Planning and Designing Green Infrastructure

Resiliency in the Raritan River Basin

Christopher C. Obropta, Ph.D., P.E.

[email protected]

www.water.rutgers.edu

January 20, 2015

Page 2: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

The Water Resources

Program is one of many

specialty programs under

Rutgers Cooperative

Extension.

Our Mission is to identify

and address community

water resources issues

using sustainable and

practical science-based

solutions.

The Water Resources

Program serves all of New

Jersey, working closely

with the County Extension

Offices.

Water Resources Program

Page 3: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Page 4: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Raritan River Basin

• 1,100 square miles in size

• Portions of seven counties and 98 municipalities

• Frequent localized flooding

• Impaired for total suspended solids (TSS) and phosphorus

• Impaired aquatic community

The goals of this project are to enhance the climate resilience of

the municipalities within the Raritan River Basin study area by

providing each municipality with a plan to reduce stormwater

runoff.

Page 5: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Plan Options• Regional Stormwater Management Plans

– Specific NJ regulations for plan components

– Addresses flooding and water quality issues

– Public engagement component

– Incorporated into regulation

• Watershed Restoration Plans

– Nine minimum components

– Requires collection of water quality data

– GIS mapping

– Addresses primarily water quality

• Impervious Cover Assessments and

Reduction Action Plans

Page 6: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Impervious Cover

Assessment

Page 7: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Impervious Cover Assessment

• Analysis completed by watershed and by

municipality

• Use 2007 Land Use data to determine

impervious cover

• Calculate runoff volumes for water quality, 2, 10

and 100 year design storm and annual rainfall

• Contain three concept designs

Page 8: Planning and Designing Green Infrastructure Resiliency in
Page 9: Planning and Designing Green Infrastructure Resiliency in

Barren Land

4.2%

Forest

5.2%

Urban

79.1%

Water

10.1%

Wetlands

1.4%

Page 10: Planning and Designing Green Infrastructure Resiliency in

Commercial

13.2%

High Density

Residential

40.2%

Industrial

26.2%

Mixed Urban

8.7%

Recreational

Land

5.6%

Transportation/Infrastructure

6.1%

Page 11: Planning and Designing Green Infrastructure Resiliency in
Page 12: Planning and Designing Green Infrastructure Resiliency in

WatershedTotal Area

(ac)

Impervious

Cover (ac)%

Arthur

Kill Waterfront1,099 568 51.9%

Raritan Bay 38.7 0.00 0.0%

Lower Raritan

River1,336 618 58.3%

Woodbridge

Creek839.0 381 46.3%

Total 3,312 1,567 52.6%

Page 13: Planning and Designing Green Infrastructure Resiliency in

Subwatershed

NJ Water

Quality

Storm

(MGal)

Annual

Rainfall

of 44"

(MGal)

2-Year

Design

Storm

(3.3”)

(MGal)

10-Year

Design

Storm (5.0”)

(MGal)

100-Year

Design

Storm (8.2”)

(MGal)

Arthur

Kill Waterfront19.3 678.6 50.9 78.7 132.6

Raritan Bay 0.0 0.0 0.0 0.0 0.0

Lower Raritan

River21.0 738.3 55.4 85.6 144.3

Woodbridge

Creek12.9 455.2 34.1 52.8 89.0

Total 53.2 1,872 140.4 217.0 366

Page 14: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

How do we identify potential sites?

• EPA SWMM model of the drainage of each municipality

– Evaluate the existing stormwater sewer system and stormwater

control measures (SCMs)

– Prepare GIS maps of the storm sewer system and existing

SCMs

– Install flow meters throughout the municipality and storm sewer

system

– Model overland flow, stormwater sewer system, and SCMs

– Use long-term data to calibrate and validate the model

• Identify where SCMs are needed

• Prioritize sites

• Complete cost benefit analysis

• Secure property owner permission

Page 15: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

No! WE LOOK HERE FIRST:

Schools

Churches

Libraries

Municipal Building

Public Works

Firehouses

Post Offices

Elks or Moose Lodge

Parks/ Recreational Fields

• 20 to 40 sites are entered

into a powerpoint:

• Site visits are conducted

Page 16: Planning and Designing Green Infrastructure Resiliency in
Page 17: Planning and Designing Green Infrastructure Resiliency in
Page 18: Planning and Designing Green Infrastructure Resiliency in
Page 19: Planning and Designing Green Infrastructure Resiliency in
Page 20: Planning and Designing Green Infrastructure Resiliency in

Total Area Impervious Cover Total AreaImpervious

Cover

Municipality County (ac) (ac) (%) Municipality County (ac) (ac) (%)

Delaware Twp Hunterdon 23,692 489 2.1% Woodbridge Twp Middlesex 15,368 5,725 38.7%

East Amwell Twp Hunterdon 18,272 461 2.5% Englishtown Boro Monmouth 378 104 28.3%

Flemington Boro Hunterdon 690 329 47.7% Freehold Boro Monmouth 1,236 514 41.6%

Franklin Twp Hunterdon 14,831 428 2.9% Freehold Twp Monmouth 24,881 2,990 12.1%

Raritan Twp Hunterdon 24,094 2,137 5.7% Manalapan Twp Monmouth 19,759 2,539 13.0%

Readington Twp Hunterdon 30,612 1,733 5.7% Marlboro Twp Monmouth 19,477 2,893 14.9%

Dunellen Boro Middlesex 680 269 39.8% Millstone Twp Monmouth 23,800 1,053 4.5%

East Brunswick Twp Middlesex 14,340 3,304 23.0% Bound Brook Boro Somerset 1,085 373 35.2%

Edison Twp Middlesex 19,611 6,925 36.2% Branchburg Twp Somerset 12,970 1,513 11.9%

Helmetta Boro Middlesex 561 90 17.6% Bridgewater Twp Somerset 20,711 3,888 19.1%

Highland Park Boro Middlesex 1,170 429 36.9% Franklin Twp Somerset 29,998 4,244 14.4%

Jamesburg Boro Middlesex 570 217 38.4% Green Brook Twp Somerset 2,820 592 21.1%

Metuchen Boro Middlesex 1,817 698 38.5% Hillsborough Twp Somerset 20,711 3,888 19.1%

Middlesex Boro Middlesex 2,249 812 36.8% Manville Boro Somerset 1,568 514 34.0%

Milltown Boro Middlesex 1,021 407 40.9% North Plainfield Boro Somerset 1,805 593 33.2%

Monroe Twp Middlesex 26,989 3,112 11.7% Raritan Boro Somerset 1,298 482 38.0%

New Brunswick City Middlesex 3,686 1,648 49.4% Somerville Boro Somerset 1,501 593 40.1%

North Brunswick Twp Middlesex 7,860 2,483 32.3% South Bound Brook Boro Somerset 473 138 33.4%

Old Bridge Twp Middlesex 24,754 3,307 13.7% Warren Twp Somerset 12,563 1,550 12.4%

Perth Amboy City Middlesex 3,312 1,566 52.6% Watchung Boro Somerset 3,867 641 16.7%

Piscataway Twp Middlesex 12,131 3,609 30.2% Berkeley Heights Twp Union 4,004 1,008 25.3%

Sayreville Boro Middlesex 11,252 2,364 23.5% Fanwood Boro Union 857 308 35.9%

South Amboy City Middlesex 1,264 341 34.7% Mountainside Boro Union 2,585 555 21.7%

South Brunswick Twp Middlesex 26,243 4,157 16.1% Plainfield City Union 3,819 1,521 40.0%

South Plainfield Boro Middlesex 5,331 2,090 39.4% Scotch Plains Twp Union 5,796 1,220 21.2%

South River Boro Middlesex 1,873 598 33.6% Springfield Twp Union 3,308 1,016 31.0%

Spotswood Boro Middlesex 1,546 454 31.2% Summit City Union 3,868 1,182 30.9%

• 54 Municipalities totaling 831 square miles

• Total population is 1,346,436 (15.3% of NJ)

• % of Impervious Cover ranges from 2.1 to 52.6

• Average Impervious Coverage is 26.6%

Page 21: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Impervious Cover

Reduction Action Plan

Page 22: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Miry Run Watershed

Location Map

Project Sites1. Clover Square

2. Ibis Plaza Office Suites

3. University Plaza

4. Nottingham Volunteer Fire Company

5. St. Mark United Methodist Church

6. Morgan Elementary School

7. University Heights/H.D. Morrison Elementary School

8. Hamilton Square Baptist Church

9. Greater Victory Ministries

10. Hamilton Township School District

11. First Presbyterian Church

12. Baseball Fields

13. Our Lady of Sorrows School

14. Merlin Industries Inc.

15. Enterprise Volunteer Fire Co.

16. Christ Presbyterian Church

Page 23: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Nottingham Volunteer Company

At this site, there is a potential to replace parking lot

islands with tree filter systems and install cistern to

harvest rainwater from the rooftop to wash the fire

trucks. According to the NRCS soil survey, the soils

are suitable for infiltration at this site.

Address Latitude Longitude

200 Mercer

Street40.233412 -74.65753

Existing Loads (lbs/year)

Area (sq.ft.) Lot Block TP TN TSS

153,281 24.01 1839 5.3 56.3 703.8

Page 24: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Nottingham Volunteer Company (cont’d)

Impervious Cover Runoff Volume (Mgal)

% Square feetFor the 1.25” Water

Quality Storm

For an Annual

Rainfall of 44”

72 110,362 0.23 3.03

Recommended

BMP

Recharge

Potential

(Mgal/yr)

Total

Suspended

Solids Removal

Potential

(lbs/yr)

Maximum

Volume

Reduction

Potential

(gal/storm)

Peak

Discharge

Reduction

Potential

(cu.ft./second)

Tree Filter

Systems 0.146 24 1,541 0.40

Cistern 0.055 18 461 0.32

Estimate cost is $16,675 for 667 square feet of tree filter systems with two

feet of porous media. Estimate cost is $10,000 for 5,000 gallon cistern.

Page 25: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Page 26: Planning and Designing Green Infrastructure Resiliency in

Water Resources Program

Final Thoughts

• Plans promote action

• Plans are a conduit for funding

• Impervious Cover Reduction Action Plan provide sites for

developers to offset impacts

• Wide range in cost of projects (Eagle Scout Projects to

Stimulus Money Projects)

• Foundation for stormwater utilities, watershed restoration

plans, and integrated water quality plans

• Plans are quick and easy to develop

Page 27: Planning and Designing Green Infrastructure Resiliency in

Please consider engaging the urban extension service

at the Land Grant University near you.

Page 28: Planning and Designing Green Infrastructure Resiliency in

Questions?

Christopher C. Obropta, Ph.D., P.E.

[email protected]

www.water.rutgers.edu