problems with
a large number of loads in a BDFB. Second, with the cable termination in the back
and the fuse or breaker position in the front there is a possibility of misidentifying
a position and placing the wrong size fuse or breaker resulting in a power failure to
equipment when the only problem is the fuse is too small. Third, this
configuration requires rear access to the bay.
9
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 10/14
Distributed architecture frames can be produced that are 100% front access. This
allows the user to place the bay against the wall if so desired. Also, with front
access, the cable is terminated directly above and on the same side as the
distribution fuse eliminating the possibility of placing the wrong size fuse on a
power feed. On the same lines, since there is no DC input to the distributed
architecture bay, and only a maximum of 40 outputs, DC cable congestion in the
bay is eliminated.
F. RECTIFIERS
Our original goal was to develop a distributed architecture bay. Since the
discussion revolves around a single bay, the rectifiers must be chosen to provide
the power and redundancy required in the space available. There are generally
three rectifier sizes that can be placed in a 15 inch deep relay rack. (All of thesolutions will be 208/240 VAC – 120 VAC and 480 VAC solutions are not
practical for this architecture.) Rectifiers for plants that will meet these
requirements are in the 20 to 50 amp range. We will look at 20, 30, and 50 AMP
rectifiers.
One of the critical considerations is whether to go with N+1 reliability in the
rectifier plant or – since the two bays cross feed – to go with 2N redundancy. If the
configuration is going to power both the A and B side of up to 20 bays, the typical
solution – and one that provides the same reliability as most existing bulk DC
plants, N+1 philosophy can be used.
If the configuration is a two bay pairing where each distributed architecture power
bay provides power to either the A or B load of 40 frames, the 2N rectifier
redundancy design looks practical. This would provide added reliability of the
system by feeding each of the mated bays from a different commercial AC service
entrance. Using separate AC service entrances (usually available only in the largest
offices) decreases the probability of a simplex AC failure causing the power
system to go on batteries.
The 2N solution provides an AC electrical advantage. By using a 2N configuration
in a MPS power plant with two rectifier shelves, it is possible to feed each pair of
rectifiers with a single AC breaker. This solution results in 4 rectifiers per shelf
each shelf balance fed with two AC breakers and a bulk output to the distribution
panels.
10
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 11/14
G. AC CABLE ROUTING
The first question to ask – and this is another first and last question is “Is AC
available?” This is not a capacity question but it is a distribution question. It is the
first and last thing to consider when contemplating this technology. It is an
economic question. When AC fuse/breaker panels are assigned, there is an
assumption that there will be no point in time when all of the circuits draw full
load. Therefore typically (you can see this in your home) a 150 amp AC panel will
have 300 to 500 amps of fuse or breaker positions. As there is never a time when
everything in the home is on and attempting to pull full power, this is not a
problem. However, when rectifiers are installed, THERE WILL BE TIMES
WHEN ALL RECTIFIERS PULL 100% OF THEIR MAXIMUM DRAIN
SIMULTANEOUSLY. Having said that, it is essential that the breaker panel that
provides power to the rectifiers be dedicated to those rectifiers and have enough
capacity to handle all of the rectifiers pulling 100% - this is not 100% of thebreaker, but 100% of the AC rectifier current required at full load. So a 50 amp
rectifier running at 208 VAC and 95% efficiency will pull approximately
(54*50/.05)/208 = 14.4 amps. NOTE: This is with the rectifier running at 100% not
110% (which some rectifiers can be set to).
A breaker panel must be available (this could be installed for the application). If
two pairs of distributed architecture power bays are being installed, the panel will
need 16 positions. Each position will have approximately 30 amps of drain at full
load so the panel must be sized for and capable of 480 amps. Adding 20% for a
“safety margin” means that the source feeding this panel needs to be capable of
576 Amps. (NOTE: This discussion is not based on available fuse sizes, but on
projected loads.)
At this point it is necessary to go back to the house service entrance. There are two
questions to ask here. First, is the site being fed with enough AC to handle the
additional load? The second question is “Is there a breaker position on the panel
with enough available capacity to handle the load? (If as an alternative to powering
4 bays from one panel the decision is made to power 1 bay from each distribution
panel, then it will be necessary to have 4 feeds with a minimum of 144 amps each.If it is necessary to replace the house service entrance to install distributed power,
then it may not be the best solution.
11
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 12/14
H. GROUNDING FOR DISTRIBUTED POWER
Bonding and grounding this system is critical to safe and proper operation.
Integrated Versus isolated grounding is generally beyond the scope of this paper.
However, it is critical to bond and route the AC conduit correctly. The first general
assumption is that distributed power will be used for toll room transport equipment
as opposed to switch. To that end, distributed architecture will always power
integrated equipment. If the distributed power bay is within 6 feet of any isolated
equipment bays, it will be necessary to run the AC conduit past and bond it to the
ground window.
The same situation exists with the DC ground and return. Equipment positioning
will be required to determine whether the return on the distributed architecture
should be bonded to the ground window, or merely tied to the vertical riser and
then back to the OPGP.
I. CONTROLLER
It is the nature of these small switch mode rectifier plants that the controller and
rectifiers are in integrated unit. The MPS controller must be capable of providing
everything from dry contact alarms to a full featured web based interface for
managing the power plant and alarms from a centralized location.
The advanced features deal with the operation and maintainability of the plant.
There are also several questions that must be asked. The first question “Does this
equipment require remote monitoring?” is always yes in today’s environment. For
functionality it is necessary that monitoring of the distributed power component fit
in with the architecture of the user’s monitoring system. As there are several of
these available, this document will hit the highlights.
The first monitoring would be a customer that required dry contact major and
minor alarms. These would be routed to the site alarm panel or the remote alarm
center to provide major and minor alarms for rectifier fail and fuse fail.
The next configuration would be an “intelligent” controller that provided full
power plant information to a down-stream intelligent alarm center. Because of the
distributed nature of the power, it is critical that any alarm or information (load,
battery, discharge state, etc.) include enough information to uniquely identify the
power bay. For example, the RBOCS use a CLLI code to define a site –
ALBQNMMACGO – where ALBQ means Albuquerque NM is the state – New
12
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 13/14
Mexico, MA is the site location (Main) and CGO is traditionally the switch
associated with the power plant. To use this scheme for distributed architecture, the
CGO could be replaced with the bay location (ALBQNMM214). Of course, this
would only work in a site with less than 10 floors and fewer than 100 bay locations
on each floor.
The next function is to get the informaiton out. Because ports in an office may be
limited, one possibility is to daisy chain all of the power plants together so that
there is only one physical appearance for all of the distributed plants at the site. A
second solution is to provide each power plant with a unique address and have
intranet access to each bay from a private network.
Since the concept is for a distributed architecture plant to be truly maintenance
free, the down stream alarm should uniquely identify the plug and play part that
has failed or the status of the plant. This would include distribution, rectifiers, andespecially batteries.
6. DISTRIBUTED POWER CONSIDERATIONS
So far this presentation has pointed out the technical issues and sizing
considerations to be addressed when making a choice between centralized power
and distributed power. One of the first considerations is to determine if converting
to distributed power would leave a lot of “stranded capacity” in the existing DC
power plant. This would mean that the rectifiers, batteries, controller, and adequate
AC is available for the proposed additional load. The decision in this situation can
be simple or thorough. The simple decision is merely one of comparing the cost of
feeding from the power board or placing a BDFB VS the costs associated with a
distributed architecture bay. The thorough solution would additionally look at the
condition of the existing DC plant. For example, if the existing plant had one or
two 400 Amp Manufacturer Discontinued rectifiers in service, the customer could
remove those rectifiers and replace them with the distributed power option. This
would 1) get rid of obsolete equipment; and 2) provide AC breaker capacity for the
distributed architecture bays.
When the new bays can be fed from the main power board (for example in a small
CDO where the outside room dimensions are approximately 40 by 80 feet), there is
no need for a BDFB. In this situation, there is only the ½ volt drop to the served
equipment, there are no 750 MCM DC distribution cables, and the savings
associated with distributed power are questionable. (NOTE: the exception to this
would be where one or two bays of distributed power could be used to replace the
13
8/6/2019 Portable and Distributed Power for Telecommunications
http://slidepdf.com/reader/full/portable-and-distributed-power-for-telecommunications 14/14
14
entire existing DC plant with one or two distributed architecture power bays. This
would allow removal of the entire existing DC plant (including batteries) and
provide prized growth space in a small CDO.
An entire dimension is added when growth of the main DC plant is required. The
economic comparison here is much more favorable to distributed architecture.
When this is coupled with the need for a BDFB to be placed a considerable
distance from the existing power plant, then the economic consideration will favor
distributed architecture even more.
In the end, the decision to grow distributed or centralized power could be a
corporate decision based on reduced maintenance requirements or the increased
overall site reliability because the catastrophic failure of one DC power plant
would not take the entire site down.