Åpen informasjon / Public information
RIMA seminar, Amsterdam, 5/2
- 2019
The future is electric 1
Drones and automation in Statnett's grid
Åpen informasjon / Public information
RIMA seminar
Amsterdam, 5/2 - 2019The future is electric 2
This is Statnett
Statnett is the Transmission System Operator in the Norwegian energy system
Statnett operates and owns over 11 000 km of power lines and
cables, over 35 000 towers and approximately 150 transformer stations throughout Norway
Operations are monitored 24/7/365 from one national control centre and two regional control centres.
Statnett is responsible for interconnectors to Sweden, Finland, Russia, Denmark and the Netherlands
Statnett has 1 300 employees, and is owned by the Norwegian state
Regional
control
center
north
Regional
control
center
south
National
control
center
Åpen informasjon / Public information
The future is electric 3
- R&D
RIMA seminar
Amsterdam, 5/2 - 2019
Use of drones in Statnett•Needs and operations are based upon a drone strategy•Drone center•Flight operations manager•Technical managers•30+ pilots•Operational inspections•R&D
Åpen informasjon / Public information
The future is electric 4RIMA seminar
Amsterdam, 5/2 - 2019
•Foot in rough terrain
•ATV
•Snowmobile
•Helicopter
•Boat
•AND drones
Inspections by:
Åpen informasjon / Public information
1. Automatic inspections on substation
2. AI-4-UAS (automatic fault detection from images
using machine learning and artificial intelligence)
3. Automatic long distance line inspections(to be initiated)
The future is electric 5
R & D
RIMA seminar
Amsterdam, 5/2 - 2019
Åpen informasjon / Public information
The future is electric 6
Automatic inspections on substation
RIMA seminar
Amsterdam, 5/2 - 2019
Åpen informasjon / Public information
Åpen informasjon / Public information
Åpen informasjon / Public information
Åpen informasjon / Public information
The future is electric 10
AI-4-UAS
?
Collect Images Tag Images Train AI Model DeployHow to add new
intelligence to the system?
RIMA seminar
Amsterdam, 5/2 - 2019
Åpen informasjon / Public information
RIMA seminar, Amsterdam, 5/2
- 2019
The future is electric 11
Åpen informasjon / Public information
The future is electric 12
Long distance line inspectionsTask
Drone hangar
UAS*
Sense & avoid
Pathplanning
VTOL, fixed wing, multirotor?
Long range flight
Communication BVLOS/BRLOS
Sensors
RIMA seminar
Amsterdam, 5/2 - 2019
Åpen informasjon / Public information
• All power lines are laser scanned
• 3d vector of lines and height of all towers
• Digital elevation model (5 cm)
• GPS position is not reliable
• Intelligent sensors that know what which components to photograph
• Multiple pictures of each component
• Over 200 km flight range
• Reliable communication with the drone
• Need clear and sharp images of the right component
The future is electric 13
Prerequisites and challenges
RIMA seminar
Amsterdam, 5/2 - 2019
Åpen informasjon / Public information
RIMA seminar, Amsterdam, 5/2
- 2019
The future is electric 14
Åpen informasjon / Public information
RIMA seminar, Amsterdam, 5/2
- 2019
The future is electric 15
Åpen informasjon / Public information
RIMA seminar, Amsterdam, 5/2
- 2019
The future is electric 16
Åpen informasjon / Public information
RIMA seminar, Amsterdam, 5/2
- 2019
The future is electric 17
Åpen informasjon / Public information
RIMA seminar, Amsterdam, 5/2
- 2019
The future is electric 18
Åpen informasjon / Public information
The future is electric 19
E-mail: [email protected]
RIMA seminar
Amsterdam, 5/2 - 2019
Thank you for your attention