Perspectives on Insurance Coverage for … on Insurance Coverage for Construction Projects: ... of insurance costs and timing ... Joint Task Force report found bowing of upper brick

Embed Size (px)

Citation preview

  • Perspectives on Insurance Coverage for

    Construction Projects:

    Lessons Learned from Real Coverage

    Disputes

  • Outline of Presentation

    Introductions of Panel

    Topics for Discussion

    I. Placement of Insurance for Construction Projects

    II. General Liability Insurance

    III.

    IV. Ocean Marine Cargo Insurance

    V. Professional Liability Insurance

    Q&A & Closing Remarks

  • Moderator: Jim Malloy Partner, DFL Legal

    Panel: Joe Luciana Partner, DFL Legal

    Walter Bacsik Risk Manager, Dragados USA, Inc.

    Jim Tedjeske Vice President, Legal, Kvaerner

    Americas Holding, Inc.

    Jim Bly Managing Director, Alliant

    Construction Services Group

  • I. Insurance Placement on Construction Projects

    Deciding what coverage is necessary for Project

    Project specific insurance versus general underwriting

    Different forms of coverage to consider

    General Liability

    Builders Risk

    Professional Liability

    Ocean Marine

    SDI v. Surety

    Underwriting Broker in sync with project team?

    Documentation requirements

  • I. Insurance Placement on Construction Projects

    Owner Controlled Insurance Programs

    Advantages : Risk management control (control of coverage terms, duration

    and scope, claims handling, etc.) and reduction of insurance costs and timing

    Drawbacks : Increased risk management costs, administrative burdens, and

    risk of loss. G/L only wrap and its benefits/costs.

    Advantages : Broader coverage, coordinated claims procedure, and reduced

    coverage/subrogation disputes between contractor and owner

    Drawbacks

    difference in conditions coverage, additional reporting/administrative burdens

  • I. Insurance Placement on Construction Projects

    Subcontractor Default Insurance (SDI)

    SDI v. payment and performance bonding

    3 Party v. 2 Party agreement

    Coverage trigger = default under SDI, not proof of default

    Expediting the Proof of loss and RFI process

    Indirect costs

    SDI Market volatility and outlook

  • I. Insurance Placement on Construction Projects

    Accelerated Adjudication Bonds

    Newer format for more prompt resolution of bond claims

    Built in arbitration process with JAMS decision in 90 days

    Advantages of AAB v. Irrevocable letter of credit

    AAB approach in the subcontractor bond market v. SDI

    Example: Pennsylvania P3 project

    Advantages for Joint Venture team, owner, and subcontractors.

    Challenges?

  • II. General Liability Insurance

    Case Study : Coke Oven Battery Property Damage

    Coverage Issue -

    Policy

    Coke Oven Battery rebuild ($180 million project)

    Heat up process completed

    Battery operated continuously at levels exceeding all performance

    requirements

    Smoke from roof structures observed led to Joint Task Force investigation

    Joint Task Force report found bowing of upper brick work in roof:

    Premature grouting of roof

    Halloween Rains

  • II. General Liability Insurance (cont.)

  • II. General Liability Insurance (cont.)

  • II. General Liability Insurance (cont.)

    Owner lawsuit alleged breach of contract and breach of warranty

    against contractor

    $80 million claim

    Third-party beneficiary claim against engineering subcontractor

    Complaint incorporated non-performance listing the following

    Physical damage to the Battery (cracked bricks, bowed tie rods, tilted oven

    walls)

    Premature grouting

    Expert reports alleged damage from Halloween Rains

    Ultimate Result: $17.6 million settlement payment by insurers

  • II. General Liability Insurance (cont.)

    Insurance Coverage Disputes

    Insurance coverage lawsuit filed against Builders Risk Insurer,

    Professional insurer, and CGL insurer

    Professional insurer entered coverage agreement.

    CGL insurer filed motion for summary judgment arguing:

    No occurrence of property damage under the policy

    Ultimately resolved by PA Supreme Court 908 A.2d 888 (Pa. 2006)

    Held: claim for faulty workmanship is not an occurrence under CGL policy

  • II. General Liability Insurance (cont.)

    Common CGL Exclusions on Construction Claims

    Your Work

    Broad Form Property Coverage

    Does the subcontractor exception apply?

    Your Product

    Damage to your product and/or other property?

    Completed Products & Operation Hazard

    Expected or Intended Damage

  • II. General Liability Insurance (cont.)

    Coverage enhancements for G/L construction defect risk

    Amended definition of occurrence:

    The definition of "occurrence" is hereby amended to include:

    "Property Damage" to that portion of "your work" performed on your

    behalf by a subcontractor and included in the "products-completed

    operations hazard" may constitute an occurrence if the 'property

    damage" to "your work" was not expected or intended and is not

    otherwise excluded under the policy.

    Elimination or modification of damage to your work exclusion

  • II. General Liability Insurance (cont.)

    Coverage enhancements for construction defects (cont.)

    Most favorable state endorsement:

    The law of the state most favorable to the "Named Insured" shall govern in determining

    whether third-party "Property Damage" included within the "Products-Completed

    Operations Hazard" is caused by an "occurrence," provided that such state is a part of

    the United States of America including its territories and possessions; and

    has a substantial relationship to the "Named Insured"; or

    has a substantial relationship to the state in which such claim or "Suit" is brought; or

    is the state in which we are incorporated, or we have our principal place of

    business, or where this insurance contract was delivered to the "Named Insured".

    Removal of Impaired Property exclusion

  • III.

    Why Builders Risk ?

    Advantages:

    Protects works

    Subcontractors covered

    Reduce subrogation issues

    One package instead of multiple coverages

    Hypothetical example: One subcontractor damages work of other

    subcontractors when lifting equipment.

    Who pays?

  • III.

    Case Study : Tunnel collapse causing fatality

    Big Dig: I-90 Seaport Access Tunnel (EB, WB, HOV and Ramps)

    Construction Completed on December 31, 2004

    Accident in the EB Portal

    Concrete ceiling system attached with epoxy bolts

    Passenger killed/driver escaped with minor injuries

    July 14, 2006 legislation closed I-90 Tunnel until approved by Governor

    Findings of NTSB Hearing: Primary cause of the accident - use of Fast

    Set polymer epoxy (Powers Fasteners) subject to creep and not

    capable of sustaining long-term live loads

  • III.

  • III.

  • III.

  • III.

    Insuring Agreement

    Coverage Extensions : Debris removal, Demolition/increased cost of

    construction, Extra expense, Expediting expense, Professional fees, Soft costs,

    Contractual fines and penalties, Preservation of property.

    Policy Exclusions :

    Inherent Defect

    Government Order Exclusion -

    incurred or sustained by or imposed on any Insured at order of any

    government agency, court or other authority arising from any cause

  • III.

    Case Study : Hurricane Ike damage to LNG facility

    Storm surge inundated facility causing shutdown

    Construction All-Risk Insurer paid portion of claim but denied coverage

    as to certain costs.

    Coverage Issues

    Consequential loss/ delay in completion

    72-hour period for dredging costs

  • IV. Ocean Marine Cargo Insurance

    Case Study : Turbines/heat recovery generators lost at sea

    Vessel transporting HRSG components encountered a tropical storm

    Shipped without notice to Owner and EPC Contractor

    HRSGs destroyed and remanufactured (6 month delay to the project)

    EPC Contractor claimed force majeure event

    Owner paid contractor (with insurance) to settle and meet schedule

    Owner and EPC Contractor notified the insurers of the incident

    -shipment survey

  • IV. Ocean Marine Cargo Insurance (cont.)

    Consequential loss coverage by endorsement

    reduction in production (delay-in-startup)

    increase in cost to avoid reduction in production

    -

    shipment survey warranty

    Endorsement added project to the facility for delay-in-start-up

  • IV. Ocean Marine Cargo Insurance (cont.)

    Trial court held policy did not impose a pre-shipment survey requirement on

    HRSGs

    Eighth Circuit affirmed in Assicurazoni Generali S.P.A. v. Black & Veatch Corp.,

    362 F.3d 1108 (8th Cir. 2004)

    Missouri law applied because there was no established federal admiralty rule

    addressing pre-

    Insurance Co., 348 U.S. 310 (1955)).

    serves an important purpose in the law. When the parties establish a clear

    mechanism for determining rights and obligations, lawyers and judges should not

    thereafter search through and interpret copious e-mail exchanges and deposition

    transcripts in an effort to discern whether the parties might really have intended

  • V. Professional Liability Insurance

    Case Study : GC Contract with CM Responsibilities

    Owner/contractor agreement is for general contractor but

    -

    performance, value engineering, managing trades, etc.)

    Owner sues contractor for problems with sanitary system

    Contractor tenders claim to GL and PL insurers

    Professional insurer raises defense that contractor was general

    contractor and not engaged in professional services.

    Significant verdict for owner

    Professional insurer ultimately contributes large share. GL lesser share

  • V. Professional Liability Insurance (cont.)

    Case Study : Construction of baseball stadium

    Untimely/incomplete structural steel drawings and fabrication delays

    Coverage issues: Acceleration costs (and bonding/SDI issues)

    Coverage advantages: G/L and P/L within the same policy and the

    same carrier.

  • V. Professional Liability Insurance (cont.)

    Case Study : Flat -products steel mill facility

    Project Management Agreement with GMP (excluding certain equipment)

    Project Manager recommended contractor for design-build contract for buildings

    Insurer bound professional coverage under OCIP

    Contractor abandoned project.

    Owner/PM brought E&O claim for improper pre-bid design.

    Insurer denied coverage.

    Contractor stipulated to damages and arbitrated liability.

    Owner brought suit against PM as well.

    PM tendered claim to insurers

  • Q&A & Closing Remarks

    Questions for Panel?

    Thank you!