Planning Concepts Basics of Project Planning

Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Embed Size (px)

Citation preview

Page 1: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Planning Concepts

Basics of Project Planning

Page 2: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Construction PlanningSetting Milestones for overall completionOrganizing activities for Individual area

completion, duly acknowledging their inter dependence

Providing various Resources

Directing the Planning for execution

Review and Redirection

Page 3: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Planning in total….Planning is assembling total inputs

Men, Machine, Materials Tools / Small ToolsLay down area Clearances

Page 4: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Apply productivity while planning Break job into activitiesQuantify each activityFind out unit quantum of the job, may be a

joint, major or minor liftStudy rate of achieving unit quantumPace the job by setting tougher norms

every day

Page 5: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Sequencing ActivityInterdependence to each otherGang MovementResource Leveling

Page 6: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Review and RedirectPlanning once done, is not done for everPeriodical review sets the rhythmMore looks on planning throw more clarity

on the path of our progressYou need to set new dates, reschedule

resources

Page 7: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Planning Levels

Term Objectives Periodicity

Total Project milestones setting and resource budgeting

Quarterly

3 months Intermilestones setting and Resource mobilisation

Monthly

Week Direction for field execution Weekly

Day Productivity, Quality, Safety assurance Day

Page 8: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

MPCS SchedulesS0 - Work ScheduleS1 - Invoicing ScheduleS2 - Milestone ScheduleS3 - P&M ScheduleS4 - Staff ScheduleS5 - Labour ScheduleS6 - Material ScheduleS7 - Special Agency ScheduleS8 - Direct Cost ScheduleS9 - Indirect Cost ScheduleS10- Fund Flow Schedule

Schedule Template

Page 9: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

3 Months look ahead planning - Pictorial Representation

Present Month

2nd Month

1st Month

3rd Month

Resource Mobilisation

Resource Direction

Resource Budgeting

Page 10: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

1 2 3 4 5 6 7 8

1 MOBILIZATION LS - 15 DAYS

2 EXCAVATION CUM 1480 45 DAYS495 985

3 FOUNDATION WORK CUM 476 60 DAYS215 261

4 PAINTING & BACKFILLING CUM 443 45 DAYS295 148

5 STRUCTURE FABRICATION MT 660 75 DAYS200 300 160

6 STRUCTURE ERECTION MT 660 60 DAYS130 400 130

7 SPOOL FABRICATION LM 1500 75 DAYS500 700 300

8 SPOOL ERECTION LM 1500 75 DAYS200 750 550

9 TESTING AND COMMISSIONING LS - 60 DAYS

10 HANDING OVER # LS - 45 DAYS

SCOPE DURATIONPERIOD IN MONTH

SL NO ACTIVITY UNIT

NSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSH

CONSTRUCTION PROGRAMME FOR PIPE RACK WORK

Page 11: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

EQUIPMENT SCHEDULE FOR PIPE RACK WORK

1 2 3 4 5 6 7 8

1 EXCAVATOR / JCB NO 1 45 DAYS

2 DUMP TRUCK NOS 2 75 DAYS

3 LOADER NO 1 60 DAYS

4 BOBCAT NOS 3 45 DAYS

5 PLATE COMPACTOR NOS 5 90 DAYS

6 CRANE, 100T NOS 2 135 DAYS

7 CRANE, 50T NO 1 90 DAYS

8 TRAILER NO 1 90 DAYS

9 MAN BASKET NOS 2 135 DAYS

QTY DURATIONPERIOD IN MONTH

SL NO EQUIPMENT DESCRIPTION UNIT

NSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSH

Page 12: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

DIRECT MANPOWER SCHEDULE FOR PIPE RACK WORK

1 2 3 4 5 6 7 8

1 CIVIL FOREMAN EA 1 90 DAYS1 1 2 1

2 MASON EA 7 60 DAYS6 10 6

3 STEEL FIXER EA 9 75 DAYS6 8 12

4 CARPENTER EA 15 60 DAYS12 18

5 LABOUR EA 19 225 DAYS8 20 30 25 25 18 12 10

6 SCAFFOLDER EA 21 150 DAYS15 25 25 25 15

7 STRUCTURAL FOREMAN EA 2 60 DAYS1 2 2 2

8 STRUCTURAL FITTER EA 13 60 DAYS8 16 16 12

9 PIPING FOREMAN EA 2 135 DAYS1 2 2 2 2 1

10 PIPE FITTER EA 12 135 DAYS8 14 18 16 8 6

11 WELDER EA 7 135 DAYS4 8 10 10 8 6 2

TOTAL EA 107 240 DAYS 15 60 122 101 94 69 43 19

QTY DURATIONPERIOD IN MONTH

SL NO TRADE UNIT

NSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSHNSH

Page 13: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

DIRECT MANPOWER SCHEDULE FOR PIPE RACK WORK 1 2 3 4 5 6 7 8

1 MOBILIZATION LS - 15 DAYS

2 EXCAVATION CUM 1480 45 DAYS495 985

3 FOUNDATION WORK CUM 476 60 DAYS215 261

4 PAINTING & BACKFILLING CUM 443 45 DAYS295 148

5 STRUCTURE FABRICATION MT 660 75 DAYS200 300 160

6 STRUCTURE ERECTION MT 660 60 DAYS130 400 130

7 SPOOL FABRICATION LM 1500 75 DAYS500 700 300

8 SPOOL ERECTION LM 1500 75 DAYS200 750 550

9 TESTING AND COMMISSIONING LS - 60 DAYS

10 HANDING OVER LS - 45 DAYS

1 2 3 4 5 6 7 8

1 EXCAVATOR / JCB NO 1 45 DAYS

2 DUMP TRUCK # NOS 2 60 DAYS

3 LOADER NO 1 60 DAYS

4 BOBCAT NOS 3 45 DAYS

5 PLATE COMPACTOR NOS 5 90 DAYS

6 CRANE, 100T NOS 2 135 DAYS

7 CRANE, 50T NO 1 120 DAYS

8 TRAILER NO 1 150 DAYS

9 MAN BASKET # NOS 2 120 DAYS

1 2 3 4 5 6 7 8

1 CIVIL FOREMAN EA 1 90 DAYS1 1 2 1

2 MASON EA 7 60 DAYS6 10 6

3 STEEL FIXER EA 9 75 DAYS6 8 12

4 CARPENTER EA 15 60 DAYS12 18

5 LABOUR EA 19 225 DAYS8 20 30 25 25 18 12 10

6 SCAFFOLDER EA 21 150 DAYS15 25 25 25 15

7 STRUCTURAL FOREMAN EA 2 60 DAYS1 2 2 2

8 STRUCTURAL FITTER EA 13 60 DAYS8 16 16 12

9 PIPING FOREMAN # EA 2 135 DAYS1 2 2 2 2 1

10 PIPE FITTER # EA 12 135 DAYS8 14 18 16 8 6

11 WELDER # EA 7 135 DAYS4 8 10 10 8 6 2

TOTAL EA 107 240 DAYS 15 60 122 101 94 69 43 19

DIRECT MANPOWER SCHEDULE FOR PIPE RACK WORK

SL NO

TRADE UNIT QTY DURATION

PERIOD IN MONTH

REMARKS

EQUIPMENT SCHEDULE FOR PIPE RACK WORK

SL NO

EQUIPMENT DESCRIPTION UNIT QTY DURATIONPERIOD IN MONTH

REMARKS

CONSTRUCTION PROGRAMME FOR PIPE RACK WORK

SL NO

ACTIVITY UNIT SCOPE DURATIONPERIOD IN MONTH

REMARKS

NNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNS

NNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNS

NNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNSNNSHNS

Page 14: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Schedule : LabourPurpose ….

Histogram (Average / Peak Strength)

Labour License / Colony Planning Sub-contracting strategyStaff Planning

Page 15: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Schedule : MaterialPurpose ….

Bulk purchase arrangementVendor developmentLocal / outside purchase decisionStorage facilities

Page 16: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Schedule : P&MPurpose ….

Resource levelingWorkshop facilities planningElectrical infrastructureMobilization / Release commitments

Page 17: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area

Schedule : Work / InvoicingSchedule : Work / InvoicingPurposePurpose ….

Peak capacities Peak capacities Client input datesClient input datesWork valuation / Annual Work valuation / Annual BudgetingBudgeting

Working capitalWorking capitalFabrication / enabling facilitiesFabrication / enabling facilities

Page 18: Planning Concepts Basics of Project Planning. Construction Planning Setting Milestones for overall completion Organizing activities for Individual area