PFP Demolition Briefing

May 2017

Page 2: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

2

PFP: Last Stop of Plutonium Production at Hanford

Employees working in glove boxes during plutonium production at PFP. PFP produced

approximately two-thirds of the nation’s plutonium stockpile.

Page 3: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

3

PFP: The Lay of the Land

236-Z Plutonium

Reclamation

Facility (PRF)

242-Z McCluskey

Room

234-5ZPlutonium

Finishing Plant

(PFP)

291-ZFan House,

Stack

Page 4: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

4

PFP Demolition Progression

PFP – August 2010

Page 5: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

5

PFP Demolition Progression

PFP – September 2016

Page 6: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

6

PFP Demolition Progression

PRF Demolition – November 2016

Page 7: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

7

PFP Demolition Progression

PRF Demolition – December 2016

Page 8: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

8

PFP Demolition Progression

PRF Demolition – February 2017

Page 9: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

9

PFP Demolition Progression

PRF Demolition – March 2017

Page 10: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

10

PFP Demolition Progression

PRF Demolition – April 2017

Page 11: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

11

PFP Demolition Progression

PRF Gallery Glove Boxes

Page 12: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

12

PFP Demolition Progression

PRF Gallery Glove Boxes

Page 13: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

13

PFP Demolition Progression

PRF Gallery Glove Boxes

Page 14: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

14

Hazards Removed/Mitigated before Demolition

Page 15: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

15

Hazards Removed/Mitigated before Demolition

Page 16: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

16

• Demolition complete of one of

four main buildings (242-Z)

• Demolition well underway on

PRF

• Proven robust hazard mitigation,

control and monitoring

• Crews redeployed to complete

demolition preparations

• Demolition to continue through

Summer 2017

Summary of Demolition Progress

Page 17: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

17

Hazard Mitigation: Summary

Beryllium Asbestos Radiological

Maintaining beryllium controls as

a conservative measure

Postings as necessary

Extensive fogging, water

suppression and fixative used

Fully characterized according to

Hanford Site Chronic Beryllium

Disease Prevention Program

(CBDPP)

Removed 32,527 of 36,694 ft2 of

asbestos insulation (4/17/17)

All friable (easily crushed)

asbestos removed

All transite (asbestos-containing)

panels to be removed prior to

demolition

Will be fully characterized

according to EPA demolition

standards (40 CFR 61.145) and

CHPRC guidance for demolition

(PRC-GD-EP-52776)

Source term removed or

prepared for removal during

demolition

Extensive fogging, water

suppression and fixative used

Boundaries modeled by PNNL

based on conditions

Will be fully characterized

according to sampling and

analysis plan

(DOE/RL-2004-29)

Air Monitoring for All Hazards

Page 18: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

18

Conservative Demolition Prerequisites

• Real time radiological

monitoring helps control

process

• Ground maintenance, fixatives

and fencing to avoid

contamination spread

• Expeditious packaging and

load out of contaminated debris

• Modeling dictates ready for

demolition criteria

• Fixatives and fogging to control

airborne hazards

• Water runoff management

Air monitoring Demo fence/silt fencing

Precision fogger at PFP

Page 19: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

19

Hazard Mitigation: Radiological

Air Monitoring for All Hazards

• The highest contaminated items removed as a unit before, or prepared for removal during, demolition

• Residual surface contamination controlled via fixative and/or epoxy prior to demolition

• Extensive fogging, water suppression and fixative used

• Boundaries modeled by Pacific Northwest National Lab based on radiological conditions and demolition methods

242-Z painted out

Painted out gallery glove box

Page 20: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

20

Site Map – Zones and Monitoring

Outer Fence/Laydown Area HCA/ARA

Radiological Buffer Area Contamination Area

Page 21: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

21

Extended Air Monitoring

Page 22: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

22

Environmental Air Sampling Locations Near PFP

Page 23: PFP Demolition Briefing - Hanford SitePFP Demolition Briefing May 2017. 2 PFP: Last Stop of Plutonium Production at Hanford Employees working in glove boxes during plutonium production

23

Demolition Sequence and Duration

1 Plutonium Reclamation Facility (236-Z)Nov. 2016-July

20173 Plutonium Finishing Plant (234-5Z)

June 2017-

Aug. 2017

2 Americium Recovery Facility (242-Z) Complete! 4 Ventilation Stack and Fan House (291-Z)June 2017-

July 2017

Timeline and Sequence