35
1 RISK MANAGEMENT: Oh Oracle! … What are You Telling Me? RISK MANAGEMENT AS A BUDGETING TOOL

PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

1

RISK MANAGEMENT:

Oh Oracle! … What are You Telling Me?

RISK MANAGEMENT AS A BUDGETING TOOL

Page 2: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Remember?..... Risk Characteristics

• A definable event

• Probability (Likelihood) of occurrence

• Impact (Consequence) of occurrence

A risk event that has materialized

i.e. ”became a reality”

is a

PROBLEM (an “ISSUE” for PMBOK®)

Page 3: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

3

StartCompletion

Data History Current Experience Hindsight

Information GeneralUncertainty

SpecificUncertainty

TotalCertainty

RiskUnknown Unknowns

KnownsKnown Unknowns

What is Risk?

Presenter
Presentation Notes
PMBoK® December 2000, An uncertain event or condition that, if it occurs, has a positive or negative effect on a project's objectives.
Page 4: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Remember?..... Characteristics of Risk Events

Risk Events are—

• Situational

– They have no textbook answer

– Team must relay on sound use of tools and methods/techniques

• Time based

– Risk is a future phenomenon only

– Time affects risk perceptions

• Interdependent

– One risk event (or mitigations) can affect others

– One risk can cause others

– Quantity of risks may affect perceptions

Page 5: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Remember?..... Characteristics of Risk Events (continued)

• Magnitude dependent– The greater the payoff, the more the risk is acceptable

– The higher the impact, the more significant the risk

• Value based– Personal and cultural values affect company risk taking

– Company values affect individual choices

– Everyone sees risk differently

Page 6: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

6

Internal

External

Requirements CreepMacro-Management

Teamwork

ScheduleIntegration

Personnel

Technical

Constructive Change

CommunicationCosts

Policy Changes

Customers

Labor Force

Budget

Acts of Congress

Micro-Management

EconomyActs of God

Scope Changes

Regulatory

Industrial Base

Internal

Policy Changes

Customers

Micro-Management

Labor Force

Scope Changes

Budget

Regulatory

Seek to CONTROL the Internal and INFLUENCE the External

Remember?..... Sources of Risk

Page 7: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Do Not Forget!....The Nature of Risk

THREAT OPPORTUNITY

Probability of Failure (Pf)

Consequence of Failure (Cf)

Probability of success

Benefit of success(the Consequence)

Note: Failure to properly control the risk…

The “Balance” of Risk

Page 8: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Do Not Forget!.... The Nature of Risk

THREAT OPPORTUNITY

Probability of Failure (Pf)

Consequence of Failure (Cf)

Probability of Success

Benefit of success(the Consequence)

The “Balance” of RiskQuestion: Why should you take a risk?

Answer #1: To gain a specific reward!

Answer #2: Sometimes you don’t have a choice!

Page 9: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Probability and Impact (Matrix) Samples

5

4

3

2

1

1 2 3 4 5

HIGH

MODERATE

LOW

5

4

3

2

1

12345

HIGH

MODERATE

LOW

Risk vis – a – vis Opportunity

Page 10: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

THREAT OPPORTUNITY

Probability of Failure (Pf)

Consequence of Failure (Cf)

Probability of Success

Benefit of success(the Consequence)

Key Messages on Risks

Conclusion Related to Risk Characteristics and Perceptions

Presenter
Presentation Notes
Must have a process rooted in group dynamic techniques Must have a set of analytical tools that supports these factors Planning and preparing for risk management must be continuous and ongoing Risks is like a Balance has a dual nature that includes Threats & Opportunities. Risk has three components: the event, the probability of occurrence, and the impact of occurrence. Project risk is an uncertain event or condition that has a positive or negative effect on a project objective. Risk management is the systematic process of identifying, analyzing, and responding to project risk. Risk events are situational, time based, interdependent, magnitude dependent, and value based.
Page 11: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

R I S K D O C U M E N T A T I O N

11

Project Risk Management Overview

PerformQualitative

Risk AnalysisIdentify Risks

PerformQuantitative

Risk Analysis

PlanRisk

Responses

Monitor &

Control Risks

PlanRisk

Management

Presenter
Presentation Notes
The Project Risk Management Process has Six Basic Components Some consider 5 with Qualitative & Quantitative Analysis combined.
Page 12: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Risk Response Control Terms

• Problem (ISSUE): a negative risk event (known or unknown) that has materialized

• Windfall: a positive risk event (known or unknown) that has materialized

• Workaround: unplanned (not defined in advance) response to negative risk event

• Corrective action: performing the response to a negative risk event (either planned, as with contingency plans, or unplanned, as with workarounds)

Page 13: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Risk Response Control Terms

• ASSUME A RISK: A GAMBLE that the Risk Event is not going to occur.

– Program Manager DO NOT CONTINUE MESSING WITH IT!

• MITIGATE A RISK: To lessen the effects of event.

– Mitigations create own Risks!

– Use Experimentation

– Requires Plans, Schedule, and $$$

Page 14: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Risk Response Control Overview

Risk response control

Updatedrisk

responsedevelopment

Project executionand

control processes

Riskreassessment

Execute

Evaluate

Document

RiskManagementPlan

Updatedrisk

management plan

Planned responses,evaluations, additionalresponses

Updated prioritizedrisk list

Progress,deviations,variances

Page 15: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Risk Response Control – A Closer Look

Risk ResponseControl

Contingency Plans Workarounds

Additional RiskResponse Development Acceptance

RiskEvents

AdditionalRisk Identification

CorrectiveAction

LessonsLearned

Updated Risk Management Plan

Page 16: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Risk Response Control Guidelines

• For risk response control to work, project managers must

– Closely monitor project progress

– Timely execute risk responses when problems (issues) or windfalls occur

– Thoroughly evaluate effectiveness of risk responses

– Continuously follow up

• The only way to do this effectively is as part of the overall project management plan and process

– The Risk Management Plan is a critical component of the project plan

Page 17: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

• Carry out risk management plan as part of project execution although it is done throughout the project

• Carry out risk strategies as risk becomes actual events

• Communicate plan status to project team members

Risk Management

Planning

Identify

Analyze

Prioritize

Document

Evaluate

Execute

Plan

Communicate

Page 18: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Execute Risk Strategies

InputEstablish an

early warning system (Trigger

Events)

Input• Project plan• Risk management plan• Actual risk events• Additional risk identification

Tools• Risk response strategies• Personal management tools

• Communication• Time management

• Project management tools• Network • Cost and schedule reporting process• Team Meetings and status reports

• Decision-making tools• Decision trees• Lifecycle cost analysis• Financial measures• Probability functions

Assignresponsibility

forrisk control

Executeproject plan

ExecuteRisk

ManagementPlan

Monitorproject status

Carry outcontingency

plans

Carry outwork-arounds

Communicate Risk

Response Control

Results of corrective

action

Page 19: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Establish Early Warning System

Establish an early warning system to detect deviations from plan that may be or may cause risk triggers

– Exposure increases as cost and schedule variances increase

– Example of an early warning system include –

• Earned value (EVM)

• Cost variance

• Schedule variance

• Change in forecasted project end date

• Change in float

• Change in stakeholder attitude

Page 20: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Risk Quantification and Expected Monetary Value

• Involves numerically assessing probability and impact

• Expected Monetary Value (EMV) is a statistical assessment of risk value, not a prediction of final cost should the risk occur or not occur

• EMV = (probability of occurrence) amount at stake)

• Assess –

– Best case (all good things happen and no bad)

– Worst case (all bad things happen and no good)

• Final actual value will probably fall between best case and worst case

Page 21: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Based on Analysis – Decide

Strategies for Threats (Negative Risks)

Strategies for Opportunities (Positive Risks)

Avoid Exploit

Transfer Share

Mitigate Enhance

Accept Accept

Page 22: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Based on Analysis –What Do You Decide

Handling Strategy is decided– Mitigate

• Experimentation• Transferring of Risk

– Sub-Contractor– Hiring Expert Consultants

– Accept (Higher Authority can Effect)• Passive Acceptance

– Team deals with risk when it occurs (i.e.- when it becomes a problem)

• Active Acceptance-– A Contingency Plan is in place in case risk event occurs.– No Action taken until risk event occurs.

» Most common strategy-set up Contingency Reserve for time, money and resources

Page 23: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Based on Analysis –What Do You Decide

• Contingency response strategies can include:

– Contingency Plans• Includes actions taken if:

– An identified risk occurs

– A risk trigger is detected that identifies when the contingency plan should be implemented.

• Fallback Plan:– A fallback plan is developed when a selected risk strategy is

» not fully effective, or

» Risk has high impact.

Example Changing project scope, developing alternatives, or allocating a contingency amount

Page 24: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Contingency vs. Management Reserves

• Contingency Reserves are set within the project/program to deal with Known Risks.

– Project Manager controls this reserve.

– Part of project budget

– Part of EVM calculations.

• Managements Reserves Work are set within the sponsor portfolio/senior executive management to deal with Unknown Risks.

– Project Manager does not control this reserves.

– Not part of project budget

– Not part of EVM calculations.

Page 25: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Decision Tree – The Rules

• Represent decisions by boxes (decision nodes); represent outcomes or events by circles

• Enter the primary decision on the left side of the tree and work from left to right

• Represent all possible scenarios by paths

• Assign probabilities to all path segments leading from events

• Determine expected value for each segment

• Work from right to left, adding expected values of all path segments leading to a decision node

• Work until the most advantageous path is established

Page 26: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Decision Tree Example

Should we build a prototype of the new flight simulator product? Project requirements were poorly defined. As a result, there is a risk that the final product will not pass the customer acceptance test. A prototype also would substantially reduce the cost of rework for failures at customer acceptance test.

Cost to build prototype $98,000Probability of passing customer acceptance test

with prototype 90%without prototype 20%

Cost of rework after customer acceptance testwith prototype $20,000without prototype $250,000

Page 27: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Decision Tree Example with Probability

Build prototype

Do not build prototype

90%

10%

80%

20%

Pass customer acceptance test

Fail customer acceptance test

Pass customer acceptance test

Fail customer acceptance test

Page 28: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Decision Tree Scenario with Expected Value

Build prototype

Do not build prototype

Pass customer acceptance test

Fail customer acceptance test

Pass customer acceptance test

Fail customer acceptance test

Expected Value with prototype$98,000 + $2,000 = $100,000

Expected Value without prototype$0 + $0 + $200,000 = $200,000

Page 29: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

29

Purchase or Code Software

Purchase Software-$50,000

Code Software

-$120,000

Fills Need

Does Not Fill Need

40%

No Added Impact

60%

- 50,000 X .40 = - $20,000

- $250,000 X .60 = - $150,000-$200,000

-$170,000

Works

Does Not Work

80%

No Added Impact

20%

- 120,000 X .80 = - $96,000

- $120,000 X .20 = - $30,000-$30,000

-$126,000

DecisionDefinition Decision Node Chance Node Net Path Value

Expected Monetary Value

(EMV)

Page 30: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Cost Reserve Allocated

• What cost reserve should I allocate for these risks?

– Say on a risk you have…..

• 25% Probability that a key Design Engineer will be reassigned to project with a extra cost of $6000,

• 40% probability that the new technology inserted/used will require additional training at an extra $4,000 cost to budget

• and 20% probability of using existing computer applications saving project $8,000.

<.25 X $6000> +<.40 X $4,000> + (.20 X $8,000)=

<threat (negative risk)> + <threat (negative risk)> + (opportunity (positive risk)) =

<-$1,500> + <-$1,600> + ($1,600) = -$1,500

Page 31: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Build Your Planned Costs

• As part of Project Cost Mgt-Knowledge Area under Planning Process Group

– Estimate Costs

– Determine Budget

• Build Mitigation plans

– Determine Schedules, Resources and associated Costs

• Each Risk Event (perhaps combination thereof) has a Mitigation “packet”

• Stack these Mitigation Packets

– Update Project Plan

– Inform Stakeholders

Page 32: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

Build Your Planned Costs

• As part of Risk Analysis (Qualitative and Quantitative)

– Prioritize Risks

• Propose Responses (Handling Strategies)

• Schedule responses based of the strategy

• Effect mitigations

• Acceptance risks (Active) upon decisions from PM

– Whatever can be scheduled into future-Mitigation Packet becomes an input into new budgeting process.

Page 33: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

33

Risk Management As Budget Summary

• Risk Management provides a glimpse into the future of Project

• Risk Management is a tool that assists

– the preparation of budgets,

– cost controls,

– and stakeholder expectation management

• Reduce the impact of less desirable outcomes

• Decrease the probability of the risk event itself

• Assist bottom line by surfacing Opportunities and leveraging them into cost savings.

• Help out-year budgeting, leveling “burn rate”, historical files

Page 34: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

34

QUESTIONS?

Presenter
Presentation Notes
The Department of Defense (DOD) has mandated that all major acquisition programs must ensure that Environmental, Safety, and Occupational Health (ESOH) risks are identified and managed throughout the acquisition process. The PMS377 Program has integrated ESOH into all aspects of the PMS377 Program. The Programmatic Environmental, Safety, and Health Evaluation (PESHE) summarizes the Program Manager’s (PM) strategy for meeting ESOH requirements, establishes responsibilities, and identifies how progress will be tracked.
Page 35: PMP Risk Presentation - PMI Emerald Coast FL · • Risk Management provides a glimpse into the future of Project • Risk Management is a tool that assists – the preparation of

35