Upload
clifton-cooper
View
216
Download
0
Embed Size (px)
Citation preview
PLANNING LAW UPDATEor “Top Ten from 2006”
JAMES FINDLAY
2-3 GRAY’S INN SQUARE
1. OUTLINE/DETAILED PERMISSIONS
• DCLG Circular 01/2006 – Design and Access statements from Aug 10th 2006 on nearly all new applications (not change of use, engineering or mining or mostly existing dwelling houses).
• Amendments to Articles 1 & 3 GDPO to definition of reserved matters. Details to be supplied on outlines, e.g. upper and lower heights of buildings to be supplied.
• No longer just able to deal with general principle of development.
1. OUTLINE/DETAILED PERMISSIONS
• With regard to EIA development, EA no longer just at outline stage, may be needed at detailed stage too, see R. (Barker) v Bromley LBC & FSS [2006] UKHL 52
• Carry out at detailed stage if (a) significant environmental effects not identified at outline stage or (b) they were, but fresh assessment required (probably arising from a change in circumstances)
2. Village Greens
• Oxfordshire County Council v. Oxford City Council [2006] UKHL 25
• The House of Lords has spoken, yet again on village greens.
• Once registered for dog walking can be used for any reasonable sporting pursuit.
• 20 years runs to date of application, not decision
• Commons Act 2006 – article [2006] Nov. JPL
3. GYPSIES
• New Circular – ODPM 01/06
• Trio of cases: South Bucks DC v Smith [2006] EWHC 281, South Cambs v. Flynn [2006] EWHC 1320 & BANES v. Connors [2006] EWHC 1595. Paragraphs 45/6 of Circular have had an impact but not as great as first thought in injunction cases.
• Article February 2007 JPL
4. Planning obligations
• New guidance issued by DCLG but not in a Circular!
• Planning Obligations: Practice Guidance
• Model Planning Obligations (Section 106) Agreement (drafted by Law Society’s Planning & Environmental Law Committee) – see article and response in December [2006] JPL
5. Enforcement – 2 points
• First, intensification can lead to a material change of use – see R (Childs) v FSS [2005] EWHC 2368.
• Secondly, time limit for breach of condition in respect to use of a building as a dwellinghouse – 4 or 10 years?
• CA overrule 1st instance Judge and determine that it is 4 years in all cases.
• FSS v Arun DC [2006] EWCA Civ 1172,
[2007] JPL 237
6. EXCEPTIONS TO TPO’S• PERRIN & RAMAGE v NORTHAMPTON
BC [2006] EWHC 2331 (TCC)• When can one top, lop, cut down etc to
abate a nuisance (s.198(6)(b))?• 1st – Nuisance means actionable nuisance,
not just an overhanging branch.• 2nd – Irrelevant that an alternative scheme,
ie root protection, could also abate nuisance.
• On appeal. See article [2007] Feb JPL
7. Housing – new PPS 3
• Plan, monitor and manage remains.
• New definition of affordable housing – excludes low cost market housing
• Low cost market housing will be part of mix required on larger sites.
• No presumption that PDL or whole of curtilage should be redeveloped.
8. Development in breach of condition
• Newton v Sullivan
• R.(Hart Aggregates Ltd) v. Hartlepool [2005] EWHC Admin “has blurred the boundaries” of the rule in Whitley.
• Norris v FSS & Ano [2006] EWCA Civ 12 – no mention of Hart.
• “Unlawful operations cannot amount to the commencement of development”. Laws LJ
9(a) DELAY & JR
• Hardy v Pembrokeshire CC & others [2006] EWCA Civ 240, [2007] JPL 284
• Planning challenges still need to be made promptly.
9(b) DELAY AND COMMENCEMENT
• Section 73 of the Act is amended, so that if development is not commenced within the time limits you cannot use s. 73 to extend the time.
10. BARKER REPORT
• Back to square 1
• For the new or soon to be old development plan system, see Article in 2006 February JPL.
• And PPS 25 Flooding