Upload
lamtu
View
214
Download
1
Embed Size (px)
Citation preview
1Copyright © PMI SOC 2013
Chapter # 12Project Procurement Management
PMP Exam PreparationWorkshop
Copyright © 2013 PMI SOC
2Copyright © PMI SOC 2013
Objective & Agenda Introduction to Project Procurement Management
Understanding the processes of project procurement
management in the four process groups:1. Plan Procurement Management
2. Conduct Procurements
3. Control Procurements
4. Close Procurements
Inputs, tools and techniques, and outputs (ITTO’s) of the
four processes & interaction with other knowledge areas.
Sample exam questions
3Copyright © PMI SOC 2013
Definitions
Procurement:
• Acquisition of products, services, or results.
Procurement Management:
• The processes necessary to purchase or acquire products,
services, or results needed from outside of the project team.
Assumptions
There is an existence of a formal contract between the buyers &
sellers.
The Buyer of product/services/Item for the project is assigned to
the Project team & Seller belongs to the different organization.
Project Procurement Management Introduction
4Copyright © PMI SOC 2013
Buyer-Seller Relationship
Terms for Buyer• Client• Customer• Prime Contractor• Acquiring Organization• Service Requestor• Purchaser
Terms for Seller• Contractor• Subcontractor• Vendor• Service provider• Supplier
Project Procurement Management
6Copyright © PMI SOC 2013
12.1 Plan Procurement Management
PMBOK Ref # Fig 12-2
Project Procurement Management
• The process of documenting project procurement decisions,
specifying the approach, and identifying potential sellers.
7Copyright © PMI SOC 2013
Data Flow
PMBOK Ref # Fig 12-3
Project Procurement Management 12.1 Plan Procurement Management
8Copyright © PMI SOC 2013
Project Management Plan (Section 4.2.3.1)
Requirements Documentation (Section 5.2.3.1)
Risk Register (Sections 11.2.3.1 & 11.5.3.2)
Activity Resource Requirements (Section 6.4.3.1)
Project Schedule (Section 6.6.3.2)
Activity Cost Estimates (Section 7.2.3.1)
Stakeholder Register (Section 13.1.3.1)
Enterprise Environmental Factors (Section 2.1.5)
Organizational Process Assets (Section 2.1.4)
Project Procurement Management 12.1.1 Plan Procurement Management - Inputs
9Copyright © PMI SOC 2013
Fixed Price Contracts
• Firm Fixed Price Contracts (FFP): The buyer will pay the seller one fixed fixed amount regardless of how much it costs the seller to complete the work.
• Fixed Price Incentive Fee Contracts (FPIF): The buyer will pay the seller one fixed amount plus financial incentives tied to achieving agreed upon metrics (performance goal).
• Fixed Price with Economic adjustments (FP-EPA): The buyer will pay the seller one fixed amount with a special provision allowing for predefined final adjustments based on changed conditions such as inflation & commodity price fluctuations; could be used when the seller’s performance period spans a considerable period of years.
Project Procurement Management 12.1.1 Plan Procurement Management - InputsOrganizational Process Assets – Contract Types
10Copyright © PMI SOC 2013
Organizational Process Assets – Contract Types
Cost-Reimbursable Contracts
• Cost Plus Fixed Fee (CPFF): The buyer will reimburse the seller for all allowable costs plus a fixed-fee payment calculated as a percentage of initial estimated project costs.
• Cost Plus Incentive Fee Contracts (CPIF): The buyer will reimburse the seller for all allowable costs plus a predetermined incentive fee based upon achieving certain performance objectives.
• Cost Plus Award Fee Contracts (CPAF): The buyer will reimburse the seller for all allowable costs but the majority of the fee is earned only based on the satisfaction of certain broad subjective performance criteria.
Project Procurement Management 12.1.1 Plan Procurement Management - Inputs
11Copyright © PMI SOC 2013
Contract Types- Time & Material
Time and Material Contracts (T & M)
• Buyer will reimburse the seller with the time cost of labor (time) and the cost of materials.
• Contains aspects of both cost-reimbursable and fixed-price contracts.
• Cost-reimbursable when these costs are left open ended.
• Fixed-price when certain parameters are specified in the contract:
• Not-to-exceed values
• Time Limits
Project Procurement Management 12.1.1 Plan Procurement Management - Inputs
12Copyright © PMI SOC 2013
Contract Type vs. Risk CPFF: Cost + Fixed FeeCPIF: Cost + Incentive Fee FPIF: Firm Price + Incentive Fee FFP: Firm Fixed Price
Project Procurement Management 12.1.1 Plan Procurement Management - Inputs
13Copyright © PMI SOC 2013
Make-or-Buy Analysis • Management technique used to determine whether work can best be
accomplished in-house or purchased from outside sources.• Determining factors include budget, schedule, capability, resources, quality,
supplier skills & abilities, contract types.
Expert Judgment• Often used to assess inputs/outputs from this process.
• Purchasing judgment is used to develop criteria to evaluate seller proposals.
• Legal judgment to assist with procurement terms & conditions.
Market Research• Examination of industry specific vendor capabilities through conferences,
online reviews and other sources to identify market capabilities.
Meetings• Information interchange meetings with potential bidders.
12.1.2 Plan Procurement Management – Tools & Tech.
Project Procurement Management
14Copyright © PMI SOC 2013
Procurement Management Plan
Procurement Statement of Work
Procurement Documents
Source Selection Criteria
Make-Or-Buy Decision
Change Requests
Project Document Updates
Project Procurement Management 12.1.3 Plan Procurement Management – Outputs
15Copyright © PMI SOC 2013
Procurement Management Plan
• Component of Project Management Plan.• Describes how the project team will acquire goods and services from outside the
organization.• Describes how the procurement processes will be managed from developing
procurement documents through contract closure including:• Type of contracts to be used.• Risk management issues.• If independent estimates will be used / are needed.• Standardized procurement documents.• Assumptions & constraints that could affect planned procurements.• Make-or-buy decisions.• Scheduled dates in each contract for contract deliverables.• Direction to be provided to sellers on developing and maintaining the
WBS.• Prequalified sellers.• Procurement metrics.
More…PMBOK pg 366-367
12.1.3 Plan Procurement Management – Outputs
Project Procurement Management
16Copyright © PMI SOC 2013
Procurement Statement Of Work
Developed for each procurement from the project scope baseline and defines only that portion of project scope that is to be included within the related contract.
Describes the procurement item in a clear, complete, and concise manner to allow prospective sellers to determine if they are capable of providing the products, services, or results.
Can include: Specifications. Quantity. Quality levels. Performance data. Period of performance. Work location.
Project Procurement Management 12.1.3 Plan Procurement Management – Outputs
17Copyright © PMI SOC 2013
Procurement Documents
Documents are used to seek proposals from prospective sellers. Common terms for procurement documents:
Request for information (RFI) Invitation for bid (IFB) Request for proposal (RFP) Request for quotation (RFQ) Tender notice Invitation for negotiation Seller initial response
Procurement documents are structured to facilitate an accurate and complete response from each prospective seller and to facilitate the evaluation process.
Procurement documents include a description of the desired form of seller response, the relevant procurement statement of work, source selection criteria, and any contractual provisions.
Project Procurement Management 12.1.3 Plan Procurement Management – Outputs
18Copyright © PMI SOC 2013
Source Selection Criteria
Criteria used to rate and score proposals. Often included in procurement documents.
Possible Source Selection Criteria: Understanding of need. Overall or life-cycle cost. Technical capability Risk Warranty Financial capacity Production capacity and interest Past performance of sellers References
More…PMBOK pg 369
Project Procurement Management 12.1.3 Plan Procurement Management – Outputs
19Copyright © PMI SOC 2013
Make-Or-Buy Decisions
Analysis results in a decision of whether particular work can
best be accomplished by the project team or to be purchased
from outside sources.
A buy decision drives the process of reaching agreement with a
supplier for the product or services.
Project Procurement Management 12.1.3 Plan Procurement Management – Outputs
20Copyright © PMI SOC 2013
Change Requests
Project Procurement Management 12.1.3 Plan Procurement Management – Outputs
A decision to procurement goods, services, or resources
typically requires a change request.
Change requests are processed for review and disposition
through the Perform Integrated Change Control Process (4.5).
Changes to the project management plan may result in change
requests that impact procurement actions.
21Copyright © PMI SOC 2013
Project Documents Update
Project Procurement Management 12.1.3 Plan Procurement Management – Outputs
Project documents that may be updated include:
Requirements documentation.
Requirements traceability matrix.
Risk register.
22Copyright © PMI SOC 2013
Project Procurement Management 12.2 Conduct Procurements
PMBOK Ref # Fig 12-4
• The process of obtaining seller responses, selecting a seller,
and awarding a contract.
23Copyright © PMI SOC 2013 PMBOK Ref # Fig 12-5
Project Procurement Management 12.2 Conduct Procurements
24Copyright © PMI SOC 2013
Procurement Management Plan (Section 4.2.3.1)
Procurement Documents (Section 12.1.3.3)
Source Selection Criteria (Section 12.1.3.4)
Seller Proposals
Project Documents (Section 11.5.3.2)
Make-or-Buy Decisions (Section 12.1.3.5)
Procurement Statement Of Work (SOW) (Section 12.1.3.2)
Organizational Process Assets (Section 2.1.4)
Project Procurement Management 12.2.1 Conduct Procurements - Inputs
25Copyright © PMI SOC 2013
Bidder Conferences
Proposal Evaluation Techniques
Independent Estimates
Expert Judgment
Advertising
Analytical Techniques
Procurement Negotiations
Project Procurement Management 12.2.2 Conduct Procurements – Tools & Techniques
26Copyright © PMI SOC 2013
Also known as contractor conferences, vendor conferences and
pre-bid conferences.
Meetings with Prospective Sellers & Buyers prior submitting a
bid/proposal.
Ensure that all sellers have clear & common understanding of
the procurement requirements.
Fairness is addressed by techniques such as collecting
questions from bidders or arranging field visits in advance of
conference.
Project Procurement Management 12.2.2 Conduct Procurements – Tools & Techniques
Bidder Conferences
27Copyright © PMI SOC 2013
A formal review evaluation process used for complex
procurements defined by the buyer’s procurement policies.
Source selection will be made based on seller responses
evaluated using previously defined weighted criteria.
Evaluation committee will make a selection on a seller for
approval by management prior to the award.
Project Procurement Management 12.2.2 Conduct Procurements – Tools & Techniques
Proposal Evaluation Techniques
28Copyright © PMI SOC 2013
Estimate prepared either by the procuring organization or by a
professional estimator.
Estimate serves as a benchmark on proposed response.
Significant differences in estimates can be an indication that the
statement of work was deficient, ambiguous, and /or that
prospective sellers misunderstood or failed to respond fully to
the procurement statement of work.
Project Procurement Management 12.2.2 Conduct Procurements – Tools & Techniques
Independent Estimates
29Copyright © PMI SOC 2013
Used to evaluate seller proposals.
Evaluation proposals may be accomplished by a multi-discipline
review teams with expertise in the areas covered by the
procurement documents.
Various functional disciplines that may be asked to provide
expertise include contracting, legal, finance, accounting,
engineering, design, research, development, sales, and
manufacturing.
Expert Judgement
Project Procurement Management 12.2.2 Conduct Procurements – Tools & Techniques
30Copyright © PMI SOC 2013
Advertising in general circulation publications or in specialty
trade publications.
Purpose is to extend existing list of potential sellers.
Mandatory requirement in some government jurisdictions for
certain types of procurement items.
Project Procurement Management 12.2.2 Conduct Procurements – Tools & Techniques
Advertising
31Copyright © PMI SOC 2013
Analytical techniques help organizations to identify the
readiness of a vendor to:
Provide the desired end state.
Determine the cost expected to support budgeting.
Avoid cost overruns due to changes.
Involves defining a need in such a way that vendors/sellers can
bring value through their offerings
Examining past performance information may identify high risk
areas that need to be monitored closely.
Project Procurement Management
Analytical Techniques
12.2.2 Conduct Procurements – Tools & Techniques
32Copyright © PMI SOC 2013
Clarifies the structure, requirements and other terms of the purchases to
reach mutual agreement prior signing the contract.
Final contract language should reflect all agreements reached and should
include: Responsibilities.
Authority to make changes.
Applicable terms and governing law.
Technical and business management approaches.
Proprietary rights.
Contract financing.
Technical solutions.
Overall schedule.
Payments
Price
Project Procurement Management
Procurement Negotiations
12.2.2 Conduct Procurements – Tools & Techniques
33Copyright © PMI SOC 2013
Negotiator should not do the following: Rush the process Attempt to leave one stage incomplete Rush to the next stage too quickly
Project Procurement Management
Procurement Negotiations
12.2.2 Conduct Procurements – Tools & Techniques
34Copyright © PMI SOC 2013
Protocol Stageo Introductionso Negotiator get to know each othero Atmosphere for the rest of the negotiation meeting is
determined
Probing Stageo Beginning of search processo Each party identify their issues & concernso Identify Strengths/Weaknesses and possible area of interesto Negotiation plan updated to take into account any new
information
Procurement Negotiations: Protocol & Probing Stage
Project Procurement Management 12.2.2 Conduct Procurements – Tools & Techniques
35Copyright © PMI SOC 2013
Scratch Bargainingo Bargaining Startso Differences between both parties are discussedo Points of Consensus are identifiedo Efforts made to bridge gaps/ shortfalls
Closure Stageo Documents final consensuses between both partieso Arrangements for recording the results initiated , leading to
last stage
Procurement Negotiations: Scratch Bargaining & Closure Stage
Project Procurement Management 12.2.2 Conduct Procurements – Tools & Techniques
36Copyright © PMI SOC 2013
Agreement Stageo Ensures that both parties have an identical understanding of
the agreements reached.o Clarifications may be necessary due to difference in
terminology.o Negotiations may be re-openedo Development of Plans for creating a written contract.
Procurement Negotiations: Agreement Stage
Project Procurement Management 12.2.2 Conduct Procurements – Tools & Techniques
37Copyright © PMI SOC 2013
Deadlineo Impose a deadline for reaching an agreemento Limits the time involved allowed for negotiating
Surpriseo One party takes on the other party by surpriseo One party may have some information (e.g. Price change )
and present it to the other party Limited Authority
o The agreement cannot be finalized due to the Limited authority with negotiator
o Stalling tactico Knowing the authority of the opponent early in the
negotiation meeting
Procurement Negotiations: Tactics
Project Procurement Management 12.2.2 Conduct Procurements – Tools & Techniques
38Copyright © PMI SOC 2013
Procurement Negotiations: Tactics
Project Procurement Management
Missing Mano One party may claim that the person with final authority is
absent.
Fair & Reasonableo Comparisons to other similar situations e.g. “Price is fair
because other company is paying the same price for the assignment”.
Delayso Tactical use of delays.o Delay to get back on track.o Delay to cool down when temper flares.o Need time to further research.
12.2.2 Conduct Procurements – Tools & Techniques
39Copyright © PMI SOC 2013
Procurement Negotiations: Tactics
Project Procurement Management
Reasoning Togethero Working out disagreements for benefit of all involved.
Confusing the Opponento One person deliberately distorts issues & figures to confuse
opponent.
Withdrawalo One party makes a false allegation/attack upon issue & retreats.o Usually done to avert attention from a possible area weakness.
Unreasonableo Making opponent appear un-reasonable.
12.2.2 Conduct Procurements – Tools & Techniques
40Copyright © PMI SOC 2013
Project Procurement Management
Arbitration
o Involving third party to settle down issues.
Fait accompli
o One party may claim that what is being asked has already
been accomplished and cannot be re-called/changed.
o Any changes at this stage will have an monetary & schedule
impact on the project.
12.2.2 Conduct Procurements – Tools & Techniques
Procurement Negotiations: Tactics
41Copyright © PMI SOC 2013
Non-competitive Selection
Project Procurement Management
Single Source
o Occurs when the buyer selects a single seller company to
provide products or services.
Sole Source
o Occurs when there is only one seller that can cater to the
requirements and there isn’t any competition.
o Buyers negotiation powers get affected due to monopoly of
seller in the field.
12.2.2 Conduct Procurements – Tools & Techniques
42Copyright © PMI SOC 2013
Types of Warranties
Project Procurement Management
One party assures that the goods will meet certain standards.
Expressed warranty is written in the contract.
Implied warranty is a measure of “merchantability” or “fitness for
a particular purpose”.
Waiver: Provides loss of rights under a contract.
12.2.2 Conduct Procurements – Tools & Techniques
43Copyright © PMI SOC 2013
Project Procurement Management
Selected Sellers
o Sellers who have been judged to be in a competitive range
based on the outcome of the proposal or bid evaluation.
o Draft contracts will become the actual contract when an award is
made.
Agreements
o Includes terms & conditions and other items that the buyer
specifies about what the seller is to perform or provide.
o Project team’s responsibility to ensure that all agreements meet
the specific needs of the project.
12.2.3 Conduct Procurements – Outputs
45Copyright © PMI SOC 2013
Project Procurement Management
Change Requests
o Changes to the project management plan, its subsidiary plans,
and other components.
Project Management Plan Updates
o Updates to the cost baseline, scope baseline, schedule baseline,
communications management plan, procurement management
plan.
Project Documents Updates
o Updates to requirements documentation, requirements
traceability documentation, risk register, stakeholder register.
12.2.3 Conduct Procurements – Outputs
46Copyright © PMI SOC 2013
12.3 Control Procurements
Project Procurement Management
PMBOK Ref # Fig 12-6
• The process of managing procurement relationships, monitoring
contract performance, and making changes and corrections to
contracts as appropriate.
47Copyright © PMI SOC 2013
12.3 Control Procurements
Project Procurement Management
PMBOK Ref # Fig 12-7
48Copyright © PMI SOC 2013
Project Procurement Management
Application of appropriate project management processes to the
contractual relationship(s) with selected sellers.
Integration of the outputs from these processes into the overall
management of the project.
Project management processes that are applied include:
o Direct and manage project work.
o Control quality.
o Perform integrated change control.
o Control risks.
12.3 Control Procurements
49Copyright © PMI SOC 2013
Project Procurement Management
Has a financial management component being the monitoring of
payments to seller which ensures:
Payment terms in the contract are met.
Payments are linked to seller progress; close relationship of
payments made to the work accomplished.
Reviews and documents how well a seller is performing or has
performed based on the contract.
Involves capturing details to determine if corrective actions or
early termination are needed.
Review can be used as a measure of the seller’s competency
for performing similar work on future projects.
12.3 Control Procurements
50Copyright © PMI SOC 2013
12.3.1 Control Procurements - Inputs
Project Procurement Management
Project Management Plan (Section 4.2.3.1)
Procurement Documents (Section 12.1.3.3)
Agreements (Section 12.2.3.2)
Approved Change Requests
Work Performance Reports (Section 4.4.3.2)
Work Performance Data (Section 4.3.3.2)
51Copyright © PMI SOC 2013
12.3.2 Control Procurements – Tools & Techniques
Project Procurement Management
Contract Change Control System
Procurement Performance Reviews
Inspections & Audits
Performance Reporting
Payment System
Claims Administration
Records Management System
52Copyright © PMI SOC 2013
12.3.2 Control Procurements – Tools & Techniques
Project Procurement Management
Contract Change Control System
Defines the process to modify procurements.
Procurement Performance Reviews
Structured review of the seller’s progress to deliver what is
defined in the contract.
Inspections and Audits
Performance Reporting
Payment Systems
53Copyright © PMI SOC 2013
12.3.2 Control Procurements – Tools & Techniques
Project Procurement Management
Claims Administration
Documenting, processing, monitoring and managing instances
where the buyer and seller cannot reach an agreement on
compensation for a change or cannot agree that a change has
occurred.
Also referred to as claims, disputes, appeals.
Records Management System
System used to manage contract and procurement
documentation and records.
54Copyright © PMI SOC 2013
12.3.3 Control Procurements – Outputs
Project Procurement Management
Work Performance Information
Change Requests
Project Management Plan Updates
Procurement Management Plan
Schedule Baseline
Cost Baseline
Project Document Updates
Organizational Process Assets Updates
55Copyright © PMI SOC 2013
12.4 Close Procurements
Project Procurement Management
PMBOK Ref # Fig 12-8
• The process of completing each procurement.
56Copyright © PMI SOC 2013
12.4 Close Procurements (cont’d)
Project Procurement Management
PMBOK Ref # Fig 12-9
57Copyright © PMI SOC 2013
12.4.1 Close Procurements – Inputs
Project Procurement Management
Project Management Plan
Procurement Documents
58Copyright © PMI SOC 2013
12.4.2 Close Procurements – Tools & Techniques
Project Procurement Management
Procurement Audits
Structured review of the procurement process
originating from Plan Procurement Management
through Control Procurements.
Objective is to identify successes and failures.
Procurement Negotiations
Final equitable settlement of all outstanding issues,
claims and disputes.
Settlement through negotiation is ideal.
Records Management System
59Copyright © PMI SOC 2013
12.4.3 Close Procurements – Outputs
Project Procurement Management
Closed Procurements
Formal written notice that the contract has been
completed.
Organizational Process Assets Updates
Procurement File.
Deliverable Acceptance.
Lessons Learned.
60Copyright © PMI SOC 2013
Project Procurement Management
PMP Exam PreparationSample test questions
Copyright © 2013 PMI SOC
61Copyright © PMI SOC 2013
Answer:
Question #1You are working on a very dynamic project. You need a specific technical skill which is not available in the team. Consequently you have hired a contractor. Market conditions which drive the requirements are fluctuating. What is the best way to handle this situation? A- Firm fixed price contract- this way your cost is fixed no matter what the requirements will be
B- Cost plus fixed fee contract - this way you will pay only for the work done by the contractor
C-Cost plus incentive fee contract – since the contractor has an incentive to keep their costs down -
D-Make the contactor part of the agile team which includes the customer & the project team members
E- C & D
62Copyright © PMI SOC 2013
Answer:
Question #2You’ve been contracted by an industrial design firm to manage their
contracting. Your client asks you to take over the negotiations for an important
contract to design a new lighting remote control system. You’ve narrowed it
down to one seller, and now you’re working with the legal department at the
buyer to negotiate the terms of the contract. Which of the following BEST
describes your goal?
A.You want to make sure that the seller gets as much money as possible
B.You want to get the best deal for your client by making sure the seller’s price
is as low as possible, no matter what it costs them
C.You want to prolong the negotiation so that you earn a higher fee
D.You want to get a fair deal for both the buyer and the seller
63Copyright © PMI SOC 2013
Answer:
Question #3Which of the following BEST explains the difference between a seller audit
during Administer Procurements and a procurement audit during Close
Procurements?
A.The seller audit reviews the products being created, while the procurement
audit is used to examine successes and failures and gather lessons learned
B.The seller audit reviews the products being created, while the procurement
audit reviews how well the seller is doing the job
C.The procurement audit reviews the products being created, while the seller
audit reviews how well the seller is doing the job
D.The procurement audit reviews the products being created, while the seller
audit is used to examine successes and failures and gather lessons learned
64Copyright © PMI SOC 2013
Answer:
Question #4You have been assigned to a project where the previous project manager left. You find the scope was documented but not the business objectives. The scope has suddenly changed –but the change is not documented. In addition, a contractor was hired for a Fixed Price contract to deliver the previous scope. What tasks should you do & in what order?. 1- Negotiate with the contractor to close the FFP contract & change the contract to a cost + incentive fee
2-Meet with the stakeholders to assess the situation, understand the business objective & determine how the project will deliver the benefits
3-–Document the new scope, asses where the project stands & re baseline immediately A- 3,1 B- 2, 3, 1C- 3, 1, 2 D- 2, 1
65Copyright © PMI SOC 2013
Answer:
Question #5
You are managing a project that might have to contract out work, and
you’re comparing the relative advantages and disadvantages of finding
a seller versus having your company do the work itself. Which process
are you in?
A.Conduct Procurements
B.Plan Procurements
C.Request Seller Responses
D.Plan Contracting
66Copyright © PMI SOC 2013
Answer:
Question #6
You’re looking for a seller to do work for your project. When do you
send out an RFP?
A.Before you plan contracting, but after you Plan Procurements
B.After you create the procurement documents, but before you select
the seller
C.During Administer Procurements
D.After the bidder conference, but before you select the seller
67Copyright © PMI SOC 2013
Answer:
Question #7
What are the Procurement processes?
A. Plan, Conduct, Administer, Monitor & Control, Close
B. Plan Purchases and Acquisitions, Plan Contracting, Request Seller
Responses, Select Sellers, Contract Administration, Contract Closure
C. Plan Procurements, Conduct Procurements, Administer Procurement,
Close Procurements
D. Determine, Plan, Conduct, Monitor & Control, Close
68Copyright © PMI SOC 2013
Answer:
Question #8
The project's contractor payment system should include:
A. An administrative review
B. A review of work performed
C. Negotiations over price
D. A viable account payable system
69Copyright © PMI SOC 2013
Answer:
Question #9
The contract administrator should provide ___________ at contract
closure.
A.Contract file to the contractor
B.Letters of commendation to all project staff
C.Formal notice of deliverable acceptance to the contractor
D.Lessons learned documentation to senior management/buyer
70Copyright © PMI SOC 2013
Answer:
Question #10
you inherited a project where some work was contracted as FFP. Your manager had signed off on the contract The stakeholders have just requested a scope change due to changing industry conditions. You were conducting a procurement audit & found the contractor performing to deliver the previous scope. What should you do next? 1- Understand the business conditions that caused the scope change & document the change 2-Request a contingency for your project to cover the FFP amount in the contract since you were not responsible for it3-Negotiate with the contractor to close the FFP & start a time and material contract 4- Tell the stakeholder there is a fixed price contact & any change will increase the cost of the project so they are aware A- 1, 2 & 3 B- 1, 3, & 4 C- 1, 2, 4 D 1, 3 only
71Copyright © PMI SOC 2013
Answer:
Question #11
Close Procurement documentation includes all of the following
EXCEPT:
A.Scope, schedule, and change documentation
B.Financial documents
C.The RFP or RFB and seller's working proposal
D.Results of contract-related inspections
72Copyright © PMI SOC 2013
Answer:
Question #12
Potential contract changes should be:
A.Postponed as long as possible to protect the budget
B.Viewed as negative, quantified, and tabulated
C.Quantified and fed back through the perform integrated change
control process
D.Reviewed by senior management and the buyer
73Copyright © PMI SOC 2013
Answer:
Question #13
The purpose of a procurement audit is to do all of the following
EXCEPT:
A.Maintain a complete file of contract-related records.
B.Determine if the bid documents used were effective.
C.Determine if the contract change control system was effective
D.Identify successes and failures and their implications
74Copyright © PMI SOC 2013
Answer:
Question #14
When the procurement item is available from only one supplier, all of
the following evaluation criteria should be identified and documented to
support an integrated assessment EXCEPT:
A.Management approach
B.Standard forms
C.Life cycle cost
D.Technical capabilities
75Copyright © PMI SOC 2013
Answer:
Question #15
All of the following methods are available to the project manager for
short-listing contractor proposals EXCEPT:
A.Comparing proposals against independent estimates
B.Weighting systems
C.Subjective screening systems
D.Resource distribution system
76Copyright © PMI SOC 2013
Answer:
Question #16
You have been diligent in capturing lessons learned. You have just discovered a new tool that automates testing & will save you 15 % of testing cost –on a given task – in fact there is potential for it to be applied to all testing . You also have a contractor hired on a Fixed Price contract What should you do next? 1-Llist this as an accomplishment in the stakeholder meeting & advise them you will finish your test early by 2 weeks 2_ Share it with your team & with the contractor & your manager 3- Share it only with your manager & immediate team members – but not with the contractor – since they are on an FFP contract 4- Negotiate with the contractor ½ the savings achieved by the tool A – 1 B – 3C- 2D – 2 & 4
77Copyright © PMI SOC 2013
Answer:
Question #17
FFP is an acronym for:
A.Free Flow Performance
B.Fundamentally Fixed Price
C.Firm Fixed Price
D.Free Form Project
78Copyright © PMI SOC 2013
Answer:
Question #18
Which of the following item is not a Tool & Technique used in Plan
Procurement Management :
A.Make-or-buy analysis
B.Market Research
C.Contract Negotiations with the Sellers
D.High level meetings with upper management involving the customer
79Copyright © PMI SOC 2013
Answer:
Question #19You are the PM for the Union Station Extension Project and have awarded the
electrical scope to Sparky Electrical Inc. There have been numerous issues with
the quality of the work performed by Sparky Electrical causing schedule delays
resulting in penalty charges by the client. There is a new project starting in your
organization and the project team is considering awarding electrical scope to
Sparky Electrical.
Which of the following would have assisted the new project team in the vendor
selection process :
A. Contract Change Control system
B. Procurement Contract
C. Performance Reporting
D. Payment Systems
80Copyright © PMI SOC 2013
Answer:
Question #20
A new hospital is being constructed and your company has been selected to
deliver the entire project from design to construction. The client states that there
is no room in their budget for additional charges. Your company will perform
some of the work but most of the scope will be subcontracted. As the PM, you
need to ensure that your subcontractors understand the budgetary constraints
and are clear on the scope of work.
Which of the following is the best type of contract to use on this project?
A. Cost plus fixed fee
B. Fixed Price
C. Time and Material
D. Cost plus Incentive Fee