ADDENDUM #1 ISSUED OCTOBER 9, 2020 To Bid Documents Dated September 21, 2020
REDWOOD CITY SCHOOL DISTRICT
BID NUMBER: 200921DD
PLUMBING RETROFIT FAUCET AND FLUSH VALVE REPLACEMENT
McKINLEY INSTITUTE OF TECHNOLOGY
NORTH STAR ACADEMY
400 DUANE STREET
REDWOOD CITY, CALIFORNIA 94062
SPENCERASSOCIATES
Architects & Planners 1121 San Antonio Road, Suite C201
Palo Alto, CA 94303(650) 965-7000
Plumbing Retrofit – Faucet and Flush Valve Replacement McKinley Institute of Technology/ North Star Academy Redwood City School District
10/09/2020 Addendum #1
2
I. PROJECT MANUAL CHANGES:
A. SECTION 00 52 13 – AGREEMENT 1. Replace paragraph 4 – Time for Completion, with the following:
4. Time for Completion: It is hereby understood and agreed that the Work under this
Contract shall be completed by February 26, 2021 (“Contract Time”) from the start date specified in the District's Notice to Proceed.
B. SECTION 01 32 13 – SCHEDULE OF WORK
1. Replace paragraph 1.03.C – Milestone Schedule:
C. Milestone Schedule:
ACTIVITY DESCRIPTION REQUIRED COMPLETION
Notice to Proceed 10/30/2020
Complete 2/26/2021
II. DRAWING CHANGES:
A. SHEET A3.1 – ENLARGED FLOOR PLANS (McKINLEY INSTITUTE OF
TECHNOLOGY): 1. Revise Enlarged Plan Key Note #3A as follows: “(E) FLOOR MOUNT FLUSH
TANK WATER CLOSET TO REMAIN.”
2. From Plumbing Fixture Schedule, remove item WC-2 for Flush Tank Water Closet. 3. In Enlarged Plans #1, #2, #4, #7, #9, #14, and #15, remove designation WC-2
adjacent note #3A.
B. SHEET A3.2 – ENLARGED FLOOR PLANS (NORTH STAR ACADEMY): 1. From Plumbing Fixture Schedule, remove item WC-2 for Flush Tank Water Closet.
C. SHEET A4.1 – SPECIFICATIONS: 1. In paragraph 2.01, remove item #C.6 for flush tank toilet touchless retrofit.
Plumbing Retrofit – Faucet and Flush Valve Replacement McKinley Institute of Technology/ North Star Academy Redwood City School District
10/09/2020 Addendum #1
3
III. ENCLOSURES:
1. Phasing plan (Sheets SK-1 & SK-2)
END OF ADDENDUM #1