Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
Reference:
12/00862/OUT
Ward: Aveley and
Uplands
Site: Land adjacent to Ponds Farm, Purfleet Road, Aveley.
Proposal: Outline planning application for the redevelopment of
the site for employment use totalling 38,686sq.m. (416,416 sq.ft)
with means of access and quantum of development to be
approved. All other matters to be reserved.
Plan Number(s):
Reference Name Received
TP (00) 01 Planning Application Boundary 12th September 2012
6952/01 Tree Location Plan 12th September 2012
TP O (00) 01 Rev. B Parameter Plan 12th September 2012
TP O (00) 02 Illustrative Site Layout Plan Option 1 12th September 2012
TP O (00) 03 Illustrative Site Layout Plan Option 2 12th September 2012
TP O (00) 04 Illustrative Site Layout Plan Option 3 12th September 2012
The application is also accompanied by:
Planning Statement;
Design and Access Statement;
Environmental Impact Assessment (EIA);
Flood Risk Assessment and Drainage Strategy;
Transport Assessment;
Travel Plan;
Draft Planning Obligations;
Sustainability Statement;
Energy and Water Statement;
Statement of Community Consultation;
Arboricultural Statement;
Utilities and Foul Sewerage Statement.
Applicant:
Cogent Land LLP
Validated: 18th September 2012
Date of expiry: 8th January 2013
Case Officer: Matthew Gallagher
1.0 DESCRIPTION OF PROPOSAL
Summary
1.1 This is an application seeking outline planning permission for the
redevelopment of a currently open site, totalling 8.04 hectares in area, with
employment generating uses totalling 38,686 m2 floorspace. The application is
submitted in outline, with the means of access and the amount of development
for consideration at this stage. All other matters (appearance, landscaping,
layout and scale) are reserved for future approval. The application is
accompanied by an Environmental Impact Assessment and a number of
supporting documents.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
1.2 The application seeks permission to ‘fix’ the points of access onto the
surrounding highways network. A left-in turn only access into the site is
proposed from the southbound carriageway of the A1306 London Road. This
point of access would be located approximately 90m from the Wennington
Interchange of the A1306 with the A13 and broadly opposite the existing
junction of the A1306 with Juliette Way. The primary access for the site would
be from a proposed new signal-controlled junction onto London Road, located
approximately 125m to the north of the existing London Road / New Tank Hill
Road (A1090) junction. In effect, the western-end of Purfleet Road would be
diverted to meet London Road at the new junction with physical measures to
reinforce a potential prohibition of driving order installed along the ‘old’
alignment of Purfleet Road. Illustrative plans submitted with the planning
application give an indication of access roads within the site and suggest a
main link road joining the two points of access.
1.3 The application also seeks consent for the quantum of development and
proposes a maximum of 38,686m2 of floorspace for employment uses. The
application form states that 34,817m2 (90% of the total floorspace) would
comprise storage and distribution uses within Use Class B8. The remaining
3,869m2 (10% of the total floorspace) would comprise office use within Use
Class B1(a). The Planning statement accompanying the application suggests
that the office component of the proposals would comprise internal office
floorspace ancillary to the warehousing floorspace.
1.4 As required by the Town and Country Planning (Development Management
Procedure) (England) Order 2010, as layout and scale are reserved matters
the application provides indications of the location of buildings, their
dimensions and details of routes and open spaces within the site. A
‘Parameter Plan’ seeks to fix the building zone in the central northern part of
the site adjacent to the A13, where new building(s) would be located. The
maximum and minimum dimensions for building lengths and widths would be:
Minimum Building Length: 134m
Maximum Building Length: 272m
Minimum Building Width: 66m
Maximum Building Width: 128m
1.5 Minimum and maximum building heights within the building zone would are
proposed to be 14m and 18m respectively. This building zone is adjoined to
the west, south and east by a logistics area containing service yards and
vehicle parking. The western, southern and eastern boundaries of the site are
adjoined by landscape zones containing surface water drainage features,
noise and visual screens.
1.6 The planning application is accompanied by illustrative plans which show three
potential options for the future layout of the site. These layouts are intended to
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
reflect the potential requirements of future commercial occupiers and it is
emphasised that the layouts are indicative only. The final layout of the
development would be established though the approval of reserved matters
based upon the broad parameters described above. The site is currently
being marketed by commercial agents and therefore the final layout of the site
would be partly driven by the operational requirements of a future occupier(s).
However, the main elements of the three illustrative layouts are summarised in
the table below.
Option 1 – One Building
Floorspace Building Length Building Width Car Parking
Spaces
Loading Docks
38,686m2 272m 128m 258 32
Option 2 – Two Buildings
i – 23,222m2 205m 102m 221 30
ii – 9,827m2 133m 66m 15
Option 3 – Two Buildings
i – 19,859m2 181m 99m 198 30
ii – 9,827m2 133m 66m 30
1.7 Although the application is submitted in outline form, the accompanying
Design and Access Statement details illustrative options for landscaping of the
site and the appearance of buildings. Three ‘landscape zones’ are identified,
adjacent to the Purfleet Road, London Road and Wennington interchange
boundaries of the site. Landscaping to the Purfleet Road frontage is intended
to be a visual screen and acoustic mitigation for residential properties in
Purfleet Road. With regard to appearance, the Design and Access Statement
identifies the London Road and Wennington interchange interfaces as
principal elevations.
2.0 SITE DESCRIPTION
2.1 The application site is a triangular-shaped plot of land totalling 8.04 hectares in
size. The site is located on the north-western side of Purfleet Road, with the
A13 trunk road and the A1306 London Road forming the other boundaries of
the site. The A13, which forms the northern boundary of the site, is within a
cutting and, therefore, is below ground levels on the site. The site has a
frontage to Purfleet Road of some 160m and a frontage to London Road of
approximately 360m.
2.2 The site is not currently used and comprises rough, open grassland with small
shrubs, isolated trees and other vegetation forming the boundaries of the site.
A drainage ditch is located within the site adjacent to the majority of the
London Road frontage. Levels across the site are generally flat, albeit with a
gentle fall from the A13 boundary towards the Purfleet Road / London Road
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
junction. That part of the site located closest to the A13 and the Wennington
interchange lies in a low flood risk area. However, parts of the site closest to
London Road and Purfleet Road are located within flood zones 2 and 3
(medium and high probability). In the immediate post-war period, the northern
part of the site was used as a sand and ballast pit. During the 1960’s this part
of the site was infilled with household refuse, inert waste and non-hazardous
commercial waste. Infilling ceased at the end of the 1960’s.
2.3 To the south-east of the site, on the opposite side of Purfleet Road, are mainly
residential properties comprising semi-detached bungalows and two-storey
family housing. At the junction of London Road and Purfleet Road, and
immediately adjacent to the site, is the Tunnel Garage site which originally
operated as a petrol filling station and is now used for the storage and repair of
commercial vehicles. To the south-west of the site on London Road is the
Purfleet Industrial Park which includes a range of large warehouse buildings,
small business and light industrial uses and open storage uses. The A13
trunk road lies adjacent to the northern boundary of the site and the off-slip
from the trunk road joins the A1306 London Road at a roundabout junction
(Wennington Interchange) immediately to the north-west of the site.
2.4 In the wider area surrounding the application site, the former London Fire
Brigade sports ground and clubhouse is located to the south-east to the rear of
the dwellings along Purfleet Road. On the northern side of the A13 to the west
of Purfleet Road is open land. To the south of the Purfleet Industrial Park is
the RSPB nature reserve and visitor centre at Aveley Marshes.
3.0 RELEVANT HISTORY
Ref. Description Decision
08/00858/TTGOUT Outline planning application for the
redevelopment of the site for
employment use (Classes B1 (a) /
B1(c) / B2 / B8 / Sui Generis car
showroom) totalling 38,686 square
metres (floorspace) with means of
access and quantum of development
to be approved. All other matters to
be reserved
Approved
subject to S 106
71/00906/FUL
(part of site)
Security lorry park and storage of
vehicles
Refused
57/00429/FUL
(part of site)
Use of land for residential purposes Refused
57/00003/FUL
(part of site)
Tipping of refuse Approved
48/00059/FUL Extension of mineral working and Approved
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
(part of site) new access
3.1 Members will note from the planning history set out in the above table that
parts of the site have a history of mineral extraction and subsequent infilling
with refuse. Historic Ordnance Survey mapping dating from the late 1930’s
first shows the northern part of site, now adjacent to the Wennington
interchange used as a sand and ballast pit. Mapping from the early 1960’s
shows a disused sand and gravel pit extending across a substantial part of the
north-west of the site. Records from the Environment Agency reveal that after
the extraction of minerals from part of the site, the void was infilled with
commercial and household waste. This landfill site is referred to as the Sandy
Lane site and was operated by the former Greater London Council.
3.2 In 2008 an outline planning application was submitted to the former Thurrock
Development Corporation proposing the development of the site with a mix of
employment generating uses (ref. 08/00858/TTGOUT). Following referral of
the application to the Secretary of State and the completion of a S.106 legal
agreement, conditional planning permission was granted in June 2011. No
reserved matters applications have been submitted pursuant to this outline
permission and this permission is unimplemented.
3.3 The extant planning permission approves a total floorspace of development
identical to the current proposal. However, the parameters set by the consent
permit a more diverse range of uses (Classes B1, B2, B8 and Sui-Generis)
with specified proportions of each use class. For example, the existing
consent specifies a large proportion of Class B1 and B8 floorspace (58%) and
a more modest proportion of Class B8 uses (36%). The current application
seeks permission for a predominantly Class B8 development (90%) with
ancillary office floorspace (10%).
4.0 CONSULTATIONS AND REPRESENTATIONS
Statutory Consultees
4.1 Environment Agency: (response dated 8th October 2012)
“We have inspected the application, as submitted, and have no objection to
the application provided the following conditions related to flood risk,
contaminated land and pollution control are appended to any approval
granted.
Flood Risk
The site is shown by our flood zone map to fall partially within Flood Zone 1,
Flood Zone 2 and Flood Zone 3, the low, medium and high Flood Zones
respectively. The application proposes the use of the site for employment
which is considered to be a ‘less vulnerable’ use by the National Planning
Policy Framework (NPPF) guidance document. The application is therefore
required to pass the sequential Test and be supported by a Flood Risk
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
Assessment (FRA). As the site is greater than 1 hectare in size, the FRA
should also demonstrate how surface water will be managed.
No evidence has been submitted to demonstrate that you have applied and
passed the Sequential Test. This should be addressed before you consider
the grant of planning permission.
A FRA has however been submitted, prepared by WSP, referenced
50600022-120427-Issue 1 and dated May 2012. We are satisfied that this
complies with the NPPF and therefore raise no objections to outline planning
permission being granted if the following planning condition is included as set
out below:
Condition
No development approved by this planning permission shall take place until
such time as a scheme for the management of surface water has been
submitted to, and approved in writing by, the Local Planning Authority
including the following:
confirmation that flows can be accommodated within the receiving
sewer system;
details of the volume of storage required for the 1 in 100 year storm,
inclusive of climate change;
utilisation of sustainable drainage techniques for the storage of surface
water flows;
confirmation of who will be responsible for the maintenance of the
scheme.
The scheme shall be fully implemented and subsequently maintained, in
accordance with any timing / phasing arrangements embodied within the
scheme, or within any other period as may subsequently be agreed, in writing,
by the Local Planning Authority.
Reason:
To prevent flooding by ensuring the satisfactory storage of / disposal of
surface water from the site. Although we are satisfied at this stage that the
proposed development could be allowed in principle, the applicant will need to
provide further information to ensure that the proposed development can go
ahead without posing an unacceptable flood risk to the site and surrounding
area.
Contaminated Land
Part of the site overlies a historic landfill so there is a high risk that the water
environment may be contaminated from this previous use. A Geotechnical
and Environmental Assessment prepared by WSP, referenced 12220063-
002/rev1 and dated March 2008 has therefore been submitted to consider this
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
risk further.
The assessment does not however include the Chalk aquifer as a potential
receptor. East of London the Thames Sands are likely to be in hydraulic
continuity with the Chalk, therefore this needs to be considered as part of the
conceptual model in the risk assessment.
The chemical sampling also seems limited, for example Ammonium or any
pharmaceuticals have not been included although anecdotal evidence
suggests they may be present. Other typical contaminants expected from a
landfill would also be pesticides, like Mecoprop. We recommend considering
list 1 screening as set out in appendix 6 of the document LFTGN 01
'Hydrogeological Risk Assessments for Landfills'. All these parameters will
need to be considered for sampling. Furthermore the frequency of the
chemical sampling seems limited. A number of trial pit locations that have
been described as having a hydrocarbon smell have not been sampled for
these.
It also appears odd that that the sampling frequency has been increased in the
non-landfill area close to the boundary with Purfleet Road, rather than near the
garage or in the landfill area. We would expect more groundwater sampling to
further establish the groundwater flow regime.
Based on the information submitted it appears that the contamination on site is
impacting groundwater, in particular from hydrocarbons. Once more data has
been collected along the lines suggested above the risk to the water
environment needs to be re-assessed.
We are however satisfied that there are generic remedial options available to
deal with the risks to the water environment posed by contamination at this
site. We therefore have no objection on contaminated land grounds subject to
the following conditions being appended to any approval granted to ensure
further details are submitted to ensure that risks are appropriately addressed
prior to development commencing:
Condition
Prior to the commencement of development approved by this planning
permission (or such other date or stage in development as may be agreed in
writing with the Local Planning Authority), the following components of a
scheme to deal with the risks associated with contamination of the site shall
each be submitted to and approved, in writing, by the Local Planning Authority:
1. a preliminary risk assessment which has identified:
- all previous uses
- potential contaminants associated with those uses
- a conceptual model of the site indicating sources, pathways and
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
receptors
- potentially unacceptable risks arising from contamination at the site.
2. a site investigation scheme, based on (1) to provide information for a
detailed assessment of the risk to all receptors that may be affected,
including those off site.
3. the site investigation results and the detailed risk assessment (2) and,
based on these, an options appraisal and remediation strategy giving
full details of the remediation measures required and how they are to
be undertaken.
4. a verification plan providing details of the data that will be collected in
order to demonstrate that the works set out in (3) are complete and
identifying any requirements for longer-term monitoring of pollutant
linkages, maintenance and arrangements for contingency action.
Any changes to these components require the express consent of the Local
Planning Authority. The scheme shall be implemented as approved.
Reason:
To protect the water environment.
Condition
No occupation <of any part of the permitted development / of each phase of
development> shall take place until a verification report demonstrating
completion of works set out in the approved remediation strategy and the
effectiveness of the remediation shall be submitted to and approved, in writing,
by the Local Planning Authority. The report shall include results of sampling
and monitoring carried out in accordance with the approved verification plan to
demonstrate that the site remediation criteria have been met. It shall also
include any plan (a "long-term monitoring and maintenance plan") for longer-
term monitoring of pollutant linkages, maintenance and arrangements for
contingency action, as identified in the verification plan. The long-term
monitoring and maintenance plan shall be implemented as approved.
Reason:
To protect the water environment.
Condition
If, during development, contamination not previously identified is found to be
present at the site then no further development (unless otherwise agreed in
writing with the Local Planning Authority) shall be carried out until the
developer has submitted, and obtained written approval from the Local
Planning Authority for, an amendment to the remediation strategy detailing
how this unsuspected contamination shall be dealt with.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
Reason:
To protect the water environment.
Condition
No infiltration of surface water drainage into the ground is permitted other than
with the express written consent of the Local Planning Authority, which may be
given for those parts of the site where it has been demonstrated that there is
no resultant unacceptable risk to controlled waters.
Reason:
To protect the water environment.
The site is located over an historic landfill. Therefore infiltrative drainage is
unlikely to be suitable for this site.
Condition
Piling or any other foundation designs using penetrative methods shall not be
permitted other than with the express written consent of the Local Planning
Authority, which may be given for those parts of the site where it has been
demonstrated that there is no resultant unacceptable risk to groundwater. The
development shall be carried out in accordance with the approved details.
Reason:
To protect the water environment.
Pollution Control
The pollution of ground water and/or surface water is an offence under the
Environmental Permitting Regulations (England and Wales) 2010. Therefore,
we recommend that the following condition is appended to any approval
granted:
Condition
Prior to the commencement of any development, a scheme for the provision
and implementation of pollution control shall be submitted to, and agreed in
writing with, the Local Authority. The works/scheme shall be constructed and
completed in accordance with the approved plans/specification at such time(s)
as may be specified in the approved scheme.
Reason:
To ensure a satisfactory method of pollution control.
Supplementary Information
The applicant should consider the following, as a minimum, when producing
their scheme.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
1) Prior to being discharged into any watercourse, surface water sewer or
soakaway system, all surface water drainage from parking areas and
hard standings susceptible to oil contamination shall be passed through
an oil separator designed and constructed to have a capacity and
details compatible with the site being drained. Roof water shall not
pass through the interceptor. All washdown and disinfectant waters
shall be discharged to the foul sewer. Any detergents entering oil
separators may render them ineffective.
2) All cleaning and washing operations should be carried out in designated
areas isolated from the surface water system and draining to the foul
sewer (with the approval of the sewerage undertaker). The area should
be clearly marked and a kerb surround is recommended.
3) Vehicles' loading or unloading bays and storage areas involving
chemicals, refuse or other polluting matter shall not be connected to the
surface water drainage system.
4) No foul sewage or trade effluent, including cooling water containing
chemical additives, or vehicle washing water, including steam-cleaning
effluent, shall be discharged to the surface water drainage system.
5) Only clean, uncontaminated surface water should be discharged to any
soakaway, watercourse or surface water sewer.
6) Any facilities, above ground, for the storage of oils, fuels or chemicals
shall be provided with adequate, durable secondary containment to
prevent the escape of pollutants. The bunded area shall be designed,
constructed and maintained in order that it can contain a capacity not
less than 110% of the total volume of all tanks or drums contained
therein. All filling points, vents, gauges and sight glasses should be
bunded. Any tank overflow pipe outlets shall be directed into the bund.
Associated pipework should be located above ground and protected
from accidental damage. There shall be no gravity or automatic
discharge arrangement for bund contents. Contaminated bund
contents shall not be discharged to any watercourse, land or soakaway.
The installation must, where relevant, comply with the Control of
Pollution (Oil Storage) (England) Regulations 2001 and the Control of
Pollution (Silage, Slurry and Agricultural Fuel Oil) Regulations 1991 and
as amended 1997.
7) All drums and small containers used for oil and other chemicals shall be
stored in bunded areas that do not drain to any watercourse, surface
water sewer or soakaway.
8) Facilities should be provided to ensure that waste oil is stored and
disposed of in a manner that will not lead to pollution. Site occupiers
intending to purchase or install pollutant secondary containment
(bunding) should ensure that the materials are not vulnerable to
premature structural failure in the event of a fire in the vicinity.
Climate Change and Sustainable Construction
Climate change is one of the biggest threats to our future and will have far-
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
reaching effects on our economy and society. We need to improve our
resilience and adaptation to the effects, particularly with regards to already
stretched environmental resources and infrastructure such as water supply
and treatment, water quality, flood risk, coastal erosion, waste disposal
facilities and aquatic biodiversity.
New development, if not carefully planned, can exacerbate these pressures.
Opportunities should therefore be taken in the planning system, no matter the
scale of the development, to contribute to tackling the problem. This is
supported by the NPPF as well as Policy CSTP25 of your Development
Management Policies DPD.
We therefore recommend you append suitable planning conditions to any
approval granted to ensure the development is carried out in as sustainable
manner as possible. The following information should form the basis of the
applicant’s considerations.
Water Efficiency
Over the next 20 years, demand for water is set to increase substantially yet
there is likely to be less water available due to a drier climate and tighter
controls on abstraction. To address this we are keen to see developments
coming forward as water efficient and climate change resilient as possible.
Simple water efficient systems and fittings should be considered by the
applicant, such as dual-flush toilets; water butts; water-saving taps and
showers; and appliances with the highest water efficiency rating as a
minimum. Wherever possible greywater recycling and rainwater harvesting
schemes should be considered to produce the highest water efficiency ratings.
Any submitted scheme should include detailed information (capacities,
consumption rates, etc) on proposed water saving measures. Applicants are
advised to refer to the following for further guidance:
http://www.environmentagency.gov.uk/homeandleisure/beinggreen/118946.as
px, http://www.water-efficient-buildings.org.uk/ and
http://www.savewatersavemoney.co.uk/.
Save water, Save energy
Energy and water efficiency are inherently linked. Excluding space heating,
approximately 24% of domestic energy consumption in the UK goes to heating
water (DTI 2002). With the current high and rising energy prices, taking
measures to use more efficient fixtures and fittings (such as showers, baths
and hot water taps) will result in major cost savings for the user in both energy
and water bills. Further information is available at: www.water-efficient-
buildings.co.uk
Development should also seek to reduce the demand for energy by
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
incorporating, for example, passive systems which take advantage of natural
light, air movement and thermal mass. To meet the remaining energy demand
the use of renewable sources should be explored and implemented where
possible.
Waste
The government and construction industry have a target to halve waste to
landfill by 2012. The management of waste should therefore be considered as
early as possible during the design phase to ensure that minimal volumes of
waste arise during the construction of the development and the demolition at
the end of its life. This can include measures such as preventing the over-
ordering of materials, reducing damage to materials before use by careful
handling and segregating waste on site into separate skips. The developer
should consider how they will incorporate recycled/recovered materials into
the building programme, including the use of secondary and recycled
aggregates, and re-use of any on-site demolition waste.
The design of the development can also influence the ability of residents to
recycle their waste and we would suggest that designs incorporate facilities to
aid in this, especially in multiple-occupancy buildings. We would also suggest
that consideration is given to the provision for recycling within public areas.
We recommend the following websites which provide ideas and further
information:http://www.wrap.org.uk and http://www.tcpa.org.uk/pages/towards-
zero-waste.html
4.2 Highways Agency: (response dated 3rd October 2012)
“This proposal changes the land use split. At the scoping stage, the Highways
Agency requested the use of 85th percentile trip rates, but these have not
been used.
Additionally we have concerns about the validity of distribution and traffic flow
data used. We would require these to be validated and a rerun of the model of
the A13 Wennington Interchange to confirm that previously agreed mitigation
is appropriate.
Please find attached a Direction under Article 25 of the Town and Country
Planning (Development Management Procedure) Order 2010 which shall be
maintained until 13th November 2012.”
(The Direction states that planning permission is not to be granted for a
specified period until 13th November 2012).
4.3 Highways Agency: (response dated 17th October 2012)
“The Highways Agency (HA), on behalf of the Secretary of State for Transport,
is responsible for managing and operating a safe and efficient Strategic Road
Network (SRN) (i.e. the Trunk Road and Motorway network) in England. In the
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
case of this application the HA is concerned with the potential impact to the
A13 and the M25, particularly the A13 / A1306 junction, and M25 Junctions 30
& 31, which form part of the Trunk Road Network in this area.
The following comments are based on a review of Transport Assessment (TA)
and Travel Plan (TP) and the relevant sections of the Environmental statement
(ES) which have been prepared in support of this outline planning application.
In this response, ‘2008 application’ refers to the application
08/00858/TTGOUT that was granted permission in 2011; whilst ‘2012
application’ refers to the current proposal which is under review.
1.0 Transport Assessment
Baseline Traffic Flows
1.1 It is acknowledged that the traffic surveys collected in 2007 are no
longer representative of current traffic levels. New traffic counts have
been collected in February 2012 (6th February to the 12th February).
For the purpose of this review the HA has additionally reviewed the
Annual Average Daily Traffic (AADT) and hourly flow data for the
trunk road network at DfT count sites on the A13 and A1306 between
2008 and 2011.
1.2 It is noted that the traffic flow information provided in the TA and
accompanying appendices generally demonstrate a reduction in
traffic levels across the study area between 2007 and 2011 / 2012.
This is true for both the AM and PM peaks as well as across the
entire day. The only exception is A1306 London Road where traffic
flows have remained generally stable. We have undertaken an
independent review of the AADTs collected between 2008 and 2011
at DfT count sites located on the A13 and the A1306. In general the
comparison appears to concur with Motion’s conclusion with our
findings presented in table 1.1 below
Road 2008 2009 2010 2011
London Road (A1306) 20,459 19,057 18,817 20,566
New Tank Road 9,635 9,157 9,057 9,217
A13 east of the A1306 75,435 73,861 74,704 72,600
A13 west of the A1306 64,852 64,155 64,572 63,448
New Road (A1306) 14,457 14,302 11,170 11,399
Table 1.1 – AADT data at DfT count sites 2008-2001
1.3 Table 6.2 compares 2007 and 2012 Manual Classified Counts (MCC)
to demonstrate traffic growth between 2007 and 2012, which shows
traffic flows at the A13 / A1306 have dropped between 2007 and
2012. this is consistent with the ATC flow comparison. However, the
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
2012 MCC data have not been included, the HA requests that they
are submitted to confirm whether the trends shown in the table are
correct.
Traffic Growth
1.4 It is noted that new traffic growth factors for the opening year of 2013
and horizon year of 2022 have been calculated from TEMPRO 6.2.
The HA has checked these growth factors and considers them to be
acceptable.
Committed Development
1.5 Other committed developments included in the traffic impact
assessment are considered to be acceptable.
Consented vs Revised Land Uses
1.6 The 2008 application consisted of 38,686 square metres of mixed
use B1, B2 and B8 floorspace and a car showroom. Following
planning consent in 2011 the site was identified in the Core Strategy
as a secondary industrial and commercial area (policy CSTP6) and
was also excluded from green belt policy (policy CSSP4).
1.7 The site area of the new 2012 application remains unchanged at
38,686 square metres, but with B8 land use only and is said to have
less vehicle trips overall (see table 1.2 below). Further comments
regarding the proposed trip generation, modal split and trip
distribution are provided in the corresponding section below.
AM Peak PM Peak
Consented Revised Consented Revised
Arrivals 203 52 46 44
Departures 98 32 150 57
Table 1.2 – Comparison of consented and revised development trips
at Ponds Farm
1.8 The Trip Attraction and Distribution and Highway Impact Assessment
sections of the TA are focused on comparing the associated traffic
assumptions and impacts between the 2008 and 2012 applications.
The 2008 application included highways measures at the A13 /
A1306 Wennington Interchange, to mitigate predicted development
impacts. Although the 2012 application suggests a smaller traffic
impact, the fact that capacity improvements are no longer included
as part of the application must be taken into consideration when
evaluating this planning application and the associated impacts.
1.9 It is noted that the 2012 application has not adopted the agreed B8
trip rates included in the previous 2008 application. Updated trip
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
rates generated from the TRICs (2012a) database for B8
(commercial warehouse) land use have been used to form the basis
of the trip generation assessment for the new site proposals.
Considering the proposed in quantum of B8 land use compared to
the previous application the B8 sites selected for the 2008 trip rates
analysis are no longer considered to be comparable. Subject to
addressing our comments regarding trip generation below, the HA
concurs to adopting new trip rates in the 2012 TA.
Assessment Periods
1.10 A review of ATC count data suggests that the proposed assessment
hours (0730-0830 AM and 1645-1745 PM) to be acceptable. The
assessment years (2013 and 2022) used for the traffic impact
assessment are also considered to be acceptable.
Trip Generation
1.11 The HA has reviewed the trip rates included in table 5.3 of the TA
and carried out our own analysis using the TRICs database. Initially
the HA used the search parameters included in paragraph 5.4 of the
TA, but this resulted in only two suitable sites. Subsequently the HA
has adjusted the floor area range search parameter to include all
sites between 10,000 and 80,000 square metres. This resulted in the
identification of 11 suitable sites. The trip rates generated using
these sites are more robust than the trip rates included in the TA.
The HA therefore requests that the search parameters used by
Motion to select sites used in the TRICs analyses are adjusted to
include all sites between 10,000 and 80,000 square metres. The trip
rates and the associated TRICs site survey reports should then be
submitted for review.
1.12 During discussions regarding the 2008 application, the HA requested
that traffic impact and modelling assessments were carried out using
85th percentile trip rates for two major reasons. Firstly, to ensure that
a robust, worst case scenario was considered given the site’s poor
accessibility to public transport. Secondly this is to safeguard a fair
and consistent approach to this, and all other applications in the
surrounding area that the HA has reviewed. The latter is needed so
that, should highway mitigations be deemed necessary, including any
potential impacts at M25 J30/31, the proportion of financial
contribution is allocated fairly. For these reasons, 85th percentile
trip rates must be applied to this application and presented to
the HA for review.
1.13 In addition, paragraph b5.10 of the TA claims 35% of the vehicle trips
will be attributed to HGV activity. In the absence of any further
justification the HA is unable to confirm whether the consider this
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
percentage as reasonable. Further information justifying this
assumption must be supplied to HA for review.
Modal Split
1.14 During the 2008 application, the HA was concerned that the modal
split statistics, generated from 2001 workplace statistics for Thurrock,
may not be reflective of travel behaviour on site. Without
improvements to the public transport accessibility of the site it is
unlikely that 3.1% of employees would access the site via train. The
nearest station, Purfleet, is located in excess of 2km from the site.
However, considering the proposed improvements to the number 11
bus service, or the provision of a shuttle service between the
development site and Purfleet station outlined within the Travel Plan,
which will help to improve connections between the site and Purfleet
station, the HA considers the modal split assumptions to be
acceptable.
Trip Distribution and Assignment
1.15 It is noted that development traffic flows described in the traffic flow
diagrams presented in figures 5.5 and 5.6 have been distributed in
accordance with the traffic flow distributions described in figures 5.3
and 5.4. Although these will be subject to further review, upon
receipt of revised figures from Motion regarding our requests in
paragraphs 1.13 and 1.14 above.
1.16 Furthermore, the single biggest issue that remained unresolved in
the 2008 application was Motion’s trip distribution and the validity of
the gravity model, and the HA has further comments with regards to
both the HGV and non-HGV distributions.
HGV distributions
1.17 New to the 2012 application is a separate assumption for HGV trip
distributions, presented in figure 5.4. Whilst the HA is supportive of
this approach no explanation is provided as to how these
percentages have been derived, which currently appears overly-
simplistic. For example, Motion suggests that HGV’s are evenly
distributed across the three exits at the Wennington Interchange, this
appears questionable. Motion must provide further evidence as to
the basis behind he HGV trip distributions presented in the TA.
Non-HGV distributions
1.18 The non-HGV trip distributions presented in figure 5.3 appears to be
the same as those used in the 2008 application, which is based on
Motion’s bespoke gravity model. It should be noted that the
employee trip distribution profiles, which were based on an un-
validated gravity model were never approved by the HA during the
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
2008 application. Table 1.3 is extracted from our response in 2008,
which compared Motion’s percentages using the gravity model, and
HA’s percentages, based on workplace statistics for existing
residence locations of employees in the Aveley and Uplands ward.
Main Route to Site Motion’s Percentage HA’s percentage
A1306 (W) 35% 7%
A13 (W) 8% 5%
A13 (E) * 9% 28%
M25 (N) 2% 3%
M25 (S) 9% 2%
*At A13 / A1306 roundabout – includes traffic from M25 (N)
Table 1.3 Estimated Distribution of Traffic of the Proposed Development
1.19 The HA strongly recommends that Motion assign employee car traffic
in accordance with the HA’s trip distribution profile for employee trips
described above. In addition the network study area should be
extended to include traffic impacts at the M25 junctions 30 and 31.
This is also to ensure consistency with other planning applications in
the surrounding area, and that any potential capacity or safety
impacts are not overlooked.
Development Traffic
1.20 The traffic impact tables (table 6.4 – 6.11) imply that the 2012 Ponds
Farm outline planning application will have a smaller impact to traffic
flows than development traffic associated with the 2008 planning
application. The HA cannot confirm this, or otherwise, when the
amendments requested above have been submitted for review.
1.21 Given the need to have a clear evidence base, and to maintain
consistency with requirements made on other planning applications
in the surrounding area, HA would like Motion to undertake
operational modelling of the A13 / A1306 Wennington Interchange
using the new 2012 MCCs and 85th percentile trip rates, to determine
the impact of the proposed development proposals. The HA
suggests that the following scenarios (table 1.4) are undertaken:
Base Future baseline (background
growth + committed
developmentsA)
With
development
2012 AM & PM √
2013 AM & PM √ √
2022 AM & PM √ √ A – With development means 85th percentile development traffic distributed
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
using HA traffic distributions
Table 1.4 – Scenarios Requiring ARCADY Modelling
1.22 For robustness all future year scenarios should assume that the
Purfleet Centre Travel Plan is not operational, i.e. without the
reduction in trips assumed in tables 6.11 to 6.13 of the TA.
1.23 In addition, Motion is also expected to present the absolute changes
in traffic volume, movement-by-movement, at M25 junctions 30 and
31 for both AM and PM peaks during 2013 and 2022, to enable the
HA to determine what further measures, if any, are required to limit
the impact at these locations. Trip distribution must again be based
on 85th percentile trip rates using HA’s trip distribution.
Road Safety Study
1.24 It is noted that an accident assessment has been undertaken for the
surrounding study area. The accident assessment reviews all
Personal Injury Accidents (PIA) which have occurred over the past 5
years (60 months). In anticipation that there is likely to be an
increase in HGV traffic at M25 junctions 30 and 31, the accident
assessment should also include these junctions.
1.25 A summary of the fatal and severe accidents occurring within the
study area is included in table 3.4 of the TA. We have undertaken a
full review of the accident reports included in appendix B, and have
noted that table 3.4 excludes four accidents that have been classed
as either severe or fatal within the accident reports. In total, 5
serious accidents and 3 fatal accidents have occurred within the
study area since 2007. A review of the accident maps included in the
appendix confirms that all fatal accidents occurred on the A13 or the
A13 off-slips at the Wennington Interchange. One of which involved
a goods vehicle of 3.5-7.5 tonnes. Over a 5-year period this appears
to be a significant number of fatal accidents.
1.26 With regard to fatal and severe accidents, the TA states that ‘In all
cases, the identified possible causation factors indicate that the
accidents were the result of driver error’. The accident reports state
that a number of accidents occurred when drivers lost control and
collided with another vehicle. A wider review of all accident reports
indicates that accidents tended to occur in wet conditions. This
suggests that carriageway surfacing within the vicinity of the site may
lack the required level of skid resistance. This was raised as an
issue during discussions over the previous planning application in
2008. The HA is therefore supportive of proposals to introduce skid
resistant surfacing on approaches to the new signalised access
junction to the site. However, it is noted that the 2012 application
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
does not include proposals to enhance the skid resistance of
surfaces on all approaches to the A13 / A1306 Wennington
Interchange. Considering the number of accidents involving vehicles
in excess of 3.5 tonnes and the likely increase in HGV’s from the
development site, the development proposals could exacerbate
existing safety issues on the A13 and the Wennington Interchange.
1.27 In an effort to mitigate any potential impact to safety as a result of the
development proposals, the HA requests that the developer commits
to delivering the above as part of this 2012 application.
Parking Arrangements
1.28 It is noted that the proposed parking provision is generally in line with
Essex County Council parking standards, however the standards
state that for a B8 type development, accessible spaces should make
up 5%of the total car parking provision. Current site plans confirm
accessible parking to total 11 bays. Based on a total provision of 258
car parking spaces, and a provision of 5% for accessible parking, the
total number of accessible parking bays should be 13. This should
be confirmed within the planning application proposals.
2.0 Travel Plan
2.1 It is noted that the Travel Plan (TP) has adopted the same general
format as the approved 2008 TP. Subject to the revised
development trip generation and distribution not altering the overall
development traffic impact, the HA is supportive of the TP and is
satisfied that an appropriate action plan is in place to ensure the
success of the TP. The targets set in the TP must be realistic and
measurable, whilst at the same time covering a sufficiently wide
spectrum so that all staff travel patterns are captured. In addition to
measuring the percentage of employees driving to work, the HA
suggests that the TP should include other targets such as the
percentage of staff cycling to work and travelling by public transport.
2.2 It is critical that sufficient funding is in place to ensue the continual
delivery of the Plan. The HA is satisfied that the Plan includes
contingency measures which would be considered in the event that
targets are not met. The TP should also identify how penalties will
be enforced in the event that the development fails to meet the
agreed targets. The TP and associated measures should be
conditioned as part of the planning approval for the site.
3.0 Environmental Statement
3.1 The HA has also reviewed relevant chapters of the Environmental
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
Statement (ES) to determine the traffic impact due to construction.
Construction
3.2 The ES suggests that construction site personnel could be in the
range of 250 arrivals and 250 departures on a typical day. However
paragraph 7.5.2 also states that it has not been possible to estimate
the number of vehicles associated with construction works on a day-
to-day basis because of uncertainties surrounding the programme. It
is noted that these figures are consistent with those referenced in the
environmental statement for the previous planning application.
Although shift patterns of staff may not be available at this time, it is
conceivable that the majority of them will arrive and depart around
the start and end of construction hours, which is between 07:30 and
17:00. The potential traffic impact during the PM peak must
therefore be considered. Given the site’s relatively poor access to
public transport a significant proportion of construction workers may
arrive by car, this could cause severe congestion on the A13 and
M25. Mitigation targeted towards reducing the impact of construction
traffic, including worker trips on the A13 and M25 should be included
in the Construction Environmental Management Plan (CEMP).
3.3 The ES states that Construction Transport Plan will be put in place
as part of the CEMP to control the number of construction vehicle
movements. It is important that this includes measures to limit the
number of single person vehicle movements to and from site. Other
measures that could help reduce the potential highway impacts may
include limiting the number of parking bays available on-site, car
sharing and the provision of shuttle bus services to and from Purfleet
and / or other local railway stations.
3.4 It is stated in paragraph 7.5.2 that ‘volume of construction traffic will
be insignificant and is considered likely to result in a negligible effect
on traffic capacity and highway safety issues’. As soon as additional
information becomes available it should be submitted to the HA for
review so that the potential impacts on the A13 and the M25 can be
reviewed. The developer and the contractor should also ensure that,
as far as reasonably practicable, construction traffic movements are
limited to outside the network peak hours so that traffic delays are
minimised.
4.0 Summary
4.1 Table 4.1 summarises the list of requests made by HA:
Paragraph Item
1.3 MCC data to be submitted for HA to review
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
1.12 TRICs analysis adjustment to include further comparable sites
1.13 85th percentile trip rates must be adopted
1.14 Provide justification on how the 35% HGV development trips
have been derived
1.18 Provide justification regarding HGV trip distributions
1.19 Adopt HA’s trip distribution percentages
1.20 Assessment extended to M25 J30 and 31
1.22-1.23 Undertake ARCADY modelling as detailed within these
paragraphs
1.24 Provide, movement-by-movement, absolute changes to traffic
volumes at M25 J30 and 31
1.25 Accident study to extend to M25 J30 and 31
1.28 Reinstate proposal to provide skid-resistant surfacing on
approaches to Wennington Interchange
3.2 CEMP to mitigate impact of construction traffic, including worker
trips, on the A13 and M25
In conclusion, the HA requires further information before we can support this
application moving forward.”
4.4 Highways Agency: (response dated 7th November 2012)
“The Highways Agency requires further information before we can support this
application moving forward, and to date the information has not been received.
Please find attached a Direction under Article 25 of the Town and Country
Planning (Development Management Procedure) Order 2010 which shall be
maintained until 19th December 2012.”
(The Direction states that planning permission is not to be granted for a
specified period until 19th December 2012).
4.5 Highways Agency: (response dated 10th December 2012)
“The Highways Agency (HA) provided their comments for Technical Note
2012-01 to the developers’ consultants Motion Transport Planning in our letter
dated 27 November 2012. These secondary comments follow the HA’s initial
response to the Transport Assessment (TA), Travel Plan (TP) and the relevant
sections of the Environmental Statement (ES) dated 17 October 2012.
The HA’s response on Technical Note 2012-01 raised a number of issues
requesting Motion to provide additional information. Motion responded with
Technical Note 2012-02, dated 29 November 2012 (referred to hereafter as
‘TN2012-02’), which the HA has reviewed and our observations are outlined in
this letter.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
As per our previous response, ‘2008 application’ refers to the application
08/00858/TTGOUT that was granted permission in 2011; whilst ‘2012
application’ refers to the current proposals under review.
Our previous response identified seven outstanding items (below) requiring
further attention. For ease of reference, this letter is structured to follow the
same sequence.
Section Item Status after this review
1 Provide justification on how 35%
HGV development trips have been
derived
Further information needed
2 Provide justification regarding HGV
trip distribution
Closed
3 Adopt HA’s trip distribution
percentages
Closed
3 Assessment extended to M25 J30
and 31
Further information needed
3 Undertake ARCADY modelling as
detailed within these paragraphs
Closed
3 Provide, movement-by-movement,
absolute changes to traffic volumes
at M25 J30 and 31
Further information needed
4 Accident study to extend to M25 J30
and 31
Further information needed
1 HGV Development Trips
1.1 The TRICS database has been interrogated by Motion to identify and
justify suitable HGV development trip percentages using 85th
percentile trip rates. Paragraph 3.2 and Table 3.1 in TN2012-02
seek to explicitly present this information. Based on the information
presented, trip rate percentages have been calculated by the HA and
are shown in the table below.
Peak Travel Period HGV % Trip Rates
Arrivals Departures
Weekday Morning (07.30 to
08.30)
39.8 52.0
Weekday Evening (16.45 to
17.45)
39.0 35.4
Daily (07.00 to 19.00) 41.3 38.6
1.2 The percentages shown in the table indicate that only the HGV
departure trips during the weekday PM peak period will have a
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
percentage rate of approximately 35%, whilst the HGV percentage
rate during the AM peak is as high as 52%. Based on the figures
shown in the table above PB request that for robustness a HGV
development trip percentage of 40% is used.
2 HGV Trip Distributions
2.1 Motion has assumed that the majority of HGV traffic exiting the site
will distribute north (75%) rather than south (25%) during the PM
peak period, whilst traffic will leave in equal distributions during the
AM peak (50% north, 50% south). This assumption is not based
wholly on any definitive empirical evidence but on Motion’s belief that
the A13’s location north of the site will encourage more traffic to
travel in this direction in order to access central London or the M25.
2.2 Some evidence has been provided by Motion to justify the 75/25
north/south HGV percentage split using the Purfleet Centre 2011
HGV baseline flows at the nearby A1306/A1090 New Tank Hill Road
signalised junction. This junction can currently be used by HGVs to
access the Purfleet Industrial Area. The 2011 HGV baseline flows
show a 50/50 north/south split in the AM peak, whilst the PM peak
shows a 75/25 north/south split.
2.3 The HA accept that the HGV distribution percentages, whilst not
based on empirical data, have a methodology that appears to be
suitable given the use classes that are known to operate out of the
Purfleet Industrial Area. For robustness however, the HA
recommend that the 75/25 north/south split for HGV movements at
the proposed site entrance is applied to all time periods throughout
the day i.e. both AM and PM peaks.
2.4 Motion has also used the turning percentages from the Purfleet
Centre 2011 baseline flows to derive turning movements for HGV
development traffic at the Wennington Interchange. The HA are
satisfied with this approach.
3 Overall Trip Distribution
3.1 The HA can confirm that Motion have rectified the errors in the flow
diagrams Figures 5.1, 5.2 and 5.5 to 5.8 and accordingly adopted the
HA’s distribution percentages and the 85th percentile trip rates as
requested.
3.2 Following receipt of the updated flow diagrams 5.1(B), 5.2(B), 5.7(B)
and 5.8(B), comparisons between the 85th percentile trip rates for the
consented site and the current proposal indicates an overall
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
reduction in the impact of development traffic on the local road
network. Due to this decrease in development flows, the HA are
satisfied that ARCADY modelling is not required in this circumstance
to assess traffic impacts at Wennington Junction.
3.3 However, Motion has not provided a turn-by-turn assessment of
development traffic accessing M25 J30 which would allow the HA to
have a direct comparison between the 2008 and 2012 applications.
The HA request that this information is still provided in order to fully
complete the development impact assessment for this site and make
it consistent with previous and current applications in the local area
with regard to M2 traffic impact assessments.
4 Road Safety Audit
4.1 Accident data for the M25 junction 31 has been provided by Motion
for a five year period, up until 29 March 2011. However, this
information has yet to be presented in a clear map format highlighting
the locations of the accidents on the network. The HA requires this
information so that accident trends can be assessed, in this case
identifying factors which may be causing HGV accidents at the
junction along with remedial solutions.
4.2 Accident data has also not yet been provided for M25 Junction 30 as
it is currently being sought by Motion from Connect Plus (M25
Maintenance Consortium). The HA again requires this data to come
to a reasoned outcome on accident causations at the junction.
Most of the outstanding issues previously identified have now been addressed
by Motion and only a few items remain. Upon receipt and validation of the
missing information the HA will be satisfied to approve and progress this
application further.”
4.6 Highways Agency: (response dated 17th January 2013)
“With reference to my letter of 17 December 2012 regarding the above
planning application, the Highways Agency has no objection subject to the
attached obligations being included with the S106. Please find attached a
form TR110 to this effect.
Planning obligations relating to the highway issues and the A13 trunk road:
1. No occupation shall be brought into beneficial use or occupation until
such time a detailed Vehicle Monitoring Scheme has been submitted to
and approved by the Thurrock Thames Gateway Development
Corporation in consultation with the Highways Agency and Thurrock
Council.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
2. By no later than first beneficial occupation, the developer to implement
and thereafter to maintain and, as the case may be, to fund the Vehicle
Monitoring Scheme at no expense to the Thurrock Thames Gateway
Development Corporation (should be the Council) in consultation with
the Highways Agency and Thurrock Council until such time (if it occurs
at all) as one year shall have elapsed from the date on which the last of
the Steps set out in Schedule 2 has been completed.
3. If during any agreed Monitoring Period the average number of inbound
and outward bound motorised vehicles during the peak periods
identified in Column 1 of Table A shall exceed the number specified in
columns 2 and 3 of Table A then the Applicant will without
unreasonable delay take or procure to be taken (or as the case be
funded) the measures identified as remedial actions in schedule 2, so
that the measures required by Step 1 in Schedule 2 shall be
implemented after the first Monitoring Period in which any such excess
has occurred, those required by Step 2 shall be implemented after the
second Monitoring Period in which any such excess has occurred,
those required by Step 3 shall be implemented after the third Monitoring
Period in which any such excess has occurred, those required by Step
4 shall be implemented after the fourth Monitoring Period in which any
such excess has occurred. For the avoidance of doubt and within
reason, the earliest possible date at which the measures required by
Step 4 shall be required to be implemented is 12 months after Full
Beneficial Occupation.
4. For the purposes of paragraph 3 above, the average number of inbound
and outbound vehicles during the peak periods identified in column 1 of
Table A shall be taken to have exceeded the number specified in
columns 2 and 3 of Table A if the number in column 2 and has been
exceeded by the aforesaid average number in relation to any one or
more working days of the week, such that, for example, and for the
avoidance of doubt: if, for 50% occupation in Table A and the average
number of outward bound vehicles between 0730 and 0830 on the
Mondays during a Monitoring Period exceeds 45 then the appropriate
Step of the remedial measures specified in Schedule 2 must be
implemented.
Schedule 1
Table A
Column 1 Column 2 Column 3
Peak Periods Inbound Vehicles Per Hour Outbound Vehicles Per Hour
Monday to Friday 50% Occupation 50% Occupation
0730-0830 60 45
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
1645-1745 15 75
75% Occupation 75% Occupation
0730-0830 90 70
1645-1745 20 115
Full Occupation Full Occupation
0730-0830 120 95
1645-1745 25 150
Schedule 2
Remedial actions to be taken if monitored numbers of vehicles exceed the allowable
figures
Step Action
Corrective Step One Formal notification to the Development Corporation of
failure to stay within the limits referred to in Table A on the
basis of the monitoring undertaken; set in hand a review of
the travel patterns of individual occupiers of the
Development and controls upon them being able to keep
within the vehicle limits.
Corrective Step Two Meting with the Travel Plan Co-ordinator (referred to in the
Travel Plan Framework) with the Development Corporation,
Thurrock Council and the Highways Agency to identify
which excess vehicle movements are occurring and to
discuss action which can be taken to reduce numbers of
vehicles entering and leaving the site.
Corrective Step Three Meetings with the Travel Plan Co-ordinator the
Development, the Development Corporation, Thurrock
Council and the Highways Agency, agree voluntary
measures to seek to resolve the excess vehicle movements
entering and leaving the site.
Corrective Step Four Signalisation (with limited green time for outbound traffic) of
the site access road to control flows entering and leaving
the Development in accordance with details first approved
by Thurrock Council to restrict vehicle movements from and
out onto the public highway to the limits set out in the Table
A without any expense to the Development Corporation,
Thurrock Council and the Highways Agency PROVIDED
that this Step (i) shall be taken in consultation with the
Thurrock Council as highways authority and (ii) may take
the form of funding the Thurrock Council to implement the
requisite signalisation (including reasonable monitoring and
commissioning).
4.7 Natural England: (response dated 8th October 2012)
“No objection -with conditions
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
This application is in close proximity to the Inner Thames Marshes Site of
Special Scientific Interest (SSSI). However, given the nature and scale of this
proposal, Natural England is satisfied that there is not likely to be an adverse
effect on this site as a result of the proposal being carried out in strict
accordance with the details of the application as submitted. We therefore
advise your authority that this SSSI does not represent a constraint in
determining this application. Should the details of the application change,
Natural England draws your attention to Section 28(I) of the Wildlife and
Countryside Act 1981 (as amended), requiring your authority to re-consult
Natural England.
Conditions
A suitably worded condition should be attached to any permission granted,
which seeks to achieve the production of a Construction Environmental
Management Plan, which should seek to mitigate the adverse effects of dust
contamination in particular (amongst other environmental impacts).
This condition is required to ensure that the development, as submitted, will
not impact upon the features of special interest for which Inner Thames
Marshes SSSI is notified.
If your authority is minded to grant consent for this application without the
conditions recommended above, we refer you to Section 28I (6) of the Wildlife
and Countryside Act (as amended), specifically the duty placed upon your
authority, requiring that your Authority:
provide notice to Natural England of the permission, and of its terms,
the notice to include a statement of how (if at all) your authority has
taken account of Natural England’s advice; and
shall not grant a permission which would allow the operations to start
before the end of a period of 21 days beginning with the date of that
notice.
The application is also in close proximity to Purfleet Road, Aveley Site of
Special Scientific Interest. However, given the nature and scale of this
proposal, Natural England is satisfied that there is not likely to be an adverse
effect on this site as a result of this proposal being carried out in strict
accordance with the details of the application as submitted. We therefore
advise your authority that this SSSI does not represent a constraint in
determining this application. Should the details of the application change,
Natural England draws your attention to Section 28(I) of the Wildlife and
Countryside Act 1981 (as amended), requiring your authority to re-consult
Natural England.
Other Advice
We would expect the Local Planning Authority to assess and consider the
other possible impacts resulting from this proposal on the following when
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
determining this application:
local sites (biodiversity and geodiversity)
local ;landscape character
local or national biodiversity priority habitats or species.
Natural England does not hold locally specific information relating to the
above. These remain material considerations in the determination of this
planning application and we recommend that you seek further information from
the appropriate bodies (which may include the local records centre, your local
wildlife trust or other recording society and a local landscape characterisation
document) in order to ensure the LPA has sufficient information to fully
understand the impact of the proposal before it determines the application. A
more comprehensive list of local groups can be found at Wildlife and
Countryside.
If the LPA is aware of, or representations from other parties highlight the
possible presence of a protected or Biodiversity Action Plan (BAP) species on
the site, the authority should request survey information from the applicant
before determining the application. The Government has provided advice on
BAP and protected species and their consideration in the planning system.
Natural England Standing Advice for Protected Species is available on our
website to help local planning authorities better understand the impact of
development on protected or BAP species should they be identified as an
issue at particular developments. This also sets out when, following receipt of
survey information, the authority should undertake further consultation with
Natural England.
Biodiversity Enhancements
This application may provide opportunities to incorporate features into the
design which are beneficial to wildlife, such as the incorporation of roosting
opportunities for bats or the installation of bird nest boxes. The authority
should consider securing measures to enhance the biodiversity of the site from
the applicant, if it is minded to grant permission for this application. This is in
accordance with Paragraph 118 of the NPPF. Additionally, we would draw
your attention to Section 40 of the Natural Environment and Rural
Communities Act (2006) which states that ‘every public authority must, in
exercising its functions, have regard, as far as is consistent with the proper
exercise of those functions, to the purpose of conserving biodiversity’. Section
40(3) of the same Act also states that ‘conserving biodiversity includes, in
relation to a living organism or type of habitat, restoring or enhancing a
population or habitat.”
4.8 Highways Development Control:
“Summary
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
The principle of employment use on this site has been previously agreed and
there are no objections in principle. There are some minor layout issues that
need addressing and recent LDF policy slightly changes the consideration of
the proposals. The use of IEA guidelines to assess whether the traffic / safety
impact is material is not agreed, as these tend to be more suited to
comparative scheme appraisal. However the level of traffic impact is not so
high as to warrant any short term local road network mitigation, aside from the
previously agreed Purfleet Road realignment. Enhancements to public bus
services are required and some funding is required in order to enable the
Council to relocates the Elfes access. It is recommended that a Section 106
agreement is made to deal with these issues. There are few local issues
concerning walking and cycling infrastructure that need addressing. Can you
please ensure that the Highways Agency are consulted concerning the impact
on the trunk road and their longer term proposals for junction 30/31.
Policy
PMD8 Parking standards. All 3 options show car parking levels that comply
with the Council’s draft parking standards. A condition will be required
concerning the level of car parking, disabled driver car parking, powered two-
wheeler parking and cycle parking.
PMD9 Road Network Hierarchy. The issue of a presumption against access
onto a principal distributor road has been previously considered and agreed on
the basis that it resolves a pre-existing safety problem at the junction of
Purfleet Road. I has been agreed that the former alignment of Purfleet Road
will be closed to through traffic, a planning condition will be required
concerning the traffic regulation order.
PMD11 Freight Movement. This indicates that a sustainable freight
distribution plan should be submitted which considers opportunities for rail,
port, pipeline or conveyor. In this location there are no common user rail
sidings or opportunities for direct synergy with ports such as at London
Gateway or Tilbury. Therefore this assessment will not be required.
This policy does require a number of other provisions for developments in
excess of 30,000 sq.m. This includes submission of a vehicle booking system,
HGV driver facilities and overnight parking of HGV’s. These issues can be
dealt with by planning condition.
National Planning Policy Framework. This removes PPG13 and refers to a
presumption in favour of sustainable development. The site is very poorly
served by public transport. The no. 11 service passes the site and is
scheduled for every 90 minutes on a weekday, the no. 44 travels along Tank
Hill Road every 30 minutes. The enhancement of bus services would cost-
effectively limit the traffic impact of the development and it is recommended
this is implemented to increase travel choice for employees. The previous
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
Transport Assessment suggested that the applicant would either seek to
increase the frequency of the no. 11 service or to allow the no. 44 service to
divert closer to the site, or the applicant would fund a shuttle bus service
between the site and Purfleet railway station. This was not agreed at the time
and it was recommended that there is at least a half-hour service to Purfleet,
Aveley and South Ockendon. The S.106 Agreement subsequently provided
for a contribution and it is recommended this is included in this consent, along
with the flexibility to target the funding to any provision that increases bus
access in the vicinity of the site.
Site Access and Layout
The proposed realignment of Purfleet Road has been amended. The new
A1306 junction is now further west on the A1306. This improves the junction
spacing to the Elfes access, however it is still a substandard arrangement to
have a ‘keep clear’ access in the queuing area for the traffic signals.
Accordingly it is probably reasonable to change the existing S.106
commitment to relocate the Elfes access from a direct obligation on the
developer to a financial contribution to the Council to facilitate the Elfes
junction relocation.
Can you ask the applicant to amend the plan to show a forward visibility sight
line in accordance with the Design Manual for Roads and Bridges along the
realigned Purfleet Road on the approach to the new traffic signals.
The proposed left-in access on the A1306 appears to be confined for the use
of cars only. This does not realise the full potential of this ingress in removing
HGV movements from the traffic signal junction of the A1306 and providing for
an access strategy with a more economic use of land. It is assumed this
approach is to segregate HGV traffic, however it is recommended that the
arrangement is reviewed to see if HGV’s could use this left-in. A condition will
be required for appropriate signing and flow direction control plates at this
access to prevent vehicles leaving in the wrong direction.
The previously consented arrangement proposed a new bellmouth on the
realigned section of Purfleet Road to provide access to the existing garage
‘island’ site, the new arrangement shows a crossover which is not acceptable.
Can you ask the applicant to amend the plans to show a similar bellmouth
arrangement to that which was previously consented, along with the requisite
emerging visibility sight lines.
Can you ask the applicant to amend the traffic signal arrangement to show a
pedestrian refuge in the middle of the carriageway of the side road, to improve
pedestrian and cycle movements along the A1306. Can you ask the applicant
to show a cycleway along their frontage with Purfleet Road.
Transport Assessment and Travel Plan
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
The TA refers to the use of IEA criteria as a planning screening process in
considering the potential environmental effects of traffic. This approach is not
agreed as the EIA criteria do not adequately reflect relative impacts on
sensitive streets and is more suited to comparative scheme appraisal. That
said the environmental impact has been previously agreed and HGV’s will be
precluded from travelling to and from the north along Purfleet Road.
Para. 7.4.3 and 7.5.16 refer to cycling infrastructure. Please note that there
are a number of breaks in the A1306 cycle infrastructure and it also switches
from the north to the south. It would be desirable to address this as part of
any planning gain infrastructure.
Again para. 7.3.12 and 7.5.34 seem to be suggesting that the IEA criteria can
be used to measure the effects on transportation and access and that not
exceeding IEA thresholds concerning environmental impact means that the
development proposal will not lead to unacceptable increases in driver delay
and reduce current road safety levels. This approach is not agreed, that said
the percentage traffic impacts are relatively low and do not require any short
term mitigation along the A1306 or at its junction with the A13. The approach
at junction 30/31 will have to be agreed with the Highways Agency, but clearly
the accumulative impact of traffic from this site and other development sites in
south Essex and east London should be taken into account when fairly
apportioning costs of these infrastructure improvements.”
Non-Statutory Consultees
4.9 Anglian Water:
No reply received.
4.10 Essex County Council (Archaeology):
No reply received.
4.11 Essex Field Club:
No reply received.
4.12 Essex & Suffolk Water:
No reply received.
4.13 Landscape & Ecology Consultant:
“The site retains some sense of its original open landscape character,
however the surrounding development and the A13 cutting have fragmented it,
significantly impacting on its value. I would agree with the landscape
character assessment that the site lacks a clear sense of place as it is largely
disconnected from the surrounding areas. The site currently contains no
features of landscape significance.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
I agree with the arboricultural assessment that the few trees on the site are of
poor quality and do not warrant retention.
The site has been subject to periodic cultivation that served to prevent the
development of features of landscape or ecological value.
No detail has been provided for any landscape scheme other than to provide
trees and shrubs to screen any development from the houses on Purfleet
Road in particular.
The building options included in this application would result in significantly
larger units than those proposed for the previous scheme. Their visual impact
however could be more effectively mitigated due to them being set further
back from the boundaries. Despite the scale of the proposed development the
space shown to be available for landscape around the boundaries however is
constrained in some sections, particularly along the south-eastern boundary
adjacent to Purfleet Road. Should outline permission be granted I would wish
to see the boundary landscape buffers extended.
The landscape and visual impact assessment states that the proposed bund
and tree planting on the boundary closest to Purfleet Road should be in
advance of the start of the main development in order to minimise the visual
impacts to these residents. If this scheme is to progress I would wish to have
a condition requiring this.
No detail has been provided yet as to the layout and gradients for the bund.
Ideally this should be set back from the road and graded to prevent it
becoming a dominating feature and to help ensure that any planting on it is
more likely to survive drought conditions.
The Ecological Assessment highlights the need for measures to minimise dust
contamination of the SSSI and Local Wildlife site. It is important for these
measures to be secured as part of a condition requiring the production of a
Construction Environmental Management Plan.
The mitigation measures outlined are focused on preventing specific damage
to protected species and sites. While these are important it is considered that
the site provides an opportunity to achieve positive gains for biodiversity by
including suitable habitat features within the landscape scheme such as
flower-rich grassland, areas of bare ground and inert material such as PFA
that will benefit a range of invertebrates in particular. Consideration should
also be given to the potential for use of green or brown roofs on some
buildings. Similarly the SuDS including new water bodies should be managed
to maximise their ecological value. There should be an objective to use
predominantly native tree and shrub species within the wider landscape
scheme.”
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
4.14 London Borough of Havering:
“Please have regard to the comments from our highways officers, which are as
follows:
Trip Attraction
There would appear to be a significant amount of scoping work carried out by
the applicant with the local highway authority (Thurrock Council) and the
Highways Agency. It would appear from the Highways Agency response that
not all their requirements have been met. In reviewing the impact on
Havering’s network it is clear from the information submitted that there is a
significant reduction in vehicular traffic flows on the A1306 between 2007 and
2012. The car based trip attraction of the development is higher than we
would normally expect for a development in Havering, but given its location in
Thurrock, we assume this to be correct.
We are content that the extra car borne trips would have negligible impact on
highways managed b the LB Havering although we retain an interest in the
performance of the double roundabout junction of the A1306 / A13 and the
removal of the Highway Agency objection to the proposals.”
4.15 National Grid:
No reply received.
4.16 Thurrock Council (Environmental Health):
Air Quality
“I have reviewed the air quality assessment for the proposed development for
mixed commercial use. The proposed site is located along the London Road
Arterial Road, just to the north of Air Quality Management Area (AQMA) 13.
The modelled results using ADMS-Roads indicated that some of the receptors
(namely receptors 5 & 6) modelled will be above the Air Quality Objectives for
both the Annual Mean nitrogen dioxide (NO2) and the hourly mean objective
for NO2 and that the daily mean objective for particulate matter (PM10) will be
breached at receptor 5. The assessment concludes that the overall impact
from the development for air quality will be slight adverse to negligible for NO2
and negligible for PM10. They propose as mitigation to introduce a Travel Plan
including bus links and highway improvements which will help to reduce the
effect of the proposed development on local air quality.
Although the impact from the development does not pose a major impact on
air quality, it is in an area where air quality is very poor and is clearly in breach
of the air quality objectives for NO2 and PM10 and any further increases from
any development in this area would not be desirable. I would advise that if this
development were to go ahead, then they would need to make sure that these
mitigation measures are imposed in order to minimise any further increase in
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
concentrations. It would be appropriate to require the proposed measures to
be implemented by the developer by condition.
Construction Phase
Section 4.5.14 of the environmental statement refers to the production of a
construction environmental management plan (CEMP), which is to be finalised
prior to the commencement of construction activities (section 4.5.14). 4.5.16
provides for the agreement of the contents of the CEMP with the relevant
authorities prior to the commencement of construction activities. 4.5.17
summarises the measures to be adopted:
a commitment to ‘Considerate Contractors’ scheme 1;
choice of methodologies to minimise generation of noise, vibration and
dust, for example the use of cutting rather than breaking in order to
reduce the transfer of vibration;
use of hoardings for as long as practicable to provide acoustic
screening;
requirement for engines to be switched off on-site when not in use, use
of quieter plant, regular plant maintenance, screening of plant (if
appropriate);
spraying of areas with water supplied as and when conditions dictate;
effective wheel / body washing facilities to be provided and used as
necessary;
a road sweeper will be readily available whenever the need for road
cleaning arises;
vehicles carrying waste material off-site to be sheeted;
under no circumstances will fires be allowed on the Assessment Site;
and
the safety method statement will outline the control measures
necessary to minimise the risks to an acceptable level, and all statutory
notices will be placed with the Health and Safety Executive.
The proposed measures provide the background for the mitigation measures
that will be required if permission is granted. I would expect the finalised plan
to have regard to those mitigation measures outlined in Chapter 8 (Noise)
section 8.5.49
‘Prior to the commencement of the construction works the contractor should
prepare a detailed Construction Environmental Management Plan (CEMP) in
consultation with Thurrock Council. The CEMP should include noise
amelioration measures and/or noise limits and restrictions to hours of
operation.’
And Chapter 9 (Air Quality) section 9.5.13 mitigation
vehicles carrying loose aggregate and workings should be sheeted at
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
all times;
dampening of exposed surfaces and haulage routes;
implementation of design controls for construction equipment and
vehicles and use of appropriately designed vehicles for materials
handling (e.g. minimising drop heights and matching bucket sizes to
lorries);
regular inspection and, if necessary, cleaning of local highways and site
boundaries to check for dust deposits (and removal if necessary);
minimise surface areas of stockpiles (subject to health and safety and
visual constraints regarding slope gradients and visual intrusion) to
reduce area of surfaces exposed to wind pick-up;
use of dust-suppressed tools for all operations;
ensuring that all construction plant and equipment is maintained in good
working order and not left running when not in use;
restrict on-site movements to well within site and not near the perimeter,
as far as possible; and
no unauthorised burning of any material anywhere on site.
‘The applicant proposes the hours of construction as follows (Section 4.5.2):
TC will stipulate the hours of work prior to the commencement of the works. It
is anticipated that these will be 07.30 to 18.00 Monday to Friday and 07.30 to
13.00 on Saturdays. All work outside these hours will be subject to prior
agreement, and/or reasonable notice, by TC, who may impose certain
restrictions. Night-time construction working and working on public and bank
holidays will be restricted to exceptional circumstances.’
I am not happy with this proposal as it stands. The hours of work as proposed
for normal working is reasonable for general construction work, but reference
is made to piles in section 4.5.1, depending on the method of piling proposed
will affect the hours of operation. If impact driven piling is the preferred
method then I would expect the hours of piling activity to be restricted further.
This would not be the case if a quieter method of piling were to be employed.
I therefore recommend that the method of piling and the hours of piling should
be submitted and agreed prior to piling works commencing. No working
outside of the proposed normal working hours should be carried out without
consultation and approval. In this case the applicant may wish to enter into a
Section 61 prior consent for work on construction sites (Control of Pollution Act
1974) with the local authority to formalise the procedure for working outside of
normal hours.
I am happy with the proposed method for managing complaints during the
construction phase (section 4.5.20 and 4.5.21):
‘4.5.20 Any complaints will be logged on site and, where necessary, reported
to the relevant individual within TC (and vice versa) as soon as practicable.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
4.5.21 The CEMP will specify the roles and responsibilities of the designated
site liaison officer and TC in respect of breaches and complaints from the
public. The required action will be different in each specific case, depending
on the operation, equipment or location or applying additional controls.’
Subject to the submission and implementation of an agreed CEMP I am
satisfied that mitigation measures can be taken to minimise the impact of the
construction on sensitive receptors.
Contaminated Land
The site will be suitable for the end use as commercial / industrial usage if the
recommendations of chapter 12 of the EIA Volume 1 are undertaken.
The Environment Agency should be consulted on this application.
Noise
Chapter 8, Noise and Vibration within Volume 1 of the Environmental
Statement dealt with construction and operational noise. Construction noise is
considered above. The principal operational noise impact from the
development for residential receptors in Purfleet Road is from HGVs and cars
manoeuvring in the logistics service area.
The noise consultant has used generic noise levels derived from several years
of monitoring data at other logistics sites and the values used for the
assessment appear to be reasonable. A worst-case set of assumptions are
made for the calculations.
The assessment shows that, without mitigation in the form of boundary
treatment, the night time period LAmax is in excess of the WHO guidelines for
sleep disturbance. During the day, the received levels are comparable with
the WHO guidelines.
In order to reduce the noise impact to acceptable levels during the night time
period a noise barrier is proposed. In paragraph 8.5.24 two barriers are
described that will give at least 10dB of attenuation. With either of these
barriers in place and assuming 10dB attenuation, the resulting LAmax level at
the nearest receptor is reduced to 54dB LAmax, 6dB below the WHO guideline.
The attenuation provided by each of the barriers is calculated from the site
geometry in Appendix 8.4 with the 4.5 metre acoustic fence giving 10dB
attenuation and the bund with acoustic fence, total height 8.9 metres, 15dB.
Naturally the latter option would be preferred for its increased performance
and visual appearance.
Noise from car parking is considered and is shown not to be an issue.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
Noise from mechanical services plans will need to be controlled by design to
ensure that plant noise at the nearest receptor is not more than 5dB above the
background level as determined by the BS4142:1997 methodology. Since the
lowest background level will occur during the night.
Given the busy nature of surrounding roads, the noise generated by
development traffic is negligible. I therefore agree with the report and the
summary at paragraph 8.6.
A condition should be included for the developer to submit a scheme of noise
mitigation, detailing the barrier to be employed, for the LPA to approve prior to
the development commencing.
A condition should be included so that fixed mechanical plant should be
designed and installed so that the specific noise from the plant noise at the
nearest noise sensitive receptor is not more than 5dB LAeq,5min above the
lowest night time background noise level.”
4.17 Thurrock Council (Travel Plan Co-ordinator):
“This development will need to have a travel plan presented at application
stage which should include provision for showers and locker facilities for staff
cycling and walking to the site. There should also be consideration given to
providing car share spaces adjacent to the main entrance along with the
disabled car parking spaces.”
4.18 Representations:
This application has been publicised via a press notice, the display of site
notices and consultation letters sent to 81 surrounding addresses.
4.19 Three letters of objection have been received, two of which raise the following
concerns:
loss of Green Belt land;
increased traffic congestion;
impact on wildlife;
no need for the development;
increased pressure on infrastructure.
The third letter objects to the application on the following grounds:
the desk study for invertebrates in the EIA is inadequate;
invertebrate survey data for the site is inadequate.
5.0 POLICY CONTEXT
5.1 National Planning Policy Framework (NPPF)
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
The NPPF was published on the 27th March 2012. The NPPF largely carries
forward many planning policies and protections, albeit in a significantly more
streamlined form and makes adjustments to some specific policies. The policy
documents listed at Annex 3 of the Framework (including many existing
Planning Policy Guidance notes (PPG’s) and Planning Policy Statements
(PPS’s) are cancelled.
5.2 Paragraph 13 of the Framework sets out the presumption in favour of
sustainable development. Paragraph 196 of the Framework confirms the tests
in s.38(6) of the Planning and Compulsory Purchase Act 2004 and s.70 of the
Town and Country Planning Act 1990 and that the Framework is a material
consideration in planning decisions. Paragraph 197 states that in assessing
and determining development proposals, local planning authorities should
apply the presumption in favour of sustainable development.
5.3 Annex 1 makes clear that Development Plan policies should not be considered
out-of-date simply because they were adopted prior to publication of the
Framework. It also sets out how decision-takers should proceed, taking
account of the date of adoption of the relevant policy and the consistency of
the policy with the Framework. For 12 months from the day of publication,
decision-takers may continue to give full weight to relevant policies in
development plan documents adopted in accordance with the Planning and
Compulsory Purchase Act 2004, even if there is a limited degree of conflict
with the Framework (Annex A paragraph 4 for further advice). In other cases
and following this 12-month period, due weight should be given to relevant
policies in existing plans according to their degree of consistency with the
Framework (the closer the policies in the plan to the policies in the Framework,
the greater the weight that may be given).
5.4 The following headings and content of the NPPF are relevant to the
consideration of the current proposals.
5.5 Building a strong, competitive economy:
The Government is committed to ensuring that the planning system does
everything it can to support sustainable economic growth. Therefore
significant weight should be placed on the need to support economic growth
through the planning system.
5.6 Promoting sustainable transport:
All developments that generate significant amounts of movement should be
supported by a Transport statement of Transport assessment. Decisions
should take account of whether:
the opportunities for sustainable transport modes have been taken up
depending on the nature and location of the site, to reduce the need for
major transport infrastructure;
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
safe and suitable access to the site can be achieved for all people; and
improvements can be undertaken within the transport network that cost
effectively limit the significant impacts of the development.
Development should only be prevented or refused on transport grounds
where the residual cumulative impacts of development are severe.
Decisions should ensure developments that generate significant movement
are located where the need to travel will be minimised and the use of
sustainable transport modes can be maximised. Development should be
located and designed where practical to:
accommodate the efficient delivery of goods and supplies;
give priority to pedestrian and cycle movements, and have access to
high quality public transport facilities,
create safe and secure layouts which minimise conflicts between traffic
and cyclists or pedestrians, avoiding street clutter and where
appropriate establishing home zones;
consider the needs of people with disabilities by all modes of transport.
5.7 Requiring good design:
The Government attaches great importance to the design of the built
environment. Good design is a key aspect of sustainable development, is
indivisible from good planning, and should contribute positively to making
places better for people.
Local planning authorities should consider using design codes where they
could help deliver high quality outcomes. However, design policies should
avoid unnecessary prescription or detail and should concentrate on guiding
the overall scale, density, massing, height, landscape, layout, materials and
access of new development in relation to neighbouring buildings and the local
area more generally. Although visual appearance and the architecture of
individual buildings are very important factors, securing high quality and
inclusive design goes beyond aesthetic considerations. Therefore, planning
policies and decisions should address the connections between people and
places and the integration of new development into the natural, built and
historic environment.
Permission should be refused for development of poor design that fails to take
the opportunities available for improving the character and quality of an area
and the way it functions. However, local planning authorities should not refuse
planning permission for buildings or infrastructure which promote high levels of
sustainability because of concerns about incompatibility with an existing
townscape, if those concerns have been mitigated by good design (unless the
concern relates to a designated heritage asset and the impact would cause
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
material harm to the asset or its setting which is not outweighed by the
proposal’s economic, social or environmental benefits).
5.8 Promoting healthy communities:
The planning system can play an important role in facilitating social interaction
and creating healthy, inclusive communities. Planning policies and decisions
should aim to achieve places which promote:
opportunities for meeting between members of the community who
might not otherwise come into contact with each other, including
through mixed-use developments, strong neighbourhood centres and
active street frontages which bring together those who work, live and
play in the vicinity;
safe and accessible environments where crime and disorder, and the
fear of crime, do not undermine quality of life or community cohesion;
and
safe and accessible developments, containing clear and legible
pedestrian routes, and high quality public space, which encourage the
active and continual use of public areas.
5.9 Meeting the challenge of climate change, flooding and coastal change
In determining planning applications, local planning authorities should expect
new development to:
comply with adopted Local Plan policies on local requirements for
decentralised energy supplied unless it can be demonstrated by the
applicant, having regard to the type of development involved and its
design, that this is not feasible or viable; and
take account of landform, layout, building orientation, massing and
landscaping to minimise energy consumption.
Inappropriate development in areas at risk of flooding should be avoided by
directing development away from areas at highest risk, but where
development is necessary making it safe without increasing flood risk
elsewhere. When determining planning applications, local planning authorities
should ensure flood risk is not in creased elsewhere and only consider
development appropriate in areas at risk of flooding where, informed by a site-
specific flood risk assessment following the Sequential Test, and if required
the Exception test, it can be demonstrated that:
within the site, the most vulnerable development is located in areas of
lowest flood risk unless there are overriding reasons to prefer and
different location; and
development is appropriately flood resilient and resistant, including safe
access and escape routes where required, and that any residual risk
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
can be safely managed, including by emergency planning; and gives
priority to the use of sustainable drainage systems.
5.10 Conserving and enhancing the natural environment
When determining planning applications, local planning authorities should aim
to conserve and enhance biodiversity by applying the following principles:
if significant harm from a development cannot be avoided, adequately
mitigated or, as a last resort, compensated for, then planning
permission should be refused;
opportunities to incorporate biodiversity in and around developments
should be encouraged;
decisions should aim to avoid noise from giving rise to significant
adverse impacts on health and quality of life as a result of new
development;
mitigate and reduce to a minimum the adverse impacts on health and
quality of life arising from noise from new development, including
through the use of conditions.
5.11 Regional Planning Policy
On 3rd January 2012 an Order formally revoking the Regional Strategy for the
East of England came into force. The effect of this Order is to revoke the East
of England Plan and all directions preserving policies contained in structure
plans in the corresponding area.
Local Planning Policy
5.12 Thurrock Local Development Framework:
Thurrock Council adopted the “Core Strategy and Policies for the Management
of Development Plan Document” on 21st December 2011.
5.13 The key diagram within the Core Strategy identifies the application site as a
‘Green Belt Release for Employment Use’. Furthermore, the indicative
proposals map produced as an appendix to the Core Strategy identifies the
site as a ‘Green Belt Release for Existing Permission for Employment Use’.
The Proposals Map accompanying the Core Strategy identifies the application
site as a Secondary Industrial and Commercial Area.
5.14 Policy CSSP2 (Sustainable Employment Growth) sets an indicative total of
2,800 new jobs for Purfleet to the year 2026.
5.15 Policy CSSP4 (Sustainable Green Belt) refers to a number of Green Belt
alterations to the Green Belt (including Ponds Farm), including the exclusion of
land from the Green Belt at the application site as permission has been
granted for employment uses.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
5.16 Policy CSTP6 (Strategic Employment Provision) states that within the Key
Strategic Employment Hubs the Council will seek to maintain high and stable
levels of economic and employment growth. Land within primary and
secondary industrial and commercial areas will be reserved for employment
generating uses within Classes B1, B2, B8 and sui-generis uses.
5.17 The following policies for the management of development are also relevant to
the consideration of this application:
5.18 PMD1 (Minimising Pollution and Impacts on Amenity) – development will not
be permitted where it would cause unacceptable effects on amenity;
5.19 PMD2 (Design and Layout) – design proposals should respond to the
sensitivity of the site and its surroundings and proposals should consider the
urban design issues of character, continuity, public realm etc;
5.20 PMD12 (Sustainable Buildings) – sets targets for compliance with BREEAM
and Code for Sustainable Homes targets;
5.21 PMD13 (Decentralised, Renewable and Low Carbon Energy Generation) –
sets current and future targets for generation.
5.22 Between November 2012 and January 2013 the Council consulted on a
Focused Review to the Core Strategy and Policies for the Management of
Development DPD to ensure consistency between this document and the
NPPF. The Focused Review updates a number of policies listed above, but
does fundamentally alter the objectives or intentions of those policies.
5.23 Public consultation for the LDF Site Specific Allocations and Policies DPD
Issues and Options was conducted between April and June 2012. Comments
and responses are currently being considered. The site is identified within this
document as ‘Land for Primary Industrial and Commercial Employment’ (ref.
E2u).
6.0 ASSESSMENT
6.1 Members will note from the planning history that permission was granted in
June 2011 for employment generating development (ref. 08/00858/TTGOUT).
This permission is unimplemented and is extant. The issues to be considered
in this case therefore include an assessment of the material differences
between the approved scheme and the current proposals. The impact of the
proposals upon the surrounding highway network, especially with regard to the
A13 and A1306 (London Road) are also important considerations. The effect
on local residential amenity, archaeology, air quality, ecology, ground
conditions and flood risk are all indentified within the Environmental Statement
(ES) and are material planning considerations in the determination of this
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
planning application. Design and sustainability issues are also issues for
consideration in this case and are issues concerning S.106 planning
obligations. All of these issues were considered during the determination of
application reference 08/00858/TTGOUT and the issues raised are discussed
below.
6.2 Planning permission for commercial development on this former Green Belt
site was granted in June 2011 (ref. 08/00858/TTGOUT). The permission
grants outline consent for:
“Outline planning application for the redevelopment of the site for employment
use (Classes B1(a) / B1(c) / B2 / B8 / Sui Generis car showroom) totalling
38,686 square metres (floorspace) with means of access and quantum of
development to be approved. All other matters to be reserved.”
6.3 Conditions attached to this planning permission restrict the maximum
floorspace which can be constructed and for individual use classes within this
total. Therefore, if all of the permitted development were to be constructed,
the following mix of uses would be achieved:
Use Class Floorspace % of Total Floorspace
B1 (Business) 5,029m2 13%
B2 (General Industry) 17,409m2 45%
B8 (Storage & Distribution) 13,927m2 36%
Sui-generis (car showroom) 2,321m2 6%
Totals 38,686m2 100%
6.4 Although the current application does not seek to increase the total quantum
of development on the site (38,686m2), it does seek permission for a different
mix of uses. Permission is now sought for a predominantly Class B8
development, comprising 90% of the total floorspace, with ancillary offices
accounting for remaining 10% of floorspace.
6.5 With reference to employment generation, based on an Employment Densities
Guide produced by English Partnerships in 2001, it was estimated that the
approved scheme has the potential to generate 900 full-time equivalent (FTE)
jobs when complete. Since the consideration of the earlier application, an
updated employment densities guide was produced by the Homes and
Communities Agency in 2010. Based on this more up to date guide, it is
estimated to up to 750 FTE jobs could be created by the development. The
applicant suggests that up to 819 jobs could be created by the completed
development. However, this is considered to be an optimistic forecast given
the trend for reduced employment densities in the warehousing sector due to
technological advances.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
6.6 Despite the differences in modelling employment generation from the
development, it is clear that the current scheme would result in a reduction in
potential employment compared with the approved mix of uses. The
magnitude of this reduction can be estimated at approximately 150 FTE jobs
(from 900 to 750). Although the reduction is employment generation is
regrettable, it is still clear that the completed development will generate a
significant number of new jobs. The proposals will therefore contribute
towards new employment targets set out within adopted Core Strategy
policies. Furthermore, despite the contraction in the range of uses proposed,
the Class B8 warehousing with ancillary Class B1(a) offices are compliant with
the range of uses promoted by Core Strategy Policy CSTP6 (Strategic
Employment Provision
6.7 The proposed variation to the mix of employment uses also raises implications
for the layout and massing of the development. Planning conditions attached
to the existing planning permission restrict the arrangement of building uses
across the site and also limit the height of buildings. The effect of these
conditions is to position the tallest buildings (up to 18m in height) closest to the
A13 and therefore away from the London Road and Purfleet Road frontages.
The maximum building height currently proposed is no taller than the approved
scheme, although the proposed reduction in the mix of uses would reduce the
potential variations in building height across the site. The implications of the
current proposals on design and amenity implications are considered later in
this report.
6.8 Highways Issues
The planning application has been submitted in outline form though the matter
of access is submitted for consideration at this stage.
6.9 The application proposes two points of access to serve the site. Firstly, a left-
in only access is proposed from the southbound London Road, located
approximately 200m south of the Wennington interchange. The second point
of access is a proposed signal controlled junction where a re-aligned Purfleet
Road would join London Road. Currently, Purfleet Road meets London Road
at a ‘T’ junction where there are restricted left-in only movements from London
Road to Purfleet Road and left-out only movements from Purfleet Road to
London Road. This left-in / left-out arrangement has only been introduced in
recent years. Previously unrestricted movements were available at this
junction and the Council had identified the junction as a priority for
improvement
6.10 The proposed new signal controlled junction involves the re-alignment of
Purfleet Road to a position some 125m north of the existing junction. The
main site access road would emerge onto the re-aligned section of Purfleet
Road. A new access for the Tunnel Garage site would also be provided from
the re-aligned road. The ‘old’ alignment of Purfleet Road would be subject to
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
either a future prohibition of driving order to stop-up the road to through traffic
or a combination of traffic calming and width restrictions to deter through
traffic.
6.11 London / Purfleet Road junction considerations
The proposals for re-aligning Purfleet Road and creating a new signal
controlled junction to London Road originally emerged as a result of pre-
application discussion with the local highways authority prior to the submission
of application reference 08/00858/TTGOUT. After submission of this planning
application, the highways authority welcomed the principle of consolidating a
realigned access of Purfleet Road onto London Road.
6.12 In September 2008, the position of the new junction was moved some 15m to
the north along London Road in order to achieve greater separation from an
existing access on the western side of London Road. In a response dated
January 2009 the highways authority expressed concern regarding potential
conflict from the new junction and the existing access on the western side of
London Road mentioned above. Currently, a commercial business has a
vehicular crossover providing access to the A1306. The ‘stop line’ for vehicles
on the northbound A1306 would be positioned close to this access and the
application proposes ‘keep clear’ markings to protect vehicles using the
access. The highways authority has suggested that the access be moved
further to the south in order to increase the separating distance to the new
junction. In response to this concern, the applicant commissioned a peak-time
survey of the access which confirms a very low frequency of use, with limited
right turn movements. It should be appreciated that the access onto London
Road is an existing access which allows uncontrolled movements. The
proposed positioning of the new junction close to the access would have the
effect of reducing vehicle speeds, thereby improving road safety.
6.13 In view of the low usage of the access, any further benefits resulting from its
re-positioning are considered to be marginal. Re-positioning of the access
would also require third party consent and a re-configuration of parking
arrangements within the third party site. This is a further impediment to the
highways authority suggestion. Nevertheless, the re-positioning of the access
would be the most preferable solution and it is suggested that a planning
obligation could be used to facilitate relocation of the access.
6.14 The highways authority also previously requested the inclusion of pedestrian
crossing facilities across the re-aligned Purfleet Road and are have now been
incorporated into the application drawings. Further analysis of the relationship
between the proposed junction and the existing London Road / New Tank Hill
Road (A1090) signal controlled junction, located 370m to the south, was also
provided in response to an earlier request of the highways authority.
Modelling of the impact on junction capacity and queue length has been
undertaken, which included an assessment of the effect of the pedestrian
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
crossing cycle. The analysis concluded that the proposed signals can be
synchronised with the existing New Tank Hill Road signals and that the two
junctions would operate satisfactorily in terms of capacity and queue length.
6.15 Allied to the proposed re-alignment of Purfleet Road, is an intention to
introduce a prohibition of driving order in order to close the ‘old’ alignment to
through traffic. Indicative drawings were prepared to accompany application
08/00858/TTGOUT showing a 105m long section of the Purfleet Road altered
to form two cul-de-sacs. The eastern cul-de-sac of the ‘old’ alignment would
serve seven residential properties between nos. 235 and 247 Purfleet Road.
A vehicle turning area, bin collection areas and the accommodation of existing
private drawings are indicated on the drawing. The western cul-de-sac would
retain access from London Road to serve The Rosina Café and the adjacent
MOT garage. The eastern and western accesses would be physically
separated to stop through traffic.
6.16 In order to carry out the necessary works to prohibit through traffic, the
Council, exercising its powers as the local highway authority, would need to
introduce a Traffic Regulation Order. Such an Order would be subject to
consultation and advertisement phase before the Order could be confirmed.
This process relies on the actions of the local highway authority and it is
possible that the authority may decide not to make an Order. In this situation,
robust road calming measures along the ‘old’ alignment would be required to
deter through traffic movements. Grampian planning conditions would be
required to cover both of these scenarios.
6.17 Public Transport Accessibility
In considering application reference 08/00858/TTGOUT, the local highways
authority expressed concern that the site was poorly served by public transport
and that the development should enhance travel choices for employees.
6.18 It is still the case that the site is poorly served by public transport links.
Purfleet railway station is located 2km walking from the site and is therefore
considered to be beyond a reasonable walking distance. A bus stop on the
no.11 bus route is located on the Purfleet Road frontage of the site. However,
this bus service, linking Purfleet-Aveley-Ockendon-Orsett-Basildon, is of a low
frequency with only 1 bus per 90 minutes on Mondays-Fridays. The no.44 bus
route, linking Lakeside-Purfleet-Grays, provides a 30 minute service.
However, the nearest bus stops served by this route are 1km walking distance
from the site boundary.
6.19 The consultation response from the Highways Officer notes that enhanced bus
services would limit the traffic impact of the development and increase travel
choices available to potential employees. The S.106 agreement attached to
the extant planning permission makes provision for a total payment of
£240,000 (indexed) to be used to increase the frequency of buses between
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
the site and Purfleet railway station. The Highway Officer suggests that a
similar financial contribution is included within any future S.106 agreement. A
draft agreement submitted to accompany this application includes reference to
a bus services financial contribution.
6.20 As the site is located adjacent to the Strategic Road Network (A13 trunk road),
the Highways Agency have been consulted. Whilst detailed technical
discussion between the Agency and the applicant, a number of Article 25
‘holding directions’ were issued by the Agency preventing the grant of planning
permission. However, in January 2013 the Agency advised that they no
longer objected to the application, subject to a number of obligations to be
incorporated into a S.106 legal agreement. The Agency’s suggested
obligations are intended to introduce a number of remedial actions, referred to
as corrective steps, in the event that specified inbound and outbound vehicle
movements are exceeded in the weekday morning and evening peak hours.
The S.106 agreement for the extant planning permission includes reference to
a similar package of remedial measures.
6.21 Access and Layout
Means of access for the site is a detail for consideration at this stage. The left-
in only access from London Road, close to the Wennington interchange, is
considered to be acceptable in highways terms as it will not significantly
interfere with the free flow of traffic on the A1306. Appropriate signage and
road markings within the site will be required to ensure that drivers do not
attempt to exit the site at this point.
6.22 Within the site a main internal road is notated on the Parameter Plan, aligned
north-west to south-east, providing a link between the London Road and
Purfleet Road accesses. The three illustrative site layout options
accompanying the application indicate an arrangement of parking areas,
service yards and turning areas accessed from the main internal road. The
required visibility splays at the junction of the main access road and the re-
aligned Purfleet Road would be provided.
6.23 With reference to vehicle parking and turning areas, the submitted plans show
areas for parking and servicing on an illustrative basis. Nevertheless, the
three illustrative plans show car parking levels which comply with the Council’s
draft standards. However, the final details of parking spaces and vehicle
turning areas will emerge through future reserved matters applications. The
TA suggests that parking spaces will be provided in accordance with adopted
standards and will include provision for disabled users. Areas for cycle
parking are also indicated on the submitted drawings.
6.24 Amenity Issues
Residential properties are located to the south-east of the site on the opposite
side of Purfleet Road. The impact of the proposals with reference to noise and
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
vibration, lighting, sunlight / daylight and outlook are therefore considerations
in this case.
6.25 Noise and Vibration - Construction
The effects of noise during both the construction and operational phases of the
development require consideration. The ES includes a 2012 update of a 2007
baseline survey of noise levels using two monitoring locations along Purfleet
Road, opposite the dwellings. The proximity to the A13 is a major factor in
noise generation and is the reason why both ambient and peak noise levels for
the two monitoring locations exceed World Health Organisation guidelines
during the day and night. During construction the ES predicts a short-term,
“moderate negative” effect on residential occupiers as a result of construction
noise. However, mitigation measures, to be included within a Construction
Environmental Management Plan (CEMP) would reduce the magnitude of
effects to “minor negative”. The consultation response from the Council’s
Environmental Health Officer (EHO) notes the requirement for measures within
the CEMP to be agreed prior to the construction of development. General
construction activities can be limited by condition to reasonable hours in order
to protect neighbouring amenity. However, as piling activities may be
undertaken as part of the construction process, the EHO has recommended
that the proposed method of piling is submitted and agreed prior to the
commencement of construction. If driven piles are proposed it may be
necessary to limit the times of piling beyond the general construction hours.
The EHO does not foresee any significant issues regarding vibration except
with the possibility of some minor effect during piling, dependent on the
method of piling used. However, the effects are not likely to be significant.
6.26 Noise and Vibration – Operation
The main generators of noise during the operation of the development are
likely to be service yard activity, car parking and noise from mechanical plant
and equipment. The submitted Parameter Plan proposes the positioning of a
‘Logistics Area’ for use as a service yard and parking to the south, east and
west of the ‘Building Zone’ which accommodate the new building(s). This
Logistics Area would be positioned between 37m and 70m from the front walls
of dwellings in Purfleet Road and would be screened from these neighbours
by a ‘Landscape Zone’, which would include noise and visual screens.
6.27 The response from the Council’s EHO notes that the principal operational
noise impact from the development on receptors in Purfleet Road is from the
manoeuvring of vehicles in the parking and servicing areas. The noise
assessment within the ES assumes a worst-case scenario and the values
used are considered by the EHO to be reasonable. The ES predicts that,
without mitigation, maximum night-time noise levels will be in excess of WHO
guidelines for sleep disturbance. During daytime hours, predicted noise levels
at residential receptors are modelled as comparable with WHO guidelines.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
6.28 In order to mitigate predicted night-time noise levels. the ES proposes acoustic
screening at the south-eastern boundary of the site, adjacent to Purfleet Road.
This screening would comprise a landscaped mound, acoustic boundary
fencing or a combination of both. An illustrative site section drawing
accompanying the application suggests that the landscaped mound could be
constructed to a maximum height of 4.4m above the service yard level, with a
4.5m high acoustic fence on top of the mound. The Council’s EHO confirms
that an acoustic fence, on its own, would provide 10 dB attenuation and the
combined mound and fence 15 dB attenuation. Both measures would mitigate
maximum noise levels to a point within WHO guidelines, although the EHO
expresses a preference for the mound and fence combination which will
provide the superior acoustic performance. It is suggested that a planning
condition is used to require details of the mound and/or fence.
6.29 The ES also considers the effect of noise from plant within the future
development, comprising air conditioning units, condensers, fans boilers and
generators. The ES recommends that that noise levels from future items of
plant should not exceed existing background noise levels by more than 5 dB,
when measured at the nearest noise sensitive receptors in Purfleet Road. The
Council’s EHO confirms that a condition should be attached to any grant of
planning permission requiring that fixed mechanical plant should be designed
and installed so that noise from plant at the nearest receptor is not more than
5 dB LAeq,5min above the lowest night time background noise level.
6.30 Therefore, subject to conditions, there are no objections to the proposals with
reference to the impact from noise and vibration.
6.31 Lighting
The ES includes a day and night-time baseline lighting survey undertaken in
February 2012 which establishes the existing ambient lighting conditions on
and immediately adjacent to the site. The application site itself does not
contain any sources of light although the adjacent A13 and Purfleet industrial
Park are well-lit with street lighting columns and floodlighting. Assessed
against the ‘Environmental Zones’ defined by the Institution of Lighting
Professionals, the site itself is categorised as of low district brightness, whilst
areas immediately surrounding the site are described as of medium district
brightness.
6.32 During the construction phase it is likely that temporary lighting on the site will
be required to illuminate the construction compound and parking areas. In
order to reduce the impact of this temporary lighting, details of the type of light
source, its location and direction can be included within the CEMP. The
effects of light spill, glare and sky glow upon receptors, including residential
properties in Purfleet Road can be controlled in this way. An outline lighting
specification has been prepared for the operation of the development. The
specification assumes the use of low light pollution lanterns which will achieve
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
a low district brightness area classification. Whilst the change in the lighting
characteristics of the site, from a relatively dark site to an area of low
brightness, will impact upon receptors, the magnitude of change is assessed
as being minor.
6.33 Sunlight / Daylight
The nearest dwellings to the site are located along Purfleet Road to the south-
east of the site and comprise a mix of bungalows, chalet-bungalows and two-
storey houses closer to London Road.
6.34 With reference to sunlight and shadowing, the fronts of these dwellings face in
a north-westerly direction and, therefore, only receive direct sunlight during
late afternoon and evening hours when the sun is in the west during the
summer months. Based upon the submitted Parameter Plan, the nearest part
of any new building would be located a minimum of 70m from the front wall of
no. 231 Purfleet Road, increasing to a distance of 120m from no. 191 Purfleet
Road. Compared with the existing outline approval, the current proposal
would position new building(s) a greater distance from dwellings in Purfleet
Road. In view of the above factors loss of direct sunlight and overshadowing
from the development would not cause any material harm to residential
amenity.
6.35 The recognised test for assessing the impact of development on the daylight
received by neighbouring properties is the Building Research Establishment
(BRE) guidance for site layout planning. This test involves applying a 25o line
from the centre of the lowest affected window. As applied to the proposed
building zone on the site, and taking into account the maximum building
height, the BRE test is comfortably passed. Consequently, adequate
daylighting would be maintained to the nearest residential dwellings.
6.36 Impact on Outlook
The planning system does not exist to protect private views and this is not a
material planning consideration. However, the impact of the massing and bulk
of the development on visual amenity is a relevant consideration.
6.37 The principal differences between the current proposals and the approved
scheme relate to the building uses, their height and their position in relation to
Purfleet Road. The extant scheme could result in the positioning of small
footprint, Class B1 units up to 8m high close to the Purfleet Road frontage. In
contrast, the current proposals could result in large footprint, Class B8
building(s) up to 18m in height, but positioned at a greater distance from the
neighbouring dwellings. An element of the space between Purfleet Road and
the B8 building(s) will be occupied with parking areas and service yards.
However, as noted above, the proposals now include the provision of a
landscaped mound and/or acoustic fencing adjacent to the Purfleet Road
frontage. An indicative site section drawing incorporating the acoustic
mitigation measures suggests that the line of sight from neighbouring
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
dwellings would be screened such that new building(s) would not be visible to
occupiers in Purfleet Road. Consequently, it is considered that the impact on
residential outlook is acceptable.
6.38 Archaeology
Previous intrusive archaeological investigation works identified evidence of
post-medieval / modern land division and isolated medieval features within the
eastern part of the site, that is, the part of the site unaffected by earlier
quarrying and landfill activities. No other archaeological remains were
uncovered by the trial trenching.
6.39 Essex County Council recommended that, in addition to an archaeological
watching brief, some areas of the site will require open area excavation prior
to the commencement of any development. A standard planning condition can
be employed to secure the implementation of a programme of archaeological
investigation.
6.40 Air Quality
Under the heading of air quality, the ES assesses the effects of the proposed
development with regard to particulate matter (PM10), or dust and nitrogen
dioxide (NO2) from road traffic emissions associated with the construction
phase and the operation of the development.
6.41 The baseline air quality conditions for this area indicate a location where air
quality is influenced by emissions from transport using the busy A13, A1306
and Purfleet Road. The Council has designated an Air Quality Management
Area (AQMA) along part of London Road, a short distance to the south of the
application site. This Area has been designated due to air quality
exceedences for NO2 from HGV traffic.
6.42 During the construction of the development, the ES predicts that
concentrations of PM10 would be elevated, but would be limited to the
immediate vicinity of the site. In addition, the impact of dust from construction
activities would occur on a temporary basis and the ES assesses the
magnitude of the effect as of minor negative to negligible significance. By way
of mitigation, the applicant suggests that the CEMP should include measures
to control and suppress dust.
6.43 The operational impacts of the development on local air quality are also
modelled within the ES. The current baseline for air quality predicts that the
Air Quality Standard for annual mean NO2 concentrations will not be met for 7
of the 8 modelled locations surrounding the site. In a modelled opening year
for the development (2013), the highest annual mean concentrations of NO2
are predicted in Purfleet Road, where concentrations are 70.12 micrograms/m3
without the development and 70.51 micrograms/m3 with the proposed
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
development. The development is therefore modelled as resulting in small to
imperceptible increases in annual average NO2 concentrations at surrounding
receptors. Modelling for annual mean concentrations of PM10 show that both
baseline and with development scenarios would meet the air quality standard.
The impacts are therefore considered to be of negligible importance.
6.44 The consultation response from the Council’s EHO notes that, although the
impact from the development does not pose a major impact on air quality, the
site is located in an area where air quality is very poor and is in breach of air
quality objectives. Further increases in emissions from any development in
this area would ‘not be desirable’. Therefore, mitigation measures are
required to ensure that any further increases in emissions are minimised.
Mitigation proposals promoted by the application include Travel Plan
measures, enhanced local bus services and improvements to highways
infrastructure. Collectively, these measures will assist in managing traffic
generated by the development and thereby influence emissions and air
quality.
6.45 Ecology
The application site has been subject to an ecological survey, the results of
which are incorporated into the ES. The application site does not contain any
statutory ecological designations. However, a geological Site of Special
Scientific Interest (SSSI) is located some 50m to the east of the site at Purfleet
Road, on the opposite side of the A13. In addition, the extensive Inner
Thames Marshes SSSI is approximately 500m to the south of the site. As the
Purfleet Road SSSI is designated due to its geological interest, the ES does
not consider further the potential impact of development on this site. The
Inner Thames Marshes SSSI is a minimum of 500m from the application site
and the ES concludes that there would be no direct impacts as a result of the
development.
6.46 The ES includes a habitat survey of the application site which updated
previous habitat surveys and confirms that the site has a low ecological value.
Large parts of the site comprise bare or re-colonised ground, ruderal
vegetation associated with waste ground, and rough grassland. A small
number of native trees and dry ditches make up the reminder of habitats on
the site. These habitats support plant species which are both common and
widespread locally and the loss of these habitats is considered to be of minor
or negligible significance given their low ecological value.
6.47 The site has also been assessed for the presence of protected species.
Common lizards were previously found, within areas of rough grassland on the
southern part of the site. A trapping and relocation exercise was undertaken
during 2007. No other protected species have been found on the site. Natural
England does not object to the proposals. However, it suggests that the
impacts of the construction phase are mitigated through a CEMP and that
biodiversity enhancements, such as landscaping and the provision of bat and
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
bird boxes, are incorporated into the design.
6.48 One of the letters of objection to the application refers to the subject of
invertebrate interest. In detail, this objection makes the following points:
the pre-application EIA Scoping Statement identified sources of
information from bodies which do not exist;
at the EIA Scoping stage, the applicant undertook a datasearch of
protected and notable species. However, the results of this
datasearch are not are not submitted with the ES and the desk study
is therefore not fit for purpose;
there is a lack of invertebrate survey effort for the site and
accordingly there is insufficient information on which to base a
decision.
6.49 In response to these objections, the applicant’s ecological consultant makes
the following points:
a number of bodies were contacted when preparing the EIA,
including EECOS and the Essex Field Club who hold the relevant
records;
ecological data from a number of bodies was collected by the
applicant, including invertebrate records provided by the Essex Field
Club;
ecological data provided to the applicant’s consultant was subject to
copyright restrictions and therefore could not be reproduced within
the ES;
the desk survey for invertebrates retrieved a large number of records.
However, no records of rare, notable or scarce species within or
immediately adjacent to the site were returned;
the applicant therefore considers that the desk study accompanying
the ES is comprehensive and fit for purpose.
6.50 In considering the matter of potential invertebrate interest, it should be noted
that this site is not identified as a site with elevated potential within the “All in a
Buzz – Planning for Invertebrate Biodiversity” document produced by Buglife
and English Nature (now Natural England). Furthermore, in their consultation
response to this application, Natural England raises no objections, subject to
planning conditions.
6.51 Ground Conditions and Contamination
The northern part of the site was excavated for sand and gravel after World
War II until the 1960’s. After the cessation of extraction, the pit was filled with
household refuse, inert waste and non-hazardous industrial and commercial
waste. Landfilling ceased by the mid 1960’s but details of the capping of the
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
site are not available. For the purposes of assessment, the ES divides the site
into non-landfill and landfill areas. The general geological sequence
underlying the site comprises reworked topsoil (up to 0.5m thick), underlain by
landfilled material (up to 8.2m thick) which is in turn underlain by the natural
geology of sand, gravel and clay deposits.
6.52 Site investigation reveals that there is no significant soil contamination across
the site, including both landfilled and non-landfilled areas with respect to the
proposed end-use of the site for commercial purposes. Investigations of
groundwater samples from the area of historic landfill reveal slightly elevated
levels of contaminants. However, given the commercial end-use of the site
the ES considers that no significant risk is generated.
6.53 The consultation response from the Environment Agency considers the impact
of contamination and its effect on the water environment. Although the
Agency makes a number of detailed points regarding the analysis within the
ES, they conclude that there are generic remedial options to deal with risks to
the water environment. These remedial options can be secured by planning
conditions.
6.54 The Council’s contaminated land officer has commented on the content of the
ES and confirmed that there are no objections, subject to the implementation
of the mitigation measures outlined in the ES. These measures can be
secured by planning condition.
6.55 Flood Risk
As noted in paragraph 2.2 above, the application site is located within all three
flood risk zones (low, medium and high risk). National planning policy
contained within the NPPF is, therefore, a material planning consideration.
6.56 The consultation response received from the Environment Agency confirms
that the proposals are required to pass the ‘Sequential Test’ and that the
application should be accompanied by a Flood Risk assessment (FRA). A
Sequential Test has been applied using the standing advice for local planning
authorities provided by the Agency. The FRA has been considered by the
Agency who considers that the document is NPPF compliant. Consequently,
there are no objections to the application, on the grounds of flood risk, subject
to a condition for the management of surface water.
6.57 Design Issues
Good design is important for all types of development in all locations and is a
key factor in delivering sustainable development. High quality design is a
requirement of the NPPF.
6.58 The application has been submitted in outline form and seeks to establish the
principle of the use, the quantum of development and means of access at this
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
stage. The matters of appearance, landscaping, layout and scale are
reserved for future approval. Therefore, the issue of ensuring that a high
quality design is delivered through future submissions is an important planning
consideration.
6.59 Current planning regulations require, as a minimum, that an outline
submission should contain information regarding the uses proposed for a
development, the amount of development proposed for each use, an indicative
layout, upper and lower limits for height, width and length of each building and
indicative access points. The information to be provided within a Design and
Access Statement complements the requirements for an outline application
and also requires design concepts and principles relating to landscaping and
appearance. Nevertheless, there is a tension between the limited matters
which can be fixed at the outline planning stage, the indications of potential
site layout, building parameters, appearance and landscaping.
6.60 The application is accompanied by a Parameter Plan which seeks to delineate
the zones across the site where building(s), servicing / parking and
landscaping will be located. This plan also defines building elevations facing
towards the A13, London Road and the Wennington interchange. Three
distinct landscaped areas are proposed comprising:
Purfleet Road Landscape Zone – described as an extension to the
existing planting within the A13 cutting and comprising a bund and
planting to form a visual and acoustic screen between existing
dwellings and new building(s) on the site. This zone would also
incorporate sustainable drainage features.
London Road Landscape Zone – to include tree and shrub planting in
order to provide a landscape buffer to London Road. This zone will
include a swale.
Gateway Landscape Zone – located adjacent to the A13 / A1306
junction. This zone will complement the elevation of building(s) to
address the A13 / A1306 ‘gateway’ into the site.
6.61 The Design and Access Statement also provides illustrative options for the
main building elevation(s). Those elevations which would face onto London
Road and the A13 / A1306 junction are described as principal elevations,
designed to provide legible routes to the main building(s) entrances. The
appearance of the development is a reserved matter and accordingly no firm
details are provided regarding building elevations or finishing materials.
6.62 If Members resolve to grant planning permission, planning conditions can be
used to fix a number of development parameters, which would inform future
reserved matters submissions. For example, the maximum floorspace, mix of
uses and maximum building heights can be controlled by condition. It is also
recommended that a planning condition be used to require the submission of a
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
Masterplan / design code to accompany the first reserved matters application,
which develops design principles within the DAS. This method would ensure a
greater degree of certainty about the final delivery of design quality.
6.63 Sustainability
The planning application is accompanied by a Sustainability Statement and an
Energy & Water Statement which set out a commitment to sustainable design
and construction measures. There are a number of Adopted Core Strategy
policies which address the issues of environmental sustainability and which
are relevant to this application. These policies comprise:
CSTP22 (Thurrock Design);
CSTP25 (Addressing Climate Change);
CSTP26 (Renewable or Low Carbon Energy Generation);
CSTP29 (Waste Strategy);
PMD2 (Design and Layout);
PMD12 (Sustainable Buildings); and
PMD13 (Decentralised, renewable and Low Carbon Energy
Generation).
6.64 In particular, PMD12 requires that major proposals for non-residential
development must achieve minimum BREEAM standards of ‘Very Good’ up to
2016, ‘Excellent’ from 2016 and ‘Outstanding’ from 2019. In response to the
requirements of this Policy, the Sustainability Statement includes a BREEAM
Predictive Assessment which anticipates that the scheme will achieve a rating
of at least ‘Very Good’. This matter can be addressed by a planning condition.
However, as it is not known when the scheme will be implemented, it is
recommended that any condition reflects the escalation in BREEAM standards
over time.
6.65 Policy PMD13 requires that major non-residential developments should
achieve 10% of their predicted energy demands from decentralised,
renewable or low-carbon sources. This requirement increases to 15% from
2015 and 20% from 2020. The application proposes the use of an air source
heat pump to address space heating and potentially hot water demand to
achieve PMD13 targets. As above, a condition can be used to secure this
renewable energy technology, thought the condition will need to be flexible
enough to respond to the changes in policy targets.
6.66 Planning Obligations
The applicant has submitted a draft S.106 agreement in support of the
planning application. The draft contains the following obligations upon the
owner / developer of the site:
Travel Plan – submission for approval, implementation and review of
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
a Travel Plan. Payment of the Council’s Travel Plan review fees;
Vehicle Monitoring Scheme – submission for approval,
implementation and maintenance of a Vehicle Monitoring Scheme.
Carrying out of relevant corrective highways measures;
Highway Works – completion of a Section 278 Highways Agreement
for a range of works to Purfleet Road and London Road prior to
implementation of the development. Completion of the highways
works prior to occupation of the development;
Relocation of the private commercial access onto London Road –
use of reasonable endeavours to secure relocation of this access;
Bus Services Contribution – financial contribution of £120,000
(indexed) three months prior to occupation and a further contribution
of £120,000 (indexed) on occupation of 50% of the floorspace.
6.67 These obligations are based on the items within the existing S.106 agreement
which was negotiated after submission of the original outline planning
application in 2008. Since the date of this agreement, the Council has
adopted, on an interim basis, the former Development Corporation’s Planning
Obligations Strategy (POS). The POS refers to a discounted standard charge
of £50 per m2 for commercial development, including the warehousing
development currently proposed. On the basis of a maximum floorspace of
38,686m2, the POS would require a maximum financial contribution of
£1,934,300.
6.68 After submission of this planning application, the applicant was referred to the
content of the POS and asked to justify their approach to planning obligations,
as set out above, by submitting an ‘open-book’ development appraisal. The
POS allows for an applicant to submit such an appraisal if they consider that
the development proposals will not be viable, taking account of the discounted
standard charge and any exceptional development costs.
6.69 A ‘Toolkit Viability Assessment’ has been submitted by the applicant. The
main conclusions of this Assessment are summarised below:
the applicant’s main contribution relates to the provision of additional
bus services (£240,000), although a budget of £450,000 has been
set to allow for monitoring;
the applicant is also committed to finance highway works;
the site has a number of abnormal factors which affect development
costs and viability, comprising –
o compliance with Building Regulations and BREEAM;
o on-site surface water attenuation and SUDS;
o costs related to new highways, reinforcement of utility supply
network and utility diversions;
o low ground bearing capacity resulting in the need for piling;
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
o need for methane venting;
o handling of contaminated spoil from excavations;
the POS is only being used on an interim basis, pending adoption of
the Community Infrastructure Levy (CIL);
the preliminary draft charging schedule for CIL would impose a lesser
charge than the current POS;
it is unreasonable for a developer to pay the higher POS charge in an
interim period pending the adoption of CIL.
6.70 The applicant’s viability assessment ( which has been submitted in confidence
as it contains commercially sensitive information) provides the necessary
development cost estimates, market value appraisals and economic models
for the applicant’s viability appraisal to be tested. An independent surveyor
has been commissioned to provide an independent assessment of the Toolkit
Viability Assessment. This commission includes requirements to:
i. appraise of Viability Assessment including the appropriateness of the
model(s) used, the robustness of the information within the model
and the reasonableness of the assumptions made (including the
book and threshold values used);
ii. provide an analysis of the information submitted and an appraisal of
the scheme’s viability and its ability to achieve the planning
objectives sought.
6.71 At the time of writing, the independent appraisal of the applicant’s viability
assessment is awaited. Members will be updated verbally of the conclusions
of the appraisal. However, as the applicant is keen for the proposal to be
determined as soon as possible, the application is brought before Members at
the early opportunity.
7.0 CONCLUSIONS AND REASON(S) FOR APPROVAL
7.1 This application seeks outline planning permission for employment generating
development on a site allocated for such purposes in the LDF. There is an
extant and unimplemented outline planning permission for mixed employment
uses at the site, but the current proposal seeks a different mix of employment
uses to those permitted. The principle of the land use is supported and,
subject to S.106 obligations and planning conditions, there are no highways
objections. Subject to planning conditions to mitigate impact, it is considered
that the development will have acceptable impact on residential and ecological
receptors and conditions can be employed to mange flood risk, ground
conditions, design and sustainability.
7.2 The ES considers the impact of the development on a range of receptors and
concludes that any impact would be within acceptable limits. Having taken
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
into account representations received from others, the Council considers that
the proposed development is acceptable, subject to a legal agreement and
compliance with a number of planning conditions that are imposed upon the
permission.
7.3 The applicant has made a S.106 offer similar to the commitments and
obligations contained with the agreement for the extant planning permission.
As the Council has adopted the POS on an interim basis, the applicant has
been asked to provide an ‘open book’ viability assessment. An assessment
has been provided and is currently subject to independent appraisal. In these
circumstances, it is recommended that Members resolve to grant planning
permission subject to the conditions below, subject to the final S.106 heads of
terms being negotiated between the applicant and the Head of Major Projects,
in light of the results of the independent viability appraisal. The items for
inclusion within the S.106 will, as a minimum, include the matters described at
paragraph 6.66 above.
7.4 Policy CSSP 4 of the adopted LDF Core Strategy has the effect of excluding
this site from the green belt as there is a previous planning permission.
However the exact status of the site in advance of the LDF Site Specific DPD
is not absolutely certain therefore, subject to the Committee’s resolution to
approve the application it is recommended that before any planning
permission is granted the application be first referred to the secretary of state
under the terms of the Town and Country Planning (Consultation) (England)
Direction Order 2009.
8.0 RECOMMENDATION
A. That authority for the negotiation of the detailed content and obligations of
a S.106 legal agreement be delegated to the Head of Major Projects,
following the receipt of an independent appraisal of the applicant’s ‘Toolkit
Viability Assessment’, but to include as a minimum the items described at
paragraph 6.66. above.
B. Subject to the application first being referred to the Secretary of State
under the terms of the Town and Country Planning (Consultation)
(England) Direction 2009 and there being no “call in” and to the completion
of a S.106 legal agreement that planning permission be APPROVED
subject to the following conditions:
1. Application for the approval of details of the appearance, landscaping,
layout and scale of development (the reserved matters) must be made to
the Local Planning Authority within three years from the date of this
permission and the development shall not be carried out except in
accordance with the approved details.
Reason: To comply with Section 92 of the Town and Country Planning
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
Act 1990, as amended by Section 51 of the Planning and Compulsory
Purchase Act 2004.
2. The development hereby permitted shall be commenced not later than the
expiration of two years from the date of the final approval of the last of the
reserved matters.
Reason: To comply with Section 92 of the Town and Country Planning
Act 1990, as amended by Section 51 of the Planning and Compulsory
Purchase Act 2004.
3. The development shall not exceed a maximum gross floorspace of
38,686m2.
Reason: To ensure that the scheme implemented is in accordance with
the principles established by this permission.
4. Unless otherwise agreed in writing by the Local Planning Authority, the
total of floorspace within each Use Class shall not exceed the following
parameters:
Use Class Percentage of Total Floorspace
B1(a) 10%
B8 90%
Reason: To ensure that the scheme implemented is in accordance with
principles established by this permission.
5. Unless otherwise agreed in writing by the Local Planning Authority,
maximum building heights across the site shall accord with the content of
the Parameter Plan (drawing no. TP O (00) 01 rev. B).
Reason: To ensure that the scheme implemented is in accordance with
the principles established by this permission and in order to protect the
appearance of the development and the visual amenities of the
surrounding area.
6. Unless otherwise agreed in writing by the Local Planning Authority, the
arrangement of the developable building zone, logistics area and
landscape zones within the site shall accord with the content of the
Parameter Plan (drawing no. TP O (00) 01 rev. B).
Reason: To ensure that the scheme implemented is in accordance with
the principles established by this permission and In order to protect the
amenities of nearby residential occupiers.
7. No development shall take place until details of existing and finished site
levels and finished external surface levels have been submitted to, and
approved by, the Local Planning Authority. The development shall be
implemented in accordance with the agreed details.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
Reason: In order to protect the amenities of surrounding occupiers and to
ensure the satisfactory development of the site.
8. No development shall take place until a comprehensive programme for the
undertaking of the off-site highway works necessary to close Purfleet Road
to through traffic (as indicated on drawing number 51014-05 Rev. D and
Rev. E), including the processing of any Traffic Regulation Order, has
been submitted to, and approved in writing by, the Local Planning
Authority, and the highway works undertaken and completed in
accordance with the approved programme, or any variation to that
programme that may be approved in writing by the Local Planning
Authority, before the first occupation of the development.
Reason: In the interests of highway safety.
9. In the event that the Local Highway Authority do not make a Traffic
Regulation Order under the terms of condition number 8 above, no
development shall take place until a scheme of traffic calming measures
and width restrictions to deter through traffic on Purfleet Road (as
indicated on drawing number 51014-09) has been submitted to, and
approved in writing by, the Local Planning Authority and the measures
undertaken and completed in accordance with the approved details, or any
variation to those details that may be approved in writing by the Local
Planning Authority, before the first occupation of the development.
Reason: In the interest of highway safety.
10. Prior to the commencement of development details of wheel washing
facilities, which shall include a barrier to stop all vehicles before they enter
the highway, shall be submitted to, and agreed in writing by, the Local
Planning Authority. Such facilities shall be installed in accordance with the
agreed details and operated throughout the construction of the
development.
Reason: In order to prevent materials from the site being deposited on
the adjoining public highway in the interests of highway safety and the
amenity of the surrounding area.
11. No development shall take place until a Construction Environmental
Management Plan (CEMP) has been submitted to, and approved in writing
by, the Local Planning Authority. The approved CEMP shall be adhered to
throughout the construction period and shall provide detailed information
under the headings of:
site information;
construction information;
environmental management;
monitoring; and
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
legal requirements
as detailed in Chapter 16 of the Environmental Statement (Volume 1 Text
and Figures).
Reason: In order to minimise the impacts arising from the construction of
the development.
12. No construction work in connection with the development shall take place
on the site at any time on any Sunday or Bank Holiday, nor on any other
day except between the following times:
Monday to Friday 0730-1700 hours
Saturday 0800-1300 hours
Unless such work –
(a) is associated with an emergency; or
(b) is carried out with the prior written approval of the Local Planning
Authority; or
(c) does not cause existing ambient noise levels to be exceeded.
Reason: In the interest of protecting residential amenity.
13. No development or groundworks of any kind shall take place until the
applicant has secured the implementation of a programme of
archaeological work in accordance with a written scheme of investigation
which has been submitted by the applicant and approved by the Local
Planning Authority.
Reason: To ensure that investigation and recording of any archaeological
remains takes place prior to the commencement of development.
14. Prior to the commencement of development a scheme for the
management of surface water shall be submitted to and approved in
writing by the Local Planning Authority. The submitted scheme shall
include the following:
confirmation that flows can be accommodated within the receiving
sewer system;
details of the volume of storage required for the 1 in 100 year storm
inclusive of climate change;
utilisation of sustainable drainage techniques for the storage of
surface water flows;
confirmation of who shall be responsible for the maintenance of the
scheme.
The approved scheme shall be fully implemented and subsequently
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
maintained in accordance with any timing / phasing arrangements
embodied within the scheme, or within any other period as may
subsequently be agreed in writing by the Local Planning Authority.
Reason: To prevent flooding by ensuring the satisfactory storage and
disposal of surface water from the site.
15. Prior to the commencement of development, or such other date or stage in
development as may be agreed in writing by the Local Planning Authority,
the following components of a scheme to deal with the risks associated
with contamination of the site shall each be submitted to, and approved in
writing by, the Local Planning Authority:
a. a preliminary risk assessment which has identified:
all previous uses;
potential contaminants;
a conceptual model of the site indicating sources, pathways and
receptors;
potentially unacceptable risks arising from contamination at the
site.
b. a site investigation scheme, based on (a), to provide information for
a detailed assessment of the risk to all receptors that may be
affected, including those off-site.
c. the site investigation results and the detailed risk assessment (b)
and, based on these, an options appraisal and remediation strategy
giving full details of the remediation measures required and how
they are to be undertaken.
d. a verification plan providing details of the data that will collected in
order to demonstrate that the works set out in (c) are complete and
identifying any requirements for longer term monitoring of pollutant
linkages, maintenance and arrangements for contingency action.
Any changes to these components require the express consent of the
Local Planning Authority. The scheme shall be implemented as approved.
Reason: To protect the water environment.
16. No occupation or beneficial use of any part of the development shall take
place until a verification report demonstrating completion of the works set
out in the approved remediation strategy and the effectiveness of the
remediation shall be submitted to and approved in writing by the Local
Planning Authority. The report shall include results of sampling and
monitoring carried out in accordance with the approved verification plan to
demonstrate that the site remediation criteria have been met. It shall also
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
include any plan (a long term monitoring and maintenance plan) for longer
term monitoring of pollutant linkages, maintenance and arrangements for
contingency action, as identified in the verification plan. The long term
monitoring and maintenance plan shall be implemented as approved.
Reason: To protect the water environment.
17. If, during development, contamination not previously identified is found to
be present at the site, then no further development (unless otherwise
agreed in writing by the Local Planning Authority) shall be carried out until
the developer has submitted, and obtained written approval from, the
Local Planning Authority for an amendment to the remediation strategy
detailing how this unsuspected contamination shall be dealt with.
Reason: To protect the water environment.
18. No infiltration of surface water drainage into the ground is permitted other
than with the express written consent of the Local Planning Authority,
which may be given for those parts of the site where it has been
demonstrated that there is no resultant unacceptable risk to controlled
waters.
Reason: To protect the water environment.
19. Piling or any other foundation designs using penetrative methods shall not
be permitted other than with the express written consent of the Local
Planning Authority, which may be given for those parts of the site where it
has been demonstrated that there is no resultant unacceptable risk to
groundwater. The development shall be carried out in accordance with the
approved details.
Reason: To protect the water environment.
20. Prior to the commencement of development a scheme for the provision
and implementation of pollution control shall be submitted to, and
approved in writing by, the Local Planning Authority. The works / scheme
shall be constructed and completed in accordance with the approved plans
/ specifications as may be specified in the approved scheme.
Reason: To ensure a satisfactory method of pollution control.
21. There shall be no external storage of goods, machinery, plant or materials
on the site, unless otherwise agreed in writing by the Local Planning
Authority.
Reason: In the interests of visual amenity and to ensure that the proposed
development is satisfactorily integrated within its immediate surroundings.
22. No manufacturing, fabrication or other industrial process shall take place
outside of the buildings on the site.
Reason: In the interests of visual amenity and to ensure that the proposed
development is satisfactorily integrated within its immediate surroundings.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
23. All fixed plant and machinery within the development should be designed
and installed such that the rating level of the fixed plant and machinery
shall not exceed the background level by more than 5dB using
BS4142:1991 at the nearest noise sensitive receptor.
Reason: In the interest of protecting residential amenity.
24. No development shall take place until there has been submitted to, and
approved in writing by, the Local Planning Authority details of the
locations, heights, designs, materials and types of all boundary treatments
to be erected on site. The boundary treatments shall be completed in
strict accordance with the approved details before the first occupation of
any of the buildings.
Reason: In the interests of visual amenity and to ensure that the proposed
development is satisfactorily integrated with its immediate surroundings.
25. Prior to the commencement of development details of any external
lighting, including details of the spread and intensity of light together with
the size, scale and design of any light fittings and supports, shall be
submitted to, and agreed in writing by, the Local Planning Authority.
Thereafter, external lighting shall only be provided in accordance with the
agreed details or in accordance with any variation agreed in writing by the
Local Planning Authority.
Reason: In the interests of visual amenity and to ensure that the proposed
development is satisfactorily integrated within its immediate surroundings.
26. The development hereby permitted shall be built to a minimum standard of
‘very good’ under the Building Research Establishment Environmental
Assessment Method (BREEAM). Within 3 months of the first use of any of
the building(s) a copy of the Post Construction Completion Certificate for
the building(s) verifying that the ‘very good’ BREEAM rating has been
achieved shall be submitted to the Local Planning Authority.
Reason: To ensure that the development takes place in an
environmentally sensitive way.
27. Prior to the commencement of development full details of the number,
location and design of secure cycle parking facilities shall be submitted to,
and approved in writing by, the Local Planning Authority. The approved
facilities shall be installed prior to the first occupation of any of the
buildings and shall be permanently retained thereafter.
Reason: To reduce reliance on the use of private cars and promote
cycling in the interests of sustainability.
28. No development shall take place until samples of the materials to be used
in the construction of the external surfaces of the development have been
submitted to, and approved in writing by, the Local Planning Authority.
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
The development shall be carried out in accordance with the approved
details.
Reason: In the interests of visual amenity and to ensure that the
development is satisfactorily integrated with its surroundings.
29. Prior to the commencement of development, details of measures to secure
at least 10% of the energy needs of the development from decentralised
and renewable or low carbon energy generation technologies on-site
should be submitted to, and approved in writing by, the Local Planning
Authority. The approved measures shall be installed and operational on
the first occupation of the building(s) and shall be retained thereafter,
unless otherwise agreed in writing by the Local Planning Authority.
Reason: In order to reduce carbon dioxide emissions in the interests of
sustainable development as required by Policy ENG1 of the East of
England Plan.
30. Prior to the commencement of development details of measures to
enhance the ecological interest of the site, including a study of the
feasibility of incorporating green / brown roofs and / or walls into the
buildings, shall be submitted to, and approved in writing by, the Local
Planning Authority. The approved measures shall be implemented prior to
the first occupation of any of the development.
Reason: In the interest of securing the sustainable development of the
site.
31. Prior to the commencement of development a scheme for noise mitigation
on site, including details for the landscaped buffer adjacent to Purfleet
Road, shall be submitted to and approved in writing by the Local Planning
Authority. The approved scheme shall be completed and retained on site
prior to the first occupation or beneficial use of the development, unless
otherwise agreed in writing by the Local Planning Authority.
Reason: In order to protect the amenities of adjacent residential
occupiers.
Informatives
1. The applicant is reminded that under the Wildlife and Countryside Act
1981 (Section 1) it is an offence to take, damage or destroy the nest of
any wild bird while the nest is in use or being built. Planning consent for
a development does not provide a defence against prosecution under
this Act. Trees and scrub are likely to contain nesting birds between 1st
March and 31st July. Any trees and scrub present on the application site
should be assumed to contain nesting birds between the above dates
unless survey has shown it is absolutely certain that nesting birds are not
present. Bothe the RSPB booklet “Wild Birds and the Law” and guidance
notes relating to local planning and wildlife law produces by Natural
Planning Committee: 9th May 2013 Application Reference: 12/00862/OUT
England are useful.
2. Anglian Water has assets close to, or crossing the site or there are
assets subject to an adoption agreement. Therefore the site layout
should take this into account and accommodate those assets within
either prospectively adoptable highways or public open space. If this is
not practicable then the applicant will need to ask for the assets to be
diverted under Section 185 of the Water Industry Act 1991. Or in the
case of apparatus under an adoption agreement, liaise with the owners
of the apparatus. It should be noted that the diversion works should
normally be completed before development can commence.
3. An application to discharge trade effluent must be made to Anglian Water
and must have been obtained before any discharge of trade effluent can
be made to the public sewer.
4. Anglian Water recommends that petrol / oil interceptors be fitted in all car
parking / washing / repair facilities. Failure to enforce the effective use of
such facilities could result in pollution of the local watercourse and may
constitute an offence.
5. The development site is within the 15m cordon sanitaire of a pumping
station. Whilst Anglian Water takes all reasonably practicable steps to
prevent any nuisance arising from the station, it is recommended that
development which is potentially sensitive to odour is located away from
the pumping station.
6. The Local Planning Authority has considered and assessed the content of
the Environmental Assessment (EA) submitted with the application as
well as consultation responses received from statutory bodies on
particular technical matters. Consideration has also been given to the
statutory planning policy framework and the views expressed by third
parties. The Development Corporation considers that subject to the
further information and mitigation measures identified in the EA being
carried out, the conditions of the permission being complied with and the
terms of the Planning Obligation met, the proposed development is
acceptable.
Documents:
Applications can be viewed online: http://www.thurrock.gov.uk/planning/
Documents also available to view at Planning, Thurrock Council, Civic Offices, New
Road, Grays, Essex, RM17 6SL.