PETER VROLIJK        PROJECT MANAGER4240 kW (5766 HP)  LNG ‘DUAL’ FUELED  IWW  PUSH BOAT

KOOIMAN MARINE B.V.MEMBER OF

Page 2: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

VEERHAVEN X “ORKA” 

Sailing upstream with6 loaded barges approx

16.800 Tonnes(coal and ore)

Page 3: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Service routes ThyssenKrupp Veerhaven BV

Page 4: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

FUTURE PUSHERDESIGN CHALLENGE

• Performance and functionality:                          Not to be less than existing vessels of the fleet.• Overall fuel consumption: Less than existing vessels of the fleet.• Range: 4 round trips (=one week 24/7 sailing).• Bunker operations: Within 2 hours  once a week. • Environmental: Able to fulfill  ( at that time expected)

requirements of CCR4.  • Redundancy:      Independent of alternative fuel supply.• Draught:       Less than existing vessels         

of the fleet.Target draught: 1,60 m

Page 5: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Why ADN ?

Page 6: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Timeline• 2011‐2012 Future Pusher project• May 2012 Start Concept Design LNG fueled push boat• December 2012 Official presentation vertical tank concept to Lloyds R• January 2013 Introduction LNG project to Ministry I&E in The Hague• February 2013 Submission call for Ten T in LNG Master plan Rhine‐Main‐Danube• March 2013 Hazid study Lloyds ( TNO present at all meetings with Class)• April‐May 2013 Working at recommendations Hazid study• June 2013 Presentation at CCR meeting in Brussels• August 2013         Presentation at AND meeting in Genève

• July‐Dec. 2013 Detailed design and submission plans and calculations to Lloyds Plan Approval

• January 2014 Start hull construction and Keel laying• June 2015 Tests, trials and maiden voyage.

Page 7: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

KOOIMAN MARINE B.V.MEMBER OF

THE KOOIMAN GROUP

MAIN PARTICULARS LNG PUSH BOAT:• LENGTH: 40 M• BEAM 18 M• DRAUGHT    (WITH 30% CONSUMABLES)                      1,60 M• PROPULSION                             4 X 1060 kW• WÄRTSILÄ                       6L20 DF• ( 1% DIESEL  99% LNG )• BUNKER CAPACITY:

DIESEL     80 M3LNG  160 M3

Page 8: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Propulsion concept

Page 9: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

LNG conceptStainless steel Tankroom

Vent stack

Stainless outer tankStainless inner tank

Top fill / spray

Page 10: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Tank position

Page 11: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Bunkeringlocations

Page 12: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Can we sail this LNG push boat under AND flag in 2015?

Thank you all for your interest in this presentation of our LNG push boat design

Page 13: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Hierna hulpsheets voor evt uitleg

Page 14: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

3 * 8L20 ‐ Reference configuration

FPP             

GEAR

G

Gen Set

FPP             

GEAR

FPP             

GEAR

G

Gen Set

8L20

WÄRTSILÄ 8L20

8L20

WÄRTSILÄ 8L20

8L20

WÄRTSILÄ 8L20

Bow thruster

Bow thruster

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

Page 15: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

4 * 6L20DF – conventional configuration

G

Gen Set

G

Gen Set

FPP             

GEAR

6L20DF

WÄRTSILÄ 6L20DF

Bow thruster

Bow thruster

FPP             

GEAR

6L20DF

WÄRTSILÄ 6L20DF

FPP             

GEAR

6L20DF

WÄRTSILÄ 6L20DF

FPP             

GEAR

6L20DF

WÄRTSILÄ 6L20DF

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

Page 16: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

4 * 6L20DF – hybrid configuration

G

Gas / Bi‐fuel Gen Set

FPP             

GEAR

6L20DF

WÄRTSILÄ 6L20DF

Bow thruster

Bow thruster

FPP             

GEAR

6L20DF

WÄRTSILÄ 6L20DF

FPP             

GEAR

6L20DF

WÄRTSILÄ 6L20DF

FPP             

GEAR

6L20DF

WÄRTSILÄ 6L20DF

G

G

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

Page 17: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Operating Profile

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

Page 18: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Operating profile: Rotterdam <‐>  Duisburg (Schwelgern)

Time Power

Return trip 42 hours

Rotterdam harbor 1.5 hours 2 * 400 kW main propulsion400 kW bowthruster ¼ of time

Rotterdam to Duisburg (loaded) 26 hours 3726 kW

Duisberg harbor 2.5 hours 2 * 400 kW main propulsion400 kW bowthruster ¼ of time

Duisberg to Rotterdam (empty) 12 hours 1326 kW

Domestic consumption (all conditions) 120 kWe

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

Page 19: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Operating profile graph

0%

10%

20%

30%

40%

50%

60%

70%

Rotterdam harbor upstream Schwelgern harbor downstream

Run

ning

hou

rs

Operating mode

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

Page 20: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Operating notes

• 7500 running hours per year on the main engines

• The minimum number of engines allowed are operating– Upstream all main engines are running– Downstream minimum 2– Harbor minimum 2

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

Page 21: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Relative emissions

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

Page 22: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

0 %

20 %

40 %

60 %

80 %

100 %

REF - current vessel DF-Mech DF-Hybrid

CO2 NOx SOx PM

Emissions

‐ PM values are very small and thus subject to measurement inaccuracy and rounding errors.‐ Lub oil and pilot fuel quality of strong influence

0.1% sulfur gasoil LNG LNG

© Wärtsilä  June 2013   DF pushboat machinery analysis / Koen Vonk

Page 23: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

What do we save??

CO2 NOx SOx PM

0.1 truckload

A sand truck can load 38.4 tons

3.2 truckloads

0.2 truckload

69.2 truckloads

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

CO2:       2657 tonnes

NOx: 123 tonnes

SOx:             8 tonnes

PM: 4 tonnes

Page 24: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

CO2

NOx

SOx

A soccer field:68 X 105 meters

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

188.2  m

8.6  m

0.5  m

What  gas volume do we save annually??

68 m

105 m

Page 25: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

What mass do we save??

A single barge can load 2840 tons at full draft

The annual CO2 savings nearly fill a barge 

© Wärtsilä June 2013   DF pushboat machinery analysis / Koen Vonk

Page 26: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Annual PM emission savings

© Wärtsilä   17 June 2010   ECOFLOW machinery analysis / Koen Vonk

Savings are up to 4 tons of PM annually. If all of this is PM10, this translates to 100 billion m3 of air at the 40 microgram/m3 limit. This is equivalent to a slice of nearly 2.5 meters over all of the Netherlands that is saved.

This is equivalent to a savings of 2.25 centimeters over all of the EU

EU limits PM10 to 40 [microgram/m3] on average over the year

Page 27: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of
Page 28: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of
Page 29: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

KOOIMAN MARINE B.V.MEMBER OF

THE KOOIMAN GROUP

MAIN PARTICULARS LNG PUSH BOAT:• LENGTH: 40 M• BEAM 18 M• DRAUGHT    (WITH 30% CONSUMABLES)                      1,60 M• PROPULSION                             4 X 1060 kW• WÄRTSILÄ                       6L20 DF• ( 1% DIESEL  99% LNG )• BUNKER CAPACITY:

DIESEL     80 M3LNG  160 M3

Page 30: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

KOOIMAN MARINE B.V.MEMBER OF

THE KOOIMAN GROUP

MAIN PARTICULARS LNG PUSH BOAT:• LENGTH: 40 M• BEAM 18 M• DRAUGHT    (WITH 30% CONSUMABLES)                      1,60 M• PROPULSION                             4 X 1060 kW• WÄRTSILÄ                       6L20 DF• ( 1% DIESEL  99% LNG )• BUNKER CAPACITY:

DIESEL     80 M3LNG  160 M3

Page 31: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

KOOIMAN MARINE B.V.MEMBER OF

THE KOOIMAN GROUP

MAIN PARTICULARS LNG PUSH BOAT:• LENGTH: 40 M• BEAM 18 M• DRAUGHT    (WITH 30% CONSUMABLES)                      1,60 M• PROPULSION                             4 X 1060 kW• WÄRTSILÄ                       6L20 DF• ( 1% DIESEL  99% LNG )• BUNKER CAPACITY:

DIESEL     80 M3LNG  160 M3

Page 32: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

Methane slipBy using Wärtsilä DF 20 diesels the methane slip is reduced to less than 6 g/kWh 

(Norwegian  CO2 fee on petroleum products and measured as average in IMO / ISO test cycles)

Page 33: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of
Page 34: PETER VROLIJK PROJECT MANAGER 4240 kW (5766 HP) LNG … · peter vrolijk project manager 4240 kw (5766 hp) lng ‘dual’ fueled iww push boat kooiman marine b.v. member of

0 %

20 %

40 %

60 %

80 %

100 %

REF - current vessel DF-Mech DF-Hybrid

CO2 NOx SOx PM

Figures and Facts

© Wärtsilä  June 2013   DF push boat machinery analysis / Koen Vonk

Emissions

‐ PM values are very small and thus subject to measurement inaccuracy and rounding errors.‐ Lub. oil and pilot fuel quality of strong influence

CO2: 2657 tonnes

NOx:   123 tonnes

SOx:        8 tonnes

PM:         4 tonnes