Upload
boban-stanojlovic
View
228
Download
0
Embed Size (px)
Citation preview
7/21/2019 PIN 2009-12
1/37
DECEMBER 2009ISSUE 002
PiggingPipelayersGASTAU Pipeline
United StatesREVIEW
7/21/2019 PIN 2009-12
2/37
7/21/2019 PIN 2009-12
3/37
Your pipelines are probably your single biggest physical asset. Protecting this
asset from third party damage ensures uninterrupted service for your customers
while it protects your investment.
Fade Resistant & UV StableTemperature stable from -40 to 150C.
North Slope of Alaska
Protect Your Pipelineswith Rhino TriView Systems
Available with Terminals
Bury It
TriGrip anchorbarbs fold out,
securing theTriView in
the ground.
Detail
Drive It
Easy & Versatile Installation
Decals in any Language
Durable & Flexible
See demos in action by watchinghigh speed and cold weather impact
videos at RhinoMarkers.com
Slide It
IN AN EMERGENCYORBEFOREEXCAVATING
CALL
FIBER
OPTICCABLE
Will withstand repeated impacts
Rhino Marking & Protection Systems www.RhinoMarkers.com
Grenoble Office: +33 970 44 91 51 USA Factory: 507-835-4646
7/21/2019 PIN 2009-12
4/37
2 PIPELINES INTERNATIONAL | DECEMBER 2009
ISSUE 002 | DECEMBER 2009
The publishers welcome editorial contributions from interested
parties. However, the publishers do not accept responsibility
for the content of these contributions and the views contained
therein which will not necessarily be the views of the publish-
ers. The publishers do not accept responsibility for any claims
made by advertisers.
Unless explicitly stated otherwise in writing, by providing edito-
rial material to Great Southern Press (GSP), including text and
images you are providing permission for that material to be sub-
sequently used by GSP, whole or in part, edited or un changed,
alone or in combination with other material in any publication
or format in print or online or howsoever distributed, whether
produced by GSP and its agents and associates or another party
to whom GSP has provided permission.
NORTHERN HEMISPHERE
(Editorial and Technical)PO Box 21Beaconsfield, BucksHP9 1NSUnited KingdomTel: +44 1494 675139Fax: +44 1494 670155
www.pipelinesinternational.com
SOUTHERN HEMISPHERE
(Sales and Subscriptions)GPO Box 4967Melbourne VIC 3001AustraliaTel: +61 3 9248 5100Fax: +61 3 9602 2708
REGULARS4 From the Editor15 Pipes & People61 Media Kit64 Advertisers Index Subscriptionform Comingin future issues
AROUND THE WORLD
6 TransCanada supersizesKeystone project
7 IP Pipeline moves forwardafter much discussion
8 Technological breakthrough crucial forSecond West East Gas Pipeline
9 South Stream: providing moregas to Europe
10 Peru to complete Camisea pipelineexpansion ahead of schedule
11 Egyptian pipeline complete12 World Wrap14 Project briefs
MEET THE COMPANY
16 Enags: expanding pipelinesin Europe
REGION REVIEW: USA
18 Pipeline development in
the land of the free23 REX appeal: pipeline construction
in the Rockies
TERRAIN REVIEW
24 Protecting pipelines in mountain areas
POLICY AND OPINION
26 Canadian perspective: a goal-orientedapproach to regulating pipelines
TECHNICAL
28 Environmental navigation of Germanlandfall and modelling pull-back
operations
PROJECTS
30 GDK: innovative pipeline constructionon GASTAU
33 Pipeline link constructedin central Australia
PIPLINE EQUIPMENT35 Pipelayers and sidebooms: the
essential pipeline machinery
38 Pipelaying with the PL61
PIGGING
40 Optimal identification: getting up closewith ID anomalies
43 GEs MagneScan inspectsNormandy pipeline
44 Prickly pigging: PipeWays Porcupinereaches the international market
45 PPSA: providing squeaky clean piggingadvice
46 Ensuring pipeline integrity:talking pigging in Houston
VALVES
48 5 simple steps tototal valve integrity
TECH TALK
50 A place for science in pipeline design
INDUSTRY NEWS
52 CTDUT: a model for sharing facilitiesand costs in research and development
HISTORY
54 Trans-Mediterranean Pipeline
PRODUCTS AND SERVICES56 Learn to weld with Lincoln Electrics
virtual welding system
56 Production begins on worlds largestthree-screw crude oil pipeline pump
56 Latest edition of WinDOT thePipeline Safety Encyclopedia
56 Cure pipes with Curapipe
EVENTS
57 Pipeline carnivale in Rio!58 Evaluating different
rehabilitation approaches
59 Pipeline Technology Conference:a scientific update from Ostend
60 APCE: pipeline success inSouth East Asia
60 Australian industry gathersin northern Australia
24 26 54
CONTENTS
Theglobal organizationfor oil and gas
pipeline engineers
www.pipeinst.org
Recognizing your skills and status
Promoting the highest engineering standards
Providing a professional network
SIGN UP TODAY!
7/21/2019 PIN 2009-12
5/37
4 PIPELINES INTERNATIONAL | DECEMBER 2009
It seems a paradox: 1015 years ago, as
intelligent inspection was developing
and the science was coming into its
own, a major point of discussion was to do
with the technology itself. The big question
was high resolution or low resolution?,
relating to the capacity of the equipment to
detect pipewall features. Putting this another
way, did the operator want a quick-and-
dirty (and therefore cheap) inspection,
or was the Full Monty required? The
issue revolved around the capacity of the
intelligent inspection tools to inspect, and
the cleanliness of the pipeline that the tool
was to inspect was sometimes considered of
less significance.
Now, however, intelligent inspection
tools are of an unimaginably greater
sophistication, and the general questionbeing asked is no longer to do with their
capacity to accurately and precisely detect
features, but to do with how clean the
pipeline is. A pipelines internal cleanliness
has, quite properly, become a question of
great significance. Nevertheless, there are
no published standards of cleanliness and
although there are many ways in which
deposits can be removed from a pipe wall,
ensuring a pipeline is clean enough for
an inspection to be carried out remains a
subjective process.
It has often been said that the best
cleaning tool is a magnetic-flux leakage
intelligent pig, and this remains true.
While it is clear that each pipeline and its
operating regime are different, it seems
surprising that it has not been found
possible to establish some basic guidelines
for achieving cleanliness. Under normal
operating conditions, minimisation of
pipewall deposits will improve flow
conditions as well as a pipelines overall
efficiency and cost-effectiveness, to say
nothing of the effect on reducing the
potential for corrosion. When its time foran inspection, deposits and other debris
must be removed, both to ensure that
the tools sensors can have unimpeded
access to the pipewall, and to remove the
possibility of debris clogging-up the tool,
and even causing it to become stuck.
The question of how clean is clean?
is not unfamiliar and, in fairness, is
being asked more frequently. One of the
most detrimental cleaning problems
for gas pipelines is the formation and
accumulation of so-called black powder.
This material which is as fine as flour,
although far more dangerous because it is
both abrasive and pyrophoric is one of
the least understood but most prominent
contamination problems in gas pipelines.
Black powder is the name given to the
mixture of iron oxides, carbonates, and
sulphides found in gas lines. Its sources
include millscale, corrosion products,
salts and scales from gas wells and wet
gas gathering systems, and atmospheric
corrosion. The variability of its composition
is illustrated by reports of the powder
ranging from being completely iron sulphide
to completely iron oxide.
Black powder can cause product quality
problems and excessive wear and erosion on
internal pipewalls and many other pipeline
components, including compressors,turbines, and valves. The accumulated solids
can plug small orifices and consequently
affect measurement equipment and, as the
particles settle out of the gas stream, they
can fill-in surface pits and other internal
pipewall anomalies, preventing accurate
inspection. In sag bends, these build-ups can
harbour corrosive bacteria.
Although difficult to deal with, the
problems caused by accumulations of this
material can be overcome as can most
pipeline problems by careful planning
and attention to detail. However, removal
of the black powder from the pipeline is
not the end of the affair. As the material
is hazardous, necessary arrangements for
its disposal must be made, and obviously
these should be in place before any pigging
operations begin.
A special session on this problem is
being organised at the Pipeline Pigging and
Integrity Management (PPIM) Conference
being held in Houston on 1718 February
(see page 46), and other papers at the event
will also address the issue.
The more the subject of how clean isclean? can be discussed, the more likely it is
that shared experiences can lead to a shared
solution; at the very least, clean needs to
be kept in the spotlight of pipeline integrity
management and operations.
John Tiratsoo
Editor-in-Chief
FROM THE EDITOR
Cover shows workersfinalising pipe
stringing on a portion
of Enbridges Alberta
Clipper Pipeline project,
a 36 inch, 450,000 barrels
per day crude oil pipeline
from Hardisty, Alberta,
Canada, to Superior,
Wisconsin, USA.
Editor-in-Chief: John TiratsooAssociate Editor: Lyndsie Mewett
Product Manager: Scott Pearce
Journalists: Stephanie Clancy
Julia Cooke
Sales Manager: Tim Thompson
Snr Account Manager: David Marsh
Sales Representative: Brett Thompson
Design Manager: Michelle Bottger
Designers: Sandra Noke
Stephanie Rose
Venysia Kurniawan
Publisher: Chris Bland
ISSN: 1837-1167
January 19-20 DIMP Distribution Integrity Management Program (Houston)
February 2-5 Subsea Production Systems Engineering (Aberdeen)
February 15-16 Pigging & In-line Inspection (Houston)
February 15-16 Defect Assessment in Pipelines (Houston)
February 15-16 Pipeline Repair Methods / In-Service Welding (Houston)
February 15-16 Introduction to Excavation Inspection & Applied NDE for Pipeline IntegrityAssessment (Houston)
February 15-16 Pipeline Risk Management (Houston)
February 15-16 Performing Pipeline Rehabilitation (Houston)
February 15-16 DOT Pipeline Safety Regulations - Overview and Guidelines for Compliance(Houston)
February 15-18 Pipeline Pigging & Integrity Management Conference (Houston)
February 15-19 Subsea Pipeline Engineering Course (Amsterdam)
April 12-16 Practical Pigging Training (Rio de Janeiro)
April 20-23 Engineering for Arctic Environments (Houston)
April 26-27 Microbiological Corrosion in Pipelines (Houston)
April 26-30 Subsea Pipeline Engineering Course (Houston)
April 27-30 Subsea Production Systems Engineering (Houston)
May 10-14 Pipeline Defect Origination, Characterization and Sizing (Houston)
May 17-21 Deepwater Riser Engineering Course (Houston)May 17-21 Onshore Pipeline Engineering (Houston)
January 2010
February 2010
APRIL 2010
May 2010
e ru DOT n e Sa e ati vervi Gui e Co ceHo
ruar Pip ggi & Int ty emen re e Hou
ruary Su e i gineer ng e A m
12-1 Prac iggi g JaneirAPRIL 201L 2
Training coursesearly 2010
Are you up to speed?
Working with a faculty of some 38 leading industry experts, Clarion and Tiratsoo Technical areprivileged to provide some of the best available industry based technical training courses for
those working in the oil and gas pipeline industry, both onshore and oshore.
Complete syllabus and registration details for each course are available at:
www.clarion.org
102000 0
7/21/2019 PIN 2009-12
6/37
PIPELINES INTERNATIONAL | DECEMBER 2009 7
TransCanada is seekingregulatory approvals inCanada and the United Statesto construct and operate a3,200 km expansion of its3,456 km Keystone Pipeline,which would make it one of thelargest oil delivery systems inNorth America.
In September 2009, Canadas National
Energy Board held a hearing to review
the application for the Canadian
portion of the Keystone Gulf Coast
expansion dubbed Keystone XL with
a decision expected in early 2010. Permits
for the US portion of the expansion are
expected by mid-2010. Construction of the
Keystone expansion is expected to begin
once TransCanada receives the necessaryregulatory approvals.
The proposed Keystone XL Pipeline
would increase the capacity of the original
pipeline system from Western Canada to the
US Gulf Coast by 500,000 barrels of oil per
day. Once completed, the pipeline system
would have the capacity to deliver 1.1 million
barrels of oil per day.
The extension is proposed to originate in
Alberta, Canada, and extend south to serve
markets on the Gulf Coast, Texas.
The 36 inch diameter pipeline would
begin in Hardisty, Alberta, and travel
527 km to Monchy, Saskatchewan, and
then 1,360 km from Morgan, Montana, to
Steele City, Nebraska, where it would link
into the original 477 km Keystone Pipeline
extension to Cushing, Oklahoma, scheduled
for construction in 2010. From Cushing,
Keystone XL will run to Houston and Port
Arthur, Texas.
The total cost of the Keystone and
Keystone XL project is expected to be
approximately $US12 billion.
Meanwhile, the initial phase of
TransCanadas Keystone Pipeline isnearing completion with the pipelay
works set to reach Patoka, Illinois, by the
first quarter 2010.
At the time of writing, the first phase
of the project was 90 per cent complete,
with TransCanada on schedule to begin oil
deliveries in the first quarter of 2010.
The Keystone Pipeline originates in
Alberta, Canada, and extends 3,456 km to oil
refineries in Wood River and a tank farm in
Patoka, Illinois.
The first phase involves the construction
of 2,592 km of pipe and the conversion of
864 km of natural gas pipeline to oil service.
Converting the existing facilities in Canada
began in 2008.
TransCanada supersizesKeystone project
6 PIPELINES INTERNATIONAL | DECEMBER 2009
AROUND THE WORLD AROUND THE WORLDAROUND THE WORLD
Iran has completed a major portion of the construction work on the Iran Pakistan (IP) Pipeline projectwith the gas pipeline to reach the Iran Pakistan border within the next few months, according to theIranian Consul General based in Pakistan, Masoud Mohammad Zamani.
Iranian Foreign Minister Manouchehr
Mottaki has said that over 100 km of
the 1,935 km pipeline project has been
constructed in Iran. Pakistan has also started
construction on the project, added Mr Mottaki.
With an anticipated gas capacity of
26,485 cubic feet per annum, the 42 inchdiameter gas pipeline will run from the
Assaluyen Gas Field in southern Iran to
Pakistan.
Formerly called the Iran Pakistan
India Pipeline, the project has been under
discussion for almost two decades and
initially intended to inc lude India. However,
when Iran and Pakistan signed a gas sales
purchase agreement for the pipeline project
in May this year, India refrained from
partaking in signing the agreement due to
security concerns about the pipeline.
In July 2009, the Iranian Ministry of
Petroleum and Natural Resources announced
that supply of gas from Iran has been
scheduled for October 2013.
The Pakistani Economic Co-ordinationCommittee (ECC) approved the $US3.2 billion
Iran Pakistan gas pipeline the following
month. A sub-committee of the ECC decided
that the route of the pipeline would mainly run
through the state of Balochistan, in Pakistan.
Pakistan Federal Minister for Petroleum and
Natural Resources told local media that only local
companies would be involved in the project.
In September, the Pakistani ambassador
to Iran Muhammad Bux Abassi claimed
that India had definitely quit the pipeline,
however Iranian officials are said to have
denied these comments. Officials from Iran
and Pakistan said that the option remains
open for India to join the project at a later
stage, but Iran said that it would not wait
indefinitely for India to commit to the project.Shortly after, the Iranian Ambassador to
India Seyed Mehdi Nabizedeh told local news
sources that China was interested in the project,
but no formal agreements have since been made.
The original Iran Pakistan India
Pipeline was proposed to be 2,670 km long,
running from the Assaluyen gas field in
southern Iran to the Gas Authority of India
Limiteds Hazira Vijaipur Jagdishpur
Pipeline in Gujarat.
IP Pipeline moves forwardafter much discussion
COPON Internal Pipe Linings have been
applied to over 140,000 km of diverse
service pipelines worldwide during a
period spanning more than 45 years:
Gas & Oil
Sour Gas & Oil
Water
Aviation Fuel
Refined Product
Petrochemical
+44 (0)1609 780170
+44 (0)1609 780438
COPON Pipelinings
www.pipelinings.com
COPON AND THORTEX HAVE BEEN REBRANDED TO FORM PART OF THE SCOTCHKOTE PRODUCT RANGE FROM 3M
COPON Pipelinings - one of the world leaders in flow coating & lining technology
Corrosion Protection Products
3M United Kingdom plc
23 Standard Way, Northallerton, North Yorkshire DL6 2XA United Kingdom
Tel:
Fax:
Email:
7/21/2019 PIN 2009-12
7/37
8 PIPELINES INTERNATIONAL | DECEMBER 2009
Europes energy demand continues to grow, with an additional 205 billion cubic metres of naturalgas estimated to be required by 2030. Gazproms South Stream Pipeline will make an importantcontribution to improving Europes energy security.
South Stream: providingmore gas to Europe
AROUND THE WORLD AROUND THE WORLDAROUND THE WORLD
The South Stream Pipeline will deliver gas
from the Russian Unified Gas System,
which sources its gas from Russian
domestic gas sources and Central Asian gas
suppliers, to Europe via the Black Sea.
The pipeline i nvolves the construction
of three sections of pipeline: an onshore
Russian section, an offshore section, and an
onshore south and central European section.
Onshore route selectionThe Russian onshore section of the
pipeline will run from the Pochinki
Compressor Station to the Black Sea coast.
A feasibility study is currently underway to
select the route for this section of pipeline.
Several possible routes for the onshore
south and central Europe sections are
currently being considered. Gazprom has
negotiated inter-governmental agreements
with Greece, Serbia and Bulgaria, which
contemplate the creation of joint venture
enterprises between Gazprom and local
companies to develop and operate the South
Stream Pipeline on their territories. Gazprom
is currently in the process of starting those
joint ventures with its partners.
Offshore challengesThe offshore section of South Stream
will extend 900 km across the Black Sea
at depths of up to 2 km and connect the
Russian and Bulgarian coasts. Italian
company Eni will partner Gazprom in the
offshore construction of the project.
Gazprom and Eni have gained experience
in the course of construction and operation
of the Blue Stream Pipeline across the
Black Sea. Gazprom says that Blue Stream
has demonstrated that the construction of
subsea projects has only a temporary and
local effect on the marine environment,
and the risk of potential pollution can be
effectively minimised.
Currently, Gazprom and Eni are
carrying out a detailed feasibility study
of the projects offshore section, which is
scheduled to be completed in the beginning
of 2010. At the conclusion of the study the
pipeline route, technical requirements and
capacity will be finalised.
Speaking about the progress of the
pipeline, Gazprom Management Committee
Chair Alexey Miller said We have the
technical know-how required to build
South Stream in compliance with the
latest environmental and technological
requirements, and we are making significant
progress on the pipeline. We are currently
carrying out feasibility studies which will
allow more accurate routeing.
Pipeline construction works are scheduled
to be completed by the end of 2015.
PIPELINES INTERNATIONAL | DECEMBER 2009 9
The 8,704 km pipeline consists of onetrunk link and eight branches that will
connect Horgos, located in Xinjian
Uygur Autonomous Region with the Hong
Kong Special Administrative Region after
traversing 14 provinces, autonomous regions
and municipalities.
CNPC has successfully incorporated
technological breakthroughs from six
of its research projects to support the
construction.
Seven new products have been
developed and manufactured domestically
on an industrial scale. These products
include large diameter, high grade steel
pipe materials, spiral submerged arc welded
pipes, hot bending bends and hot-drawn
T-joint pipe fittings.
The new X80 steel welding wire and flux
increased welding speed by up to 1.7 m per
minute, which is 30 per cent higher than the
speed achieved on the first West East Gas
Pipeline.
Welders on the Second West East
pipeline received guidance on more than
100 techniques developed through the
project including automatic welding,semi-automatic welding, joint-connecting
welding and rework welding of the X80
steel pipes. Significant progress was also
made in fracture control, anti-corrosion
field coating, gas storage location, integrity
management technologies, and safety pre-
warning technologies, which have benefited
the construction and safe operation of the
pipeline.
Pipeline progressThe project has been divided into
eastern and western sections with Zhongwei,
located in Ningxia Hui Autonomous Region,
designated as the pipelines midpoint.
The western section, running 2,461 km
from Horgos to Zhongwei, commencedconstruction in February 2008 and the
welding work on the principle parts of the
trunk line is now complete.
The eastern section, running 2,477 km
from Zhongwei to Guangzhou with designed
pressure of 10 MPa, commenced construction
in December 2008. The eastern section is
expected to connect into the Turkmenistan
China Gas Pipeline, which is currently
under construction, by the end of 2009 and
is scheduled to be comissioned in 2011.
On November 16, the tunnelled crossing
of the Changjiang River was successfully
completed. The crossing was a key
engineering project for the Second West
East Gas Pipeline. The crossing took place
between Jiujiang City in Jiangxi Province
and Wuxue City in Hubei Province, with a
horizontal crossing span of 2,590 m. China
Oil and Gas Pipeline Company was the
engineering, procurement and construction
contractor.
The next step is to lay a 48 inch diameter
pipeline in the tunnel, which is expected to
be completed in April 2010.
Once completed, the pipeline willtransport natural gas imported from Central
Asian countries, as well as gas produced
domestically in the Tarim, Junggat, Tuha
and Ordos basins, to the Pearl and Yangtze
River delta areas and the central west part of
China.
The pipeline is expected to increase
the share of natural gas in Chinas energy
consumption by 12 per cent and play a
significant role in boosting the countrys
domestic natural gas demand, facilitate
the improvement of Chinas machinery
manufacturing, improve the nations energy
structure and promote economic and social
development to the adjacent regions along
the pipeline.
China National Petroleum Corporations (CNPC) intensive research and development programme hasbeen integral in the construction of its Second West East Gas Pipeline.
Technological breakthrough crucialfor Second West East Gas Pipeline
Construction progressed as planned onthe first West-East Gas Pipeline.
7/21/2019 PIN 2009-12
8/37
10 PIPELINES INTERNATIONAL | DECEMBER 2009 PIPELINES INTERNATIONAL | DECEMBER 2009 1110 PIPELINES INTERNATIONAL | DECEMBER 2009
Pluspetrol was scheduled to begin
the mobilisation of materials and
equipment to expand its Malvinas
Gas Processing Plant, which extracts gas
from the Camisea Gas Fields to feed into the
Camisea Gas Pipeline, in November 2009.
The Camisea pipeline connects the
Camisea Gas Field, located in the UcayaliBasin, 431 km east of Lima, to the Port of
Pisco, Peru. The downstream project consists
of two pipelines: a 714 km natural gas
pipeline and a 540 km liquids pipeline.
The two pipelines run parallel to each
other from the Camisea field passing through
the Andes mountain range via the Malvinas
gas processing plant to Pisco. From Pisco,
the natural gas pipeline turns north along
the coastline to the Lima city gate to supply
gas for domestic use.
Transportadora de Gas Peruano (TGP) is
a consortium led by Argentinas Tecgas and
includes Pluspetrol, Hunt Oil,
SK Corporation, Sonatrach and Grana y
Montero. TGP was awarded three different
33 year contracts by the Government of Peru
as part of the Camisea downstream project
in 2000 a contract for the transportation of
gas from Camisea to Lima, a second contract
for the transportation of natural gas liquids
from Camisea to the coast, and a third for the
distribution of gas in Lima and Calleo.
Two major upgrades, both due for
completion in the second half 2009, are
under way: an increase of capacity at a
compressor station in the Ayacucho region
and the construction of a loop along
Peru's coast. The upgrades will expand
the pipeline from its current capacity of
115 billion cubic feet per annum (Bcf/a)to a capacity of 164 Bcf/a in an attempt to
meet the demand for gas in Perus densely
populated coastal regions. It was originally
anticipated that the pipeline would reach
164 Bcf/a in 2015; however the spike in
Peruvian gas consumption from 95 Bcf/a in
2007 to 120 Bcf/a in 2008 has led domestic
pressure to be placed on the Peruvian
Government to meet domestic natural gas
supply needs.
TGP is on schedule to complete the
pipeline expansion in December 2009
according to Mr Gamarra.
TGP has made considerable advances in
this process of amplification and its likely to
be ready by the end of the year, he said.
The Camisea Gas Pipeline, commissioned in August 2004, will increase its capacity by 43 per cent bythe end of 2009, according to the Peruvian Minister of Energy and Mines, Pedro Sanchez Gamarra.
Peru to complete Camisea pipelineexpansion ahead of schedule
AROUND THE WORLD
Nile Valley Gas Company (NVGC) was
granted an exclusive franchise by
the Egyptian General Petroleum
Corporation (EGPC) in April 1998 to develop
a natural gas transmission and distribution
pipeline system to provide natural gas to
consumers in Upper Egypt.
NVGC was formed as a joint venture led
by British Gas with a 37.5 per cent interest,
Edison with a 37.5 per cent interest, Orascom
with a 20 per cent interest and Middle EastGas Association holding the remaining
5 per cent. Edison has since sold most of its
Egyptian assets to Petronas of Malaysia.
NVGC holds the right to develop a pipeline
system across an area, which commences at
El Wasta, a small town 80 km south of Cairo,
and extends through the governorates of Beni
Suef, El Minya, Asyut, Sohag, Qena, Luxor and
Aswan, including the New Valley governorate
and Toshka.
The completed pipeline extends
1,200 km and its ultimate marketing capacity
is targeted to be as much as 6 billion cubic
feet per day (Bcf/d).
The 1,200 km pipeline has been constructed
in five stages. In the first phase of the project,
NVGC took over a pipeline built by the
Government from Cairo to the Kuraymat
Power Station located near Beni Suef. Stage 2
involved the construction of 150 km of 32 inch
diameter pipeline extending from Beni Suefto Abu Qurqas. Stage 3 saw 136 km of 32 inch
diameter pipeline laid from the governorate of
Minya to Assiut at a cost of $US75 million, while
Stage 4 involved the laying of 100 km of 30 inch
diameter pipeline from Assiut to Sohag.
The final stage involved the laying of
408 km of 30 inch diameter pipeline from
Sohag to Aswan. The last section of the
pipeline was brought online at the end of
November and Egyptian Minister of Petroleum
Sameh Fahmi attended a ceremony in Aswan
to celebrate the completion of the project.
The project also involved the design and
construction of three compressor stations
two between Beni Sueg and Assiut and one
near Cairo.
The 1,200 km pipeline was worth
approximately $US9.3 billion in investment
and forms part of a broader development
programme. Mr Fahmi said that the delivery of
natural gas to the provinces of North and SouthSinai would accelerate the reconstruction and
development of the area by providing energy to
attract industrial projects.
The whole pipeline has a design capacity
of 0.84 Bcf/d across a zone populated with
massive agricultural and agro-industrial
settlements.
The pipeline will have a major role in
reshaping the investment map of the entire
southern Egypt, said Mr Fahmi.
The Upper Egypt Gas Pipeline reached the governorates of Minya, Assiut and Sohag in August this yearand the final stage was completed in November, bringing gas to Aswan homes and businesses for thefirst time.
Egyptian pipeline complete
AROUND THE WORLD
The spike in Peruvian gas
consumption from 95 Bcf/a
in 2007 to 120 Bcf/a in
2008 has led domestic
pressure to be placed onthe Peruvian Government
to meet domestic natural
gas supply needs.
7/21/2019 PIN 2009-12
9/37
WORLD WRAP
Gas pipeline extends into Northwest LouisianaAcadian Gas plans to extend its 1,609 km Louisiana intrastate natural
gas pipeline system into Northwest Louisiana to provide producers in the
Haynesville shale play with access to multiple markets through connections
with the pipeline system in South Louisiana, as well as nine major interstate
pipelines. The 400 km extension will have a capacity of 1.4 Bcf/d of gas.
12 PIPELINES INTERNATIONAL | DECEMBER 2009
Pemex awards pipeline contractsto UPMPetrleos Mexicanos (Pemex) has
awarded United Pipeline de Mexico
(UPM) a $US12.4 million contract for
the construction, replacement and
rehabilitation of approximately 40 km
of pipelines in Mexicos Chicontepec
oil region, as well as a $US13.9 million
contract for the construction of
connecting pipelines and associated
infrastructure to tie-in the oil wells
produced in the same region.
WORLD WRAP
Vietnam to build nationslongest gas pipelinePetroVietnam will construct a
400 km pipeline running from
Depot B on the southwestern
continental shelf to the
Mekong Delta to supplythe O Mon Power Station.
Military Zone 9 Command will
provide services to protect
the pipeline in areas under
its management during the
time of construction and
after completion. The project
will be Vietnams longest gas
pipeline.
Construction commences on China Myanmar PipelineChina National Petroleum Corporation (CNPC) has commenced
construction on the 771 km China Myanmar Pipeline and a
crude oil port in Myanmar. The pipeline will have a capacity
of 12 MMt/a and connect Myanmars port at Maday Island in
the Indian Ocean via Mandalay in central Myanmar, to Ruili in
Chinas southwestern province of Yunnan.
PIPELINES INTERNATIONAL | DECEMBER 2009 13
Nord Stream granted Swedish andFinnish permitsThe Swedish and Finnish governments
have granted permits to Nord Stream
AG to construct the twin 1,220 km Nord
Stream natural gas pipelines through their
exclusive economic zones in the Baltic Sea.
The approvals process for the pipeline is
also continuing in Russia and Germany,
with construction scheduled to begin in
early 2010.
Austria and Slovakia sign-off onBratislava-Schwechat PipelineA joint venture between Slovakian
company Transpetrol and Austrian
OMV AG will build the Bratislava-
Schwechat Pipeline, a 62 km oil
pipeline connecting Slovakias
Friendship Pipeline, which brings
crude oil to the country from Russia,
with a refinery in Schwechat, Austria.
Construction of the 5 MMt/a capacity
pipeline is scheduled to begin in 2012.
Kenya, Uganda agree to reverse-engineer oil pipeline
The Eldoret Kampala Oil Pipeline, locatedin East Africa, will be reverse engineered to
allow oil to flow in both directions through the
pipeline, as it is becoming increasingly likely
that an oil refinery will be built in Western
Uganda. The 320 km pipeline is being built
under a public private partnership between
the Kenyan and Ugandan governments as well
as Libyan contractor Tamoil East Africa.
Saudi Aramco begins offshorepipeline constructionPipeline construction and associated
works have commenced at Saudi
Aramcos offshore Karan Gas Field,
in Saudi Arabias Khuff region,
approximately 160 km north of
Dhahran. The Karan onshore facility
will have the capacity to process
1.8 Bcf/d of Karan Khuff gas, which
will then be transported through a
110 km subsea pipeline from the field
to onshore processing facilities at the
Khursaniyah Gas Plant.
Fugro maps out Peruvian oil pipelineOil and gas exploration and development company
Perenco has engaged Fugro to provide detailed
topographic mapping of a proposed oil pipeline route in
northern Peru. Perencos proposed pipeline system will
transport oil production to the Bayovar export terminal,
located 1,000 km from its Block 67 group of oil fields,
located in the Maranon Basin on the Pacific coast.
To stay informed on all this news and more, subscribe to the Pipelines InternationalUpdate www.pipelinesinternational.com
7/21/2019 PIN 2009-12
10/37
PIPELINES INTERNATIONAL | DECEMBER 2009 15
Name change for StatoilhydroSTATOILHYDRO ASA HAS changed its
name to Statoil ASA.
The company advised that ticker symbols
will remain unchanged as STL on the Oslo
Stock Exchange and STO on the New York
Stock Exchange.
Statoil is an i nternational energy
company with operations in 40 countries.
The company is based in Norway and has
more than 35 years of experience from
oil and gas production on the Norwegian
continental shelf.
Statoil is technical service-provider for
approximately 7,000 km of pipeline from the
Norwegian continental shelf to Europe.
New Chair at PRCITHE BOARD OF Directors of Pipeline
Research Council International (PRCI)
elected Vice President of TransCanada
Pipelines Operations and Project Services
Paul F. MacGregor as Chair at its Annual
Meeting on 15 September 2009. He replaces
Enbridge Pipelines Oil Sands Projects Senior
Vice President Art Meyer.
Mr MacGregor has been a PRCI Board
member for four years, serving most recently
as Vice Chair, a member of the Executive
Committee, and Chair of the Audit and
Finance Committee.
He has held numerous key positions
with TransCanada since joining the company
in 1981, and is currently responsible for
the companys supply chain management,
procurement activities, and performance
standards.
Mr MacGregor said This is an
important time for research, and
particularly collaborative research, in the
energy pipeline industry. I am honoured
that my colleagues in PRCI have entrusted
me with this position, and I look forward
to working with them and the PRCI team
to continue to extend the success of PRCIs
collaborative model.
New Vice President at PLMPIPELINE MACHINERY INTERNATIONAL
(PLM) President Mel Ternan, is pleased to
announce that Anthony (Tony) J. Fernandez
has taken on the position of Senior VicePresident with PLM.
With Tony taking responsibility for daily
operational and sales issues, we will have
more opportunity at the president level to
concentrate on strategic and PLM expansion
plans, said Mr Ternan.
Mr Fernandez has been with PLM since
its inception in May 2005. He previously
worked with Ring Power Corporation for
17 years as International Accounts Manager
and later Pipeline Division Manager. Tony
participated in the early discussions that
resulted in a four-dealer partnership to form
PLM and provide Caterpillars global focus to
the pipeline industry.
Additional PLM information is available
on the PLM website at www.plmcat.com
Role changes at RosenAFTER YEARS of direct involvement in
the Australasian industry, Vice President
and General Manager Operations of Rosen
Asia Pacific Chris Yoxall has relocated within
Rosen to Houston, United States, to take up
the position of Vice President, Rosen USA.
He has been succeeded by Neil Pain who
has been appointed as General Manager,
Rosen Australia. Mr Pain is well known,
having been in the industry for more than a
decade, and has been with Rosen for over six
years. In this time, Mr Pain has undertaken
a number of responsibilities including
quality assurance, project management and
business development.
As part of the restructured changes,
Myles Youngs has assumed the role of
General Manager, Operations in Australia.
Mr Young has been with Rosen for three
years in capacity of Operations Manager. He
is now responsible for all operational aspects
including the processors of data evaluation,
operations and maintenance within the
Australian organisation.
PROJECT BRIEFS
14 PIPELINES INTERNATIONAL | DECEMBER 2009
Project briefsKasimovskoye UGS Voskresensk CS Gas TrunklinePROPONENT:OAO Gazprom, 16 Nametkina Street, Moscow GSP-7, Russian Federation Tel: +7 495 719 3001
JOINT VENTURE PARTNERS: Gazprom Transgaz Moscow, Gazprom UGS
PROJECT SCOPE:The Kasimovskoye UGS Voskresensk CS pipeline, which began construction in 2005,
connects the Kasimovskoye underground gas storage (UGS) to the Voskresensk compressor station (CS). The
pipeline includes two compressor stations located at Tuma and Voskresensk and one gas metering station at
Kasimov. The project includes a total of 108 rivers, streams, railways and highway crossings during construction
and the trunkline will provide highly reliable and uninterrupted gas supply to Moscow and its suburbs.
PROJECT UPDATE: Commissioning occurred on the trunkline in October.
PIPELINE LENGTH: 204 km
PIPELINE CAPACITY:95 Bcf/a of gas when fully operational.
COMPLETION DATE: The pipeline has been commissioned with a ceremony marking the occasion held in
Voskresensk District, Moscow Oblast on 23 October, 2009.
Shandong Natural Gas Pipeline NetworkPROPONENT: China National Petroleum Corporation
(CNPC), 9 Dongzhimen North Street, Dongcheng District,
Beijing 100007, P.R. China. Tel: +86 10 6209 4114
JOINT VENTURE PARTNER:Shandong Natural Gas Pipeline
Network Company
PROJECT SCOPE: The network will enable CNPC to
transport gas from central Shandong to cities including
coastal Qingdao and Weihai in the east, and tie in to the
Shaan Jing Gas Pipeline and the Second West East Gas
Pipeline via the Ji Ning Pipeline and Taian branch of the
Shandong Pipeline.
PROJECT UPDATE:Construction has commenced on the
Taian Weihai section of the pipeline network.
PIPELINE LENGTH: 1,067 km of pipeline system,
consisting of one trunk line and six branch lines.
PIPELINE CAPACITY: 388 Bcf/a of gas when fully
operational.
EXPECTED COMPLETION DATE:Late 2010.
MEDGAZ PipelinePROPONENT: MEDGAZ, Muelle de Poniente, Puerto de Almera,
04002 Almera, Spain Tel: +34 950 182 900
JOINT VENTURE PARTNERS: MEDGAZ is a consortium of fiveinternational companies: SONATRACH, CEPSA, IBERDROLA,ENDESA and GDF SUEZ.PROJECT SCOPE:The Medgaz Pipeline is a subsea gaspipeline that runs under the Mediterranean Sea from Beni Safon the Algerian coast up to l andfall on the Spanish coast ofAlmera. The pipeline is a strategic project for Algeria, Spain,and the rest of Europe, supplying natural gas directly fromAlgeria, without requiring transit through third countries.Saipem was contracted to construct the subsea infrastructure.PROJECT UPDATE:Saipem has completed subsea pipelayoperations, with the tie-in completed 1.6 km off the Algeriancoast. Hydrostatic tests are expected to be completed on thepipeline in March 2010.PIPELINE LENGTH: 210 kmPIPELINE C APACITY:282 Bcf/a of gas when fully operational.EXPECTED COMPLETION DATE:June 2010
PLMSenior Vice President AnthonyJ. Fernandez.
Thenew look Statoil.
PIPES AND PEOPLE
Fayetteville Express PipelinePROPONENT:Fayetteville Express Pipeline L.L.C, 3250 Lacey
Road, 7thFloor, Downers Grove, Illinois 60515, USA.
Tel: +1 630 725 3070
PARTNERS:Fayetteville Express Pipeline LLC is a joint
venture between Kinder Morgan Energy Partners and Energy
Transfer Partners.
PROJECT SCOPE: The pipeline will originate in Conway
County, Arkansas, and continue eastward through White
County, Arkansas, and terminate at an interconnect with
Trunkline Gas Company in Panola County, Mississippi. The
project will parallel existing pipeline or electric transmission
right-of-ways where possible to minimise impact to the
environment, communities and landowners.
PROJECT UPDATE:An application has been lodged with
the Federal Energy Regulation Commission and approval
is expected by the end of 2009. Construction contracts
are currently being negotiated and it is anticipated that
construction will commence in March 2010.
PIPELINE LENGTH:298 km
PIPELINE C APACITY:The pipeline will have an initial
capacity of 2 Bcf/d of gas.
EXPECTED COMPLETION DATE:Early 2011
Pipes & People
RosensMyles Young, Chris YoxallandNeil Pain.
7/21/2019 PIN 2009-12
11/37
16 PIPELINES INTERNATIONAL | DECEMBER 2009 PIPELINES INTERNATIONAL | DECEMBER 2009 17
Enags has developed and operated
natural gas transmission pipelines
in Spain since 1972. In 2000, the
company was appointed technical manager
of Spains gas system in accordance with the
Royal Decree-Law 6/2000, and this year the
company has been designated the operator
of the transmission system for Spains
high-pressure gas network under the Royal
Decree-Law 6/2009.
Today, Enags main activities include
natural gas transportation, regasification
and storage. The company transports gas
through over 9,000 km of high-pressure gas
pipeline and owns three regasification plants
located at Barcelona, Cartagena and Huelva,
as well as a 25 per cent interest in the Baha
de Bizkaia Gas Regasification Plant in Bilbao.
The company continues to develop its
transmission pipeline network and natural
gas assets in Spain, as well as promote the
development of a pan-European pipeline
network to ensure greater security of natural
gas to Europe.
Recent pipeline projectsEnags recently completed the
500 million euro ($US748 million)
Peninsula Baleares Pipeline project. The
company says that the project is a very
complex and important subsea pipeline
system that connects the Iberian Peninsula
with the Balearic Islands.
The project consists of three
components: a 65 km pipeline between
Montesa and Denia, the 267 km Denia
Ibiza Mallorca subsea pipeline, and a
compressor station located at Denia.
Enags says that only eight pipelay
vessels in the world specialise in this type
of project, which included installing pipe at
depths as deep as 997 m.
Operator of Spains natural gas pipeline system Enags continues to develop its transmission pipelinenetwork, recently completing the complex Peninsula Baleares Pipeline project. Here, the companytalks about the project and its plans for future pipeline expansions.
The company used the Castoro Sei
vessel and an auxili ary fleet of s ix boats
to complete the project. Approximately
22,500 pipes were used to construct the
underwater section of the pipeline.
More than 500 people were employed
to construct the pipeline, not including the
500 who worked on the Castoro Seipipelay
vessel.
"To date, this has been one of the mostcomplex pipeline projects constructed
as part of the Spanish Gas System," a
company spokesperson says.
Work began on the project in December
2007 and was completed in September
this year.
Enags says that the pipeline system
will bring important benefits to the
Islands.
Besides transporting natural gas for
distribution to residents, the project allows
the supply of natural gas to power plants
on the Islands, increasing the uptake of
natural gas in the area.
The pipeline gives Baleares energy
security as it connects the Islands directly
with the Spanish Gas System, an Enags
spokesperson said.
Enags also recently completed
construction on the 292 km Almera
Chinchilla Pipeline, which was built to
connect the Spanish Gas System with
the Medgaz Pipeline currently under
construction. The Medgaz Pipeline is a
strategic project for Algeria, Spain, and the
rest of Europe, supplying natural gas directlyfrom Algeria, without requiring transit
through third countries.
The 300 million euro ($US448.7 million)
project was constructed in two sections a
42 inch diameter, 122 km pipeline between
Almera and Lorca, and a 42 inch diameter,
170 km pipeline between Lorca and
Chinchilla.
The importance of gas storage andregasification facilities
Enags has been investing in storage and
regasification facilities since the company
first began. This year, the Barcelona
Regasification Plant is celebrating its 40 th
year of operations.
In September this year, Enags signed
a contract for the purchase of a 25 per cent
interest in a regasification plant at Bilbao.
The company also owns an underground
natural gas storage facility at Serrablo.
The company is currently working on
the construction of its fourth regasification
plant at El Musel Port in Gijn in the north of
Spain, and another underground gas storage
at Yela, Guadalajara.
Regasification plants give flexibility
to the gas system...reinforcing the security
of natural gas supply for Spain, says a
company spokesperson.
The company says that it will continue
to construct regasification plants and
underground storage facilities as necessary
to increase storage capacity.
Future pipeline projects:international connections
Enags says that construction of
international pipeline connections is
essential for a secure natural gas supply for
Europe. Spain has one of the most diverse
natural gas supply portfolios in the world,
and last year received natural gas from ten
different countries.
International connections are strategic
investments and essential to continue
guaranteeing gas system security, says an
Enags spokesperson.
There are currently two pipeline
connections between France and Spain
the 2.7 billion cubic metre per annum
(Bcm/a) Larrau Pipeline, and the 0.2 Bcm/a
Irun Pipeline.
Enags is part of the European Union
organisation, the High Level Group of the
South West Regional Energy Market. The
working group aims to:
Double the current capacity of the
Larrau Pipeline from 2.7 Bcm/a to
5.2 Bcm/a via looping and additional
compression. The project is expected toreach completion in 2013;
Increase the capacity of the Euskadour
Pipeline from 0.12 Bcm/a by 2013; and,
Construct the 190 km MidCat Pipeline,
which will run along the Mediterranean
coast and have a capacity of 7.5 Bcm/a.
The project is planned for completion
in 2015.
Having a pan-European gas network
is essential to have a real European natural
gas market. It is necessary to have a
network connecting Europe from north to
south, making it possible that in case of
any supply crisis, natural gas can circulate
through Europe in both directions, an
Enags spokesperson said.
MEET THE COMPANYMEET THE COMPANY
Enags: expanding pipelinesin Europe
The Peninsula pipeline during pipelay works.
L ow eri ng -i n th e P en in su la pip el in e. E na g s h ea dq ua rt er s i n M ad ri d.
Balearic Pipeline construction.
7/21/2019 PIN 2009-12
12/37
18 PIPELINES INTERNATIONAL | DECEMBER 2009 PIPELINES INTERNATIONAL | DECEMBER 2009 19
The United States of America boasts well established oil and natural gas pipeline systems, which arecontinuing to grow with the proposal and construction of more pipelines across the country. PipelinesInternationaltakes a look at some of the major projects in the pipeline.
Southeast regionKinder Morgan Energy Partners and
Energy Transfer Partners began service on
the Midcontinent Express Pipeline (MEP)
in August this year. The MEP consists of a
single pipeline originating near the town of
Bennington in Bryan County, Oklahoma, and
terminating with an interconnection into the
Transcontinental Gas Pipeline at Transcos
compressor station near the town of Butler in
Choctaw County, Alabama.
The pipeline is comprised of
approximately 48 km of 30 inch pipe, 442 km
of 42 inch pipe and 317 km of 36 inch pipe.
The MEP also has two compressor stations.
One station is located near Paris in Lamar
County, Texas, and the other near Perryville
in Union Parish, Louisiana.
The original capacity of the pipelineis being expanded through the addition of
incremental compression. When completed
in 2010, MEP will have capacity of 1.8 Bcf/d
in Zone 1 and 1.2 Bcf/d in Zone 2.
Florida Gas Transmission is proposing
to expand its natural gas pipeline system to
meet the growing energy needs of the Gulf
Coast and Florida. The company operates
an 8,046 km pipeline system, which has the
capacity to deliver 2.3 Bcf/d of natural gas to
the Florida peninsula.
The Phase VIII Expansion Projectwill
consist of approximately 777 km of multi-
diameter pipeline in Alabama, Mississippi,
and Florida, with approximately 587 km
built parallel to existing pipelines. One new
compressor station will be built in Highlands
County, Florida. The project will provide an
annual average of 798 million cubic feet per
day (MMcf/d) of additional firm transportation
capacity. The project is expected to be
completed and in service in 2011.
In 2007, El Paso Corporation placed
Phase 1 of its Cypress Pipelineproject into
service. The pipeline is an expansion of the
Southern Natural Gas (SNG) Pipeline,and provides an incremental 220 MMcf/d
of takeaway capacity from the companys
LNG facility near Savannah, Georgia. The
268 km pipeline extends the SNG system
to interconnect with the Florida Gas
Transmission system near Jacksonville,
Florida.
Phase 2 of the project was placed
into service in 2008. During this phase.
compression facilities were installed to add
an additional 116 MMcf/d of capacity to
the pipeline. Phase 3 of the project, which
is scheduled to be in-service by 2010, will
add an incremental 164 MMcf/d through
additional compression.
ETC Tiger Pipeline Company is proposing
to construct an interstate natural gas
pipeline to provide takeaway capacity
from the East Texas Carthage Hub area and
the Haynesville Shale play. The 289 km,
42 inch diameter Tiger Pipelinewill begin
near Carthage, Texas, and extend to the
Perryville, Louisiana area.
The project will have a capacity of 2
Bcf/d and is expected to begin operation
in the first half of 2011. Four compressor
stations have been planned for the pipeline.
The majority of the pipeline is to be
constructed within the right-of-way of the
existing 276 km CenterPoint Carthage to
Perryville Pipeline and Gulf Souths 389 km
East Texas to Mississippi Pipeline.
Enbridge has conducted an open
season for the proposed 523 km i nterstate
LaCrosse Pipeline, which would run
from the Carthage Hub in Texas to aninterconnection with the SNG Pipeline in
Washington Parish, Louisiana. The pipeline
will be designed to provide an outlet f or
increasing supplies coming out of the
Haynesville shale region. The pipeline is
scheduled for completion in 2013.
Midwest regionEnbridge has recently completed
construction on the Alberta Clipper
Pipelineto transport oil between Hardisty,
Alberta, Canada, and Superior, Wisconsin.
This 1,607 km , 36 inch diameter pipeline
is expected to be in service by mid-2010,
complementing the recently completed
Southern Access Project as crude oil supplies
from Western Canada continue to increase.
Initial capacity will be 450,000 barrels per
day (bbl/d), with an ultimate capacity of up
to 800,000 bbl/d.
Enbridge is expected to complete
construction of itsSouthern Lights
Projectby the end of 2009. The project will
transport oil from Canada to markets in the
US Midwest. It involves the construction of
new pipeline and the use of some segments
of existing pipeline on which the flow
direction has been reversed. The 20 inch
diameter pipeline was constructed at the
same time as and along the Alberta Clipper
line.
Enbridge is progressing the Southern
Access Extensionproject. The project
extends the companys Lakehead System
from the Flanagan Terminal near Pontiac,
Illinois, south to a petroleum transportationhub in Patoka, Illinois.
Stage 1 began operations in 2008 and
included 516 km of new pipeline along
the Lakehead System in Wisconsin and
the construction of additional pump
stations. Stage 2 involved the construction
of approximately 214 km of pipeline from
Enbridges Delavan pumping station near
Whitewater, Wisconsin, to the Flanagan
terminal. This stage began operation earlier
this year.
Stage 3 will see the system extend from
the Flanagan, Illinois, to Patoka, Illinois.
The cities are approximately 400 km apart.
The pipeline system will be constructed in
Northeast regionTennessee Gas Pipeline Company
(TGPC), a subsidiary of El Paso Corporation,
plans to increase the capacity of its
300 Line to transport new natural gassupplies to serve the growing demand in the
northeastern US.
The300 Line Expansion Project
involves the installation of seven looping
segments in Pennsylvania and New
Jersey totalling approximately 205 km of
30 inch pipeline, the installation of two
new compressor stations to be located in
northwestern Pennsylvania, and upgrades at
seven existing compressor stations.
Upon completion, TGPC expects that
the project will increase natural gas delivery
capacity in the region by approximately
3.4 billion cubic feet per day (Bcf/d). The
project is planned to be in service by
November 2011.
Spectra Energy has proposed the
HubLine/East to West Expansion Project,
which will be an expansion of the companys
Algonquin Pipeline System. The 1,800 km
Algonquin Natural Gas TransmissionSystem, located in New England, transports
2.2 Bcf/d of gas. The pipeline connects to the
Texas Eastern Transmission System and the
Maritimes & Northeast Pipeline.
The expansion project will involve a
total of 74 km of multi-diameter pipeline
and associated support facilities. Of this,
20 km of new pipeline will be located in
Massachusetts with 53 km of upgrades to
existing pipeline in Massachusetts and
Connecticut. The project is expected to be
completed in November 2010.
Dominion Transmission, Dominion
Resources natural gas transmission
and storage subsidiary, is proposing the
Appalachian Gateway Projectto meet
demand for natural gas in the mid-Atlantic
and northeastern US.
The project includes the construction of
approximately 177 km of pipeline between
20 and 30 inches in diameter to run betweenWest Virginia and Pennsylvania, as well
as four new gas compressor stations.
Construction is expected to start in 2011,
with transportation services to begin by
September 2012.
The pipeline will deliver natural
gas to Spectra Energys 14,000 km
Texas Eastern Transmission Pipeline
Systemat Dominions Oakford Station in
Delmont, Pennsylvania. The Texas Eastern
Transmission Pipeline connects Texas and
the Gulf Coast with markets in the mid-
Atlantic and northeastern US. The 6.7 Bcf/d
capacity pipeline connects the Algonquin Gas
Transmission Pipeline with Spectra Energys
430 km East Tennessee Natural Gas Pipeline.
REGION REVIEW
Pipeline development inthe land of the freeBy BJ Lowe, Clarion, Houston, USA and Lyndsie Mewett, Associate Editor
REGION REVIEW
CONTINUED ON PAGE 20
Construction works at Denbury Resources' Green Pipeline.A map of the Florida Gas Transmission Pipeline.
7/21/2019 PIN 2009-12
13/37
PIPELINES INTERNATIONAL | DECEMBER 2009 2120 PIPELINES INTERNATIONAL | DECEMBER 2009
2010 and begin operation later that year or
by early 2011.
The 5,600 km Lakehead System was
constructed in 1949 and is the worlds
largest crude oil and liquids pipeline
system, bringing crude oil from Western
Canada to the US.
Vector Pipeline and Vector Pipeline
Partnerships have launched a binding
open season to secure shipper interest in
a third expansion of the 550 km Vector
Pipelines System, which transports
natural gas between Joliet, Illinois, and the
storage complex at Dawn, Ontario, Canada.
The additional expansion proposes to
add long-haul capacity of up to 115M Mcf/d
by adding two new compressors andupgrades to the US portion of the system.
The expansion could also include
incremental short-haul capacity by adding
a loop to the US and/or Canadian portion
of the pipeline system. The project is
expected to be complete by November 2011.
The Vector Pipeline System, constructed
in 2000, has already undergone two
expansion projects. The first involved
the installation of compressor stations
at Joliet, Illinois, and Washington,
Michigan. The second expansion was
completed in October 2009 and involved
the construction of a compressor station at
Athens, Michigan, increasing the nominal
capacity of the pipeline from 1.2 Bcf/d to
approximately 1.3 Bcf/d.
Southwest regionKinder Morgan Energy Partners
and Energy Transfer Partners 298 km
Fayetteville Express Pipeline has been
proposed to run from Conway County
Arkansas, via White County, to an
interconnect on the 5,632 km Trunkline
Pipeline, located in Panola County,Mississippi.
Willbros Group has been awarded a
contract to construct spreads three and four
of the pipeline, which includes laying 193 km
of 42 inch diameter pipeline to parallelexisting utility corridors in the region,
beginning near Bald Knob, Arkansas, and
ending at the Trunkline Gas Company
interconnection. Spreads one and two of the
pipeline are yet to be awarded.
Construction of the pipeline is expected
to commence in March 2010 with the
pipeline to be in service by January 2011.
In addition, Kinder Morgan and
Copano Energy have entered into a letter
of intent to construct, as a first phase,
an approximately 35 km, 24 inch natural
gas gathering pipeline. The natural gas
pipeline will originate in LaSalle County
and terminate in Duval County, Texas, and
will have an initial capacity of 350 MMcf/d.
The pipeline is expected to be completed in
mid-2010.
Enterprise Products Partners and
Duncan Energy Partners are planning
to increase the capacity of the recently
announced Haynesville Extension Project
from 1.42.1 Bcf/d. As a result, Enterprise
and Duncan Energy placed an order
increasing the size of the 249 km pipeline
extension of their jointly-owned AcadianGas intrastate pipeline i nto Northwest
Louisiana to 42 inches in diameter.
The project is expected to be complete by
September 2011. The Haynesville Extension
will intersect with nine interstate pipeline
systems.
Central regionThe Rockies Express Pipeline(REX)
runs from the Meeker Hub in Rio Blanco
County, Colorado, to Audrain County,
Missouri, and Warren County, Ohio. The
531 km section f rom Meeker to the Cheyenne
Hub was placed in service in February 2007.
The completion of REX-West in May 2008,
added 1,147 km of 42 inch diameter pipeline,
which runs from the Cheyenne Hub in
Weld County, Colorado, to Audrain County,
Missouri.
The 1,027 km REX-East Pipeline section
completed commissioning in November
this year. REX-East is the final segment of
the REX Pipeline, and runs from Audrain
County, Missouri, to the Lebanon Hub in
Warren County, Ohio.
Following the completion of REX-East, the
pipeline has a capacity of 1.8 Bcf/d of gas.
The pipeline is a joint venture between
Kinder Morgan Partners, Sempra Pipelines
and Storage, and ConocoPhillips.
TransCanada is currently constructing
the 3,456 km Keystone Pipeline project,which combines both the new construction
of pipeline and the conversion of an existing
pipeline from natural gas to oil service.Approximately 2,219 km of new
pipeline is to be constructed in the US. The
Canadian portion of the project includes
the construction of approximately 373 km
of new pipeline and the conversion
of approximately 864 km of existing
TransCanada pipeline from natural gas to
crude oil transmission. It is expected that
the project will be complete by 2012.
In addition, the Federal Energy
Regulatory Commission (FERC) has
prepared a draft environmental impact
statement for TransCanadas proposed
Bison Pipeline.
The project includes approximately
486 km of 30 inch diameter natural gas
transmission pipeline extending northeast
from Wyoming through Montana to North
Dakota. TransCanada has also proposed
one compressor station at Hettinger County,
North Dakota.
The pipeline is designed to have a
capacity of approximately 477 MMcf/d of
gas, but will be expandable to 1Bcf/d.
TransCanada has said that future
development plans for the pipeline includethe expansion and extension of the Bison
Pipeline into the Rockies Basin.
Construction is expected to begin on
the pipeline in 2010, with the pipeline to be
operational in November of that year.
Colorado Interstate Gas Company (CIG),
a subsidiary of El Paso, is building the Raton
Expansion Projectto serve increasing
demands for Rocky Mountain natural gas
supplies. The Raton Expansion Project
involves the installation of approximately
188 km of 16 inch pipeline in Las Animas,
Huerfano, Pueblo and El Paso counties,
Colorado.
The Raton 2010 Expansion Project will
start in southern Las Animas County and
will terminate in southern El Paso Countyat an interconnection with CIGs pipeline
system. This expansion will enable gas to be
transported to CIGs mainline for ultimate
delivery to the Cheyenne Hub in northern
Colorado for delivery to major national
markets.
CIG had hoped to receive FERC
authorisation for the project by October
2009, with a proposed in-service date in May
2010. The authorisation is still pending.
Enbridge has proposed the North
Dakota System Expansion Phase 6 project
to bring its North Dakota Systemexpansion
to 161,000 bbl/d of oil by early 2010. The
expansion will involve upgrades to existing
pump station sites.
The North Dakota System consists of
531 km of crude oil gathering and 998 km
of interstate transmission pipeline. It
delivers oil from North Dakota and Motana
to Minnesota, where it connects with the
Lakehead System and the third party
Minnesota Pipeline.
Alliance Pipeline and Questar Overthrust
Pipeline Company have jointly proposed the
1,738 km, 42 inch diameter Rockies AlliancePipeline(RAP) to connect the Rocky
Mountain Region to the Chicago market hub.
The project will take advantage
of existing Overthrust and Alliance
infrastructure. The companies are currently
undergoing a second open season to
evaluate the potential gas capacity
expansion of the pipeline.
The pipeline will originate from
Wamsutter, Wyoming, where Questars
Overthrust Pipelinewill be expanded from
the Opal and Meeker receipt hubs to meet the
need for additional capacity. During an open
season, Questar Overthrust Pipeline received
interest for approximately 1 Bcf/d of new
pipeline capacity for delivery into RAP.
Upon in-service of the proposed
project, RAP will initially provide 1.3 Bcf/d
of transportation capacity. The pipeline is
expected to be commence construction in
2012 and completed by 2013.
Questars Overthrust Pipelineis a
270 km, 36 inch diameter pipeline, located in
southwestern Wyoming. The 141 km pipeline
section from Whitney Canyon to Kanda
comprises the western-most segment of the
701 km Trailbalzer Pipelinesystem. The
128 km section from Kanda to Wamsutter,
completed in 2007, makes up the western
segment of the REX Pipeline.
The Questar Overthrust Pipeline
expansion would run west from a
compressor station near Rock Springs to
Black Fork, Wyoming, and parallel an
existing Questar pipeline that runs from
Wamsutter to Blacks Fork and on to Opal.
The 69 km, 36 inch diameter pipeline
would cost approximately $US94.3 million to
construct and have a capacity of 800 MMcf/d
of gas. The pipeline is expected to tie into El
Paso Corporations proposed Ruby Pipeline.The Ruby Pipeline will connect natural
gas reserves in the Rocky Mountain region
with markets the western US. The project will
involve approximately 1,086 km of 42 inch
diameter pipeline beginning at the Opal Hub
in Wyoming and terminating at interconnects
near Malin, Oregon.
The project will have an initial design
capacity of up to 1.5 Bcf/d of gas and f our
compressor stations will be constructed:
one near the Opal Hub in southwestern
Wyoming; one south of Curlew Junction,
Utah; one at the mid-point of the project,
north of Elko, Nevada; and, one in
northwestern Nevada.
REGION REVIEWREGION REVIEW
CARBON DIOXIDE PIPELINES
Denbury Resources recently began a feasibility study into constructing an 804 km and1,126 km long carbon dioxide pipeline project connecting proposed gasification plantsin the Midwest to existing pipeline infrastructure in Mississippi and Louisiana.Denbury has said that it expects the pipelines to take four to five years to complete.The study comes as two proposed Midwestern gasification plants, with whichDenbury has carbon dioxide purchase contracts, have been granted approval to theterm sheet negotiation phase under the US Department of Energy loan guaranteeprogramme.
A third proposed gasification plant has also been selected by the loan guaranteeprogramme to be built along the Gulf Coast of Mississippi. Denbury plans tocommission a study for a 177 km pipeline that could connect the plant to the existingFree State Pipeline.
CONTINUED FROM PAGE 19
CONTINUED ON PAGE 22
Enbridge is expected to complete construction of its
Southern Lights Project by the end of 2009. The project
will transport oil from Canada to markets in the US
Midwest. It involves the construction of new pipeline and
the use of some segments of existing pipeline on which
the flow direction has been reversed.
Welded pipe during the construction of Alberta Clipper.
Pipestacking inpreparationfor the Vector
Pipeline Systemconstruction.
7/21/2019 PIN 2009-12
14/37
The Rockies Express Pipeline, or REX, crosses eight states and travels approximately 2,735 km.Beginning in Colorado and ending in eastern Ohio, the REX project is one of the largest natural gaspipelines constructed in North America over the last 25 years.
Kinder Morgan Energy Partners;
Sempra Pipelines & Storage, a unit of
Sempra Energy; and, ConocoPhillips
jointly developed the Rockies Express
(REX) Pipeline project. The pipeline was
constructed in three phases:
The 528 km REX-Entrega section across
Colorado;
REX-West, which runs 1,147 km from
Colorado to eastern Missouri; and,
The recently completed REX-East portion,
which stretches from eastern Missouri to
eastern Ohio.
The REX-West section was completed in
early 2008, after receiving Federal Energy
Regulatory Commission authorisation in
April 2007. REX-East finalised construction
and was placed into service on 12 November
2009. Following the completion of REX-East,
the pipeline has the capability to transport
up to 1.8 billion cubic feet (Bcf) of natural
gas per day.
Each region along the 2,735 km pipeline
route offered unique challenges for the
construction of the pipeline. The majority
of the route passed through mountainous
terrain starting in the Rocky Mountains
and extending to the Appalachian Region
which brought with it significant technical
challenges.
The REX-Entrega and REX-West pipeline
routes cross the Rocky Mountains and
much of the REX-East route also covers
mountainous terrain, which presented the
projects crews with a variety of construction
issues. However, the crew successfully
managed to move the project forward
without delay.
Most of the REX Pipeline was constructed
along existing pipeline corridors. Much
of the terrain was already level and ready
for the pipe stringing and trenching in
preparation for pipelaying, Mr Fore said,
however construction crews faced a variety of
landscape and geographical challenges as the
pipeline construction progressed eastward
along the route into the Appalachian Region
on the REX-East Pipeline route.
Welding to scheduleNew technology was employed to
ensure that pipeline construction proceeded
smoothly.
REX was designed with a construction
schedule that favoured automatic field
welding. The automatic welding equipment
provided by CRC Evans of Houston, Texas,
and RMS Welding Systems of Nisku, Alberta
was a large part of how the construction
proceeded in such an efficient fashion.
The automatic welding systems enabled
a very high level of productivity that
exceeded 100 welds per day for the mainline
pipelay. Additional project pace was gained
by the establishment of mini pipe gangs,
which were capable of laying up to 20 joints
of pipe per day. The mini gangs were ideal to
lay pipe in the rough terrain encountered on
the project.
The welding work was completed using
cutting edge components.
Tie-in welds were made with Hobart
welding wire, Trimark Flux Core and Fab
Shield X80, which is a special wire produced
to weld the high strength X80 pipe used.
Once the welding was completed, each joint
was checked carefully by the onsite scanning
technology. Weld integrity was ensured by
using ultrasonic weld inspection systems
to scan 100 per cent of the field welds for
defects.
The system used was an analog to digital
conversion unit, but an innovative phased
array weld inspection system, provided by
UT Quality of Texas, was also used on the
pipeline. The totally digital system was first
qualified in the US for the REX-West project.
By allowing the system to be less complex
and highly accurate in weld interpretation,
REX saw more robust results.
REX Director of Community Relations
Allen Fore said The REX Pipeline was
constructed using the latest technology
in all aspects of the construction process,
but the biggest asset was the skilled and
experienced workers employed on the
project.
The pipeline construction process is
often compared to a sort of moving assembly
line and during peak construction efforts,
there were thousands of construction
workers on the pipeline spread.
The innovative technology employed
ensured that the pipeline was built in the
safest and most efficient way possible and
will maintain the integrity of the pipeline in
the future, said Mr Fore.
REX appeal:pipeline construction in the Rockies
REGION REVIEW
Western regionWilliams subsidiary Northwest Pipeline
has proposed to construct the 30 inch diameter,
192 km Blue Bridge Pipelineproject.
The project involves six pipeline loops
running parallel to Northwests existing
26 inch mainline along the Columbia
River Gorge, Washington. Construction is
set to begin in the first half of 2012, and
commercial service to launch in the second
half of 2012.
The proposed Palomar Gas
Transmission Pipeline is a new interstate
natural gas pipeline that will provide
additional energy infrastructure to serve
Oregon, the Pacific Northwest, and other
western states. Palomar is a joint venture
between TransCanada and NW Natural.The 36 inch diameter pipeline will be
approximately 354 km long. The proposed
Palomar project is seeking a certificate from
the FERC for permission to construct and
operate the pipeline.
Subsidiaries of Williams, PG&E
Corporation and Fort Chicago Energy
Partners, have agreed to jointly pursue
construction of a LNG import terminal
(Jordan Cove LNG), to be located in Coos
Country, Oregon, and a interstate natural
gas transmission system (Pacific Connector).
This project will increase the supply of
natural gas for the Pacific Northwest,
northern California and northern Nevada.
The Pacific Connector Pipelineproject
is a 370 km, 36 inch diameter pipelinedesigned to transport up to 1 Bcf/d of natural
gas from the proposed Jordan Cove LNG
terminal to markets in the region. The Pacific
Connector project includes interconnects to
Williams 6,276 km Northwest Pipeline, the
386 km Tuscarora Gas Transmission system,
and Gas Transmission Northwests system,
all located in Oregon.
Alaskan proposalsThere are currently two competing large
diameter pipeline projects proposed that
would link Alaskas North Slope gas reserves
to markets in Canada and the US.
The proposed Denali Pipelineproject
consists of a gas treatment plant on the North
Slope, an approximately 3,219 km long pipelineto Alberta, Canada, and if required, a 2,414 km
long pipeline from Alberta to Chicago at a
current estimated cost of $US30 billion.
The proposed TransCanadaAlaska
Pipeline project would include a gas
treatment plant to be built at Prudhoe Bay,
a 2,736 km long pipeline from North Slope
Alaska through Yukon and northeastern
British Columbia to the British Columbia/
Alberta border near Boundary Lake,
and would include new and existing
infrastructure in Alberta.
The pipeline projects require a certificate
of public convenience and necessity to be
granted by the FERC in order to commence
construction and operation activities.
CONTINUED FROM PAGE 21
REGION REVIEW
22 PIPELINES INTERNATIONAL | DECEMBER 2009 PIPELINES INTERNATIONAL | DECEMBER 2009 23
The REX Pipeline before lowering in.
Above:Overland Pass Natural Gas Pipelinemap.Constructionworks on theTexas Eastern TransmissionPipelineSystem.
7/21/2019 PIN 2009-12
15/37
24 PIPELINES INTERNATIONAL | DECEMBER 2009 PIPELINES INTERNATIONAL | DECEMBER 2009 25
Steel transmission pipelines going through mountain areas often face significant risks during theirconstruction and service life. One of the biggest challenges is to protect the pipe and its externalcoatings against mechanical damage from impact and penetration.
When installing and operating
transmission pipelines in
mountain regions, one has to
account for specific risks in order to mitigate
potential lost time, increased costs, and
accidents with human and economic costs.
Climate is an important consideration
during both pipeline construction and
operation in mountain areas. Some seasonscan be harsh, with heavy snowfall or rain,
and extreme temperatures and winds,
restricting the access to the right-of-way
(RoW) during construction. In addition,
weather patterns are usually rapidly
changing quick temperature changes
and flash rains which can delay the
construction of the pipelines. During pipeline
operation, pipelines in permafrost regions
face stability issues.
Geography is another significant risk
factor with two sub-categories topography
and geology. Mountain areas can have
a challenging topography such as steep
slopes, river and lake crossings. Geology can
also raise issues during both construction
and operation, with companies faced with
hard rock, wet or frozen ground conditions,
earthquake and fault zones, erosion and
landslides, karst and sinkholes.
Mountains often include environmentally
sensitive and protected areas, such as
national parks. Pipeline projects have to
be designed, installed and operated with
a minimum footprint on flora and fauna,
usually translated in reduced RoW and
temporary workspace. Minimising any
risk of accidental harmful discharge or
contamination is also important.Supplying some of the required materials
such as sand for padding, and safely
disposing of surplus materials can be difficult
during the construction phase of a mountain
pipeline.
Finally, building and operating pipelines
in mountain regions can be dangerous for the
people involved. Clear safety standards and
operating procedures have to be in place to
avoid accidents.
In order to address the above-mentioned
risk factors, the pipeline industry is
dedicating a lot of effort to prepare and
standardise the construction and operation
of pipelines in mountain regions.
The International Pipeline and
Offshore Contractors Association (IPLOCA)
presents ten different pipeline construction
environments in its recently released
recommended construction practices for
onshore pipelines, Onshore Pipelines: The
Road to Success. Three of these environments
directly describe mountain areas the
side slope, ridge and rock RoW scenarios.
Another two refer to arctic conditions and
the environmentally sensitive area often
encountered in mountain terrain. In all the
scenarios, one of the most efficient ways of
mitigating the pipeline construction andoperating risks is to protect the steel pipe
against mechanical damage from impact and
penetration.
The need for supplementarymechanical protection
Mechanical damage to the pipe can
occur during all phases of the pipeline
construction and operation, for example
during transportation, handling (loading in
and out), storage, lowering-in, backfilling,
and during pipelines service life. Impacts
and penetration damage can be caused by
many factors:
Other pipes or pipe handling equipment;
Lowering-in; and,
Rocks in the trench bottom or impact
from the backfill material.
Steel pipe is impact resistant by itself and
some of the external coatings applied on steel
increase this basic mechanical protection.
However, in order to ensure an incident-free
service life for the pipeline, the steel pipe
and the anti-corrosion coating have to be
intact during construction and operation.
This cannot be guaranteed by the basic
mechanical protection of the steel and anti-
corrosion coatings. Therefore, the industry
has developed supplementary mechanical
protection systems that are aimed at reducing
or eliminating the risk of mechanical
damage.
As the industry uses a wide range of
supplementary mechanical protection
systems, this article will focus on the systems
that protect the entire diameter and length
of the pipe, and which are the most efficient
in protecting the pipe and its coating against
impact and penetration. Today, most pipelineprojects use the following supplementary
mechanical protection system: concrete
coatings, sand padding and select backfill
(mechanical padding), as well as non-woven
geotextiles and rockshield materials.
Mechanical protection systemsConcrete coatings for mechanical
protection have been developed during the
last 2530 years in North America, Australia
and Europe, and are usually applied in
specialised coating facilities.
Steel wire mesh reinforced concrete
coatings that are usually 2025 mm thick and
fibre-reinforced concrete coatings
(810 mm thick) are the two types of
mechanical protection concrete coatings.
Wire-mesh concrete coatings are applied
using a side-wrap process, while the fibre-
reinforced concrete coatings are applied
using a spraying process, without any
damage to the pipe and the pipe coating
during application.
The concrete coatings offer excellent
damage resistance minimum impact
resistance of 150 J for the fibre-reinforcedconcrete coatings and 450 J for the
wire-reinforced concrete coatings. The
mechanical protection concrete coatings
are fully bendable according to the industry
standards; do not need additional equipment
or manpower for installation; and, do not
have any usage limitations in terms of
terrain configuration, ground conditions or
climate. Concrete coatings are currently the
only supplementary mechanical protection
systems that protect steel pipe through all the
construction and service life phases from
transportation, handling and storage to
lowering-in, backfilling and long-term service
life.
Sand bedding and padding is still
the most frequently used supplementary
mechanical protection system. Sand is
usually supplied to the RoW, where it
is used in the trench to protect the pipeagainst impact and penetration from rocky
outcrops in the trench bottom or impacts
from rocks in the excavated trench material.
The sand layer usually has a thickness
of 2030 cm around the pipe and has a
minimum impact resistance of 300450 J.
Sand padding needs additional equipment
such as sand trucks, padding machines,
temporary work and storage space at the
RoW, as well as additional manpower and
materials. Additional costs are usually
incurred for the transportation and disposal
of the original trench material that becomes
surplus material after the use of sand. This
system protects