PEA Thailand 1
PEA Microgrid
Prachya LaochooEngineer
Smart Grid Planning Division, PEA, Thailand
PEA Thailand 2
IEEE: a group of interconnected loads and DistributedEnergy Resources (DER) with clearly defined electricalboundaries that acts as a single controllable entity withrespect to the grid. It can connect and disconnect from thegrid to enable operation in both grid-connected or islandmodes.
IEC TS 62898-2-2018: group of interconnected loads and distributed
energy resources with defined electrical boundaries that acts as a single
controllable entity and is able to operate in both grid-connected or island mode.
Microgrid
PEA Thailand 3
• To accumulate energy produced by large, less responsive thermal generation plants (also RE) and then re-dispatch it based on peak demand.
• Storage facilities were largely financed by arbitrage (buying energy at a low price and selling it at a higher price).
• Energy storage currently contributes to reliability, efficiency, power quality, transmission optimization, black-start functions, and support Demand Response (DR) function.
Load Duration Curve 2
9000.00
11000.00
13000.00
15000.00
17000.00
19000.00
21000.00
23000.00
25000.00
1 834 1667 2500 3333 4166 4999 5832 6665 7498 8331 9164 9997 10830 11663 12496 13329 14162 14995 15828 16661 17494
Hours ( x 2 )
Sy
ste
m G
en
(M
W)
95% of Peak = 22809 MW : 87 Hours per year
90% of Peak = 21609 MW : 650 Hours per year
5% OF PEAK DEMAND < 100 HOURS
Energy Storage System (ESS)
PEA Thailand 4
STAGE 1: Pilot
PEA Microgrid
Khun PaeChang Mai
R&D
BetongYala
Mae Sariange
Mae Hongson
PEA Thailand 5
Khun Pae
Khun Pae Microgrid (R&D Project) Chom Tong, Chiang Mai
90kW in 2019
PEA Thailand 6
Microgrid Controller
BESS 100kW/100kWh Mobile App
Khun Pae Microgrid (R&D Project) Chom Tong, Chiang Mai
Remote Control Switch
PEA Thailand 7
AC/DC AC/DC
BESSPVHydro
ชุมชนอนามัย
โรงเรียน ชุมชน
ชุมชน
400V
22kV
S1
S2 S3
S4
ชุมชน
Grid ConnectedMicrogrid at
Khun Pae
(R&D)
PEA Thailand 8
AC/DC AC/DC
BESSPVHydro
ชุมชนอนามัย
โรงเรียน ชุมชน
ชุมชน
400V
22kV
S1
S2 S3
S4
ชุมชน
IslandingMicrogrid at
Khun Pae
(R&D)
PEA Thailand 9
Khun Pae Microgrid (R&D Project) Chom Tong, Chiang Mai
PEA Thailand 10
Khun Pae Microgrid (R&D Project) Chom Tong, Chiang Mai
PEA Thailand 11
Khun Pae Microgrid (R&D Project) Chom Tong, Chiang Mai
PEA Thailand 12
Khun Pae Microgrid (R&D Project) Chom Tong, Chiang Mai
BESS supply power during islanding condition (24 Apr 2018).
PEA Thailand 13
Energy Storage (3MW/1.5MWh)to cover significant load
1 Units
Micro grid Controllerwith Building Energy Management System (BEMS) and Fault Location Isolation & Service Restoration (FLISR)
1 System
Communication System 1 System
Interface System 1 System
Mae Sariang
Microgrid at Mae Sariang
PEA Thailand 14
1. Islanding 2. Intermittent Resources Integration
3. Peak Shaving
Others e.g.-Generation PV forecast- Load forecast
Microgrid at Mae Sariang: Modes of Functions
PEA Thailand 15
with Fault Location Isolation & Service Restoration (FLISR)
Microgrid at Mae Sariang
PEA Thailand 16
with Fault Location Isolation & Service Restoration (FLISR)
Microgrid at Mae Sariang
PEA Thailand 17
with Fault Location Isolation & Service Restoration (FLISR)
Microgrid at Mae Sariang
PEA Thailand 18
with Fault Location Isolation & Service Restoration (FLISR)
Microgrid at Mae Sariang
PEA Thailand 19
with Fault Location Isolation & Service Restoration (FLISR)
Microgrid at Mae Sariang
PEA Thailand 20
BetongEnergy Storage (4MW/4MWh)to cover significant load 1 Units
Micro grid Controllerwith Fault Location Isolation & Service Restoration (FLISR)
1 System
Communication System 1 System
Interface System 1 System
Scope of Work
ExistingDiesel Gen. (1MW) 7 Units
Microgrid at Betong, Yala Province
PEA Thailand 21
Microgrid at Betong, Yala Province
PEA Thailand 22
THANK YOU FOR YOUR ATTENTION