Resource Management

PMINEO Chapter Meeting - March 17, 2010

Presented by

- Bob Zoller, Cleveland Clinic

- Todd Jones, Westfield Insurance

- Diane Gormley, American Greetings

See “View > Notes Page” in powerpoint for details

For copies, examples, contact [email protected]

Page 2: PMINEO_2010_03_Resource_Management

2

Four Golden Rules for Resource

Management

1. Schedule projects when requested, even if you

don’t know if deadlines are realistic

2. Add “important” new projects to the workload,

without removing other work

3. Shift resources from one project to another, to

temporarily calm angry stakeholders

4. When running late…. reduce testing, training,

and documentation

… just kidding …

Page 3: PMINEO_2010_03_Resource_Management

3

Resource Management Functions

Resource allocation

Performance appraisal

Career planning

Page 4: PMINEO_2010_03_Resource_Management

4

Agenda

Background

PMINEO survey

Recommendations

Example Tools

Panel presentations

Todd Jones, Westfield Insurance

Diane Gormley, American Greetings

Panel Q&A

Page 5: PMINEO_2010_03_Resource_Management

5

PMINEO Survey

1) Description

2) Maturity Levels 1-5

3) Tool Usage

4) Relationship Of Staff Size and Maturity

5) Items That Varied By Maturity Levels

6) Items Consistent Across Maturity Levels

7) Benefits, Summary

Page 6: PMINEO_2010_03_Resource_Management

6

PMINEO Survey -

1)Description

Reviewed existing surveys and background.

Built 28 items in survey tool (Sheryl Sovie)

Sent to email list (3,000) (Joe Anastasi)

Responses:

125 opened the survey, to instruction page

100 answered at least first question

57 finished the entire survey

Page 7: PMINEO_2010_03_Resource_Management

7

PMINEO Survey

2)Maturity Levels (1-5) Responses by self-ranking on maturity level:

Level Description of Resource Mgmt

Processes (paraphrase survey)

% Sum

1 Do not exist in consistent form 32 32

2 Exist, used on some projects 25 57

3 Exist, used on most projects 21 78

4 Exist, on most projects. Integrated

with other systems. Performance

data exists.

17 95

5 Exist, on most projects. Integrated.

Performance data exists.

Mandated.

5 100

- TOTAL 100 -

Page 8: PMINEO_2010_03_Resource_Management

8

PMINEO Survey

3)Tool Usage

(*) Percentage using a tool; multiple tools used (% > 100)

Nbr Tool % (*)

1 MS-Excel (Microsoft) 84

2 MS-Project, Desktop (Microsoft) 78

3 MS-Sharepoint (Microsoft) 29

4 MS-Access (Microsoft) 21

5 MS-Project, Server (Microsoft) 19

6 Custom in-house application 18

6 IBM Lotus Domino/Notes (IBM) 18

8 CA-Clarity (CA) 11

9 SAP Enterprise (SAP) 8

10 Primavera (Oracle) 7

10 PeopleSoft Enterprise (Oracle) 7

Page 9: PMINEO_2010_03_Resource_Management

9

PMINEO Survey

3)Enterprise Tool Usage

Enterprise tools more common in larger orgs

Relative to project resource pool size:

For all tools, average size [51-200] resources

For Enterprise tools, average size [201-500] resources

Page 10: PMINEO_2010_03_Resource_Management

10

PMINEO Survey

4)Relationship Of Staff Size and Maturity

Maturity level tends to be higher for larger groups

Typical resource pool size and maturity (1-5)

[Resource pool size]/(maturity level)

[1-50]/(1,2) [51-200]/(3-4) [200+]/(4-5)

Page 11: PMINEO_2010_03_Resource_Management

11

PMINEO Survey

5)Items that varied by maturity level

Is PMO involved in managing resources?

No (level 1) Yes (increasing rates for levels 2, 3, 4, 5)

Frequency of Resource Planning & Forecasting

Inconsistent (1, 2) At least annual (3) At least qurtrly (4,5)

Resource planning is performed mostly by

PM or functional mgr (1,2) Resource Mgr (3,4,5)

Resource availability is determined mostly from

Manual check (1,2,3,4 decreasing) RM system (5)

Page 12: PMINEO_2010_03_Resource_Management

12

PMINEO Survey

6)Items Consistent Across Maturity Levels

Project planning/forecasting granularity level(*):

Project (73%), task (27%), phase (25%)

Project tracking granularity level (*):

Milestone (49%), task (38%), Earned Value (8%)

Plan significant change in coming year to RM process:

Yes (40%), No (60%)

Multi-tasking:

2-4 projects (70%), 5 or more (18%), 1 (12%) (*) select multiple; total not = 100%

Page 13: PMINEO_2010_03_Resource_Management

13

7)Process Benefits, from references

From references [2] and [3], improvements in RM processes lead to improvements in the following. Magnitude is not described.

- Alignment of projects with strategy

- Project Success

- Financial success

- Stakeholder satisfaction

From reference [4]

- Project Managers can handle twice as many projects

- Construction times reduced by up to 15% (Optional slide)

Page 14: PMINEO_2010_03_Resource_Management

14

PMINEO Survey

7)Summary and key points

Maturity rankings: 57% with inconsistent or no process

Larger organizations tend to have more mature

processes because they must

Enterprise-type tools typically used for PMINEO orgs

with roughly 200 or more project resources.

Organizations can predict resource workloads at level

3 or above (“process in place, used on most projects”)

Page 15: PMINEO_2010_03_Resource_Management

15

Recommendations

1) Portfolio and Project Planning

2) Resource Identification

3) Time Management

4) Monitoring Project Progress

5) Tools and Other Organizational Issues

6) Implementation

Page 16: PMINEO_2010_03_Resource_Management

16

Recommendations

1)Portfolio and Project Planning

Portfolio-level planning

longer horizon, ex: one year, for high level priority and sequencing

rough time estimates in man-weeks/months, by skillset (ex: DBA)

use resource buffers and staggering to prevent domino effect

Project-level scheduling

shorter horizon, ex: quarterly window, refreshed monthly

use “rolling wave” for execution-level schedule. PMBOK 6.1.2.2

Coordinate forecast cycle with fiscal or business cycles

Define a way to show resource demand vs supply

Execute with simple spreadsheets or enterprise style tools

Page 17: PMINEO_2010_03_Resource_Management

17

Recommendations

2)Resource Identification Planning staff granularity

When possible, forecast with pools. Individuals vary more.

In larger orgs, establish a way to find resources by skillset

Identify Bottleneck resources

Typically key resources set pace. See “drum” in ref [7] Ch 15

Bottleneck resources may be sufficient for pipeline sequencing

Cross-train for more flexibility

Try to separate “project” resources from “support” resources

Assign resources to as few projects as practical

Reference: (ABC,123) vs (A1B2C3) Example

Page 18: PMINEO_2010_03_Resource_Management

18

Recommendations

3)Time Management

Time reporting

Track time at least at project level, preferably phase level

Value of time reporting

Historical time records can be used in future estimates

Implement time tracking early, to start building history

Short term value for monitoring project progress (below)

Long term value for management decisions

Ex: excessive maintenance is a symptom of problems

Time estimating Expert, analogous, parametric, 3-point. See PMBOK 6.4.2

Page 19: PMINEO_2010_03_Resource_Management

19

Recommendations

4)Monitoring Project Progress

Focus on progress overall, not primarily task completion

Compare actual to forecast at least monthly

Recalibrate project schedules if appropriate

Take corrective action: reduce scope; cancel (save 10% ?)

For relief - look at critical path and bottleneck resources

Find lessons learned for estimating and forecasting. Ex:

Find ways to improve estimating process

Find other factors that contribute to schedule slippage, such as poor

requirements docs or poor change control

Page 20: PMINEO_2010_03_Resource_Management

20

Recommendations

5)Tools and Other Organizational Issues

There are environmental or organizational issues that affect

Resource Management potential

Some major examples:

availability of a Portfolio/Resource tool, especially in large org

frequent priority shifts

organizational bias towards getting projects started ASAP

For full coverage see “Organizational Enablers” in OPM3, ref [9]

Page 21: PMINEO_2010_03_Resource_Management

21

Recommendations

6)Implementation

Evaluate where you are today.

Consider OPM3, CMMI, or IIL models, or parts of models

Identify pain points and business needs

Develop short and long term goals

Consider tool options

Avoid temptation to overdo it

Page 22: PMINEO_2010_03_Resource_Management

22

Example Tools

1) Excel worksheet samples

2) MS-Project file(s); see ref [8]

3) MS-Sharepoint; see ref [10]

4) Enterprise Level Tools

Page 23: PMINEO_2010_03_Resource_Management

23

Sample Tools

1)Excel worksheet samples

Simple single sheet for PM assignments

Multi-tab template with inputs and report tabs

Combination of Excel tools for all resource hours

Estimating worksheet, with phases by percentage

Page 24: PMINEO_2010_03_Resource_Management

24

Sample Tools

2)MS-Project File(s)

File combination options

Single file for managing one or more projects

Nest individual project files within aggregate files

Multiple files, with one file as “resource master”

See reference [8]

Note that detailed files can become maintenance burden

Page 25: PMINEO_2010_03_Resource_Management

25

Sample Tools

3) MS-Sharepoint

MS-S as Project/Portfolio Management system:

Document repository

Workflows for portfolio or project level processes

Apparently offers native WBS capability?

Integrates with MS-Project

Includes reporting tools

Above is based on ref [10] not personal experience

Is worth exploring for orgs already using MS-S

ASPE training, April 22-23, Cleveland, $1300

Page 26: PMINEO_2010_03_Resource_Management

26

Sample Tools

4) Enterprise Tools

Available as purchase or as hosted service

Purchase can be $200,000 and up

Arbitrary list of examples from random experience:

Planview

Clarity

Primavera (probably higher cost; was construction)

Daptiv (hosted service, 2009 list price $50/user/month)

@Task (hosted service, gaining some popularity)

Page 27: PMINEO_2010_03_Resource_Management

27

Page 28: PMINEO_2010_03_Resource_Management

28

Page 29: PMINEO_2010_03_Resource_Management

29

Resource Management

at Westfield Group

Todd R Jones, PMP

March 17, 2010

Page 30: PMINEO_2010_03_Resource_Management

30

Background

Resource pool of 161 resources from 10 skill disciplines

Matrix organization

Resources are assigned for duration of project

Mix of full-time and part-time

Portfolio Management team

Portfolio manager; seven Project Managers (PMs); two project

support admins; and financial reporting support

12 Enterprise Projects

Monthly reporting cycles

Page 31: PMINEO_2010_03_Resource_Management

31

Resource Assignment – New Project

Starts in Portfolio planning

Section 1, 2, 3 documentation

OOM estimate by role (discipline)

Resource managers (RMs) juggle project and maintenance requests

Resources provided based on need, skills, timing, availability, development plan (stretch role)

Allocate both internal resources and contractors (shared responsibility with PMs)

PM responsible for onboarding and setting expectations for project work

Page 32: PMINEO_2010_03_Resource_Management

32

Section 3 – OOM Resource Estimates Project Name: << Manual UpdateProject Type: << Manual Update

Project Duration (Quarters): <<Enter number of Quarters

Estimating Confidence Medium << Confidence Controls Estimate Range

FTEs by Month Enter Data Here

Calc Value Calc Value Manual Update Manual Update N/A Mth 1 Mth 2 Mth 3

Team Members by Role Utilization

(Annual FTE

Not Head Cnt)

Cost Notes Internal

or

Consultant

Staffing

Managers

Confidence

(H, M, L, ?) Roles Annual FTE Jan-10 Feb-10 Mar-10

AADA - Application Developer 0.00 AADA - Application Developer 0.00

AADA - SIG (Service Integrators) 0.13 $8,034 AADA - SIG (Service Integrators) 0.13 0.25 0.25 0.25

AADA - Software Architect 0.00 AADA - Software Architect 0.00

AADA - Systems Analyst 0.10 $6,427 AADA - Systems Analyst 0.10 0.10 0.10 0.10

AD - Designer 0.00 AD - Designer 0.00

AD - Integrators / Implementers 1.67 $107,120 AD - Integrators / Implementers 1.67 2.00

AD - Software Architect 1.00 $64,272 AD - Software Architect 1.00 1.00 1.00 1.00

AD - Systems Analyst 0.88 $56,238 AD - Systems Analyst 0.88 1.00 1.00 1.00

AD - Technical Coordinator 0.50 $32,136 AD - Technical Coordinator 0.50 0.50 0.50 0.50

AD - User Experience Designer 0.00 AD - User Experience Designer 0.00

121.10 5.75 5.75 11.35

IT Resource Total 10.09 $648,612 0.04748 0.047481 0.093724

Analysts & Communication Specialists 0.00 Analysts & Communication Specialists 0.00

Claims Professionals 0.23 $14,461 Claims Professionals 0.23 1.00 0.50 0.25

Complex Claims Professionals 0.00 Complex Claims Professionals 0.00

Directors & Sr Mngrs 0.00 Directors & Sr Mngrs 0.00

Field U/W & Sr Analysts 0.00 Field U/W & Sr Analysts 0.00

2.70 1.00 0.50 0.25

Business Resource Total 0.23 $14,461 0.37037 0.185185 0.092593

EDP Consulting Dollars $675,000 Tester Manual Update Manual Update

Estimating Range -15% 25% Calc Value Calc Value

IT Resource Cost range $551,320 $810,765 Calc Value Calc ValueBusiness Resource Cost range $12,292 $18,077 Calc Value Calc ValueEDP Consulting Range $573,750 $843,750 Calc Value Calc ValueHardware & Software Manual Update Manual UpdateTotal $1,140,000 $1,670,000 Calc Value Calc Value

Resource and EDP consulting estimate will need to be revised once high level requirements are available.

Project Estimate:

Assumptions:

Business requests first implementation by no later than January 2011. Project needs to start no later than January 2010.

<Project Name>

<Project Type>

Calc Values

4

Page 33: PMINEO_2010_03_Resource_Management

33

Ongoing Management

Bi-weekly Portfolio Staffing Meeting

All resource managers

Review in-flight and upcoming projects/needs

Confidence by project by role

Discuss downstream impacts of project/portfolio changes

PMs visit as needed to discuss changes

Single view - monthly updates provided to IT-Steering Committee (Sr Execs)

Supports ongoing (rolling) planning window for new business requests

Page 34: PMINEO_2010_03_Resource_Management

34

Portfolio Staffing Confidence Report

Page 35: PMINEO_2010_03_Resource_Management

35

Career Development

Career development is the responsibility of each

resource, supported by the resource manager and PM

PM provides on-going and quarterly feedback

2 x 1 (PM, Resource manager, Resource)

Aligns project opportunities to development goals, as realistic

Resource manager responsible for traditional

performance management (annual review, development

plan, etc.)

Page 36: PMINEO_2010_03_Resource_Management

36

Page 37: PMINEO_2010_03_Resource_Management

37

Resource Management

at American Greetings

Diane Gormley

March 17, 2010

Page 38: PMINEO_2010_03_Resource_Management

38

Background

Resource Pool of 54 resources assigned to

development work only

PMs, BAs, Developers, TAs

Resources are augmented by contractors

Separate groups performing application

maintenance, technical maintenance, and

architecture

Often pulled into projects for design and testing

Page 39: PMINEO_2010_03_Resource_Management

39

RM Responsibilities

Fulfilling project resource needs

Acquiring contractors

Training and development

Performance evaluation

Resource hiring

Manage intern program

Resource usage and optimization

Page 40: PMINEO_2010_03_Resource_Management

40

RM Responsibilities

Resource Planning & Career Development

Monthly meetings with each resource

Address single threaded resources

Plan for transitioning resources to new roles

Page 41: PMINEO_2010_03_Resource_Management

41

Tools used by RM

Clarity

Skills database

Master Schedule

Recruit Alliance

360 evaluation tool

Page 42: PMINEO_2010_03_Resource_Management

42

ISD Master Schedule

Master Schedule As of 03/02/2010

Mar

2010

Apr

2010

May

2010

Jun

2010

Jul

2010

Aug

2010

Sep

2010

Oct

2010

Nov

2010

Dec

2010

Jan

2011 Totals

Total AG Capacity 30268 28776 27468 28776 28776 28776 28776 27468 28776 30084 27468 315412

Contractor Capacity 7920 5581 3856 3290 2957 2746 2621 2301 2176 2176 0 35623

Total AG & Contractor Capacity 38188 34357 31324 32066 31733 31522 31397 29769 30952 32260 27468 351035

(includes Off-shore resources in capacity & demand)

Total Active Project Demand 43442 29883 24969 20855 19446 18288 17845 16232 18014 19530 16416 244921

Hours Variance -5253 4474 6355 11211 12286 13233 13552 13537 12938 12730 11052 106114

% Variance 114% 87% 80% 65% 61% 58% 57% 55% 58% 61% 60%

PIPELINE Demand 0 0 355 595 994 1687 1215 1113 945 864 777 8545

Anticipated Capacity for PIPELINE Projects 0 0 0 0 0 0 0 0 0 0 0 0

Total Active and PIPELINE Capacity 38188 34357 31324 32066 31733 31522 31397 29769 30952 32260 27468 351035

Total Active and PIPELINE Project Demand 43442 29883 25324 21450 20440 19975 19060 17344 18959 20394 17193 253466

Hours Variance -5253 4474 6000 10616 11293 11547 12337 12424 11993 11866 10275 97569

% Variance including PIPELINE Development 114% 87% 81% 67% 64% 63% 61% 58% 61% 63% 63%

Page 43: PMINEO_2010_03_Resource_Management

43

Value of ISD Master Schedule

Provides capacity versus demand

Status of active projects

Pipeline of new projects

Provides data to make decisions on resource

constraints

Gives estimated timeframe to launch new

projects

Page 44: PMINEO_2010_03_Resource_Management

44

Page 45: PMINEO_2010_03_Resource_Management

45

Question and Answer Session

Page 46: PMINEO_2010_03_Resource_Management

46

Business cards/signup for followup

Page 47: PMINEO_2010_03_Resource_Management

47

References

1 Project Management Body of Knowledge (PMBOK), 4th Edition, PMI

Primarily Chapter 6: Project Time Management, and Chapter 9: Project

Human Resource Management

2 Portfolio Resource Management: The Most Significant Challenge to

Project Management Effectiveness, James S. Pennypacker.

PMI paper from 2008 Global Congress.

Summary of a survey of Resource Management uses and benefits.

Available from PMI for $10 to members. Good survey reference.

3 Project Resource Management 2009: Tools, Processes, and Challenges;

Bruce A. McGraw, Kathryn L. Jackson.

White paper describing Resource Management survey of 2009. Available

from Cognitive Technologies Incorporate of Austin, Texas. Good survey

reference.

Note that they will be conducting a survey in the summer of 2010. If

interested in articipating, send an email to the “info” email address.

Contact: [email protected]

Page 48: PMINEO_2010_03_Resource_Management

48

References

4 “Do More With Less”, article from PM Network, March 2006, Pages 28 –

34. Minor misc reference points.

5 “Future Perfect”, article from PM Network, April 2004, pages 38 –

44.“Putting People In Their Place”, article from PM Network, April 2007,

pages 66 – 69. Minor misc references.

6 “Future Perfect”, article from PM Network, April 2004, pages 38 –

44.“Putting People In Their Place”, article from PM Network, April 2007,

pages 66 – 69. Minor misc references.

7 Advanced Project Portfolio Management and the PMO, Gerald Kendall, Steven

C. Rollins, Copyright 2003, IIL and J. Ross Publishing

Good PMO Reference overall.

For this subject, see Chapter 15, Resource Portfolio Management

Page 49: PMINEO_2010_03_Resource_Management

49

References

8 Meet the Resource Management model

Includes tutorials on using MS-Project files individually or grouped with shared

resources. 4-part article on gantthead.com:

(1) http://www.gantthead.com/article.cfm?ID=236451

(2) http://www.gantthead.com/content/articles/236556.cfm

(3) http://www.gantthead.com/content/articles/236662.cfm

(4) http://www.gantthead.com/content/articles/236676.cfm

9 OPM3, Organizational Project Management Maturity Model, from PMI.

This is the process-level equivalent to the PMBOK which is for project

management. See www.pmi.org, search OPM3. Some docs free for PMI

members.

10 Sharepoint_for_project_management.pdf

High-level generic discussion of Sharepoint for PM, available as download from

http://www.aspe-it.com/offers/ Details in training by ASPE, Cleveland, April 22-

23, $1295 before discount

Page 50: PMINEO_2010_03_Resource_Management

50

Priming Questions

· How long have you been operating under this model (developers split into maintenance vs. project work)? · What productivity gains have you realized? · How did you implement the model? · Based on your experience, what advice do you have for an organization converting to this model? · What issues did you experience with implementing the model? · What is your organizational structure within IS? · Number of developers in the maintenance and project groups? · Number of Project Managers and Business Analysts? · How do you define maintenance? Projects? · What tool(s) do you use for tracking maintenance and projects?

Page 51: PMINEO_2010_03_Resource_Management

51

Panel: Todd Jones, Westfield Insurance

Todd Jones is a Project Manager in the Technology Portfolio Management unit at Westfield Group, responsible for leading both business and IT projects. He has been in this role for six years after transitioning from an application development, testing, & architecture background. As a PM, he has led a multi-year enhancement of the Personal Lines policy sales & servicing application; an upgrade & business enhancement of the Enterprise Content Management system to support paperless initiatives for multiple business units; a business process automation & software implementation for the Premium Audit unit; and multiple initiatives to develop/enhance IT capabilities. Todd is currently leading an extensive optimization of the Websphere Application Server infrastructure that includes migrating all web-based applications & services, and he is teeing up a new project to select & implement a full-scale e-Discovery solution.

Page 52: PMINEO_2010_03_Resource_Management

52

Panel: Diane Gormley, American

Greetings

Diane Gormley is the Project Office Manager and

Resource Manager for the Information Services

Division at American Greetings. The ISD project

office is responsible for managing ISD's master

schedule of projects, managing over 50 internal

resources and 30+ contracted resources,

administering the Clarity toolset, and maintaining the

project methodologies and PM standards. Diane has

been with AG for 14 years and has been part of the

project office for 6 years.

Page 53: PMINEO_2010_03_Resource_Management

53

Panel: Bob Zoller, Cleveland Clinic

Bob Zoller has been an IT Project Manager at The

Cleveland Clinic for the past year, on the

development of a system for managing medical data

for the Heart and Vascular Institute. Prior to that,

Bob worked at various Cleveland-area firms as an IT

technical resource, a testing services supervisor, an

IT Project Manager, and the manager of an IT

Project Management office. Bob volunteered for

this evening’s program because the challenges of

Resource Management are something he considers

a hot-button item for him and many in the profession