Planning and Designing the External
Hospital
November 2016
Planning processPlanning process
The Planning Process
Planning is
“a technical and political process,
concerned with the development and use ofland,
protection and use of the environment (EIA),
public welfare (HIA), and
the design of the urban environment”
• Guides orderly development in urbanareas
• Statutory and legally binding processregulated by the Planning Authority –Department of Environment
Preferred Site Debate
Funding Strategy Debate
Detailed
Proposals
Debate
1 2
Outline
Planning
Application
3 4
Detailed
Planning
Application
5
Main Hospital
Construction
Completed
Main Hospital
Commissioning
Completed
Main Hospital
Soft Landing
Aftercare
6 7
Relocation
and
Enabling Works
Key Planning Applications for the Future Hospital Project
Dec 2016 July 2017 Nov 2017 Sep 2018 Dec 2022 June 2023 2026
1860’s
Garrison Re-
purposed as
HQ / Education
Centre
Outline
Planning
Application
“Seeks to establish whether the scale and
nature of a proposed development would
be acceptable before a fully detailed
proposal is put forward”
Westaway
Court
Temporary
Clinic Block
Catering
Unit
Building
Control
1860’s
Granite Block
Planning
Application
Formal Planning Applications to the Planning Authority
Preferred Site Debate
Funding Strategy Debate
Detailed
Proposals
Debate
1 2
Outline
Planning
Application
3 4
Detailed
Planning
Application
5
Main Hospital
Construction
Completed
Main Hospital
Commissioning
Completed
Main Hospital
Soft Landing
Aftercare
6 7
Relocation
and
Enabling Works
Key Planning Applications for the Future Hospital Project
Dec 2016 July 2017 Nov 2017 Sep 2018 Dec 2022 June 2023 2026
1860’s
Garrison Re-
purposed as
HQ / Education
Centre
Outline
Planning
Application
Detailed
Planning
Application
“Seeks to establish whether the scale and
nature of a proposed development would
be acceptable before a fully detailed
proposal is put forward”
“All the information that was not included in
the Outline Application will need to be
submitted and approved through a detailed
or reserved matters application before any
works can start.”
Westaway
Court
Temporary
Clinic Block
Catering
Unit
Building
Control
1860’s
Granite Block
Planning
Application
Formal Planning Applications to the Planning Authority
Environmental Impact Assessment
Environmental Impact Assessment (EIA) is
“a process that identifies both the positive andnegative environmental effects of significantdevelopments prior to planning permissionbeing considered.
It aims to prevent, reduce or offset anyidentified significant adverse environmentaleffects of development proposals.”
The EIA process is a method of ensuring thatplanning decisions are made in the fullknowledge of the environmental effects andwith full engagement of statutory bodies, localinterest groups and members of the public.
The responsibility of completing an EIA lieswholly with the developer.
It is mandatory for a hospital in Jersey.
Protection and use of the Environment
Topics Construction
impacts
Operation
impacts
Air
quality
Noise
and
Vibration
Ecology Landscape
character
Waste
generation
Traffic
Health Impact Assessment
Health Impact Assessment (HIA) is
“a process that uses a range of methods andapproaches to help identify and consider thepotential – or actual – health and equity impactsof a proposal on a given population”
Its primary output is a set of evidence-basedrecommendations geared to informing thedecision making process.”
These recommendations aim to highlight practicalways to enhance the positive impacts of aproposal and remove or minimise any negativeimpacts”
The responsibility of completing an HIA lieswholly with the developer (i.e. the FutureHospital Project)
It is an optional process.
Public Welfare
Health Impact Assessment
Health Impact Assessment (HIA) is
“a process that uses a range of methods andapproaches to help identify and consider thepotential – or actual – health and equity impactsof a proposal on a given population”
Its primary output is a set of evidence-basedrecommendations geared to informing thedecision making process.”
These recommendations aim to highlight practicalways to enhance the positive impacts of aproposal and remove or minimise any negativeimpacts”
The responsibility of completing an HIA lieswholly with the developer (i.e. the FutureHospital Project)
It is an optional process.
Public Welfare
How you can help
How you can shape how the
Future Hospital engages with
its external environment
• Be engaged in the formal planningprocess as a consultee, individual or(hopefully not) an objector
• Volunteer to help us identify theenvironmental impacts that concern youor your organisation through ourEnvironmental Impact Assessmentprocess
• Volunteer to help us identify the healthimpacts that concern you or yourorganisation through our Health ImpactAssessment process
1
2
34
5 ways to get involved