Upload
amtris
View
12
Download
0
Embed Size (px)
DESCRIPTION
t
Citation preview
LIST OF BREAKDOWN OF LUMP SUM ITEMS
BoQ No. Description Unit
1 GENERAL ITEMS1 1.1 Insurance Works and Contractor's Equipment L.S.2 1.2 Establishment L.S.3 1.4 Documentary Video L.S.4 1.5 Environmental Protection and Monitoring Measures L.S.5 1.6 Process Commissioning and Testing L.S.6 1.7 Inspection Trip to overseas factories L.S.
2 WASTEWATER TREATMENT FACILITY2.1 Preparative Earthworks
7 2.1.1 Strippping of Soil L.S.2.8 Mechanical and Electrical Works
8 2.8.1 Ventilation System (Roof Fan System) L.S.9 2.8.2 Pipe Gallery Lighting System L.S.
10 2.8.3 Fire Alarm System L.S.11 2.8.4 Pipe Gallery Cable Rack L.S.12 2.8.5 Sub-Transfo Lighting System L.S.13 2.8.6 Sub-Transfo Fire Alarm System L.S.14 2.8.7 Sub-Transfo Cable Rack L.S.
3 LIFT PUMPING STATION
15 3.1 L.S.
4 DISINFECTION TANK
16 4.1 L.S.
5 BLOWER BUILDING
17 5.1 L.S.
6 DEWATERING BUILDING
18 6.1 L.S.
8 BUILDING WORKS8.1 Lift Pumping Station
19 8.1.1 Architectural and Structural Works L.S.20 8.1.2 Mechanical and Plumbing Works L.S.
Item No.
Excavation including retaining wall, soil improvement, backfill and disposal of soil
Excavation including retaining wall, soil improvement, backfill and disposal of soil
Excavation including retaining wall, soil improvement, backfill and disposal of soil
Excavation including retaining wall, soil improvement, backfill and disposal of soil
Second Ho Chi Minh City Water Environment Improvement Project Package J: Expansion of Wastewater Treatment Plant The Consortium of
21 8.1.3 Electrical Works L.S.8.2 Blower Building
22 8.2.1 Architectural and Structural Works L.S.23 8.2.2 Mechanical and Plumbing Works L.S.24 8.2.3 Electrical Works L.S.
8.3 Dewatering Building25 8.3.1 Architectural and Structural Works L.S.26 8.3.2 Mechanical and Plumbing Works L.S.27 8.3.3 Electrical Works L.S.
8.4 Stair Cases: Stair D28 8.4.1 Architectural and Structural Works L.S.29 8.4.2 Mechanical and Plumbing Works L.S.30 8.4.3 Electrical Works L.S.
8.5 Stair Cases: Stair E31 8.5.1 Architectural and Structural Works: Electric Room L.S.32 8.5.2 Architectural and Structural Works: Stair E L.S.33 8.5.3 Mechanical and Plumbing Works L.S.34 8.5.4 Electrical Works L.S.
8.6 Stair Cases: Stair F35 8.6.1 Architectural and Structural Works: Electric Room L.S.36 8.6.2 Mechanical and Plumbing Works L.S.37 8.6.3 Electrical Works L.S.
8.7 Stair Cases: Stair G38 8.7.1 Architectural and Structural Works: Electric Room L.S.39 8.7.2 Mechanical and Plumbing Works L.S.40 8.7.3 Electrical Works L.S.
8.8 Stair Cases: Stair H41 8.8.1 Architectural and Structural Works: Electric Room L.S.42 8.8.2 Mechanical and Plumbing Works L.S.43 8.8.3 Electrical Works L.S.
9 LANDSCAPE WORK9.2 Road Work
44 9.2.4 Paint for Pavement L.S.9.8 Others
45 9.8.4 Road Sign L.S.46 9.10 Outdoor Lighting System L.S.
Sub-Total (Bill No. 1 to Bill No. 9)
10 MECHANICAL WORK
10.1 Lift Pump Facilities47 10.1.1 Detail Drawing Good for Construction L.S.
10.2 Aeration Blower Facilities48 10.2.1 Detail Drawing Good for Construction L.S.
10.3 Primary Sedimentation Facilities49 10.3.1 Detail Drawing Good for Construction L.S.
10.4 Aeration Tank50 10.4.1 Detail Drawing Good for Construction L.S.
10.5 Final Sedimentation Tank
51 10.5.1 Detail Drawing Good for Construction L.S.10.6 Disinfection Facilities
52 10.6.1 Detail Drawing Good for Construction L.S.10.7 Water Supply Facilities
53 10.7.1 Detail Drawing Good for Construction L.S.10.8 Gravity Thickening
54 10.8.1 Detail Drawing Good for Construction L.S.10.9 Centrifugal Thickening
55 10.9.1 Detail Drawing Good for Construction L.S.10.1 Dewatering Facilities
56 10.10.1 Detail Drawing Good for Construction L.S.10.11 Recycle Flow Equipment
57 10.11.1 Detail Drawing Good for Construction L.S.10.12 Floor Drain Facility
58 10.12.1 Detail Drawing Good for Construction L.S.10.13 Testing and Commissioning
59 10.13.1 Test at Mechanical Completion for Water Line L.S.60 10.13.2 Test at Mechanical Completion for Sludge Line L.S.
10.14 Provisional Sum of Mechanical Works61 10.14.1 Provisional Sum of Mechanical Works (1%) L.S.
11 ELECTRICAL WORK
11.1 HV S/G62 11.1.1 Detail Drawing Good for Construction L.S.
11.2 MV S/G panels including STR panels and SC panels63 11.2.1 Detail Drawing Good for Construction L.S.
11.3 Main transformer64 11.3.1 Detail Drawing Good for Construction L.S.
11.4 Outdoor station transformer 65 11.4.1 Detail Drawing Good for Construction L.S.
11.5 LV panels 66 11.5.1 Detail Drawing Good for Construction L.S.
11.6 Control power supply panels67 11.6.1 Detail Drawing Good for Construction L.S.
11.7 Motor control panels68 11.7.1 Detail Drawing Good for Construction L.S.
11.8 Local control panels69 11.8.1 Detail Drawing Good for Construction L.S.
11.9 Instrumentation70 11.9.1 Detail Drawing Good for Construction L.S.
11.10 Motor control center panels71 11.10.1 Detail Drawing Good for Construction L.S.
11.11 Emergency generator facility72 11.11.1 Detail Drawing Good for Construction L.S.
11.12 Control desk and relay panels73 11.12.1 Detail Drawing Good for Construction L.S.
11.13 Miscellaneous materials74 11.13.1 Accessories (e.g. Lifter, PTT CTT) L.S.
11.14 Provisional Sum of Electric works75 11.14..1 Provisional Sum of Electric works L.S.
Sub-Total (Bill No. 10 to Bill No. 11)
TOTAL
LIST OF BREAKDOWN OF LUMP SUM ITEMS
Total Amount Remarks Foreign Currency Local Currency
(JPY) (USD) (VND) Bill 1:
- 343,352.00 4,327,139,958 1.3 - 140,499.91 17,303,863,848 - 14,400.00 810,766,608 - 14,400.00 706,271,912 - 155,916.00 16,311,205,788 - 228,277.94 -
Bill 2:
- 7,961.79 390,499,202
- 67,659.45 3,318,470,521 - 7,172.81 351,802,029 - 2,945.13 144,448,515 - 66,864.04 3,279,458,380 - 477.80 23,434,311 - 3,056.06 149,889,488 - 2,986.64 146,484,786
- 87,204.72 4,277,100,922 Bill 3:
- 82,095.38 4,026,504,728 Bill 4:
- 41,068.82 2,014,288,421 Bill 5:
- 87,979.09 4,315,081,229 Bill 6:
Bill 8: - 20,050.92 1,264,411,069 - 1,643.54 80,609,943
The Consortium of
- 4,777.81 234,335,488
- 29,742.82 1,875,582,662 - 374.98 18,391,529 - 2,679.82 131,435,954
- 111,692.81 7,043,348,695 - 2,677.36 131,315,446 - 4,384.52 215,045,816
- 24,717.35 1,558,676,562 - 2,864.52 140,495,452 - 730.83 35,844,746
- 14,480.94 913,168,527 - 24,805.36 1,564,226,094 - 3,034.00 148,807,802 - 2,264.73 111,077,782
- 24,627.02 1,552,979,949 - 2,681.44 131,515,468 - 730.41 35,824,146
- 24,947.11 1,573,164,467 - 2,585.91 126,830,296 - 730.41 35,824,146
- 24,617.22 1,552,362,166 - 3,427.97 168,130,434 - 730.41 35,824,146
Bill 9:
- 1,424.08 69,846,034
- 669.56 32,839,264 - 22,155.94 1,086,674,838
1,714,567.37 83,765,299,567
-
13,445,782,704 Bill 10: - 135,493.00 -
- 161,901.00 -
- 225,095.00 -
- 181,032.00 -
To submit separately
- 421,533.00 -
- 28,966.00 -
- 40,019.00 -
3,733,200 - -
23,863,200 - -
17,860,800 - -
1,756,800 - -
- 11,112.00 -
- - 5,197,683 - 25,474.00 -
11,516,359 197,066.08 717,263,886
Bill 11:
- 9,687.00 -
- 64,754.00 -
- 5,571.00 -
- 10,275.00 -
- 8,666.00 -
- 10,326.00 -
- 44,856.00 -
- 20,830.00 -
- 67,169.00 -
- 108,843.00 -
- 78,140.00 -
- 78,711.00 -
600,803 - 12,124,264
To submit separately
3,556,276 43,336.39 902,973,448
62,887,438 1,978,855.47 15,083,341,985
62,887,438 3,693,422.84 98,848,641,552
Bill 1 896,845.85 39,459,248,114 896,845.85 39,459,248,114 Bill 2 159,123.72 7,804,487,232 159,123.72 7,804,487,232 Bill 3 87,204.72 4,277,100,922 87,204.72 4,277,100,922 Bill 4 82,095.38 4,026,504,728 82,095.38 4,026,504,728 Bill 5 41,068.82 2,014,288,421 41,068.82 2,014,288,421 Bill 6 87,979.09 4,315,081,229 87,979.09 4,315,081,229 Bill 8 336,000.21 20,679,228,785 336,000.21 20,679,228,785 Bill 9 24,249.58 1,189,360,136 24,249.58 1,189,360,136 1,714,567.37 1,714,567.37 83,765,299,567 1,714,567.37 83,765,299,567
1,427,691.08 722,461,569 551,164.39 915,097,712
- 1,978,855.47 1,637,559,281
3,693,422.84 85,402,858,848 88.00
POSCOUSD VND
512,651.91 23,148,042,326 61,200.00 3,001,651,776
OTV/HPTUSD VND
384,193.94 16,311,205,788
POSCOUSD VND
159,123.72 7,804,487,232
87,204.72 4,277,100,922
82,095.38 4,026,504,728
41,068.82 2,014,288,421
87,979.09 4,315,081,229
POSCOUSD VND
336,000.21 20,679,228,785
POSCOUSD VND
24,249.58 1,189,360,136
1,714,567.37 83,765,299,567
1,427,691.08 722,461,569
551,164.39 915,097,712
1,978,855.47 1,637,559,281 ok ok
1,978,855.47 15,083,341,985
3,693,422.84 98,848,641,552
LIST OF BREAKDOWN OF LUMP SUM ITEMS
BoQ No. Description Unit
1 GENERAL ITEMS1 1.1 Insurance Works and Contractor's Equipment L.S.2 1.2 Establishment L.S.3 1.4 Documentary Video L.S.4 1.5 Environmental Protection and Monitoring Measures L.S.5 1.6 Process Commissioning and Testing L.S.6 1.7 Inspection Trip to overseas factories L.S.
2 WASTEWATER TREATMENT FACILITY2.1 Preparative Earthworks
7 2.1.1 Strippping of Soil L.S.2.8 Mechanical and Electrical Works
8 2.8.1 Ventilation System (Roof Fan System) L.S.9 2.8.2 Pipe Gallery Lighting System L.S.
10 2.8.3 Fire Alarm System L.S.11 2.8.4 Pipe Gallery Cable Rack L.S.12 2.8.5 Sub-Transfo Lighting System L.S.13 2.8.6 Sub-Transfo Fire Alarm System L.S.14 2.8.7 Sub-Transfo Cable Rack L.S.
3 LIFT PUMPING STATION
15 3.1 L.S.
4 DISINFECTION TANK
16 4.1 L.S.
5 BLOWER BUILDING
17 5.1 L.S.
6 DEWATERING BUILDING
18 6.1 L.S.
8 BUILDING WORKS8.1 Lift Pumping Station
19 8.1.1 Architectural and Structural Works L.S.20 8.1.2 Mechanical and Plumbing Works L.S.21 8.1.3 Electrical Works L.S.
8.2 Blower Building22 8.2.1 Architectural and Structural Works L.S.23 8.2.2 Mechanical and Plumbing Works L.S.
Item No.
Excavation including retaining wall, soil improvement, backfill and disposal of soil
Excavation including retaining wall, soil improvement, backfill and disposal of soil
Excavation including retaining wall, soil improvement, backfill and disposal of soil
Excavation including retaining wall, soil improvement, backfill and disposal of soil
24 8.2.3 Electrical Works L.S.8.3 Dewatering Building
25 8.3.1 Architectural and Structural Works L.S.26 8.3.2 Mechanical and Plumbing Works L.S.27 8.3.3 Electrical Works L.S.
8.4 Stair Cases: Stair D28 8.4.1 Architectural and Structural Works L.S.29 8.4.2 Mechanical and Plumbing Works L.S.30 8.4.3 Electrical Works L.S.
8.5 Stair Cases: Stair E31 8.5.1 Architectural and Structural Works: Electric Room L.S.32 8.5.2 Architectural and Structural Works: Stair E L.S.33 8.5.3 Mechanical and Plumbing Works L.S.34 8.5.4 Electrical Works L.S.
8.6 Stair Cases: Stair F35 8.6.1 Architectural and Structural Works: Electric Room L.S.36 8.6.2 Mechanical and Plumbing Works L.S.37 8.6.3 Electrical Works L.S.
8.7 Stair Cases: Stair G38 8.7.1 Architectural and Structural Works: Electric Room L.S.39 8.7.2 Mechanical and Plumbing Works L.S.40 8.7.3 Electrical Works L.S.
8.8 Stair Cases: Stair H41 8.8.1 Architectural and Structural Works: Electric Room L.S.42 8.8.2 Mechanical and Plumbing Works L.S.43 8.8.3 Electrical Works L.S.
9 LANDSCAPE WORK9.2 Road Work
44 9.2.4 Paint for Pavement L.S.9.8 Others
45 9.8.4 Road Sign L.S.46 9.10 Outdoor Lighting System L.S.
Sub-Total (Bill No. 1 to Bill No. 9)
10 MECHANICAL WORK
10.1 Lift Pump Facilities47 10.1.1 Detail Drawing Good for Construction L.S.
10.2 Aeration Blower Facilities48 10.2.1 Detail Drawing Good for Construction L.S.
10.3 Primary Sedimentation Facilities49 10.3.1 Detail Drawing Good for Construction L.S.
10.4 Aeration Tank50 10.4.1 Detail Drawing Good for Construction L.S.
10.5 Final Sedimentation Tank
51 10.5.1 Detail Drawing Good for Construction L.S.10.6 Disinfection Facilities
52 10.6.1 Detail Drawing Good for Construction L.S.10.7 Water Supply Facilities
53 10.7.1 Detail Drawing Good for Construction L.S.10.8 Gravity Thickening
54 10.8.1 Detail Drawing Good for Construction L.S.10.9 Centrifugal Thickening
55 10.9.1 Detail Drawing Good for Construction L.S.10.1 Dewatering Facilities
56 10.10.1 Detail Drawing Good for Construction L.S.10.11 Recycle Flow Equipment
57 10.11.1 Detail Drawing Good for Construction L.S.10.12 Floor Drain Facility
58 10.12.1 Detail Drawing Good for Construction L.S.10.13 Testing and Commissioning
59 10.13.1 Test at Mechanical Completion for Water Line L.S.60 10.13.2 Test at Mechanical Completion for Sludge Line L.S.
10.14 Provisional Sum of Mechanical Works61 10.14.1 Provisional Sum of Mechanical Works (1%) L.S.
Sub Total bill no.10
11 ELECTRICAL WORK
11.1 HV S/G62 11.1.1 Detail Drawing Good for Construction L.S.
11.2 MV S/G panels including STR panels and SC panels63 11.2.1 Detail Drawing Good for Construction L.S.
11.3 Main transformer64 11.3.1 Detail Drawing Good for Construction L.S.
11.4 Outdoor station transformer 65 11.4.1 Detail Drawing Good for Construction L.S.
11.5 LV panels 66 11.5.1 Detail Drawing Good for Construction L.S.
11.6 Control power supply panels67 11.6.1 Detail Drawing Good for Construction L.S.
11.7 Motor control panels68 11.7.1 Detail Drawing Good for Construction L.S.
11.8 Local control panels69 11.8.1 Detail Drawing Good for Construction L.S.
11.9 Instrumentation70 11.9.1 Detail Drawing Good for Construction L.S.
11.10 Motor control center panels71 11.10.1 Detail Drawing Good for Construction L.S.
11.11 Emergency generator facility72 11.11.1 Detail Drawing Good for Construction L.S.
11.12 Control desk and relay panels73 11.12.1 Detail Drawing Good for Construction L.S.
11.13 Miscellaneous materials74 11.13.1 Accessories (e.g. Lifter, PTT CTT) L.S.
11.14 Provisional Sum of Electric works75 11.14..1 Provisional Sum of Electric works L.S.
Sub Total bill no.11
Grand Total
LIST OF BREAKDOWN OF LUMP SUM ITEMS
Total Amount Remarks Foreign Currency Local Currency
(JPY) (USD) (VND)
- 343,352.00 4,327,139,958 - 140,499.91 17,303,863,848 - 14,400.00 810,766,608 - 14,400.00 706,271,912 - 155,916.00 16,311,205,788 - 228,277.94 -
- 7,961.79 390,499,202
- 67,659.45 3,318,470,521 - 7,172.81 351,802,029 - 2,945.13 144,448,515 - 66,864.04 3,279,458,380 - 477.80 23,434,311 - 3,056.06 149,889,488 - 2,986.64 146,484,786
- 87,204.72 4,277,100,922
- 82,095.38 4,026,504,728
- 41,068.82 2,014,288,421
- 87,979.09 4,315,081,229
- 20,050.92 1,264,411,069 - 1,643.54 80,609,943 - 4,777.81 234,335,488
- 29,742.82 1,875,582,662 - 374.98 18,391,529
- 2,679.82 131,435,954
- 111,692.81 7,043,348,695 - 2,677.36 131,315,446 - 4,384.52 215,045,816
- 24,717.35 1,558,676,562 - 2,864.52 140,495,452 - 730.83 35,844,746
- 14,480.94 913,168,527 - 24,805.36 1,564,226,094 - 3,034.00 148,807,802 - 2,264.73 111,077,782
- 24,627.02 1,552,979,949 - 2,681.44 131,515,468 - 730.41 35,824,146
- 24,947.11 1,573,164,467 - 2,585.91 126,830,296 - 730.41 35,824,146
- 24,617.22 1,552,362,166 - 3,427.97 168,130,434 - 730.41 35,824,146
- 1,424.08 69,846,034
- 669.56 32,839,264 - 22,155.94 1,086,674,838
- 1,714,567.37 83,765,299,567 Construction
-
13,445,782,704 - 135,493.00 -
- 161,901.00 -
- 225,095.00 -
- 181,032.00 -
To submit separately
- 421,533.00 -
- 28,966.00 -
- 40,019.00 -
3,733,200 - -
23,863,200 - -
17,860,800 - -
1,756,800 - -
- 11,112.00 -
- - 5,197,683 - 25,474.00 -
11,516,359 197,066.08 717,263,886 58,730,359.00 1,427,691.08 14,168,244,273.00 Mechanical
- 9,687.00 -
- 64,754.00 -
- 5,571.00 -
- 10,275.00 -
- 8,666.00 -
- 10,326.00 -
- 44,856.00 -
- 20,830.00 -
- 67,169.00 -
- 108,843.00 -
- 78,140.00 -
To submit separately
- 78,711.00 -
600,803 - 12,124,264
3,556,276 43,336.39 902,973,448 4,157,079 551,164 915,097,712 Electrical
62,887,438 3,693,423 98,848,641,552
Lump sum items
(JPY) (USD) (VND) 62,887,438 3,693,423 98,848,641,552
PERCENTAGE0.00 9.30 4.380.00 3.80 17.510.00 0.39 0.820.00 0.39 0.710.00 4.22 16.500.00 6.18 0.00
0.00 0.22 0.40
0.00 1.83 3.360.00 0.19 0.360.00 0.08 0.150.00 1.81 3.320.00 0.01 0.020.00 0.08 0.150.00 0.08 0.15
0.00 2.36 4.33
0.00 2.22 4.07
0.00 1.11 2.04
0.00 2.38 4.37
0.00 0.54 1.280.00 0.04 0.080.00 0.13 0.240.00 0.00 0.000.00 0.81 1.900.00 0.01 0.02
0.00 0.07 0.13
0.00 3.02 7.130.00 0.07 0.130.00 0.12 0.22
0.00 0.67 1.580.00 0.08 0.140.00 0.02 0.04
0.00 0.39 0.920.00 0.67 1.580.00 0.08 0.150.00 0.06 0.11
0.00 0.67 1.570.00 0.07 0.130.00 0.02 0.04
0.00 0.68 1.590.00 0.07 0.130.00 0.02 0.04
0.00 0.67 1.570.00 0.09 0.170.00 0.02 0.04
0.00 0.04 0.07
0.00 0.02 0.030.00 0.60 1.10
0.00 46.42 84.74 From Total Project
0.00 0.00 0.00
0.00 0.00 13.600.00 3.67 0.000.00 0.00 0.000.00 4.38 0.000.00 0.00 0.000.00 6.09 0.000.00 0.00 0.000.00 4.90 0.000.00 0.00 0.00
0.00 11.41 0.000.00 0.00 0.000.00 0.78 0.000.00 0.00 0.000.00 1.08 0.000.00 0.00 0.005.94 0.00 0.000.00 0.00 0.00
37.95 0.00 0.000.00 0.00 0.00
28.40 0.00 0.000.00 0.00 0.002.79 0.00 0.000.00 0.00 0.000.00 0.30 0.000.00 0.00 0.000.00 0.00 0.010.00 0.69 0.000.00 0.00 0.00
18.31 5.34 0.7393.39 38.65 14.33 From Total Project
0.00 0.00 0.00
0.00 0.00 0.000.00 0.26 0.000.00 0.00 0.000.00 1.75 0.000.00 0.00 0.000.00 0.15 0.000.00 0.00 0.000.00 0.28 0.000.00 0.00 0.000.00 0.23 0.000.00 0.00 0.000.00 0.28 0.000.00 0.00 0.000.00 1.21 0.000.00 0.00 0.000.00 0.56 0.000.00 0.00 0.000.00 1.82 0.000.00 0.00 0.000.00 2.95 0.000.00 0.00 0.000.00 2.12 0.00
0.00 0.00 0.000.00 2.13 0.000.00 0.00 0.000.96 0.00 0.010.00 0.00 0.005.65 1.17 0.916.61 14.92 0.93 From Total Project0.00 0.00 0.00
100.00 100.00 100.00
LIST OF BREAKDOWN OF LUMP SUM ITEMS
BoQ No. Description
1 GENERAL ITEMS1 1.1 Insurance Works and Contractor's Equipment2 1.2 Establishment3 1.4 Documentary Video4 1.5 Environmental Protection and Monitoring Measures5 1.6 Process Commissioning and Testing6 1.7 Inspection Trip to overseas factories
2 WASTEWATER TREATMENT FACILITY2.1 Preparative Earthworks
7 2.1.1 Strippping of Soil2.8 Mechanical and Electrical Works
8 2.8.1 Ventilation System (Roof Fan System)9 2.8.2 Pipe Gallery Lighting System
10 2.8.3 Fire Alarm System 11 2.8.4 Pipe Gallery Cable Rack12 2.8.5 Sub-Transfo Lighting System13 2.8.6 Sub-Transfo Fire Alarm System14 2.8.7 Sub-Transfo Cable Rack
3 LIFT PUMPING STATION
15 3.1
4 DISINFECTION TANK
16 4.1
5 BLOWER BUILDING
17 5.1
6 DEWATERING BUILDING
18 6.1
8 BUILDING WORKS8.1 Lift Pumping Station
19 8.1.1 Architectural and Structural Works20 8.1.2 Mechanical and Plumbing Works21 8.1.3 Electrical Works
8.2 Blower Building22 8.2.1 Architectural and Structural Works23 8.2.2 Mechanical and Plumbing Works
Item No.
Excavation including retaining wall, soil improvement, backfill and disposal of soil
Excavation including retaining wall, soil improvement, backfill and disposal of soil
Excavation including retaining wall, soil improvement, backfill and disposal of soil
Excavation including retaining wall, soil improvement, backfill and disposal of soil
24 8.2.3 Electrical Works8.3 Dewatering Building
25 8.3.1 Architectural and Structural Works26 8.3.2 Mechanical and Plumbing Works27 8.3.3 Electrical Works
8.4 Stair Cases: Stair D28 8.4.1 Architectural and Structural Works29 8.4.2 Mechanical and Plumbing Works30 8.4.3 Electrical Works
8.5 Stair Cases: Stair E31 8.5.1 Architectural and Structural Works: Electric Room32 8.5.2 Architectural and Structural Works: Stair E33 8.5.3 Mechanical and Plumbing Works34 8.5.4 Electrical Works
8.6 Stair Cases: Stair F35 8.6.1 Architectural and Structural Works: Electric Room36 8.6.2 Mechanical and Plumbing Works37 8.6.3 Electrical Works
8.7 Stair Cases: Stair G38 8.7.1 Architectural and Structural Works: Electric Room39 8.7.2 Mechanical and Plumbing Works40 8.7.3 Electrical Works
8.8 Stair Cases: Stair H41 8.8.1 Architectural and Structural Works: Electric Room42 8.8.2 Mechanical and Plumbing Works43 8.8.3 Electrical Works
9 LANDSCAPE WORK9.2 Road Work
44 9.2.4 Paint for Pavement9.8 Others
45 9.8.4 Road Sign46 9.10 Outdoor Lighting System
Sub-Total (Bill No. 1 to Bill No. 9)
10 MECHANICAL WORK10.1 Lift Pump Facilities
47 10.1.1 Detail Drawing Good for Construction10.2 Aeration Blower Facilities
48 10.2.1 Detail Drawing Good for Construction10.3 Primary Sedimentation Facilities
49 10.3.1 Detail Drawing Good for Construction10.4 Aeration Tank
50 10.4.1 Detail Drawing Good for Construction10.5 Final Sedimentation Tank
51 10.5.1 Detail Drawing Good for Construction
10.6 Disinfection Facilities52 10.6.1 Detail Drawing Good for Construction
10.7 Water Supply Facilities53 10.7.1 Detail Drawing Good for Construction
10.8 Gravity Thickening54 10.8.1 Detail Drawing Good for Construction
10.9 Centrifugal Thickening55 10.9.1 Detail Drawing Good for Construction
10.1 Dewatering Facilities56 10.10.1 Detail Drawing Good for Construction
10.11 Recycle Flow Equipment57 10.11.1 Detail Drawing Good for Construction
10.12 Floor Drain Facility58 10.12.1 Detail Drawing Good for Construction
10.13 Testing and Commissioning59 10.13.1 Test at Mechanical Completion for Water Line60 10.13.2 Test at Mechanical Completion for Sludge Line
10.14 Provisional Sum of Mechanical Works61 10.14.1 Provisional Sum of Mechanical Works (1%)
Sub Total bill no.1011 ELECTRICAL WORK
11.1 HV S/G62 11.1.1 Detail Drawing Good for Construction
11.2 MV S/G panels including STR panels and SC panels63 11.2.1 Detail Drawing Good for Construction
11.3 Main transformer64 11.3.1 Detail Drawing Good for Construction
11.4 Outdoor station transformer 65 11.4.1 Detail Drawing Good for Construction
11.5 LV panels 66 11.5.1 Detail Drawing Good for Construction
11.6 Control power supply panels67 11.6.1 Detail Drawing Good for Construction
11.7 Motor control panels68 11.7.1 Detail Drawing Good for Construction
11.8 Local control panels69 11.8.1 Detail Drawing Good for Construction
11.9 Instrumentation70 11.9.1 Detail Drawing Good for Construction
11.10 Motor control center panels71 11.10.1 Detail Drawing Good for Construction
11.11 Emergency generator facility72 11.11.1 Detail Drawing Good for Construction
11.12 Control desk and relay panels73 11.12.1 Detail Drawing Good for Construction
11.13 Miscellaneous materials74 11.13.1 Accessories (e.g. Lifter, PTT CTT)
11.14 Provisional Sum of Electric works75 11.14..1 Provisional Sum of Electric works
Sub Total bill no.11
Grand Total
LIST OF BREAKDOWN OF LUMP SUM ITEMS
Lump sum items
Unit (JPY) (USD) (VND) 62,887,438 3,693,423 98,848,641,552
PERCENTAGEL.S. 0.00 9.30 4.38L.S. 0.00 3.80 17.51L.S. 0.00 0.39 0.82L.S. 0.00 0.39 0.71L.S. 0.00 4.22 16.50L.S. 0.00 6.18 0.00
L.S. 0.00 0.22 0.40
L.S. 0.00 1.83 3.36L.S. 0.00 0.19 0.36L.S. 0.00 0.08 0.15L.S. 0.00 1.81 3.32L.S. 0.00 0.01 0.02L.S. 0.00 0.08 0.15L.S. 0.00 0.08 0.15
L.S. 0.00 2.36 4.33
L.S. 0.00 2.22 4.07
L.S. 0.00 1.11 2.04
L.S. 0.00 2.38 4.37
L.S. 0.00 0.54 1.28L.S. 0.00 0.04 0.08L.S. 0.00 0.13 0.24
0.00 0.00 0.00L.S. 0.00 0.81 1.90L.S. 0.00 0.01 0.02
L.S. 0.00 0.07 0.13
L.S. 0.00 3.02 7.13L.S. 0.00 0.07 0.13L.S. 0.00 0.12 0.22
L.S. 0.00 0.67 1.58L.S. 0.00 0.08 0.14L.S. 0.00 0.02 0.04
L.S. 0.00 0.39 0.92L.S. 0.00 0.67 1.58L.S. 0.00 0.08 0.15L.S. 0.00 0.06 0.11
L.S. 0.00 0.67 1.57L.S. 0.00 0.07 0.13L.S. 0.00 0.02 0.04
L.S. 0.00 0.68 1.59L.S. 0.00 0.07 0.13L.S. 0.00 0.02 0.04
L.S. 0.00 0.67 1.57L.S. 0.00 0.09 0.17L.S. 0.00 0.02 0.04
L.S. 0.00 0.04 0.07
L.S. 0.00 0.02 0.03L.S. 0.00 0.60 1.10
0.00 46.42 84.74
0.00 0.00 0.000.00 0.00 13.60
L.S. 0.00 3.67 0.000.00 0.00 0.00
L.S. 0.00 4.38 0.000.00 0.00 0.00
L.S. 0.00 6.09 0.000.00 0.00 0.00
L.S. 0.00 4.90 0.000.00 0.00 0.00
L.S. 0.00 11.41 0.00
0.00 0.00 0.00L.S. 0.00 0.78 0.00
0.00 0.00 0.00L.S. 0.00 1.08 0.00
0.00 0.00 0.00L.S. 5.94 0.00 0.00
0.00 0.00 0.00L.S. 37.95 0.00 0.00
0.00 0.00 0.00L.S. 28.40 0.00 0.00
0.00 0.00 0.00L.S. 2.79 0.00 0.00
0.00 0.00 0.00L.S. 0.00 0.30 0.00
0.00 0.00 0.00L.S. 0.00 0.00 0.01L.S. 0.00 0.69 0.00
0.00 0.00 0.00L.S. 18.31 5.34 0.73
93.39 38.65 14.330.00 0.00 0.000.00 0.00 0.00
L.S. 0.00 0.26 0.000.00 0.00 0.00
L.S. 0.00 1.75 0.000.00 0.00 0.00
L.S. 0.00 0.15 0.000.00 0.00 0.00
L.S. 0.00 0.28 0.000.00 0.00 0.00
L.S. 0.00 0.23 0.000.00 0.00 0.00
L.S. 0.00 0.28 0.000.00 0.00 0.00
L.S. 0.00 1.21 0.000.00 0.00 0.00
L.S. 0.00 0.56 0.000.00 0.00 0.00
L.S. 0.00 1.82 0.000.00 0.00 0.00
L.S. 0.00 2.95 0.000.00 0.00 0.00
L.S. 0.00 2.12 0.000.00 0.00 0.00
L.S. 0.00 2.13 0.00
0.00 0.00 0.00L.S. 0.96 0.00 0.01
0.00 0.00 0.00L.S. 5.65 1.17 0.91
6.61 14.92 0.930.00 0.00 0.00
0.96
100.00 100.00 100.00
(JPY) (USD) (VND)
contract 62,887,438.00 3,693,423 98848641552VND Contract 12968647464.36 77635748096.8 98848641552 Total Contract 345,018,960,711 1,093,163,712,159 1154576634835.1% FROM TOTAL 3.76% 7.10% 8.56%
Provisional Sum JPY Portion (Rate 206.22)Bill 10 11516359 2.37E+09Bill 11 3556276 7.33E+08Bill 12 0 0Bill 13 0 0Sub Total 15072635 3.11E+09Provisional Sum USD Portion (rate 21020)Bill 10 197066.1 4.14E+09Bill 11 43336 9.11E+08Bill 12 861341.8 1.81E+10Bill 13 2727 57321540Sub Total 1104471 2.32E+10Provisional Sum VND PortionBill 10 7.17E+08 7.17E+08Bill 11 9.03E+08 9.03E+08Bill 12 1.03E+10 1.03E+10Bill 13 1.34E+08 1.34E+08Sub Total 1.21E+10 1.21E+10Total Contract Provi 3.84E+10Contingency sumContingenc 1.51E+08 3.11E+10Contingen 4627401 9.73E+10Contingen 1.03E+11 1.03E+11Total Contingency Su 2.31E+11Net Contract PriceJPY Portion 1.51E+09 3.11E+11USD Portio46274013 9.73E+11VND Portio 1.03E+12 1.03E+12Total Net Contract Pri 2.31E+12TOTAL CONTRACT PRI 2.81E+12Guarantee Appendix t10 percent of the Contract Price for local currency portion (less VAT) and 10 percent of the Contract Price for foreign currency portionJPY Portion 1.52E+08 3.14E+10USD Portio 4737848 9.96E+10Total JPY +USD Potion 1.31E+11VND Portio 1.04E+11 1.04E+11VND Portio 2.31E+10 2.31E+10Total VND Portion 1.27E+11
10 percent of the Contract Price for local currency portion (less VAT) and 10 percent of the Contract Price for foreign currency portion