Piet Van Duppen K.U.Leuven and ISOLDE-CERN
on behalf of the EURISOL Project Office
• EURISOL Transition period 2009-2013
• MYRRHA and ISOL@MYRRHA
What is EURISOL?
LINAC: H, D, He and A/q=2 ions up to 1 A GeV
Up to 150 AMeV for 132Sn Multi-user capabilities
235U 3
3 x 100 kW targets (REX-ISOLDE, SPIRAL ~ few kW HIE-ISOLDE ~ 10kW, TRIUMF ~ 50 kW) 1 x 4 MW converter (fission) target (SPIRAL-2 ~ 200kW, SPES ~ 100 kW) 3 x post-accelerators: 150 A.MeV 132Sn for secondary fragmentation 1-5 A.MeV Coulomb barrier nuclear physics ~ 1 MeV nuclear astrophysics ~ keV ground states, solid-state physics, etc. Cost: 1.3 B€
EURISOL
• Design Study finished: ~400 person-yrs, ~ 33M€ - (documents/report available on www.eurisol.org)
The “Transition” Period (2010-2013)
• The EURISOL project office: Overall coordination of EURISOL related actions Yorick Blumenfeld (chair), Alberto Facco, Marek Lewitowicz, PVD • The EURISOL collaboration: MoU between all laboratories interested in EURISOL (in preparation)
- update/shape the physics case/instrumentation - perform further R&D for RIB production/acceleration - contact with funding and political bodies - EURISOL on the ESFRI list and EURISOL Preparatory Phase
• The EURISOL User Group and the EURISOL Network in ENSAR: - EURISOL User Group will federate scientific community and update physics case; elected executive committee: A. Bonaccorso, chair
- EURISOL Network focuses on R&D at current facilities and fund workshops and town meetings; 105 k€; leader Y. Blumenfeld
- Task1: R&D coordination (Y. Kadi) - Task 2: Physics & Instrumentation (A. Bonaccorso)
- Workshops/topical meetings – town meetings: - Catania 9-11 December 2009 – Nuclei in the r-process region (~40 part.) (http://www.df.unipi.it/~angela/top_all_19dic.pdf)
- Valencia 21-23 February 2011 – N=Z region (~70 part.) - Lisbon Fall 2012: town meeting and topical meeting on light nuclei - CERN, Geneva: June 27-28, 2011: EURISOL-NET on R&D coor. - 2013: topical meeting - 2014: Final town meeting
The “Transition” Period (2010-2013)
• The EURISOL work package in TIARA: - Define/Prepare R&D platforms for EURISOL (270 k€, S. Bousson – Orsay) • Requests to NuPNET: R&D through National Funding Agencies (see also S. Gales: NuPECC meeting Paris): - Three proposals submitted: Accelerators – Charge Breeding – Target-Ion Sources systems (requested 1.25 M€)
Test Infrastructure and Accelerator Research Area
The “Transition” Period (2010-2013)
Timescale for EURISOL • 2010-2013 : Transition period; contacts with funding agencies and political bodies
• 2013 : Application to be included in ESFRI list (support from NuPECC)
• 2013 : Call for preparatory phase
• 2014-2017 : EURISOL Preparatory Phase
• 2017-2019 : Preparation of TDR
• 2020-2025 : Construction
• 2025 : First Beam
2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026
REX-ISOLDE, SPIRAL, EXCYT, ALTO, JYFL, …
RIBs from 2nd generation ISOL facilities
EURISOL Collaboration
MoU
EURISOL Preparatory
Phase TDR Construction
+ Commissioning RIB
Timeline for European ISOL RIB facilities
Construction+ commissioning
HIE-ISOLDE SPES SPIRAL2
Adapted from M. Lewitowicz and P. Butler
2nd g
ener
atio
n IS
OL
faci
litie
s
Exis
ting
ISO
L fa
cilit
ies
ESFRI List
MYRRHA - Concept
Total investment (estimation 2009): 960 M€
Sustainable fission energy: Accelerator Driven System (ADS)
Fast neutron spectrum:
Health care: production of radioisotopes for nuclear medicine
Fundamental research: ISOL@MYRRHA
2019
On site assembly
2016-2018 Construction
of components & Civil engineering
2015 Tendering & Procurement
2020-2022
Commissioning
2023
Progressive start-up
2024-
Full exploitation
2010-2014 Front End
Engineering Design
The project MYRRHA
- supported by the Belgian government (March 2010) - on the ESFRI roadmap (Nov. 2010) - on the “European Sustainable Nuclear Industrial Initiative – ESNII” roadmap (Nov. 2010) - on the NuPECC roadmap (Dec. 2010)
MYRRHA Project Schedule
ISOL@MYRRHA Pre-Conceptual Design
11 ` L. Popescu, EURISOL topical meeting, Valencia 22/02/2011
Pure and intense RIBs
of ~50-60 keV
Low-resolution mass separator
RFQ cooler and buncher
High-resolution mass separator
Beam splitter
Ruggedized target: e.g. Ta, UC/C
Sustainable 1+ ion source:
ISOL@MYRRHA
protons: 2-4 mA, CW, 600 MeV
~ 100-200 µA,
~DC
MYRRHA 5 cell Elliptical 704 MHz
2 gap Spoke 352 MHz
100 MeV
200 MeV
17 MeV 600 MeV
Facility Characteristics
based on proven technology (largely based on experience at ISOLDE and TRIUMF)
can deliver: pure RIB: selective ionization, chemistry, M/DM > 10.000 intense RIB (x100 compared to the present ISOLDE ‘standard’ RIB) RIB of good ion optical quality optimal experimental conditions/lay-out/support (green-field facility!) extended beam times with stable operation
complementary to ISOL and In-Flight facilities
=> unique possibilities for experiments that: − need very high statistics − involve many time consuming systematic measurements − hunt for very rare events − have an inherent limited detection efficiency
ISOL@MYRRHA Project at SCK•CEN
• ISOL@MYRRHA is an integral part of the MYRRHA project Delivery of the proton beam by MYRRHA Support by ISOL@MYRRHA in house group at SCK•CEN
• Building an international users group Workshops on R&D for RIB production and the physics case (update)
• Search for national and international support: ISOL@MYRRHA consortium
• More information: http://isolmyrrha.sckcen.be
2020 Assembly
& Installation
2017-2019 Manufacturing
of components & construction
2016 Awarding
construction contracts
2021-2022 Commissioning
2012-2015 Front End
Engineering Design
2023 - Exploitation
2011 Pre-
Conceptual Design