POP_Construction.pdf

Embed Size (px)

Citation preview

  • 8/14/2019 POP_Construction.pdf

    1/76

  • 8/14/2019 POP_Construction.pdf

    2/76

    Revision No. & Date _________________

    31 July 1998

    TABLE OF CONTENTS

    S.No. Description Page No.

    1.0 ADMINISTRATION

    1.1 Introduction I-1

    1.2 Project Description I-2

    1.3 Project Organization I-3

    1.4 Project Office Administration I-22

    1.5 Personnel Administration I-25

    2.0 CONTROL OF THE WORK

    2.1 Client Interface II-1

    2.2 Contractor Interface II-2

    2.3 Control of Work II-9

    2.4 Construction Operating Procedures II-19

    3.0 PROECT CONTROL

    3.1 Contract Administration III-1

    3.2 Documentation III-14

    3.3 Financial and Cost Control III-22

    3.4 Schedule Control III-23

  • 8/14/2019 POP_Construction.pdf

    3/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998

    Section 1.0 Administration

  • 8/14/2019 POP_Construction.pdf

    4/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-1

    1.0 ADMINISTRATION

    1.1. Introduction

    Description of Project The project comprises construction inspection and

    engineering supervision of a number of construction Contracts including road

    widenings, new roads, interchanges, expressway standard roads, bridges,

    parking structures, and pedestrian underpasses in and around the Municipality

    of Abu Dhabi.

    Operations Plan The Operations Plan follows the outline in the Company

    Quality Assurance Manual and is an update of the original plan prepared at the

    beginning of the TRIP program in 1980. This plan incorporates the severalpolicy and procedure memos written and distributed since the initial plan went

    into effect.

    These memos were done to keep abreast of changing conditions over time and

    have been the guiding policy and procedure statements as an adjunct to the

    original plan in the form of a well-organized appendix.

    The updated plan will weave in the essence of these documents insofar as

    practicable; will give procedures for future updates; will continue the practice

    of using the appendix to elaborate on or modify the updated plan with cross

    referencing to the applicable parts of the base plan; will reflect the presentproject activity; will be as sensitive as possible to actual practices; will discard

    and revise any sections of the original plan not covered by memo and no

    longer applicable; will re-format to comply with the format given in the QA

    Manual.

    The Purpose of construction services to be performedThe Consultant is

    responsible on a continuing basis for the engineering supervision and

    construction inspection of the Program improvements as shown in Appendix

    I.1-1and as described in the section on project description. The tasks consist

    of integral elements such as surveys, construction inspection, materials testing,

    shop drawing review, progress and schedule monitoring and review, as-builtdrawings review, and processing of interim and final payments as shown in

    Appendix I .1-2. All are aimed at assuring a quality of construction consistent

    with sound construction practices and to comply with the Contract documentsand specifications so that the project is completed on time and within budget.

    Construction Manual The client assigned DCIL the task of preparing a

    construction manual which is in final draft form. Procedural items from that

    manual will be included in this operations plan and the manual itself will be a

    supporting document by reference.

  • 8/14/2019 POP_Construction.pdf

    5/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-2

    1.2 Project Description

    The projects now under construction include road widening projects, full

    interchanges, bridges, parking structures, and pedestrian underpasses. Futureconstruction projects now under design and which are anticipated to be

    tendered and awarded in the future will include similar works.

    Appendix I.2-1 shows all of the projects under construction or already

    constructed since the inception of the program in 1980. These consist of local

    and access roads involving palaces and government institutions, the Maqta

    Bridge, interchanges and ramps for future interchanges, realigning the

    Corniche Road, multi-storied parking structures, right turn lanes and

    channelization along the main roads, traffic signal system, etc.

    All of these road improvements are within the Municipality of Abu Dhabi.

    A number of TRIP Projects are awaiting construction commencement, others

    are awaiting tendering authorization or final approval of the completed design;

    all such Projects will presumably have construction contracts eventually

    awarded.

    Design has been authorized and is in various stages of progress or it is

    completed for the following projects:

    - Contract 10, Corniche Road - North (realignment)

    - Contract 66C, Parking Structure in Sector E5- Contract 66D(R), Multi-Storey Parking Structure in Sector W5

    - Contract 66I, Multi-Storey Parking Structure in Sector E-8

    - Contract 964, Pedestrian Crossings under Main Roads

    - Contract 967( R ), Tunnel at Sea Palace Access

    - Contract 968, Bridge Interchange at IP-111

    - Contract 978, Bridge Interchange at IP-111A

    - Contract 980, Umm Al Nar Bridge Interchange

    - Contract 981, MIP-3 Bridge Interchange - Mussafah Road

    - Contract 982, MIP-76 Bridge Interchange - Mussafah Road

    - Contract 987, Breakwater Rehabilitation and Improvements

    - Contract 988, CCTV System- Additional Work AW30, Al Bateen Palace Roadworks

    Other projects within the maintenance period: 30, 35, 37A, 81, 84B, and E17

    are monitored by the construction staff who also give support to the

    Municipality in arranging maintenance and closing out the project.

  • 8/14/2019 POP_Construction.pdf

    6/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-3

    1.3 Project Organization

    The project organization is shown in Appendix I .3-1. The responsibilities and

    duties of each position are described as follows.

    Program Director The TRIP Program Director is responsible for the overall

    operations of the Companys Abu Dhabi Office.

    Project Director The Project Director is responsible for the construction

    supervision of TRIP Projects and overseeing the design efforts.

    Contract Administrator- The Contract Administrator is responsible for:

    -- Assisting the program staff in consistent interpretation of the

    Contract documents.

    -- Facilitating contractual procedures involving the Municipality,

    Consultant, and Contractors.

    -- Dealing with Contract issues involving the Contractors claims,

    disputes, change orders, and variation orders.

    -- Maintaining an up-to-date project operations plan for construction.

    -- Reviewing and advising the staff on construction schedules,program deliverables, client priorities, and additional service

    requests.

    -- Conducting quality assurance audits at least quarterly.

    Deputy Project Director, Construction-I - The Deputy Project Director,

    Construction-I is responsible for matters related to TRIP design and

    construction of Utilities, Electrical, Mechanical works, and other specifically

    assigned additional tasks, and as follows:

    -- Assist the Project Director in TRIP design and construction withinthe assigned disciplines.

    -- Maintain continuous communication and liaison with the Client and

    utility agencies.

    -- Provide supervision support for construction works related to the

    assigned disciplines.

    -- Review with the Client and utility agencies the technical matters

    involving construction for the assigned disciplines.

  • 8/14/2019 POP_Construction.pdf

    7/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-4

    -- Provide design assistance in support of the construction supervision

    staff.

    -- Delegate to the staff the specific authority and responsibilities asapproved by the Project Director for the assigned disciplines.

    -- Supervise the performance of the field staff of the assigned

    descriptions.

    -- Comply with the requirements of the TRIP Agreement and limit

    construction and supervision activities to in-scope work.

    Deputy Project Director, Construction-II - The Deputy Project Director,

    Construction-II is responsible for matters concerning TRIP construction

    supervision, and as follows:

    -- Assist the Project Director in construction supervision for TRIP

    Contracts.

    -- Assist the Project Director in overall management, planning,

    scheduling, and direction of the construction work.

    -- Review the construction progress reports and advise the Project

    Director on major deviations from approved construction programs.

    -- Supervise and control the construction work activities of

    construction Contracts.

    -- Coordinate technical matters among the construction and design

    staff; review their comments; make recommendations to the Project

    Director concerning these comments.

    -- Provide guidance and advice to the design and construction

    supervision staff.

    -- Review and advise the Project Director on importantcorrespondence, Standards and Criteria for all Contract Deliverable

    submissions that affect construction.

    -- Arrange for the preparation and submission of Contract

    Deliverables involving construction issues.

    -- Delegate specific authority and responsibilities to the assigned

    supervision staff as approved by the Program Director.

    -- Review design changes with the responsible Deputy Project

    Directors, prior to the approval of shop drawings.

  • 8/14/2019 POP_Construction.pdf

    8/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-5

    -- Restrict design changes in plans and specifications to only those

    approved by the Project Director.

    Senior Resident Engineer - On projects of a certain value and complexity a

    Senior Resident Engineer will be assigned and will have the same function as a

    Resident Engineer. Other Senior Resident Engineers will have responsibility

    for a group of Contracts and for supervising the Resident Engineers on those

    Contracts. The Senior Resident Engineer is responsible for:

    -- Supervising the work and activities of the Resident Engineers.

    -- Functioning as the Resident Engineer on the primary assignment

    project with the duties described below.

    Resident Engineer - The Resident Engineer will have responsibility for the

    one Contract under his supervision; for seeing that the work being inspected is

    constructed in accordance with the requirements of the plans and specifications

    without willfully disrupting the operations of the Contractor. He will be

    responsible for assigning the resources at his disposal in the most effective

    manner. The Resident Engineer performs the following:

    -- Supervises Inspectors, Technicians, and Project Office Staff.

    -- Writes drafts of monthly reports.

    -- Maintains Resident Engineers Daily Diary up-to-date in the

    approved format.

    -- Assures that workmanship and materials are in accordance with the

    Contract documents.

    -- Monitors, revises, and reports the Contractor's progress and updates

    cost-to-complete estimates as required.

    -- Convenes periodic meetings with the Contractor.

    -- Maintains day-to-day liaison with the Municipality field

    representative.

    -- Coordinates and expedites processing of the Contractor's partial

    payment invoices.

    -- Furnishes consultation and recommendations to the Senior Resident

    Engineer/Deputy Project Director/Project Director/Contract

    Administrator concerning the interpretation of Contract documents

    and claims by the Contractor for extra works and time extensions.

  • 8/14/2019 POP_Construction.pdf

    9/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-6

    -- Maintains necessary field records including up-to-date pay item

    quantity books.

    -- Requests, when needed, through members of the supporting

    supervision staff: surveys, materials testing, assistance with utilities,

    and structural engineering assistance.

    -- Assists in preparing necessary supplemental drawings when

    required to resolve field difficulties.

    -- Prepares correspondence and instructions to the Contractor, as well

    as various reports and other correspondence.

    -- Reviews as-built drawings.

    Assistant Resident Engineer - The Assistant Resident Engineer is responsible

    for the specific duties assigned directly by the Resident Engineer which will

    typically include:

    -- Reviewing the Inspectors Daily Reports and providing input into

    the Engineers Daily Diary.

    -- Overseeing Inspectors and Site Engineers daily activities, giving

    out work assignments; providing guidelines for constructioninspection.

    -- Reviewing survey and test requests; reviewing and approving shop

    drawings; monitoring the survey party; reviewing and approving

    proposed materials and construction methods.

    -- Preparing meeting minutes.

    -- Coordinating with the Contractors supervisory personnel in

    scheduling, sequence, and construction methods.

    -- Preparing written and oral reports to the Resident Engineer oncontractual and procedural matters.

    -- Reviewing as-built drawings.

    Quantity Surveyor - The Quantity Surveyor is responsible for the specific

    duties assigned directly by the Resident Engineer and/or the Chief of Surveys

    and Quantity Surveyors which will typically include:

    -- Maintaining up-to-date quantity books.

    -- Advising the Resident Engineer on measurements and unit rates.

  • 8/14/2019 POP_Construction.pdf

    10/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-7

    -- Preparing a BOQ Recapitulation.

    -- Preparing Monthly Financial Affairs Reports.

    -- Preparing and maintaining Interim and Final Quantity Books.

    -- Checking the Contractors interim and final pay certificates.

    -- Evaluating unit rates for new items of work.

    -- Checking joint measurements for interim payments.

    -- Computing final pay quantities.

    -- Maintaining current as-built drawings as the work progresses.

    -- Maintaining the progress schedule and cash flow chart.

    -- Assisting in preparation of change orders and variation orders.

    -- Assisting in evaluating claims.

    Senior Site Engineer- The Senior Site Engineer is responsible for the specific

    duties assigned directly by the Resident Engineer which will typically include:

    -- Coordinating with the Contractor for the inspection, survey, and

    testing requirements of the works in progress.

    -- Reviewing the Inspectors daily report and giving comments to the

    Resident Engineer.

    -- Reviewing the Contractors daily program.

    -- Reviewing shop drawings and as-built drawings and giving

    comments to the Resident Engineer.

    -- Making the initial review of the Contractors material submissions

    to ensure completeness of the package and compliance with the

    specifications. Giving comments to the Resident Engineer.

    -- Preparing reports to the Resident Engineer on the quality and

    progress of the construction and the adherence of the construction

    materials to the specifications.

    Site Engineer - The Site Engineer is responsible for the specific duties

    assigned directly by the Resident Engineer which will typically include:

  • 8/14/2019 POP_Construction.pdf

    11/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-8

    -- Reviewing the Contractors daily program.

    -- Coordinating with the Contractor for the inspection, survey, andtesting requirements of the construction in progress.

    -- Reviewing the Inspectors daily report and giving comments to the

    Resident Engineer.

    -- Reviewing shop drawings and as-built drawings and giving

    comments to the Resident Engineer.

    -- Making the initial review of the Contractors material submissions

    to ensure completeness of the package and compliance with the

    specifications. Giving comments to the Resident Engineer.

    Inspectors - The Inspectors are responsible for the specific duties assigned

    directly by the Resident Engineer which will typically include:

    -- Becoming completely familiar with the plans, general

    specifications, and particular specifications.

    -- Evaluating the construction methods for the phases of the work to

    which they have been assigned.

    -- Reporting noncompliance and seeking clarification from the

    Resident Engineer if needed.

    -- Ensuring the construction is strictly in accordance with the plans

    and specifications.

    -- Maintaining a detailed diary of the days work activities, issues,

    work approved or rejected, hours of operation, labor and equipment

    used, etc., and signed at the end of each day.

    -- Interfacing with the public, especially residents and business ownersadjacent to the work, to mitigate the construction impacts.

    -- Coordinating with the Contractors Foreman in charge of the work

    on a daily basis to advise on the execution of the work.

    -- Coordinating with the Materials Technician and arranging for

    sampling and testing of satisfactorily completed work, and quality

    assurance testing of suspect materials.

  • 8/14/2019 POP_Construction.pdf

    12/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-9

    -- Coordinating with the Survey Party Chief to check the line and

    grade of completed work for conformance with the plans and

    specifications.

    -- Reporting to the Resident Engineer any questionable methods of

    operation by the Contractor or any failure of the Contractor to

    conform to the plans and specifications or to provide good

    workmanship.

    -- Processing the joint measurement sheets and maintaining records of

    their status.

    -- Maintaining records of completed construction for interim and final

    payment and as-built plans and maintaining detailed records of

    work done by the Contractor on a Day Works basis.

    -- Making special notes and documenting the Contractors activities

    that may lead to claims.

    -- Notifying the Resident Engineer of conditions that render it

    impractical or unreasonable to enforce the specifications.

    -- Reporting and documenting any accident on site and notifying the

    Resident Engineer immediately.

    -- Enforcing performance of the work in strict accordance with the

    approved Safety Plan and checking detours and traffic control zones

    for proper placement of signs, barricades, and lights.

    Survey Party Chief - The Survey Party Chief is responsible for the specific

    duties assigned directly by the Resident Engineer which will typically include:

    -- Doing the survey work under the direction and guidance of the

    Chief of Surveys.

    -- Establishing primary horizontal and vertical control points includingreference ties for re-establishing the points in the field.

    -- Supervising the survey party staff.

    -- Rotating staff assignments to develop the skills and qualifications of

    the Surveyors.

    -- Recording measurements, rod readings, and calculations in field

    books as the work progresses.

  • 8/14/2019 POP_Construction.pdf

    13/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-10

    -- Coordinating with the Contractors surveyor on work priorities and

    schedules.

    -- Checking the work by completing traverse closures and benchcircuits.

    -- Reporting discrepancies or technical problems to the Resident

    Engineer.

    -- Jointly measuring the completed work for payment.

    -- Checking completed work for conformance to the line and grade

    required by the project plans in coordination with the inspector

    assigned to that item of work.

    -- Checking the Contractors setting out to verify execution and

    accuracy.

    -- Maintaining equipment in proper condition and checking the

    calibration frequently.

    Surveyor - The Surveyor is responsible for the specific duties assigned directly

    by the Survey Party Chief and/or the Resident Engineer. Surveyors will be

    assigned duties according to their technical abilities such as Instrumentman,

    Rodman, etc. Insofar as practicable, each Surveyor will be given anopportunity to rotate from one position to another.

    Materials Technician - The Materials Technician is responsible for the

    specific duties assigned directly by the Chief Soils and Materials Engineer

    and/or the Resident Engineer which will typically include:

    -- Coordinating the work and record keeping of the materials testing

    laboratory on the project.

    -- Setting up the field laboratory and undertaking its organization,

    maintenance, and operation.

    -- Supervising staff assistants in sampling and testing of materials.

    -- Sampling, testing, record keeping, and reporting in accordance with:

    - Municipality Policy and Procedures Directives.

    - Materials Testing Manual

    - AASHTO Standard Methods of Sampling and Testing

    - Construction Supervision Manual

    - Project Plans and Specifications

    - Construction Supervision Directives

  • 8/14/2019 POP_Construction.pdf

    14/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-11

    -- Sampling Guide and Certifications Manual

    -- Reporting test results to the Resident Engineer and Contractor.

    -- Reporting failing or marginal test results immediately to the

    Resident Engineer.

    -- Coordinating with the Inspector in charge of the work to confirm

    approval of the work for testing and to discuss areas of concern.

    -- Coordinating with the Contractor on work priorities and schedules.

    -- Sampling and testing as quickly and efficiently as possible to avoid

    undue delay to the Contractors operations.

    -- Checking material delivered to the project for conformance with the

    approved source or supplier.

    -- Maintaining neat and accurate records.

    -- Monitoring the frequency and number of tests required for every

    operation.

    Secretary - The Secretary is responsible for the specific duties assigned

    directly by the Resident Engineer. The Secretary should be aware of thevarious record keeping and reporting procedures. The Secretary has the

    responsibility to type, copy, distribute, and file the project correspondence and

    meeting minutes.

    Deputy Project Director-Design - The Deputy Project Director-Design is

    responsible for advice and recommendations with regard to the assigned design

    disciplines related to TRIP construction projects, and as follows:

    -- Maintain continuous communication and liaison with the Client

    regarding the design revisions initiated during the construction

    phase.

    -- Coordinate and review design matters with the Construction Group

    for their input.

    -- Review with the Client, in coordination with the related Design

    Section Managers and Construction Group, all design technical

    matters related to the projects under construction.

    -- Review and advise the Project Director regarding the specific

    content and format requirements of Standards and Criteria for all

    Contract Deliverable submissions.

  • 8/14/2019 POP_Construction.pdf

    15/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-12

    -- Arrange for the preparation and submission of all Contract

    Deliverables.

    -- Provide design assistance as required to support the construction

    supervision staff.

    -- Advise the Project Director of Client requests to undertake special

    assignments or additional work associated with the projects under

    construction.

    Structural Engineer Specialist - The Structural Engineer Specialist is

    responsible for advice and recommendations on all structural engineering

    matters and is responsible for:

    -- Reviewing and approving structural shop drawings.

    -- Reviewing and advising on construction procedures related to

    structures.

    -- Assisting in preparation of change orders.

    -- Providing structural design services.

    -- Reviewing as-built structural drawings prepared by theContractors.

    Electrical Engineer Specialist - The Electrical Engineer Specialist is

    responsible for advice and recommendations on all electrical engineering

    matters and he will:

    -- Review electrical shop drawings.

    -- Review electrical materials submittals and samples.

    -- Review and advise on construction procedures involving electricalworks.

    -- Assist in the preparation of change orders.

    -- Assist in the inspection of electrical works.

    -- Provide electrical design services.

    -- Assist in the review of as-built electrical drawings prepared by

    the Contractors.

  • 8/14/2019 POP_Construction.pdf

    16/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-13

    Mechanical Engineer Specialist - The Mechanical Engineer Specialist is

    responsible for advice and recommendations on mechanical engineering

    matters and he will:

    -- Review mechanical shop drawings.

    -- Review mechanical materials submittals and samples.

    -- Review and advise on construction procedures related to

    mechanical works.

    -- Assist in the preparation of change orders.

    -- Assist in the inspection of mechanical works.

    -- Provide mechanical design services.

    -- Assist in the review of as-built mechanical drawings prepared by

    the Contractors.

    Architectural Specialist - The Architectural Specialist is responsible for

    advice and recommendations on architectural matters and will:

    -- Review architectural shop drawings.

    -- Review and advise on construction procedures concerning

    architectural works.

    -- Assist in preparing change orders.

    -- Assist in inspecting architectural works.

    -- Provide architectural design services.

    -- Assist in the review of as-built architectural drawings prepared by

    the Contractors.

    Chief Soils and Materials Engineer- The Chief Soils and Materials Engineer

    is responsible for advice and recommendations on technical soils and materials

    matters and is responsible for:

    -- Completing, checking, and processing test reports.

    -- Making geotechnical recommendations.

    -- Making quality control recommendations.

  • 8/14/2019 POP_Construction.pdf

    17/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-14

    -- Ensuring that field laboratory and lab personnel are responding to

    the technical requirements.

    -- Assisting in preparing inspectors for inspection of embankments,concrete, and pavement.

    -- Ensuring that off-site testing and certifications are valid.

    -- Checking and reporting on compliance with specification

    requirements for compaction, gradation, mix proportions, strength,

    etc., in construction of embankments, structures, pavements, and

    incidental items.

    -- Establishing laboratory and field testing procedures.

    -- Analyzing foundation conditions.

    -- Developing and implementing schedules for:

    -- Test frequency.

    -- Test coverage on all Contracts.

    -- Supervising the operations of the laboratory and maintenance

    of all equipment.

    Chief of Surveys and Quantity Surveyors - The Chief of Surveys andQuantity Surveyors is responsible for advice and recommendations concerning

    construction surveys and maintenance of construction quantity records and is

    responsible for:

    -- Directing initial baseline and control surveys including

    establishment of bench marks and recovery of any existing survey

    monuments to be removed.

    -- Supervising and directing field survey parties to comply with

    requests for surveys.

    -- Checking the Contractors setting-out of centerlines, structures,

    slope stakes, etc.

    -- Checking field measurement surveys including original and final

    cross-sections.

    -- Checking critical elevations, dimensions, and locations of structural

    elements, earthwork grading, pavement, and appurtenances.

    -- Checking the Contractors detailed survey in advance of

    construction operations.

  • 8/14/2019 POP_Construction.pdf

    18/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-15

    -- Investigating and clarifying survey discrepancies.

    -- Establishing the format and standard procedures for calculation and

    documentation of quantities.

    -- Conducting training in the use of modern survey equipment.

    -- Supervising maintenance of the equipment.

    -- Scheduling and supervising the work of all survey crews.

    -- Establishing and maintaining the format for survey records.

    -- Ensuring that quantity records kept by Quantity Surveyors are up-

    to-date and in accordance with established procedures.

    -- Reviewing and supervising all quantity survey works.

    -- Reviewing the new unit rates recommended by the Resident

    Engineers.

    -- Reviewing the Change Orders prior to submitting to the

    Municipality.

    -- Reviewing interim and final payment certificates.

    Senior Transportation Engineer Senior Transportation Engineer is

    responsible for advice and recommendations with regard to the assigned

    transportation design tasks related to TRIP Construction Projects, and as

    follows:

    -- Review/design of all proposed/modified CCTV/Traffic Control

    ducts layout drawings.

    -- Review/design of all new/modified Traffic Signal network drawings

    for intersections/interchanges.-- Review of all detour plans for main roads which affect adjacent

    traffic signals.

    -- Review/design of all Traffic Control Systems component (CCTV/

    Access Control/Communications) drawings/materials submittals for

    Parking Structures. Review/design of pavement markings and signs

    within Parking Structures.

    -- Review of traffic counts/pedestrian counts/vehicle gaps survey.

    -- Review of temporary traffic signals.

  • 8/14/2019 POP_Construction.pdf

    19/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-16

    Computer System & CADD Manager Computer System and CADD

    Manager is responsible for advice and recommendations with regard to the

    computer system management and CADD works related to TRIP ConstructionProjects, and as follows:

    -- System Set-up

    Assistance to define/update the system configuration to be

    installed at the site offices. The system configuration shall

    include technical information on Computers, printers, modem

    and network cards and cables.

    Assistance to procure the computer equipment from the

    Contractor.

    Assistance to define/update procedures for using the computer

    systems by the construction staff.

    Assistance to set-up and configure the network, printers and

    computers and explain the procedures to be followed.

    -- Support and Training

    Assistance for support on all computer applications that are inuse in the company.

    Assistance for the training needs and organizing periodic

    training sessions to the construction staff.

    -- Computer Aided Design (CAD) Assistance for the site office and Contractor with the digital

    CAD files of the contract documents, addendums and revisions

    in the required format.

    Assistance to define CAD procedures for creation of as-built

    drawings if DCIL is made responsible for the as-built drawings.

    -- Application Development

    Assistance to identify computer software that could improve theefficiency of the organization. Implement any new software

    through proper training and by providing proper documentation.

    Assistance to develop applications/tools like databases, macros,

    templates etc. to automate workflows/processes in the site

    offices.

    -- General

    Assistance to the construction staff in the creation of regular

    monthly and bi-weekly progress reports.

    Assistance on all IT issues like updates to the software, backups,virus protection, etc.

  • 8/14/2019 POP_Construction.pdf

    20/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-17

    Office Engineer - The Office Engineer is responsible for providing assistance

    in:

    -- Processing variation orders.

    -- Reviewing shop drawings.

    -- Organizing, editing, and processing monthly progress reports.

    -- Maintaining the order and supply of construction forms.

    Utility Coordinator - The Utility Coordinator is responsible for advice and

    recommendations on matters related to utilities and is responsible for:

    -- Identifying general locations of utilities prior to construction.

    -- Providing liaison with Utility Agencies.

    -- Determining requirements for relocations and protective devices

    prior to and during construction.

    -- Serving as liaison with the Municipality on all utility matters.

    -- Assisting Utility Engineers as needed.

    -- Reviewing as-built drawings as they concern utilities.

    -- Assisting in the preparation of change orders.

    -- Monitoring letters of intent.

    -- Assisting the Municipality and Utility Agencies in expediting

    permits and approvals of relocation and utility protection plans and

    occupation of utility reservations.

    -- Detecting, reporting, and following up on damage to utilityfacilities.

    -- Providing supervision and guidance to the Utility Engineers.

    Structural Engineer - The Structural Engineer is responsible for assisting the

    Structural Engineer Specialist on all structural engineering matters and will

    typically include:

    -- Reviewing and approving structural shop drawings.

  • 8/14/2019 POP_Construction.pdf

    21/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-18

    -- Reviewing and advising on construction procedures related to

    structures.

    -- Assisting in preparation of change orders.

    -- Providing structural design services.

    -- Reviewing as-built structural drawings prepared by the

    Contractors.

    Utility Engineer - The Utility Engineer is responsible for the specific duties

    assigned directly by the Resident Engineer and/or the Utility Coordinator

    which will typically include:

    -- Identifying general locations of utilities prior to construction.

    -- Providing liaison with Utility Agencies.

    -- Service reservation shop drawing approval and coordination with

    Town Planning Department.

    -- Determining requirements for relocations and protective devices

    prior to and during construction.

    -- Serving as liaison with the Municipality on all utility matters.

    -- Reviewing as-built drawings of utilities.

    -- Assisting in the preparation of change orders.

    -- Monitoring notices of intent.

    -- Assisting the Municipality and Utility Agencies in expediting

    permits and approvals of relocation and protection plans and

    occupation of utility reservations.

    -- Detecting, reporting, and overseeing repairs to damaged utility

    facilities.

    Finance and Administration Manager The Finance and

    Administration Manager is responsible for:

    -- Complying with the directions and guidance of the Program

    Director.

    -- Assigning responsibilities to the Accounting Section Staff and

    monitoring their performance.

  • 8/14/2019 POP_Construction.pdf

    22/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-19

    -- Preparing project budgets, financial statements, and cash flow

    forecasts in accordance with the requirements of the corporate

    office.

    -- Providing advice and suggestions to the Program Director on

    matters relating to cost savings, employee benefits including

    training, and expenditures required to keep pace with the

    technological developments necessitated by the Companys

    business activities.

    Administrator & Human Resources Manager The Administrator &

    Human Resources Manager is responsible for:

    -- Soliciting applications for current and future TRIP personnelrequirements.

    -- Submitting proposed candidates CVs for Client approval and

    arranging for visas, mobilization, accommodations, and work

    permits.

    -- Maintaining an up-to-date employee progress rating file.

    -- Organizing and scheduling of replacement staff for those on leave.

    -- Updating the administration of any Company policies affected bynew government rules or regulations.

    -- Arranging for resident visas, medical health cards, car registrations,

    driving licenses, Company trade licenses, and apartment leases.

    -- Arranging for transportation facilities, and maintenance of

    Company cars, apartments, offices, equipment and furnishings.

    -- Maintaining a sufficient stock of office supplies and stationery and

    arranging for the purchasing of other furnishings and services as

    required.

    -- Arranging for the gate keeping and storage of Company records and

    completed project files.

    -- Maintaining inventories of Company assets.

    -- Arranging distribution of correspondence, scheduling attendance at

    training seminars, and arranging all Company parties and special

    events.

  • 8/14/2019 POP_Construction.pdf

    23/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-20

    Chief Accountant: This position calls for matrix responsibility, reporting to

    the Program Director and Finance and Administration Manager. The Chief

    Accountant is responsible for:

    -- Preparing the payroll for expat and local employees, including

    maintaining the time sheets, receipts, and accounting records.

    -- Billing for Construction Supervision and Design services based on

    the TRIP Contract agreement and billing the Contractors for

    operational costs and overtime worked by site staff.

    -- Coordinating with the Program Director and following up for the

    collection of accounts receivable.

    -- Coordinating with the corporate office for funds transfers in and outof the local bank account.

    -- Complying with corporate office requirements by providing

    submittals, on a weekly/periodical basis, concerning all matters of

    finance and accounting, project budgeting, forecast reports, project

    revision details, reconciliation of prism reports, cost to complete

    estimates, proposal pricing, foreign tax withholding (FICA),

    employee benefits (Insurance), employee earnings summary (W-2

    form), etc.

    -- Preparing MOUs for newly hired staff and renewals of expiring

    MOUs and computing final MOU settlements.

    -- Managing accounts payable in accordance with corporate office

    policies and procedures.

    -- Complying with local government laws regarding employee

    compensation, severance pay, vacation and sick leave, and

    workmens compensation insurance.

    -- Setting up various internal controls and procedures for monitoringpayments, employee allowances, fringe benefits, and salary

    advances.

    -- Carrying out internal audits and reviewing the findings for

    compliance with corporate office policies and procedures.

    -- Assisting corporate office personnel with the retrieval all relevant

    documents and records needed in carrying out an independent audit.

    -- Providing training, as and when needed, to existing and new hire

    accounts personnel.

  • 8/14/2019 POP_Construction.pdf

    24/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-21

    -- Safekeeping of employee payroll records, vendor payment records,

    important inter-office communications, Company leases for

    apartments and other rentals, etc.

    -- Coordinating and providing the Client all relevant financial details

    on TRIP Project billings, with prior approval of the Program

    Director, as and when requested.

    REFERENCES:

    1. Construction Manual, Chapter 1

    2. Memo from M.S. Khan to Staff, P/CO/IOM/6914, dated 11 April 1998, on thesubject of Construction Support Staff - Appendix I .3-2

    3. Memo from M.S. Khan to Design Section Managers, dated 15 February 1997, on the

    subject of TRIP Design Responsibilities - Appendix -I .3-3

  • 8/14/2019 POP_Construction.pdf

    25/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-22

    1.4 Project Office Administration

    The project filing system - The Resident Engineer will maintain a system of

    files for the project. The following designations and specific files will apply:

    Contract Files:

    CN-1 Chronological Correspondence

    CN-2.1 Correspondence To Contractor

    CN-2.2 Correspondence From Contractor

    CN-3.1 Correspondence To/From Municipality - Roads Section (RS)

    CN-3.2 Correspondence To/From Municipality - Agriculture Section (AG)

    CN-3.3 Correspondence To/From Municipality - Town PlanningDepartment (TP)

    CN-3.4 Correspondence To/From Municipality - Sanitary Drainage Network

    Section (SD)

    CN-3.5 Correspondence To/From Municipality Others (OT)

    CN-4 Contractors Schedule

    CN-5 Contractors Progress Reports

    CN-6 Contractors Shop Drawings

    CN-7 Contractors Plan Index Prepared plans

    CN-8 Contractors Plan Index Shop drawings

    CN-9 Material Test Requests and Results

    CN-10 Policy and Procedure Memos

    CN-11 Intra Office Memos

    CN-12 Monthly Progress Report

    CN-13.1 Minutes of Meetings - Progress Meetings

    CN-13.2 Minutes of Meetings - WEA Electrical

    CN-13.3 Minutes of Meetings - WEA Water

    CN-13.4 Minutes of Meetings - ETISALAT

    CN-13.5 Minutes of Meetings - Agriculture

    CN-13.6 Minutes of Meetings - Others

    CN-14 Correspondence To/From John Taylor (JT)

    CN-15 Correspondence To/From Etisalat (ET)CN-16 Correspondence To/From Tebodin (TB)

    CN-17 Contractors Monthly Pay Estimate

    CN-18 Resident Engineers Daily Diary

    CN-19 Claims

    CN-20 Variation Orders

    CN-21 Personnel File

    CN-22 Subcontractor Approval

    CN-23.1 Correspondence To/From WEA Electrical & Street Lighting

    (WE/E)

    CN-23.2 Correspondence To/From WEA Water (WE/W)

    CN-24 Report Forms

  • 8/14/2019 POP_Construction.pdf

    26/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-23

    CN-25 Post Tensioning

    CN-26 Configuration Management

    CN-27 Contractors Insurance

    CN-28 Bi-weekly Evaluation ReportsCN-29 Correspondence To/From ADNOC (ADN)

    CN-30 Administrative Matters

    CN-31 Addenda

    CN-32 Survey Control

    CN-33 Traffic Control and CCTV

    CN-34 Equipment Inventory

    CN-35 Construction Supervision Directives

    CN-36 Pre-Construction Contract Documents and Correspondence

    CN-37 Document Control

    CN-38 Safety

    CN-39 DrainageCN-40 Staffing

    CN-41 Pending Items

    CN-42 Supervision Management

    CN-43 Quality Assurance

    CN-44 Building Permits & Notices of Intent

    CN-45 Utility Incident Reports

    CN-46 Completion of Contract Documents

    CN-47 Potential Contract Changes

    CN-48 Document Review Summaries

    CN-49 Time Delay ChronologyCN-50 Reinforcing Steel

    CN-51 Asphaltic Concrete Materials

    CN-52 Proposed Revisions to Contract Documents (to cc: Design)

    Note: C-N - Designates Contract Number

    1-52 - Designates File Number

    Project correspondence is filed chronologically in File C-N-1 and should be a copy of

    the original. The original document is filed in the more specific subject file. Additional

    copies may be included in multiple files as assigned by the Resident Engineer. Forexample, the original copy of a letter from the Municipality providing subcontractor

    approval will be filed under C-N-22, with copies included under files C-N-1 and C-N-3.

    One filing system will be maintained in the Contract offices and one duplicate system

    in the main office.

    The format for official letters will be as shown in the included samples marked

    correspondence formatin Appendix I .4-1.

    Office forms to be used will be those in the section marked office forms as shown in

    Appendix I .4.2.

  • 8/14/2019 POP_Construction.pdf

    27/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-24

    The phone system will be a standard one used in Abu Dhabi. Each Contract will

    have a phone and fax line. Some staff may have cellular phones. Long distance calls

    will be restricted.

    Office Hours:Eight (8) hours per day, six (6) days a week.

    Office Supplies and Equipment will be provided by the Employer and/or TRIP

    Contractors as per the TRIP Agreement except for company related forms and

    documents.

    Job Number System A list of charge numbers for the current Contracts will be

    issued periodically by the Program Director.

    Emergency Contact Numbers will be as advised.

    REFERENCES:

    Construction Manual, Chapter 10, Section 1000.02

  • 8/14/2019 POP_Construction.pdf

    28/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-25

    1.5 Personnel Administration

    Introduction -- Personnel policy in general follows the labor laws of the Abu

    Dhabi Government. The memorandums of understanding (MOU) produced forexpatriate staff are in a confidential file in the main office and as such will not

    be an integral part of the operations plan. Other items in this section relate

    primarily to previous policy established for this office in addition to being

    under the labor laws of Abu Dhabi.

    Performance Evaluations will be done after the first six months for a new

    staff member and annually thereafter. The forms contained in Appendix I .4-2

    shall be used for these evaluations. Each staff member will be entitled to

    submit a separate statement as indicated.

    Housing, Subsistence, and Travel Expatriates will receive a housing

    allowance according to the provisions of their MOU. Locally hired engineers

    will receive a housing allowance according to company policy and their

    agreement with the company. Locally hired administrative and support

    personnel will be paid a living allowance in accordance with company policy

    and their agreement with the company.

    Expatriates will receive a travel allowance according to their MOUs, normally

    a roundtrip air fare for them and authorized family members to their home

    station once a year. Business travel for all staff members will be paid if on

    company business.

    Overtime

    Anything over 8 hours in one day or more than 60 hours in one week will be

    paid as overtime on the basis of 1.25 times the salary rate. For work on Fridays

    and holidays irrespective of the number of hours worked during the week, the

    payment shall be 1.5 times the salary rate.

    Sick Leave shall be accrued at 26 work days per year, unless agreed otherwise

    in the MOU.

    Vacation Leave shall be accrued at 26 work days per year.

    Employee Conduct, Disciplinary Action, Termination The company

    policy and the UAE Government labor law shall apply in all cases. A copy of

    the applicable sections of the labour law currently in force are included in

    Appendix I .5-1.

    REFERENCES:

    Appendix 1.4-2,Performance Appraisal/Rating

    Appendix 1.5-1,UAE Labour Law

  • 8/14/2019 POP_Construction.pdf

    29/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 I-26

    APPENDIX LIST - SECTION - I

    Appendix I.1-1 Project Location Map

    Appendix I.1-2 Simplified Flow Diagram Construction Supervision

    Appendix I.2-1 Project Information

    Appendix I.3-1 Project Organization Chart

    Appendix I.3-2 Memo M.S. Khan to Staff, P/CO/IOM/6914, 11 April 1998

    Appendix I.3-3 Memo M.S. Khan to Design Section Managers, 15 February 1997,

    TRIP Design Responsibilities

    Appendix I.4-1 Correspondence Format

    Appendix I.4-2 Office Forms

    Appendix I.5-1 UAE Labour Law

  • 8/14/2019 POP_Construction.pdf

    30/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998

    Section 2.0 Control of the Work

  • 8/14/2019 POP_Construction.pdf

    31/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-1

    2.0 CONTROL OF THE WORK

    2.1 Client Interface

    Delegation of Authority from Client The authority given to the Consultant

    comes by way of the original agreement between Abu Dhabi Municipality and

    De Leuw, Cather. A copy of that portion of the agreement showing the scope

    of work and the delegation of authority is included in Appendix I I .1-1.

    There have been four addenda since the original agreement. Addenda 1,2,

    and 3 simply amended one provision and added road projects to the

    Agreement with no change in authority or scope of services. Addendum 4

    added parking garages and added the following positions to the ones alreadyin the Agreement.

    Mechanical Engineer Specialist Parking Structures

    Electrical Engineer Specialist Parking Structures

    Architectural Engineer Specialist Parking Structures

    Structural Engineer Specialist Parking Structures

    Client/Consultant Relationship The Municipality relies logically on the

    Resident Engineer as the key person on the construction supervision staff as

    indicated in the letter dated 20 March 1995 from Saeed Trais Al Mazroui

    (Re: RS/CONSULTANTS/95/401.)Appendix I I .1-2. The Resident Engineerwill thus be the main link between the Client and the Consultant - supported

    by central office and site staff.

    Working Interfaces - The interfaces operate on a counterpart basis as

    follows.

    Municipality: De Leuw, Cather:

    Saeed Trais Al Mazroui Mahmud Khan

    Asst. Undersecretary Program Director

    Abdulla Salem Al Katheeri Yingsak Pancom

    Chief of Road Section Project Director

    Ali Al Aidarous P.K. Asokan

    Chief of Electrical and Deputy Project Director

    Mechanical Division

    Site Representatives Senior Resident

    Engineers, Resident

    Engineers

  • 8/14/2019 POP_Construction.pdf

    32/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-2

    These are the official connecting channels. There will be times when various

    levels of the Municipality will cross channels, and if so, each of theconsultants staff has the obligation and the freedom to answer questions

    posed to them. Their obligation extends to immediately communicating the

    nature and content of the discussion to the appropriate staff member in light of

    the framework shown above.

    Client Instructions - Client instructions will be by written letters signed by

    the Assistant Undersecretary, Chief of Road Section, or other authorized

    persons. In the event instructions are issued verbally in lieu of written

    instructions, the Resident Engineer/Senior Resident Engineer should

    immediately initiate a letter confirming the verbal instructions of the

    Municipality prior to initiating any action. Confirmation letters shall followthe format as shown in Appendix I I -1-3.

    In addition to the requirements as specifically identified in the Contract

    Documents, the Clients written directives issued from time to time during the

    execution of works shall be implemented in the execution of the works. The

    Appendices listed below include examples of the Municipalitys recent

    directives related to various construction activities.

    - Appendix I I .1-4 Interim and Final Payment Certificates

    -Appendix I I .1-5

    Excavation Works- Appendix I I .1-6 Lighting Works

    - Appendix I I .1-7 Monthly, Bi-Monthly and Financial Status Reports

    - Appendix I I .1-8 Street Naming and Numbering Signs

    - Appendix I I .1-9 Materials Resulting from Excavation Works in Road

    Projects

    - Appendix I I .1-10 Pressure Testing of Irrigation Lines

    - Appendix I I .1-11 Preliminary and Final Handing Over of Projects

    2.2 Contractor Interface

    Contractors Organization At this writing, 19 Contracts are underconstruction. Rather than include all 19 organizations, typical organization

    charts are shown in Appendix I I .2-1and a listing of Contractors is included in

    Appendix I .2-1.

    Contact with Contractor A regimented system must be maintained so that

    misunderstandings and conflicting viewpoints and interpretations can be

    avoided. Communications between the Engineer and the Contractor must be

    clear cut and without ambiguity. Conflicts and misunderstandings can cause

    delays to the schedule and unnecessary additional costs.

  • 8/14/2019 POP_Construction.pdf

    33/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-3

    The Resident Engineer and his staff will be in daily contact with the staff of

    the Contractor as the work progresses. While probably informal in tone, theissues and problems discussed should be considered as if they are official and

    formal and where necessary included in one or more written instruments.

    The following communication procedures shall be observed by the Engineers

    and Contractors staffs.

    1. Regular meetings shall be chaired by the Resident Engineer and

    attended by the Assistant Resident Engineer and the Contractors

    Project Manager and key staff. These meetings should be held at

    least monthly and usually more often than that at the discretion of

    the Resident Engineer. Typical areas of discussion:

    -- progress

    -- quality standards and control

    -- schedule

    -- change orders

    -- resources

    -- conflicts

    -- utilities

    -- operating methods

    -- any other issue of mutual interest

    The Resident Engineer will prepare an agenda to be distributed

    prior to the meeting and he will appoint one person to take the

    minutes. These will be distributed to the persons attending the

    meeting.

    2. Inspectors will deal directly with the Contractors foreman on the

    job site. The Inspectors should never interpose themselves

    between the foreman and his crew and attempt to direct the

    Contractors operations. The Inspector will notify the Foreman of

    any discrepancies in quality and deviations from the Contract orspecifications. He will have day-to-day dialogue with the Foreman

    of the construction operation the Inspector is assigned to. The

    Inspector must notify the ARE or Resident Engineer immediately

    of nonconformance.

    3. Assistant Resident Engineers will communicate with the foreman

    in the presence or with the knowledge of the Inspector. The AREs

    will maintain communication with the Contractors Project

    Manager consistent with the policy and concurrence of the

    Resident Engineer.

  • 8/14/2019 POP_Construction.pdf

    34/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-4

    4. Resident Engineers are the ones authorized to issue officialcorrespondence to the Contractor. These will be addressed to the

    Contractors Project Manager and will be signed by the Resident

    Engineer and the Project Director or Deputy Project Director. The

    Resident Engineer will meet with the Project Manager and discuss

    issues and make decisions related to the project on a routine

    frequency as necessary.

    5. The technical staff shall deal directly with the Contractor and have

    communications with key Contractor personnel only with the

    consent and knowledge and participation of the Resident Engineer

    or his designated representative from the project staff.

    6. From time-to-time site instructions may be issued depending on the

    urgency of a situation. The Resident Engineer or Assistant

    Resident Engineer with the concurrence of the Resident Engineer is

    authorized to issue site instructions. These will be followed by a

    formal letter from the Resident Engineer confirming the directions

    given in the site instruction as soon as possible.

    Approval of Subcontracts - The Contractor may normally submit a list of

    subcontractors with his tender but this isnt a hard and fast rule. As a matter

    of precedence after the construction starts, the following steps have been

    established for subcontractor approval. It is understood that this program has

    been underway for 18 years so that most of the subcontractors are repeat

    performers. Thus the approval of subcontractors has become a routine matter.

    1. The Contractor will submit a completed form to the Resident

    Engineer (see Appendix III.2-2) with the particulars of the

    subcontractor he wishes to have approved. The Contract may

    stipulate a maximum percentage of work that can be subcontracted.

    2. The Resident Engineer or whomever he assigns will review thedocuments submitted by the Contractor; check to make sure that

    contractual requirements will be met. If not, the subcontractor

    would be rejected out-of-hand. If the subcontractor is marginal in

    terms of qualifications, then the Resident Engineer should consult

    with the Senior Resident Engineer, Project Director, Contract

    Administrator, or the Deputy Project Director for construction.

    The subcontractor in some cases may be rejected, in others the

    Resident Engineer may request more information from the

    Contractor.

  • 8/14/2019 POP_Construction.pdf

    35/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-5

    3. If the Resident Engineer has no objection to the subcontractor, he

    will forward to the Project Director, through the Deputy ProjectDirector for construction, the recommendation for approval to be

    sent on with the Project Directors signature to the Municipality.

    4. If questions are raised by the Municipality then further discussions

    will be held until either the subcontractor is approved or rejected,

    or more information is requested from the Contractor.

    5. If approved by the Municipality, they will sign the form approved

    and return the document to the Consultant with a letter. The

    Resident Engineer would then send a letter to the Contractor

    approving the subcontractor.

    Schedule Approval The Resident Engineer is obligated to review and

    recommend the approval of the Contractors schedules. Refer to

    Appendix I I .2-2 for the scheduling requirements of the Contract between the

    Contractor and the Municipality and a typical work program.

    The Resident Engineer and his staff will review the Contractors initial

    schedule and will analyze it on the basis of:

    -- conformance to the Contract time for completion

    -- approvals for greenery (trees and grass) removal

    -- availability and time required for approval and procurement of

    materials

    -- construction staging plan

    -- detours and police approval

    -- utility work and accommodations of work by others

    -- labor, plant, and equipment resources

    -- critical path time scheduling and logical sequencing of activities

    -- weather and religious considerations

    -- mobilization and pre-construction activities

    -- clean-up and final inspection-- special circumstances involving the public

    The Resident Engineer will comment and discuss the schedule with the

    Contractor until he is satisfied that it will work. He then will submit the

    schedule to the Project Directors office and will notify the Contractor in

    writing that the schedule is approved, once the Department has approved it.

    Shop Drawing Approval - Shop drawings, as defined in the Contract

    documents, shall include plans, details, fabrication methods, erection layouts,

    setting drawings, marking for erection, applied finishes, and sizes of all

    prefabricated members and fittings to be constructed, erected, or installed as

  • 8/14/2019 POP_Construction.pdf

    36/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-6

    part of the permanent structure. Shop drawings also include manufacturers

    data for materials, equipment, and fixtures, including catalog sheets showingdimensions, performance characteristics, and capacities, wiring diagrams and

    controls, schedules and other pertinent required information. This scope also

    includes the review and approval process of the suppliers of such

    manufactured materials, equipment, and fixtures.

    Method Statements for specific operations may be required by the

    specifications or the Engineer to fully describe the procedures and materials.

    These should be submitted for review and approval along with the shop

    drawings and other supporting documents.

    The Contractors working drawings for temporary structures shall beprocessed in the same manner as for shop drawings.

    The Contractor shall:

    1. Supply one (1) sepia transparency and two (2) prints of each shop

    drawing to the Resident Engineer. The drawings shall be the same size

    (overall and area within the border) as the standard Contract drawings.

    The drawing title block shall contain the following:

    - Abu Dhabi Municipality and Town Planning Department, United

    Arab Emirates;

    - Consultants name;

    - Contractors name;

    - Contract designated name and number;

    - Contractors drawing title, number, and date;

    - Identification and signature of designer, draftsman, and checker;

    - Scale;

    - Future Revisions section;

    - Space for Engineers shop drawing review, receiving date,

    drawing log number, and reviewer stamps.

    2. Convey completed shop drawings to the Resident Engineer by letter on

    the Contractors stationery or by the Contractors shop drawing

    transmittal form. The Contractor shall submit six (6) copies of all

    documents relating to suppliers or materials and equipment, and/or

    manufacturers data covering materials and/or equipment.

    3. All documents and shop drawings prepared by the supplier,

    manufacturer, or subcontractor shall be submitted under the Contractors

    name and shall be identified by affixing the above given title block. In

    cases where catalogs are submitted, a schedule of items proposed shall

    be attached, as well.

  • 8/14/2019 POP_Construction.pdf

    37/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-7

    4. Shop drawing and document submittals containing deviations from thespecifications and drawings shall have the deviations tabulated on a

    sheet attached to the transmittal letter. Shop drawings and documents

    shall be submitted to the Resident Engineer well in advance of the

    scheduled manufacture or construction date.

    The Resident Engineer shall:

    1. Receive shop drawings, transmissions, catalog data, manufacturers

    data, etc.

    2. Date stamp and affix a Project shop drawing number to each sheet.The format of the Project shop drawing number shall be X-YYYY.

    X shall be the Contract number. YYYY shall be sequential

    numbers starting with 0001 for each Contract.

    3. Enter all pertinent data into a log book, including the Project shop

    drawing numbers.

    4. Assign drawings to appropriate reviewers, making two (2)

    additional prints per reviewer and entering all pertinent data in the

    log book. When submission by the Contractor involves

    manufactured materials and/or equipment to be incorporated into

    the Works, the Soils and Materials Engineer shall be consulted to

    determine testing requirements to verify conformance with the

    specification.

    5. Receive reviewed drawings, or catalog data, etc., with checkers

    comments, entering data in the log book.

    6. Consolidate all comments received from various disciplines into

    one set of comments reconciling any discrepancies or

    contradictions through discussions with the reviewer. Mark two

    (2) prints. Affix appropriate stamps, enter in the log, forward one(1) copy to the Contractor and one (1) to the appropriate file.

    7. If submission is comprised of catalog or manufacturers data, the

    Resident Engineer shall reconcile the reviewers comments, then

    include them in a letter to the Contractor, affixing stamps to

    catalog, etc., as appropriate.

    8. Maintain a file copy of every drawing or document processed.

    Note: When the drawing or document is approved, the approval stamp shall be

    placed on the sepia, and only the sepia is to be returned to the Contractor

  • 8/14/2019 POP_Construction.pdf

    38/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-8

    The Contractor, in turn, returns four (4) prints of the approved shop

    drawing for the Resident Engineers use. When the drawing is returnedto the Contractor without approval, the appropriate stamp shall be placed

    on one print only. The sepia is returned without a stamp.

    The stamp to be used will indicate the following disposition:

    STAMP SPECIMENS

    Project Name Shop Drawing No.

    Contract No. Contractor

    APPROVED APPROVED AS NOTED

    As to general detail and arrangement only. This approval does not relieve

    the Contractor of responsibility for conformity to specifications and correct

    details and fit of parts after assembly.

    (CONSULTANT)

    Date: By:

    Project Name Shop Drawing No.

    Contract No. Contractor

    NOT APPROVED ITEM INCORRECT

    COMMENTS NOTED DO NOT RESUBMIT

    REVISE AND RESUBMIT SUBMIT SPECIFIED ITEM

    (CONSULTANT)

    Date: By:

    REFERENCES

    Construction Manual, Chapter 1.0, Sections 100.07.100.10, 100.12

  • 8/14/2019 POP_Construction.pdf

    39/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-9

    2.3 Control of Work

    General - Resident Engineers Authority The Resident Engineers

    authority shall be as delegated by the Company in accordance with the

    Contract Documents and will be according to the letter dated March 20, 1995

    from the Assistant Undersecretary of the Municipality ( See Appendix I I .1-2).

    The Resident Engineer will have the responsibility and authority to direct the

    Contractor to comply with the Contract documents and specifications; monitor

    and call for adjustments in resources to meet the schedule; be the

    correspondent with the Contractor jointly with the Deputy Project Director or

    Project Director; give approvals for shop drawings and materials and

    construction methods; approve interim and final measurements for payment;

    make recommendations to the client on claims and disputes with the

    Contractor.

    Local Permits - The Contractor shall make arrangements and pay any

    associated costs for use of borrow or aggregate pits unless they have been

    designated for use by the Department. This includes permits for access roads

    he may want to use.

    The Contractor shall also obtain approval of the Department and other relevant

    Government Agencies for the use of:

    - Plant sites

    - Camp sites

    - Stockpile areas

    - Staging areas

    - Waste areas

    - Borrow sites

    Resident Engineers Diary - The Resident Engineer is required to keep a daily

    dairy for each project. The Resident Engineer's Diary is an important document

    that records all contractual and procedural events that occur on the project. On

    larger projects, the diary presents an overview of the daily activities extractedfrom the individual dairies maintained by key supervisory staff. The Resident

    Engineer's diary is also a personal record of oral communications and

    discussions that may have contractual implications. The diary is usually

    compiled by the Resident Engineer from the Inspectors and Assistant Resident

    Engineers daily diaries and reports supplemented with additional entries and

    comments. The Resident Engineer certifies these entries with his signature.

  • 8/14/2019 POP_Construction.pdf

    40/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-10

    RESIDENT ENGINEERS DIARY CHECKLIST

    ! Weather.

    ! Orders given to the Contractor.

    ! Important discussions with the Contractor or his representative, such

    as disputes.

    ! Official visitors and inspections.

    ! Work or materials rejected and reasons.

    ! Time of shutting down or resuming work and explanations.

    ! Work done by the Contractors forces during the day.

    ! Account of any time spent by the Contractors personnel or

    equipment on disputable items of work and especially any work which

    might be the basis of a claim.! Length and cause of any delay.

    ! Arrival and departure of major equipment and work crews.

    ! Record of important telephone calls.

    ! Unusual conditions, if any, such as high water, bridge failures, slides,

    unsatisfactory subgrade or foundation conditions, detour conditions,

    etc. Care should be used when explaining hazardous conditions.

    ! Progress of staking and surveys.

    ! When appropriate, daily surveillance of traffic control as to

    effectiveness.

    ! An up-to-date inventory of the Contractors equipment and a list of

    the Contractors work force.

    The Resident Engineer will be required to maintain a bound book to facilitate

    preparing the Daily Diary form. The Daily Diary will be the sole official

    record.

    The diaries shall be numbered consecutively and the Resident Engineer once

    having completed the writing for the day will draw a diagonal line across the

    empty space, if any, following the last written sentence. He will sign his name

    on this line, signifying that no more notations can be added.

    If for some reason a correction, revision, clarification, or redress of a

    misunderstanding is in order, the Resident Engineer will so note in subsequent

    diary entries.

    The diary should be completed each day.

  • 8/14/2019 POP_Construction.pdf

    41/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-11

    Inspectors Daily Report - Each Inspector is required to prepare an Inspector's

    Daily Report providing detailed information on the day's activities. Each report ispertinent to the task or construction operation assigned to the individual

    Inspector. The Inspector's work assignments will be allocated such that all

    project activities including Maintenance of Traffic Items are recorded on a daily

    basis. The report form may be supplemented by sketches, measurements, or

    calculations on additional sheets as necessary to complete the record of daily

    work. In practice, the inspector should maintain a field diary or bound field note

    book to record the days activities and make notes, sketches, etc., that may be

    summarized and neatly transformed to the prepared report form at the end of the

    day. The Inspector's reports are reviewed and signed by the Resident Engineer

    (or Assistant Resident Engineer) daily.

    Specific construction operations require use of special forms or reports. The

    Inspector assigned to the task is responsible for completing the forms and

    submitting the reports as attachments to his Daily Report.

    Progress and Construction Site Photos The Contractor provides a camera,

    the film, and pays the development costs. The Resident Engineer or his assigned

    staff member will take photos approximately each month and record and store

    the photos all according to the following criteria.

    1. The photographer should take photographs that define the before

    and after situation.

    2. He should designate the same location at critical places on the job-

    site where he takes photos each month in the same direction to show

    the amount of incremental progress.

    3. In the event of a dispute over something on the site, take photos to

    show the condition at the site.

    4. He should take photos that show the beginning of an operation.

    5. He should take photos of accidents and mishaps as evidence of what

    happened.

    6. The photos should be stamped on the reverse side of the photograph

    and the date, time of day, location, and description recorded on the

    special stamp.

    7. These should be stored in an album or other booklet so that they are

    in sequence and can be kept together as a project record.

  • 8/14/2019 POP_Construction.pdf

    42/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-12

    From these photos the Resident Engineer will select the ones for the monthly

    report.

    Utility Coordination - The Resident Engineer will, after discussion with the

    Deputy Project Director-Construction, arrange a pre-construction utility

    meeting between the Contractor and the various public agencies involved in

    the project. The intent of this meeting is to establish cooperation among all

    parties and to coordinate activities and schedules.

    During the meeting, the interested parties may be encouraged to communicate

    with each other directly for day-by-day general planning and implementation.

    It is the Resident Engineers responsibility to keep in regular touch with each

    of the concerned parties to be aware of progress and future plans. Sitemeetings with the relevant utility agencies shall be conducted monthly or as

    decided by the Resident Engineer in consultation with the Utility Coordinator.

    The meetings are to be documented and the minutes distributed.

    Utilities - Most of the TRIP construction projects are affected by utilities

    including the preservation of existing utilities and/or installation of new or

    relocated utility services. Existing utility locations shown on the project plans

    are approximate only. The exact location of existing utilities is determined as

    follows.

    Record Drawings -The Contractor is responsible for obtaining all available

    as-built or record drawings of existing utilities within the project limits from

    the appropriate government departments, utility agencies, and designated

    utility consultants. The Contractor should also request assistance in the field

    location of the services and discuss issues relating to safety, protection, and

    condition of the facilities.

    Shop Drawings - The Contractor will prepare shop drawings showing the

    existing utility locations relative to the proposed works. The first step in this

    procedure is to develop a grid or network of proposed hand excavation

    trenches as necessary to uncover all existing utilities shown on the recorddrawings. The grid will be submitted to the Resident Engineer for approval.

    Manual Excavation - Manual excavation of the approved trench locations is

    initiated by the Contractor in coordination with the various utility owners.

    Data information sheets are prepared for each trench that indicates the location

    of each utility by station and offset from the appropriate survey control line.

    Utility type, diameter, pipe material, and elevation are determined for each

    utility.

  • 8/14/2019 POP_Construction.pdf

    43/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-13

    The inspector should ensure that the information is complete for each trench.

    He should direct modifications to the trench alignment, depth, or length asnecessary to suit field conditions. Additional trenches may be authorized to

    provide enough data to accurately plot the existing utilities on drawings.

    The Contractor is responsible for the protection and safety of existing utilities

    throughout the project. The requirements for protection, relocation, and new

    services will be determined in coordination with the various utility

    departments using the completed existing utility shop drawings developed

    from the hand excavation as the basis for decision making.

    Service Reservations - The Contract drawings include identification of

    service reservations for accommodation of existing and proposed utilities. TheContractor will prepare service reservation shop drawings following an

    assessment of the existing utility locations, relocation requirements, and layout

    of proposed utilities. Modification to the reservations shown on the Contract

    drawings is often necessary to effectively accommodate a service facility.

    Revisions must be approved by the Town Planning Department and then

    copies of the approved shop drawings are distributed to all concerned

    Departments, Utility Agencies, and their consultants.

    Control of Materials - The Municipalitys approval is required for all

    materials incorporated in the Works. All materials except electrical and

    mechanical items will be subject to the review and approval by the

    Municipalitys materials approval committee. Review and approval of the

    electrical and mechanical materials will be by the Chief of the Electrical and

    Mechanical Division of the Abu Dhabi Municipality. Prior to recommending

    the approval of materials to the Municipality, the review of the Contractors

    submittal by the Chief Soils and Materials Engineer, other relevant Section

    Managers, and the applicable Utility Agencies should be completed. Approval

    of materials will be controlled and documented by Form No. AM-1 and Form

    No. AM-2 included in Appendix.II.3-1. The procedures as indicated in the

    Flow Charts for Materials Submittals and Approvals in Appendix .I I .3-2and

    as stated herein shall be followed for approval of materials to be incorporatedin the Permanent Works.

    1. The Contractor shall submit for the approval of all concerned

    parties a complete description with details of the materials together

    with the names of manufacturers/suppliers from whom he proposes

    to obtain such items. In addition to the above, the Contractors

    submission shall include:

    SM-29 form duly completed with all relevant details.

    Material Approval forms duly completed for use of the

    Department and the Consultant.

  • 8/14/2019 POP_Construction.pdf

    44/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-14

    Table of comparison listing the specified properties of the

    material vs. the actual properties of the proposed material. Original catalogues, where applicable.

    Sufficient samples for testing or inspection.

    Current inspection report by an acceptable Independent

    Laboratory stating that the materials comply with the

    requirements of all Contract Documents, or

    Material specification compliance statement explaining anydeviations in the specified and providing justifications for the

    deviations and an evaluation of the materials superiority or

    deficiency as compared to the specified item .

    2. Upon satisfaction with the Contractors submission, the Consultant

    shall recommend the Contractors submittal to the concerned

    Agency for approval.

    3. Upon receiving the Agency approval, the Consultant shall

    recommend the above and other materials (not requiring an agency

    approval) for approval of the Department.

    4. Upon receipt of the Departments approval, the Consultant shall

    notify the Contractor of the basis for the approval.

    Test requests - The recommended procedure for submitting samples for

    testing is as follows:

    1. Each sample submitted to the laboratory shall be accompanied by a

    Request for Testing from the Resident Engineer.

    2. A sample tag shall be attached to each sample.

    3. All samples shall be entered into the Sample Receipt and Testing

    Book with relevant details.

    4. Concrete cubes shall be numbered consecutively and entered at the

    back of the Sample Receipt and Testing Book. The columns shall

    be revised to show 7-day and 28-day testing dates and other

    appropriate information.

    5. The applicable standard should be referred to for the testing

    procedure. Copies of these standards and the actual testing

    procedure shall be supplied to each field laboratory and to the

    central laboratory.

  • 8/14/2019 POP_Construction.pdf

    45/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-15

    6. The tests shall be carried out promptly based on priorities

    established by the Soils and Materials Engineer. All electrical andmechanical samples shall be tested jointly by the Chief Soils and

    Materials Engineer and the Electrical/Mechanical Engineer.

    7. The test results shall be issued and signed by the Soils and

    Materials Engineer.

    8. Municipality Materials Engineer will review test results.

    9. Finally the test results are forwarded to the Resident Engineer with

    comments.

    Quality Control Procedures - Sampling and testing to ensure compliance

    with the Specifications involves a joint cooperative effort among the

    Department, Resident Engineer, Contractor, Manufacturer or Supplier, and the

    Materials Engineer. The Department or Resident Engineer can order additional

    testing as thought necessary, at any time. General quality control procedures

    are described for the basic components used in local highway and bridge

    construction.

    Testing Records - The Testing Forms numbers SM.1 through SM.39 (sample

    forms are included in Appendix I I .3-3) are used in the laboratory to calculate

    the results of the test whose subject title the individual form refers to. Results,

    where specific, are normally given at the bottom of or on the extreme right

    hand side of the forms.

    Relevant forms of specific use to the Resident Engineer are: SM-1, 3, 3A, 5,

    5(A), 5(B), 5(C), 7, 8, 9, 15, 18, 23, 24A, 24C, 24G, 25, 26, 27, 28, 29, 29A

    32 and 34.

    SM.1: Moisture Content Test The percentage of moisture in the soil is

    determined by this test.

    SM.3: Gradation Test The percentage distribution of grain sizes present in

    the soil sample is determined by this test..

    SM.3(A): Aggregate Sub-base Gradation Test The percentage distribution

    of grain sizes in the aggregate sub-base is determined by this test.

    SM.5: Gradation Distribution Curve The percentage distribution of soil

    grain sizes in the test sample and whether the soil is graded well, uniformly

    graded, or poorly graded is visually apparent by observation of the test data

    plotted on this form.

  • 8/14/2019 POP_Construction.pdf

    46/76

    Program Operations Plan Construction

    Revision No. & Date _________________

    31 July 1998 II-16

    SM.5(A): Gradation Distribution Curve, Type V The percentage

    distribution of the various size rock and soil particles in the type V perviousmaterial is determined by this test and the results as well as the specified limits

    are plotted on the form as a visual comparison aid.

    SM.5(B): Gradation Distribution Curve for Type III The percentage

    distribution of the particle sizes in the type III pervious material is determined

    by this test and the results as well as the specified limits are plotted on the

    form as a visual comparison aid.

    SM.5(C): Gradation Distribution Curve for Type II - The percentage

    distribution of the particle sizes in the type II pervious material is determined

    by this test and the results as well as the specified limits are plotted on theform as a visual comparison aid.

    SM.7: Compaction Test - The maximum dry density and optimum moisture

    content of the soil sample are determined by this test.

    SM.8: Field Density Test (Sand Replacement Method)- The percentage of

    compaction achieved at the depth of the sample is determined by this test..

    SM.9: Bulk Density of Sand - The bulk density of sand, which is used to

    ascertain the volume of the tested hole in the Field Density Test (Sand

    Replacement Method), is determined by this test.

    SM.15: Concrete Strength Test- The compressive strength of the concrete is

    determined by this test.

    SM.18: Concrete Core Test The apparent cube strength of a concrete

    sample taken by coring is determined by this test..

    SM.23: Request for Testing of Construction - The first part of this form is

    filled out by the Contractor on completion of a section of work considered

    ready for testing. Approval to carry out such testing as requested is given bythe Resident Engineer after checks for acceptable workmanship, level, and any

    other requirements the Resident Engineer may have are fulfilled. Results are

    given o