Upload
ngoque
View
226
Download
2
Embed Size (px)
Citation preview
Specifications and Installation Guide
for Underground Service to
Residential Developments
June 2010
Western Massachusetts Electric
TABLE OF CONTENTS
I. Scope………………………........................................................4 II. General Requirements…………………………………...........4
a. Plans…………………………………………………………..4, 5 b. Code Compliance……………………………………….....5 c. Environmental Permits………………………………….5 d. Customer Payment………………………………………..5
III. Division Responsibility a. The Customer………………………………………………..5 b. WMECO will……………………………………………….....6
IV. Construction Schedule…………………………………............6 V. Construction Requirements
a. Layout and Grading…………………………………..........6 b. Trenching……………………………………………………...6, 7 c. Backfilling……………………………………………………..7
VI. Inspection…………………………………………………………...7 VII. Conduit/Installation……………………………………………...8 VIII. Single-Phase mounted Transformer Vault………………..9 IX. Secondary Vault (Hand hole)……………………………….....9, 10 X. Riser Pole…………………………………………………………...10
XI. Services……………………………………………………………...10
XII. Street lighting……………………………………………………...10
XIII. Other Utilities……………………………………………………...10 Appendices………………………………………………………………….11 Reviewed and Updated June 2010
2
Required Lead Times The following lead times should be adhered to in order to facilitate timely completion of your proposed project Design lead time: 8 weeks After the Company receives all required materials (town approved plot plan, loads, easement information, street light layout, etc.) Inspection: 3 working days This is the time required to schedule a company inspector to check the construction. In no case shall any trench, conduit, silos vaults or other parts of the conduit distribution system be backfilled prior to the Company inspector’s approval. Installation of WMECO equipment will be scheduled when all requirements have been met. Note: Any changes during engineering or construction, will affect the agreed upon installation schedule and the revised project completion date must be communicated in a timely manner.
3
Requirements and Division of Responsibilities between the Customer and Western Massachusetts Electric Company
For Underground Residential Distribution Systems
I. Scope
a. This document has been prepared as a guide in the installation of Underground Residential Distribution conduit systems within residential developments.
b. The terms of the Western Massachusetts Electric Company’s New Business Policy NB-21M (Electrical Distribution to New Residential Developments) apply and are incorporated in this document.
c. The Company reserves the right to modify or amend this document and its specifications as it deems necessary.
II. General Requirements
a. Plans and documents must be submitted along with name, address and phone number for:
Developer Surveyor (creating easement maps) Attorney (recording easement)
The customer will provide, in advance and at no cost to the Company, the following:
Town approved site plan. The company cannot begin design work prior to receipt of this plan.
A minimum of two copies of the approved Planning and Zoning development map showing property lines only, total number of house lots proposed, their locations and footprint, lot numbers and associated 911 address numbers.
One set of detailed development plans showing proposed location and footprint of houses, driveways, septic systems, water lines, gas lines, sewers, etc.
A copy of all permits and approvals that have been obtained for constructing the development.
Easements (in accordance of appendix a) for all facilities required to serve the residential development.
A copy of a street light proposal for the development, approved by the municipality, or written notice from the municipality that street lighting will not be required; if installation is requested after construction is complete, additional costs, including the Company’s tax liabilities, may be borne by the municipality and /or Customer if the tariff does not collect all costs of construction.
4
A schedule of Customer’s best estimate for the timeframe of construction of homes in the development.
Such other reasonable information that may be deemed necessary for our design of the project.
b. Code Compliance
All construction must be in accordance with the Company’s Construction Standards, WMECO Information and Requirements for Electric Supply Below 600 Volts booklet as published by the Company, the Company’s New Business Policy NB-21M, and shall comply with all applicable codes and requirements.
c. Environmental Permits
The Customer will obtain any required environmental permits prior to the start of construction. In addition the customer will certify to the Company, that work areas in which the Company is to perform installation or maintenance, are free of preexisting contamination by hazardous wastes or materials as defined in the Massachusetts General Laws, Chapter 21E, and will indemnify the Company for any claims, costs, expenses, suits, demands, citations, fines or damages of any kind arising form the presence of any such contamination.
d. Customer Payment
Materials will not be ordered and the WMECO portion of the construction project shall not begin until after the Customer makes all required payments.
III. Division of Responsibility
a. The Customer, at no cost to the Company, shall:
Prior to the start of the Company’s construction, provide all applicable documents required by the Company including easements.
Install conduit for Company-owned street lights. Provide and install all other required foundations, transformer pads,
hand holes, vaults, grounding systems, and conduit including glue, warning tape, 1/4” diameter nylon pull line and conduit plugs, etc., as indicated on the Company’s plan and related construction documents.
Supply Company-approved equipment only; equipment that is not approved shall not be used without the prior written consent of the Company.
Install all primary, secondary and service conduits, from the proposed Company equipment locations, to each meter location or temporary dead-end as designated by the Company.
Ownership and responsibility of the primary and secondary conduit system will revert to the Company upon inspection and acceptance of the conduit system by the Company. Ownership and responsibility of the service conduit reverts to the future home owner.
5
b. WMECO will:
Develop the conduit plan to provide underground electric service. Furnish a list of materials, approved manufacturers and their
equipment part numbers, to be supplied by the Customer. Designate the location of all Company owned equipment and service
entrance and meter location(s). Provide Company owned street light foundations as applicable for
street light installations. Provide, install, own and maintain all transformers, Company owned
street lights, primary and secondary cable, and services up to meter. Make all connections to Company equipment. Inspect the underground conduit system and equipment foundations
installed by the Customer, prior to backfilling. IV. Construction Schedule
a. The Company may, at its discretion, construct the distribution line in segments, rather than all at once.
b. The roadway binder coat shall be installed prior to the start of installation of company facilities.
V. Construction Requirements
a. Layout and Grading Final grades shall be established with easement boundaries, street, lot, and trench lines staked by the Customer before any trenching is started
b. Trenching
The Customer shall adhere to the Company’s construction plan specifying trench locations, conduit depths and requirements specified in DTR 50.103 and DSEM 07.821, enclosed. Any changes are subject to approval by the Company.
Trench location shall be in as direct a line as possible, without reverse bends, between distribution facilities and from the distribution facility to the customer service entrance.
In order to minimize cable-pulling forces, no more than two sweeps (not including riser at house or pole) exceeding a total change in direction of 45 degrees shall be permitted.
Minimum burial depths specified for all electric conduits shall be maintained during all phases of construction. Any temporary mechanical protection required over buried conduit to prevent crushing or damage due to unusually heavy construction equipment shall be the responsibility of the Customer.
6
The trench bottom shall be solid and relatively smooth, or undisturbed earth, well tamped, and free of any debris that may be detrimental to the conduit. Excavation shall be of a size and extent to permit proper installation of conduit and structures, as required.
Where excavation is in rock, it shall be removed to 4 inches below the trench bottom. The over excavation shall be replaced with a bedding of gravel, sand or clean well tamped backfill.
Any conditions not suitable for a stable foundation shall be reported to the Company Representative for recommendation.
c. Backfilling
The Company’s representative shall be notified in advance of backfilling of any electric facility, i.e., conduit, vault, handhole, grounding, etc.
If any facility is backfilled without the Company’s prior approval, the Company reserves the right to require re-excavation of the facility.
Backfill shall not contain ashes, cinders, shell, frozen material, loose
debris or stones larger than 2 inches in maximum dimension. All backfill shall be compacted.
Trenches shall be immediately backfilled following conduit system inspection and approval by the authorized Company representative.
Backfilling shall be accomplished in a continuous manner from one structure to the next, and shall not be placed over any open-ended (unplugged) conduits.
Company approved red cable marking or “caution” tape shall be installed in the trench twelve inches above and directly over the conduit.
VI. Inspection
a. The Company’s representative shall be responsible for the inspection of the conduit system being prepared and installed by the Customer, at various stages of installation.
b. The inspection shall include, but not be limited to the following:
All trenches and excavations. All material supplied by the Customer. All backfill material during or after installation as applicable. All vaults, handholes, grounding and other facilities, after setting in place,
but prior to backfilling. All conduit installations, including cemented joints, bends, sweeps, bell-
ends, pull line and conduit plugs, prior to backfilling. All conduit terminations at transformer structures, handholes, switch
locations, riser poles and other applicable locations. All backfilling operations around structures and conduit runs. Customer shall ensure conduits are free of any obstructions and debris.
7
VII. Conduit / Installation
a. Conduit shall be installed in accordance with Company Standards and Construction Plans which accompany this specification package. Refer to DSEM 07.821 and 07.822 which cover general requirements for conduit installation.
b. Standard conduit shall be minimum 3 inch diameter, rigid PVC, heavy wall,
sunlight resistant (6% - 7% titanium dioxide by weight), listed and labeled electrical grade schedule 40 as per NEMA TC2-1990.
c. Sweeps used at house or pole risers shall have a minimum radius of 24 inches,
with 36 inches preferred. Minimum 48-inch radius sweeps are required within the conduit run.
d. Reverse bends shall not be allowed within the conduit run.
e. Conduit shall enter concrete vault perpendicular to the knockout. If this is not
practicable contractors shall provide 22-1/2 or 45-degree schedule 40 PVC bend.
f. Conduit in the trench should have a 4 inch per 100 feet downward pitch
toward the distribution facility, if physically possible, to provide drainage away from the service entrance, and prevent stagnant water from collecting in ducts.
g. Install conduit with all joints cemented, through knockout and extend 3 inches
inside concrete hand hole. Terminate conduit run with end bell and permanently mark conduit destination on conduit end.
h. Install ¼” diameter nylon pull line, including 10 feet of slack, in each duct and
secure to conduit plugs at each end. Gaps around conduit in hand hole knockout openings shall be sealed with mortar to prevent backfill from entering distribution facilities.
i. Minimum separation between electrical conduit and other utilities in the
trench shall be as indicated in DTR 50.103.
j. Conduit shall have 30-inch minimum burial depth, top of conduit to finished grade, for both primary and secondary voltages. Main electric trenches shall maintain conduit depths as shown in DTR 50.103.
k. In the event proper depth of conduit cannot be achieved, or where foreign
objects threaten to interfere with the installation of conduit, the Company’s representative may require steel conduit or concrete encasement of the conduit.
l. Unique conditions will be addressed in the Company construction plan.
m. Parallel installation of any conduits and other facilities directly above
electrical system conduits are prohibited.
8
VIII. Single-Phase Padmounted Transformer Vault
a. Padmounted transformer vault structures shall be located no further than 10 feet from a driveable, paved surface.
b. All vaults shall be level and installed in accordance with DTR 58.185.
c. A minimum of six inches base course of crushed stone (3/4 inch max. stone
size) or free-draining gravel shall be placed under all transformer vault excavations and shall be thoroughly compacted using a vibratory compactor. Certain soil conditions may require removal below normal depth and subsequent additional clean fill or stone added and compacted to insure sound base course for transformer vault.
d. Transformer vault pad /slab tops shall be three inches above final grade. In no
instance shall final grades hamper proper access or operation of Company distribution equipment.
e. Install two 5/8” X 8’ galvanized steel ground rods spaced a minimum 8’ apart
in the trench adjacent to the vault. Do not install the ground rods inside or underneath the concrete vault. Leave a 10-foot coil of #6(minimum) bare solid copper ground wire for connection to the transformer. Telephone and cable company bond wires shall be provided and tied to Company ground rods with Company-approved connectors as shown in the enclosed Material. Refer to Figures 8, 9 and 10. Such bonding or connection shall not interfere with connecting Company equipment.
f. A hill holder as shown in DTR 50.341 shall be installed where slopes exist that
would undermine or cover equipment (i.e., transformers) due to sharp drop-off or rise of grade. A customer designed retaining wall may also be considered as an alternative in such cases.
NOTE: The Company shall require that equipment easements on private
property be reasonably level. Also, all retaining walls shall fall outside of equipment easements and in no case shall they hamper door openings, safe operation (see DSEM 07.822) or placement of such equipment. Retaining wall design shall be approved by the Company.
g. Transformer vault shall be completely backfilled prior to commencing any
cable pulling.
IX. Secondary Vault (Hand hole)
a. Vaults shall be installed in accordance with details shown in DTR 54.201 or DTR 54.203.
b. Vaults shall be installed such that their covers will be flush with or slightly
above finish grade. In no case shall final grade cover or hamper access to the handhole covers.
9
c. A minimum of six inches base course of crushed stone (3/4 inch. max. stone size) or free-draining gravel shall be placed under all vault excavations and shall be thoroughly compacted using a vibratory compactor. Certain soil conditions may require excavation below normal depth. Additional clean fill or stone must be added and compacted to ensure a solid base course for the vault.
d. Vaults shall only be placed within equipment easements. They shall not be
placed within the sidewalk area or within the traveled way.
e. Covers shall be secured to all vaults immediately upon completion of their installation and backfilling.
X. Riser Pole
a. The Company shall designate conduit riser locations on the pole(s). Riser pole details shall be in accordance with DTR 12.057 and Figure 13.
b. All spare riser bends shall be terminated in a coupling and plugged or capped,
above ground at the pole base.
c. 90 bends at a riser pole shall be galvanized steel. All steel riser bends shall be grounded in accordance with Company requirements, as shown in Figure 13.
XI. Services
a. All services shall be single-phase, three-wire, 120/240 volts nominal. Reference shall be made to the WMECO Information & Requirements for Electric Supply Below 600 Volts booklet.
b. Provisions for future services shall be installed as shown in DTR 54.203 and
the attached related figures. XII. Street lighting
Conventional street lighting shall be installed in accordance with WMECO design specifications and located where indicated on construction plans. Contact a Company representative for Premium Decorative or other street lighting options.
XIII. Other Utilities
Conduit, terminal enclosures or other structures belonging to other utilities shall be located so they do not interfere with electrical installations nor impede the operation or maintenance of electrical facilities. Refer to DSEM 07.822 for a sketch indicating the acceptable zone(s) for installation of above-ground facilities belonging to other utilities.
10
Appendices
Easement Procedure for Subdivisions
Conduit System Checklist
Material Specifications/Supplier Matrix
Approved Manufactures of Other related equipment
Matrix Construction
Construction Pictures
Detailed Underground/DB Construction Specifications
11
APPENDICES Easement Procedure for Subdivision
The owner of a subdivision must provide a fully executed Utility Easement to WMECO specifications prior to the installation of any WMECO facilities.
The following information is required to process the Utility Easement:
Property owner’s name and address. Attorney’s name and address. Surveyor’s name and address. Subdivision name and address. Two copies of the approved subdivision plan. Property deed and plan book and page information. Mortgage holder name and address.
The Utility Easement area will include the proposed public way in its entirety, plus an additional ten (10) foot wide area along all lot frontages adjacent to the proposed public way. Any exceptions to this format will require approval of the WMECO field-engineering technician and real estate agent.
The subdivision owner or his attorney, working in conjunction with WMECO’s Real Estate Agent, must provide the easement document, a recordable plan showing the proposed utility easement area, subordination of mortgage holder, authorized signatures and notarization and recording of all documents.
The completed Utility Easement and plan will be submitted to WMECO’s Real Estate Agent for review prior to recording of the document.
Upon acceptance, the WMECO Real Estate Agent will notify the attorney to record the utility easement and associated plan, providing a copy of the recording information to WMECO’s Real Estate Agent.
12
SINGLE PHASE CONDUIT SYSTEM INSPECTION CHECKLIST Do not backfill BEFORE conduit system inspection and approval by the Company. Every item below must be inspected and checked off by a Company Representative. Any item found unacceptable must be initialed and rectified by the Developer prior to next inspection.
N* Y* TRENCH / CONDUIT Min. 30” depth from finished grade to top of primary and secondary conduit. Min. 24” depth from finished grade to top of service conduit Conduit minimum size 3” diameter Schedule 40 PVC, electrical grade. Min. 18” clearance in all directions between electric conduits and adjacent water, sewer,
fuel, (oil or gas) lines, and building foundations. 1/4-inch diameter nylon pull line, including 10 ft. of slack, installed and secured in conduit
with conduit plugs at both ends. Clean backfill (with less than 2” stones) on-site for backfilling entire trench, (inspector may
witness backfilling). Caution Tape – spot check. Conduit run conforms to layout in construction plan. No parallel conduits or other facilities directly above electrical system conduits. SECONDARY VAULT (HANDHOLE) 6” of crushed stone or compacted free draining gravel under vault. Vault is level. Covers installed and properly secured. Conduit plugs with ¼” diameter nylon pull line installed in all conduit ends. 3” of conduit extended into vault and properly labeled. Gaps around conduit at knockouts sealed with cement mortar. Correct orientation to road and lot lines. TRANSFORMER VAULT 6” crushed stone or compacted free-draining gravel under transformer vault. Vault is level. Top of pad surface 3” above final grade. 3” of conduit extended into vault and properly labeled. Pulling eyes properly secured in place. Conduit plugs with ¼” diameter nylon pull line installed in all conduit ends. Two ground rods installed with #6 bare cu. ground wire, spaced a minimum 8 feet apart. Bond wires provided for Telephone and Cable companies – 10’ minimum. Gaps around conduit at knockouts sealed with cement mortar. RISER POLE 90 degree galvanized steel bend installed as specified. Bend capped and secured to pole with pipe strap. Steel-PVC adapter and steel sweep not encased in concrete. Ground clamp and 6’ ground conductor installed. Conduit riser located on field side of pole opposite direction of traffic. Riser path clear to top of pole.
*NOTE: Y – Acceptable; N – Deficient
13
NU-Approved Precast Suppliers
SP
C H
-020
36"
Ro
un
d H
H
SP
C H
-019
60"x
56"
Hex
Han
dh
ole
SP
C P
-017
48"x
48"x
4" P
ad -
FG
En
c
SP
C P
-009
42"x
48"x
4" P
ad -
XF
MR
SP
C P
-010
Pad
Plu
g f
or
XF
MR
Pad
SP
C P
-013
-014
76"x
54"x
36"
Pad
75-
300
SP
C P
-015
-016
76"x
70"x
36"
Pad
500
& >
SP
C E
-946
Ext
ensi
on
-HH
Hex
36"
x4"
SP
C E
-953
Ext
ensi
on
fo
r H
H 3
6'x4
"
SP
C C
-710
42"
FG
Co
ver
Advance Materials, Inc.11 Colton RoadEast Lyme, CT 06333(860) 691-8350
X
Arrow Concrete Products, Inc.539 Oronoque RoadMilford, CT 06460(203) 301-5091 or at560 Salmon Brook StreetGranby, CT 06035(860) 653-5063 21
X
Atlas Concrete Products, Inc.575 Wallingford RoadDurham, CT 06422(860) 349-1751
X X X X X X
Connecticut Precast Corporation555 Fan Hill RoadMonroe, CT 06468(203) 268-8688
X X X X
Cromwell Concrete Products, Inc.667 Main StreetCromwell, CT 06416(860) 529-3417
X X X X
Eastern PrecastRoute 133Brookfield, CT 06805(203) 775-9380
X X X X
Jolley Precast, Inc.463 Putnam RoadDanielson, CT 06239(860) 774-9066
X X X X X X X
Oldcastle Precast151 Old Farms RoadAvon, CT 06001(860) 673-3291
X X
United Concrete Products, Inc.173 Church StreetYalesville, CT 06492(203) 269-3119
X X X X X X X
NU Material Specification
14
NU-Approved Manufacturers of Other Related Equipment Cover, Handhole, Hexagon/Round, 42” Dia., Fiberglass (SPC C-710)(SC 0174819)
Advanced Materials Inc. (AM-42) Holbeck By desc.
Nordic (NDC-42) Extension, Hexagonal Handhole, Precast, 36” Dia. x 4” High (SPC E-946)(SC 0174901)
Concast (HE-44) United Concrete Products, Inc. (By Desc)
Extension, Vault, Precast, 180-Deg. Section-36” Dia. x 4” H (SPC E-953)(SC0174870)
Concast (HE-42) United Concrete Products, Inc. (by Desc)
Extension, Handhole, Lawn
Fargo (B-120TK) (SC 0174875) PENCELL (PE-20-5) (SC 0174876)
Ground Rods (SC 0175362) Carolina (By Desc) Chance (8578) Galvan (GR6258) Joslyn (J5328) Ground Connector (SC 0178957) Blackburn (JAB58H) Joslyn (J8492) Burndy (GRC58) O-Z (GRC-62-10B) Dossert (GN62) Southport (GC31) Conduit Plugs, 3-inch 4-inch
Electrical Materials (COND PL3) (SC 0434785) (COND PL4) (SC 0434786)
Handhole, Lawn, Plastic (SC 0174991) PEN-CELL (PE-30HDX-EWB) Carson (1730183HGE20AUO) Handhole, Sidewalk, Polymer Concrete (SC 0174994) CDR (PA12-1730-18) Quazite (PG1730BA18/HA17) Highline (CHA173018HE1) Handhole, Streetlight (SC 0174953) PEN-CELL (PE-10X) Hill Holder – (SC 0183406 – 16”, SC 0183407 – 32”, SC 0183409 – 20”) Nordic (NHH-16-46-52) 16” back height (NHH-20-54-52) 20” back height (NHH-32-46-52) 32” back height
15
NU and Customer / Contractor Responsibilities
NU CONTRACTOR ITEM Provides Installs Provides Installs HIGH VOLTAGE PRIMARY SYSTEM Trench / Backfill X X Conduit X X ¼-Inch Diameter Nylon Pull Line X X Marking Tape (Red, Warning) X X Transformer Box Pads X X Switch Foundations X X Handholes / Splice Boxes X X Primary Cable X X Switching Devices X X Terminations X X Ground System per NU Standards X X LOW VOLT. SECONDARY SYSTEM Trench / Backfill X X Conduit X X ¼-Inch Diameter Nylon Pull Line X X Marking Tape (Red, Warning) X X Handholes / Splice Boxes / Pedestals X X Secondary Cable / Wire X X Connectors X X Ground System per NU Standards X X CUSTOMER SERVICE LATERAL Trench / Backfill X X Conduit X X Service Conductors (to distribution facilities) X X Connectors (at transformer or secondary HH) X X Meter Socket (Manual Bypass Type) X X Ground System per NU Standards X X TRANSFORMERS Conventional X X Padmount X X STREET LIGHTING Trench / Backfill X X Conduit X X Bases X X Marking Tape (Red, Warning) X X MISCELLANEOUS Easement (granting of) X Easement drawings / documents X Environmental Permits / Releases X Contribution in Aid of Construction Payment X As-built drawings X STATE OF MASSACHUSETTS REQUIREMENT Call DIG SAFE AT 1-888-344-7233 X
16
Pul
ling
Eye
Pul
ling
Eye
--C
heck
Tig
htne
ssC
heck
Tig
htne
ss--
Do
Not
Rem
ove
Do
Not
Rem
ove
note
: Sil
o to
be
set o
nno
te: S
ilo
to b
e se
t on
66 ”” o
f S
tone
of S
tone
Duc
t Plu
gD
uct P
lug
(In
All
Con
duit
s)(I
n A
ll C
ondu
its)
1/4
1/4 ””
Pul
l Lin
eP
ull L
ine
(In
All
Con
duit
s)(I
n A
ll C
ondu
its)
Gro
ut M
ust B
e U
sed
To
Gro
ut M
ust B
e U
sed
To
Sea
l Ope
ning
Sea
l Ope
ning
Con
duit
To
Pro
trud
eC
ondu
it T
o P
rotr
ude
33 ”” i
nto
Sil
o O
peni
ngin
to S
ilo
Ope
ning
Typ
ical
Sec
ond
ary
Vau
lt I
nte
rior
(Fig
ure
1)
Lot
1
Mar
k D
esti
nati
ons
Mar
k D
esti
nati
ons
on C
ondu
it a
nd S
ilo
on C
ondu
it a
nd S
ilo
Lot
2L
ot 2
17
Rea
r V
iew
of
a T
ypic
alS
econ
dar
y V
ault
(Fig
ure
2)
Roa
d R
oad
Pro
pert
y L
ine
Pro
pert
y L
ine
45 d
egre
e or
45 d
egre
e or
22.5
deg
ree
22.5
deg
ree
Ben
dB
end
Gro
ut F
ill
Gro
ut F
ill
To
Fut
ure
Hou
seT
o F
utur
e H
ouse
To
Fut
ure
Hou
se
To
Fut
ure
Hou
se
Tel
or
Tel
or
CA
TV
CA
TV
Tel
or
CA
TV
Tel
or
CA
TV
note
: All
Con
duit
to b
eno
te: A
ll C
ondu
it to
be
33 ”” P
VC
, Sch
edul
e 40
PV
C, S
ched
ule
40
Min
imu
mM
inim
um
of 2
4of
24 ””
Cle
aran
ceC
lear
ance
Tel
or
CA
TV
Tel
or
CA
TV
Are
aA
rea
Tel
or
Tel
or
CA
TV
CA
TV
Are
aA
rea
note
:no
te:
Sil
o to
be
set o
nS
ilo
to b
e se
t on
66 ”” o
f S
tone
of S
tone
Min
.M
in.
2424””
Cle
aran
ceC
lear
ance
18
Typ
ical
Sec
ond
ary
Vau
lt L
ayou
t(F
igu
re 3
)
Sec
onda
ry f
rom
Sec
onda
ry f
rom
Tra
nsfo
rmer
Vau
ltT
rans
form
er V
ault
Lim
it o
f E
asem
ent
Lim
it o
f E
asem
ent
Tel
or
CA
TV
Tel
or
CA
TV
Tel
or
CA
TV
Tel
or
CA
TV 4242
””F
iber
glas
s C
over
Fib
ergl
ass
Cov
er
Pro
pert
y L
ine
Pro
pert
y L
ine
House
Ser
vice
House
Ser
vice
Hou
se S
ervi
ce
Hou
se S
ervi
ceM
inim
um
Min
imu
m2424
””C
lear
ance
Cle
aran
ce
En
clos
ure
Are
aE
ncl
osu
re A
rea
for
for
Tel
or
Tel
or
CA
TV
CA
TV
En
clos
ure
Are
aE
ncl
osu
re A
rea
for
for
Tel
or
Tel
or
CA
TV
CA
TV not
e: A
ll C
ond
uit
to
be
not
e: A
ll C
ond
uit
to
be
33 ”” P
VC
PV
CS
ched
ule
40
Sch
edu
le 4
0
not
e:n
ote:
Sil
o to
be
set
onS
ilo
to b
e se
t on
66 ”” o
f S
ton
eof
Sto
ne
2424””
Min
.M
in.
45 o
r 45
or
22.5
22.5
Deg
ree
Deg
ree
Ben
ds
Ben
ds
Roa
dR
oad
Plu
gP
lug
(in
all
con
du
its)
(in
all
con
du
its)
¼”
¼”
Lin
eL
ine
(in
all
con
du
its)
(in
all
con
du
its)
19
Lim
it o
f E
asem
ent
Lim
it o
f E
asem
ent
Pro
per
ty L
ine
Pro
per
ty L
ine
Roa
Roa
dd
Typ
ical
Sec
onda
ryV
ault
Lay
out
(Fig
ure
4)
Sec
ond
ary
from
Sec
ond
ary
from
Tra
nsf
orm
er V
ault
Tra
nsf
orm
er V
ault
Tel
or
CA
TV
Tel
or
CA
TV
Tel
or
CA
TV
Tel
or
CA
TV
Hou
se S
ervi
ceH
ouse
Ser
vice
Hou
se S
ervi
ceH
ouse
Ser
vice
not
e: a
ll c
ond
uit
to
be
not
e: a
ll c
ond
uit
to
be
33 ”” P
VC
PV
CS
ched
ule
40
Sch
edu
le 4
0
En
clos
ure
Are
aE
ncl
osu
re A
rea
for
Tel
or
for
Tel
or
CA
TV
CA
TV
En
clos
ure
Are
aE
ncl
osu
re A
rea
for
Tel
or
for
Tel
or
CA
TV
CA
TV
Min
imu
mM
inim
um
2424””
Cle
aran
ceC
lear
ance
Min
imu
mM
inim
um
2424””
Cle
aran
ceC
lear
ance
Ser
vice
Stu
bS
ervi
ce S
tub
Ser
vice
Stu
bS
ervi
ce S
tub
lot
# to
be
wri
tten
inlo
t #
to b
e w
ritt
en in
Per
man
ent
Mar
ker
Per
man
ent
Mar
ker
lot
# to
be
wri
tten
inlo
t #
to b
e w
ritt
en in
Per
man
ent
Mar
ker
Per
man
ent
Mar
ker
Sil
o to
be
set
onS
ilo
to b
e se
t on
66 ”” o
f S
ton
eof
Sto
ne
Gro
ut
Fil
lG
rou
t F
ill
45 o
r 22
.545
or
22.5
Deg
ree
Deg
ree
Ben
ds
Ben
ds
1010’’
Ser
vice
Stu
bS
ervi
ce S
tub
Fro
m S
econ
dar
yF
rom
Sec
ond
ary
Vau
ltV
ault
Ser
vice
Stu
bS
ervi
ce S
tub
Con
du
it P
lug
Con
du
it P
lug
1/4
1/4 ””
Pu
ll L
ine
Pu
ll L
ine
not
e: A
ll C
ond
uit
to
not
e: A
ll C
ond
uit
to
be
be
33 ”” P
VC
PV
CS
ched
ule
40
Sch
edu
le 4
0
Typ
ical
Ser
vice
Stu
b(F
igu
re 5
)
Typ
ical
Tra
nsf
orm
erV
ault
In
teri
or (
Fig
ure
6)
Pul
ling
Eye
Pul
ling
Eye
--C
heck
Tig
htne
ssC
heck
Tig
htne
ss--
Do
Not
Rem
ove
Do
Not
Rem
ove
1010’’ -
---#6
cu
#6 c
uG
roun
d W
ire
Gro
und
Wir
eE
nter
Und
er S
ilo
Ent
er U
nder
Sil
o
note
:no
te:
Sil
o to
be
set o
nS
ilo
to b
e se
t on
66 ”” o
f S
tone
of S
tone
Rem
ovab
leR
emov
able
Con
duit
Plu
gC
ondu
it P
lug
In A
ll C
ondu
its
In A
ll C
ondu
its
1/4
1/4 ””
Pul
l Lin
eP
ull L
ine
Gro
ut M
ust B
e U
sed
Gro
ut M
ust B
e U
sed
To
Sea
l Ope
ning
To
Sea
l Ope
ning
Con
duit
To
Pro
trud
eC
ondu
it T
o P
rotr
ude
33 ”” m
ax in
to S
ilo
Ope
ning
max
into
Sil
o O
peni
ng
Mar
k D
esti
nati
ons
Mar
k D
esti
nati
ons
on S
ilo
and
Con
duit
on S
ilo
and
Con
duit
Pul
ling
Eye
Pul
ling
Eye
--C
heck
Tig
htne
ssC
heck
Tig
htne
ss--
Do
Not
Rem
ove
Do
Not
Rem
ove
Prim
ary
From
From Po
lePo
le
Sec.
Sec. T
oT
o
HH
H
H 7
40A
ToTo
HH 740
HH 740
22
Sec.
toH
H 7
40A
Prim
ary
topa
d 74
2
1010’’ -
---#6
cu
Gro
und
Wir
e#6
cu
Gro
und
Wir
eC
oil E
nter
ing
Fro
mC
oil E
nter
ing
Fro
mU
nder
neat
h V
ault
Und
erne
ath
Vau
lt
Gro
ut M
ust B
e U
sed
Gro
ut M
ust B
e U
sed
To
Sea
l Ope
ning
To
Sea
l Ope
ning
Con
duit
To
Pro
trud
eC
ondu
it T
o P
rotr
ude
33 ”” m
ax in
to S
ilo
Ope
ning
max
into
Sil
o O
peni
ng
Mar
k D
esti
nati
ons
Mar
k D
esti
nati
ons
on S
ilo
and
Con
duit
on S
ilo
and
Con
duit
Typ
ical
Tra
nsf
orm
er(o
r S
wit
ch)
Vau
lt I
nte
rior
(Fig
ure
7)
Pul
ling
Eye
Pul
ling
Eye
--C
heck
Tig
htne
ssC
heck
Tig
htne
ss--
Do
Not
Rem
ove
Do
Not
Rem
ove
not
e: I
nst
all R
emov
able
not
e: I
nst
all R
emov
able
Plu
gs a
nd
Pu
ll L
ines
Plu
gs a
nd
Pu
ll L
ines
In A
ll C
ondu
its
In A
ll C
ondu
its
23
Pro
pert
y L
ine
Pro
pert
y L
ine
lot
# to
be
wri
tten
inlo
t #
to b
e w
ritt
en in
Per
man
ent
Mar
ker
Per
man
ent
Mar
ker
lot
# to
be
wri
tten
inlo
t #
to b
e w
ritt
en in
Per
man
ent
Mar
ker
Per
man
ent
Mar
ker
Pri
mar
y fr
om P
ole
Pri
mar
y fr
om P
ole
to S
econ
dar
y V
ault
to S
econ
dar
y V
ault
Pri
mar
y to
Tra
nsf
orm
erP
rim
ary
to T
ran
sfor
mer
Sec
ond
ary
toS
econ
dar
y to
Roa
d C
ross
ing
Roa
d C
ross
ing
Duc
t P
lug
&D
uct
Plu
g &
1/4
1/4 ””
Pu
ll L
ine
Pu
ll L
ine
Tel or C
ATV
Tel or C
ATVTel o
r CATV
Tel or CATV
Ser
vice
Stu
bS
ervi
ce S
tub
Ser
vice
Stu
bS
ervi
ce S
tub
To
Sec
ond
ary
To
Sec
ond
ary
Vau
ltV
ault
Typ
ical
Tra
nsf
orm
er&
Ser
vice
Vau
lt(F
igu
re 8
)
not
e: a
ll c
ond
uit
to
be
not
e: a
ll c
ond
uit
to
be
33 ”” P
VC
PV
CS
ched
ule
40
Sch
edu
le 4
0
En
clos
ure
Are
aE
ncl
osu
re A
rea
for
Tel
or
for
Tel
or
CA
TV
CA
TV
En
clos
ure
Are
aE
ncl
osu
re A
rea
for
Tel
or
for
Tel
or
CA
TV
CA
TV
Hou
seH
ouse
Ser
vice
Ser
vice
Hou
seH
ouse
Ser
vice
Ser
vice
Eas
emen
tE
asem
ent
Min
imu
mM
inim
um
3030””
Cle
aran
ceC
lear
ance
not
e:n
ote:
Sil
os s
et o
nS
ilos
set
on
66 ”” o
f S
ton
eof
Sto
ne
Gro
ut
Fil
lG
rou
t F
ill1
ft.
1 ft
.S
ervi
ceS
ervi
ceV
ault
Vau
lt Tra
nsf
orm
erT
ran
sfor
mer
Vau
ltV
ault
88 ’’ G
rou
nd
Rod
Gro
un
d R
od(d
rive
n in
th
e tr
ench
)(d
rive
n in
th
e tr
ench
)
88 ’’ G
rou
nd
Rod
Gro
un
d R
od(d
rive
n in
th
e tr
ench
)(d
rive
n in
th
e tr
ench
)
88 ’’ m
in. a
par
tm
in. a
par
t1010
’’ co
ilco
il-- #
6 C
u G
roun
d W
ire
#6 C
u G
roun
d W
ire
En
teri
ng
Un
der
Silo
En
teri
ng
Un
der
Silo
66’’-- #
6 cu
Gro
un
d W
ire
Coi
l#6
cu
Gro
un
d W
ire
Coi
l
66 ’’-- #
6 cu
#6 c
uG
rou
nd
Wir
eG
rou
nd
Wir
eC
oil
Coi
l
#6 C
u G
roun
d #6
Cu
Gro
und
Wir
e E
nte
ring
Wir
e E
nte
ring
Un
der
Silo
Un
der
Silo
1010’’
coil
coil
-- Roa
dR
oad
Tel
or
Tel
or
CA
TV
CA
TV
Tel
or
Tel
or
CA
TV
CA
TV
Pri
mar
y fr
om P
ole
Pri
mar
y fr
om P
ole
Pri
. to
XF
MR
Pri
. to
XF
MR
to S
econ
dar
y V
ault
to S
econ
dar
y V
ault
to S
econ
dary
Vau
ltto
Sec
onda
ry V
ault
Rem
ovab
leR
emov
able
Con
du
it P
lug
Con
du
it P
lug
In A
ll C
ond
uit
sIn
All
Con
du
its
1/4
1/4 ””
Pu
ll L
ine
Pu
ll L
ine
in a
ll c
ond
uit
sin
all
con
du
its
Tel
or
Tel
or
CA
TV
CA
TV
Sec
ond
ary
toS
econ
dar
y to
Roa
dR
oad
Cro
ssin
gC
ross
ing
Tel
or
Tel
or C
AT
VC
AT
Var
eaar
eaT
el o
r C
AT
VT
el o
r C
AT
VA
rea
Are
a
3030””
Min
imu
mM
inim
um
3030””
Min
.M
in.
1010’’ -
---#6
cu
#6 c
uG
rou
nd
Wir
eG
rou
nd
Wir
eC
oil F
rom
Coi
l Fro
mU
nd
ern
eath
Un
der
nea
th
Tra
nsf
orm
er (
or S
wit
ch)
Vau
lt L
ayou
t (F
igu
re 9
)
All
Con
du
it
All
Con
du
it
33 ”” P
VC
PV
CS
ched
ule
40
Sch
edu
le 4
0
88 ’’ G
rou
nd
Rod
Gro
un
d R
odd
rive
n in
th
e tr
ench
dri
ven
in t
he
tren
chS
ilo
set
onS
ilo
set
on66 ””
of
Sto
ne
of S
ton
e88 ’’
Gro
un
d R
odG
rou
nd
Rod
dri
ven
in t
he
tren
chd
rive
n in
th
e tr
ench
66 ’’ Coi
lC
oil
To
To
Sec
ond
ary
Sec
ond
ary
Vau
ltV
ault
Sec.
11 ’’ L
ong
Lon
g
66 ’’ Coi
lC
oil
25
Primary from polePrimary from pole
to Secondary Vaultto Secondary VaultPrimary to TransformerPrimary to Transformerto Secondary Vaultto Secondary Vault
Tel or C
AT
V
Tel or C
AT
V
Secondary toSecondary toRoad CrossingRoad Crossing
Typical Transformer &Service Vault Layout
(Figure 10)
88’’ Ground RodGround RodDriven InDriven In
The TrenchThe Trench
88’’ Ground RodGround RodDriven InDriven In
The TrenchThe Trench
88’’ min. apartmin. apart
1010’’----#6 cu#6 cuGround WireGround WireCoil EnteringCoil Entering
Under SiloUnder Silo
PlugPlug(all conduits)(all conduits)
1/41/4””Pull LinePull Line
3030””MinimumMinimum
3030””
MinMin..66’’CoilCoil
66’’ -- #6 cu#6 cuGround WireGround Wire
CoilCoil
Tel orTel orCATVCATVAreaArea
Tel orTel orCATV AreaCATV Area
note:note:Silos set onSilos set on66”” of Stoneof Stone
note:note:All Conduit All Conduit 33”” PVCPVCSchedule 40Schedule 40
SecondarySecondaryServiceServiceVaultVault
1 ft1 ft..
Sec
Secondary toSecondary toService VaultService Vault
PlugPlug(all conduits)(all conduits)TransformerTransformer
VaultVault
45 or 22.545 or 22.5DegreeDegreeBendsBends
Property LineProperty Line
EasementEasement
House Service
House Service House
Ser
vice
House
Ser
vice
¼”¼” LineLine
26
Pro
per
tyP
rop
erty
Lin
eL
ine
Eas
emen
tE
asem
ent
Typ
ical
Sec
ond
ary
Typ
ical
Sec
ond
ary
Roa
d C
ross
ing
Roa
d C
ross
ing
(Fig
ure
11)
(Fig
ure
11)
1/4
1/4 ””
Pu
ll L
ine
Pu
ll L
ine
Rem
ovab
leR
emov
able
Con
du
it P
lug
Con
du
it P
lug
(in
all
(i
n a
ll
con
du
its)
con
du
its)
27
Tel
or
CA
TV
Tel
or
CA
TV
Pri
mar
y fr
om P
ole
Pri
mar
y fr
om P
ole
to S
econ
dary
Vau
lt
to S
econ
dary
Vau
lt
Hou
seH
ouse
Ser
vice
Ser
vice
Tel
or
CA
TV
Tel
or
CA
TV
Tra
nsf
orm
er(o
r Sw
itch
) V
ault
Gro
un
d R
od (
Fig
ure
12)
88 ’’ G
rou
nd
Rod
Gro
un
d R
odD
rive
n I
n T
he
Tre
nch
Dri
ven
In
Th
e T
ren
ch
#6 C
opp
er#6
Cop
per
Gro
un
d W
ire
Gro
un
d W
ire
1010’’
Coi
l In
sid
eC
oil I
nsi
de
Sil
o, E
nte
rin
gS
ilo,
En
teri
ng
Fro
m U
nd
ern
eath
Fro
m U
nd
ern
eath
Sin
gle
Ru
nS
ingl
e R
un
Pas
sin
g T
hro
ugh
Pas
sin
g T
hro
ugh
Th
e C
lam
pT
he
Cla
mp
66 ’’ C
oil
Coi
l --
#6
#6
Cop
per
Cop
per
for
for
Tel
or
CA
TV
Tel
or
CA
TV
Gro
un
dG
rou
nd
Ch
eck
Tig
htn
ess
Ch
eck
Tig
htn
ess --
Do
Not
Rem
ove
Do
Not
Rem
ove
Gro
ut
Mu
st B
e U
sed
Gro
ut
Mu
st B
e U
sed
To
Sea
l Op
enin
gsT
o S
eal O
pen
ings
not
e:n
ote:
Sil
o se
t on
Sil
o se
t on
66 ”” o
f S
ton
eof
Sto
ne
not
e:n
ote:
All
Con
du
it
All
Con
du
it
33 ”” P
VC
PV
CS
ched
ule
40
Sch
edu
le 4
0
Cla
mp
Cla
mp
28
30 d
eg.
30 d
eg.
Ele
ctri
cE
lect
ric
CA
TV
CA
TV
&& Tel
Tel
Roa
dR
oad
Pol
eP
ole
Det
ail
Det
ail
AA
AA
Tel
&
Tel
& C
AT
VC
AT
V
Pri
mar
y or
Sec
onda
ryP
rim
ary
or S
econ
dary1/
41/
4 ”” P
ull
Lin
eP
ull
Lin
e
Con
du
itC
ond
uit
Plu
gP
lug
1212””
min
imu
mm
inim
um
WM
EC
OW
ME
CO
Pol
e D
own
Gro
un
dP
ole
Dow
n G
rou
nd
Cop
per
Cop
per
Gro
un
d W
ire
Gro
un
d W
ire
AAAA
Cla
mp
Cla
mp
RoadRoad
88 ’’ G
rou
nd
Rod
Gro
un
d R
odD
rive
n I
n T
he
Tre
nch
Dri
ven
In
Th
e T
ren
ch
Ste
el S
wee
pS
teel
Sw
eep
2 ft
. Min
imu
m R
adiu
s2
ft. M
inim
um
Rad
ius
Ste
el S
wee
pS
teel
Sw
eep
Gro
un
d C
lam
pG
rou
nd
Cla
mp
Typ
ical
Ris
erG
rou
nd
edS
teel
Sw
eep
(Fig
ure
13 )
Act
ual
Fin
al G
rad
e L
evel
Act
ual
Fin
al G
rad
e L
evel
29
RoadRoad
TypicalRoad Crossing
Layout(Figure 14)
For Specific For Specific InformationInformationDetailsDetailsSee Figure 10See Figure 10
For SpecificFor SpecificInformation Information DetailsDetailsSee figure 11See figure 11
30
Pad
mou
nt
Tra
nsf
orm
er(F
igu
re 1
5)
Single-Phase DB in ConduitUnderground/DB DesignSection 07.82
07.821
Distribution System Engineering ManualNortheast UtilitiesFebruary 2003
SCOPE - This Standard covers the general requirements for electric utility installation of single-phasedirect-buried cables in conduit.
GENERAL - The preferred method of providing electrical service is installation of direct -buried electrical cables inconduit. All installations of electrical cables in conduit shall adhere to the 1997 NESC (National Electrical SafetyCode), in addition to the following requirements:
1. TRENCH - Trench location shall be in as direct a line as possible without reverse bends between distributionfacilities and from the distribution facility to the customer service entrance. In order to minimize cable pullingforces, no more than two bends (not including riser at house or pole) exceeding a total change of 45 degreesshall be permitted.
a. The trench bottom shall be undisturbed or relatively smooth earth, well tamped, and free of any debristhat may be detrimental to the conduit. Excavation shall be of a size and extent to permit properinstallation of conduit and structures as required.
1) Where excavation is in rock, it shall be removed to 4 inches below the trench bottom. The overexcavation shall be replaced with a bedding of gravel, sand or clean, well tamped backfill.
2) Backfill shall not contain ashes, cinders, shells, frozen material, loose debris, or stones larger than 2 inches in maximum dimension. Backfill shall be compacted.
b. Conduit in the trench should have a 4 inch per 100 feet downward pitch toward the distribution facility, if physically possible. (This provides drainage away from service entrance, prevents stagnant water in duct.)
c. Trench shall be of such depth to accommodate 30 inches minimum cover for primary and secondarycables in conduit installed along the roadway easement, and 24 inches minimum cover for secondary orservice cables in conduit on private property.
2. CONDUIT - Standard conduit shall be minimum 3- inch diameter, rigid PVC, heavy wall, sunlight resistant(6% -7% titanium dioxide by weight), Schedule 40 as per NEMA TC2-1990.
a. Limit the number of electric utility conduits to a maximum of four per trench.
b. Install conduit, with all joints cemented, through knockout and extend 4 inches inside handhole.Terminate conduit run with end bell (e.g., SC 0177110 for 3- inch diameter). Conduit destination shall bepermanently marked on conduit end.
c. Gaps around conduit at knockout openings shall be sealed with cement mortar to prevent backfillentering the handhole.
d. A 1/4- inch-diameter nylon pull line shall be installed in each duct, including 10 feet of slack, and securedto conduit plug. Each end of the conduit shall be sealed with a conduit plug (e.g., SC 0175141 for 3- inchdiameter), and left accessible.
e. Bends in the conduit run shall have a minimum radius of 48 inches. This requirement does not includebends used at house or pole risers where the bend radius shall be a minimum of 24 inches, with 36 inches preferred.
3. PRIMARIES - For primary in conduit, a separate bare copper grounded neutral conductor and anodes arenot required.
a. Install primary in conduit at a minimum depth of 30 inches below finished grade.
32
Single-Phase DB in ConduitUnderground/DB DesignSection 07.82
07.822
Distribution System Engineering ManualNortheast UtilitiesFebruary 2003
b. Because of grounding requirements, each section of primary in conduit is limited to a maximum of 750 feet when other utilities are in the trench. When the electric utility is sole occupant in the trench,each section of primary in conduit is limited to a maximum length of 1700 feet. (Note: Length may belimited to 1000 feet if district utilizes 1000- foot emergency primary reel trailer.)
c. The Company reserves the right to limit runs where cable pulling forces exceed recommended maximums.
4. SECONDARIES and SERVICES - The Company reserves the right to limit services in conduit which requirea cable installation pulling force in excess of 2000 pounds.
a. Conduit for secondaries and services on private property shall be installed at a minimum depth of 24 inches below finished grade.
b. Secondaries or services in conduit, installed in the same trench as primaries or on public right -of -way,shall be at a minimum depth of 30 inches below finished grade.
2′2′
3′
6′
A clearance zone of 4′ wide x 3′ deep x 6′ high isrequired at the customer end of the service. Keepshrubs, debris, fences, and other structures clear ofthis area. (Refer to sketch at right.)
c.
a. The grounding interval for primaries in the trenchwith other utilities shall be not less than eight per mile.
b. For primaries with sole occupancy in the trench, thegrounding interval shall be not less than four per mile.
GROUNDING - Primaries shall be grounded at allhandholes, structures and enclosures.
5.
6. OTHER UTILITIES - Conduit, terminal enclosures, or structures belonging to other utilities shall be locatedsuch as to not interfere with electrical installations nor impede the operation and maintenance of electrical facilities.
a. The acceptable zone for installation of above-ground facilities belonging to other utilities is as shown below.
3.5′
3.5′
3′
10 FT
3 FT
b. No shrubs, fences, or permanent structures can be placedwithin 10 feet of the front and 3 feet of the sides and back ofpad-mounted transformers. The Company has the right toremove these obstructions without notice to the owner. Foradditional clearances see DTR 42.047 and DTR 42.061.
3 FT
ÄÄÄÄÄÄÄÄÄÄÄÄ
ÄÄÄÄÄÄÄÄÄÄÄÄ
ÄÄÄÄÄÄÄÄÄ
ÄÄÄÄÄÄÄÄÄROAD SIDE
FIELD SIDE
10′ EASEMENT1′
3′
ÄÄÄÄ
LEGEND:
Electric Company Pad or VaultAcceptable Zone for Installation of Above-Ground Facilities Belongingto Other Utilities
1′
33
FINISHED GRADE
WARNING SIGN
76/2/05
11/23/76
NORTHEAST UTILITIES CONSTRUCTION STANDARD
APPROVED
ORIGINAL
SECONDARY AND SERVICE RISERS − 600 VOLT CABLE
36″ MAX
NOTE 2
SCHEDULE 80 PVC, UNLESSSPECIFIED OTHERWISE
2″ NOTE 1
6′
DTR 12.057
CABLE GRIP ATTACHMENT
SECONDARY OR NEUTRALATTACHMENT
See DSEM Section 07.82for trench specifications
SCHEDULE 40 PVC
Notes1. Top of conduit to extend at least 2 inches above the neutral/secondary attachment.2. Seal conduit from water entry at top of riser for services installed in conduit for the entire run. See DTR 12.010.3. Steel conduit shall be grounded. If the steel elbow is installed in a nonmetallic conduit installation, it shall also be
grounded. Use 5/8″ x 8′ galvanized steel ground rod and ground clamp.4. Preferred location for riser placement is on field side of pole opposite the direction of traffic. Check riser path for
obstructions, and coordinate with other utilites for placement of risers and any equipment. (Road side of poleopposite the direction of traffic is reserved for road crossings.)
5. Contact the toll−free telephone number to locate buried cables before driving ground rods.
90° STEEL BEND(ELBOW)
#6 OR #4COPPER WIRE
GROUND CLAMP
GROUND RODNOTE 3
4″ MIN
TRAFFIC FLOW
CURB/EDGE OFROADWAY
A A
A − A
NOTE 4
RISER POLE
SEE DTR 04.075
MINIMUM 12″
______________________________________________________________________________________________________________________________________________________
| CONSTRUCTION STANDARD VARIATION | CONSTRUCTION UNIT IDENTIFIER |
|____________________________________________________________________________________________________________________________________________________|
| A SINGLE PHASE 600V 1/0 AL 3CT RISER DB | DTR12.057.3A |
| B SINGLE PHASE 600V 1/0 AL 3CT RISER UG | DTR12.057.3B |
| C SINGLE PHASE 600V 1/0 AL 3CT RISER SVC | DTR12.057.3C |
| D SINGLE PHASE 600V 4/0 AL 3CT RISER DB | DTR12.057.3D |
| E SINGLE PHASE 600V 4/0 AL 3CT RISER UG | DTR12.057.3E |
| F SINGLE PHASE 600V 4/0 AL 3CT RISER SVC | DTR12.057.3F |
| G SINGLE PHASE 600V 350 AL 3CT RISER DB | DTR12.057.3G |
| H SINGLE PHASE 600V 350 AL 3CT RISER UG | DTR12.057.3H |
| I SINGLE PHASE 600V 350 AL 3CT RISER SVC | DTR12.057.3I |
| J THREE PHASE 600V 1/0 AL 4CT RISER DB | DTR12.057.3J |
| K THREE PHASE 600V 1/0 AL 4CT RISER UG | DTR12.057.3K |
| L THREE PHASE 600V 1/0 AL 4CT RISER SVC | DTR12.057.3L |
| M THREE PHASE 600V 4/0 AL 4CT RISER DB | DTR12.057.3M |
|____________________________________________________________________________________________________________________________________________________|
| STOCK CODE QUANTITY | | | U=UNIT OF PROPERTY STOCK |
|________________________________________________________________| | | |
| M | L | K | J | I | H | G | F | E | D | C | B | A |UM| STOCK CODE DESCRIPTION | M=MINOR L=LOBBY CODE |
|____________________________________________________________________________________________________________________________________________________|
| | 20| 20| 20| 20| 20| 20| 20| 20| 20| 20| 20| 20|FT| CONDUIT PVC SCH 40 3 IN X 10 FT 3.500 OD BELLED | M M017471100 |
| | 10| 10| 10| 10| 10| 10| 10| 10| 10| 10| 10| 10|FT| CONDUIT PVC SCH 80 3 IN X 10 FT 2.900 ID BELLED | M M017458600 |
| 20| | | | | | | | | | | | |FT| CONDUIT PVC SCH 40 4 IN X 10 FT 4.500 OD BELLED | M M017471200 |
| 10| | | | | | | | | | | | |FT| CONDUIT PVC SCH 80 4 IN X 10 FT 3.826 ID BELLED | M M017458700 |
| | | | | 1| 1| 1| 1| 1| 1| 1| 1| 1|EA| BUSHING CONDUIT PVC RED 3-2 INV | L M017448600 |
| | 1| 1| 1| 1| 1| 1| 1| 1| 1| 1| 1| 1|EA| CLAMP GRND CPR F/4 SOL-2/0 STR 2 1/2 - 3 1/2 IN PIPE | L M017896400 |
| 1| | | | | | | | | | | | |EA| CLAMP GRND COND S/BRONZE 4 - 5 IN PIPE | L M017896500 |
| | 1| 1| | 1| 1| | 1| 1| | 1| 1| |EA| CONNECTOR CABLE GROUNDING COPPER #8-1/0 | L M017895700 |
| | 1| 1| | 1| 1| | 1| 1| | 1| 1| |EA| ROD GROUND G 5/8 IN X 8 FT | L M017536200 |
| 14| 14| 14| 14| 14| 14| 14| 14| 14| 14| 14| 14| 14|EA| SCREW DRIVE 0.25 IN 2.5 IN LG GALVANIZED HEX HEAD | L M019016600 |
| 1| 1| 1| 1| 1| 1| 1| 1| 1| 1| 1| 1| 1|EA| SIGN WARNING UG ELECTRIC CBL 2.5 IN X 2.5 IN F/COND RISERS | L M019410700 |
| 1| | | 1| | | 1| | | 1| | | 1|EA| SIGN WARNING CBL ALIVE BY BACK FEED 4 IN X 7 IN | L M018455200 |
| | 7| 7| 7| 7| 7| 7| 7| 7| 7| 7| 7| 7|EA| STRAP PIPE POLE 3 IN GS 1 IN W 2-1/4 IN H 15D | L M017667300 |
| 7| | | | | | | | | | | | |EA| STRAP PIPE POLE 4 IN GS 1 IN W 2 1/4 IN H 15DD | L M017667400 |
| | | | | 1| 1| 1| 1| 1| 1| 1| 1| 1|EA| WEATHERHEAD FOR 2 IN PVC COND SERVICE ENTRANCE | L M018146700 |
| | 1| 1| | 1| 1| | 1| 1| | 1| 1| 1|LB| WIRE TIE BARE CU #6 SOLID | L M018034900 |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
|____________________________________________________________________________________________________________________________________________________|
| PAGE DTR12.057.3A / M | ORIGINAL ISSUE 11 / 23 / 76 |
| |__________________________________________________|
| 1 OF 1 | REVISION DATE 02 / 01 / 05 |
| |__________________________________________________|
| NORTHEAST UTILITIES CONSTRUCTION STANDARD ESTIMATING UNITS | APPROVED BY |
|____________________________________________________________________________________________________________________________________________________|
35
______________________________________________________________________________________________________________________________________________________
| CONSTRUCTION STANDARD VARIATION | CONSTRUCTION UNIT IDENTIFIER |
|____________________________________________________________________________________________________________________________________________________|
| N THREE PHASE 600V 4/0 AL 4CT RISER UG | DTR12.057.3N |
| O THREE PHASE 600V 4/0 AL 4CT RISER SVC | DTR12.057.3O |
| P THREE PHASE 600V 350 AL 4CT RISER DB | DTR12.057.3P |
| Q THREE PHASE 600V 350 AL 4CT RISER UG | DTR12.057.3Q |
| R THREE PHASE 600V 350 AL 4CT RISER SVC | DTR12.057.3R |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
|____________________________________________________________________________________________________________________________________________________|
| STOCK CODE QUANTITY | | | U=UNIT OF PROPERTY STOCK |
|________________________________________________________________| | | |
| Z | Y | X | W | V | U | T | S | R | Q | P | O | N |UM| STOCK CODE DESCRIPTION | M=MINOR L=LOBBY CODE |
|____________________________________________________________________________________________________________________________________________________|
| | | | | | | | | | | | | |FT| CONDUIT PVC SCH 40 3 IN X 10 FT 3.500 OD BELLED | M M017471100 |
| | | | | | | | | | | | | |FT| CONDUIT PVC SCH 80 3 IN X 10 FT 2.900 ID BELLED | M M017458600 |
| | | | | | | | | 20| 20| 20| 20| 20|FT| CONDUIT PVC SCH 40 4 IN X 10 FT 4.500 OD BELLED | M M017471200 |
| | | | | | | | | 10| 10| 10| 10| 10|FT| CONDUIT PVC SCH 80 4 IN X 10 FT 3.826 ID BELLED | M M017458700 |
| | | | | | | | | | | | | |EA| BUSHING CONDUIT PVC RED 3-2 INV | L M017448600 |
| | | | | | | | | | | | | |EA| CLAMP GRND CPR F/4 SOL-2/0 STR 2 1/2 - 3 1/2 IN PIPE | L M017896400 |
| | | | | | | | | 1| 1| 1| 1| 1|EA| CLAMP GRND COND S/BRONZE 4 - 5 IN PIPE | L M017896500 |
| | | | | | | | | 1| 1| | 1| 1|EA| CONNECTOR CABLE GROUNDING COPPER #8-1/0 | L M017895700 |
| | | | | | | | | 1| 1| | 1| 1|EA| ROD GROUND G 5/8 IN X 8 FT | L M017536200 |
| | | | | | | | | 14| 14| 14| 14| 14|EA| SCREW DRIVE 0.25 IN 2.5 IN LG GALVANIZED HEX HEAD | L M019016600 |
| | | | | | | | | 1| 1| 1| 1| 1|EA| SIGN WARNING UG ELECTRIC CBL 2.5 IN X 2.5 IN F/COND RISERS | L M019410700 |
| | | | | | | | | | 1| 1| | 1|EA| SIGN WARNING CBL ALIVE BY BACK FEED 4 IN X 7 IN | L M018455200 |
| | | | | | | | | | | | | |EA| STRAP PIPE POLE 3 IN GS 1 IN W 2-1/4 IN H 15D | L M017667300 |
| | | | | | | | | 7| 7| 7| 7| 7|EA| STRAP PIPE POLE 4 IN GS 1 IN W 2 1/4 IN H 15DD | L M017667400 |
| | | | | | | | | | | | | |EA| WEATHERHEAD FOR 2 IN PVC COND SERVICE ENTRANCE | L M018146700 |
| | | | | | | | | 1| 1| | 1| 1|LB| WIRE TIE BARE CU #6 SOLID | L M018034900 |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
|____________________________________________________________________________________________________________________________________________________|
| PAGE DTR12.057.3N / R | ORIGINAL ISSUE 01 / 01 / 95 |
| |__________________________________________________|
| 1 OF 1 | REVISION DATE 02 / 01 / 05 |
| |__________________________________________________|
| NORTHEAST UTILITIES CONSTRUCTION STANDARD ESTIMATING UNITS | APPROVED BY |
|____________________________________________________________________________________________________________________________________________________|
36
18″ MININ ALL
DIRECTIONS
SCOPE − All direct−buried primary cables shall be of the jacketed type. The cables may be random−laid with thesecondaries and other utilities under certain conditions, detailed in DTR 44.101.
INSTALLATION IN TRENCH − All direct−buried cables shall be installed at a depth of at least 30 inches in thefollowing order:1. Ensure that the bottom of the trench is well−tamped and free of rocks.2. Install the conduit, gluing all couplings.3. Install secondaries and other utility cables or conduits in the trench.4. Backfill with 12 inches clean fill not to contain stones larger than 2 inches in maximum diameter.5. Install cable warning tape 12 inches over the conduit.6. Fill in the remainder of the trench with native backfill.7. Install pull line, including 10 feet of slack, and secure to conduit plug at each end of conduit run.
DTR 50.103NORTHEAST UTILITIES CONSTRUCTION STANDARD
APPROVED
ORIGINAL SINGLE−PHASE PRIMARY CABLE INSTALLATIONDIRECT−BURIED − IN CONDUIT
Notes1. The trench shall be backfilled immediately following placement of the conduit.2. 1/4−inch−diameter nylon pull line and plastic conduit plugs to be supplied and installed by contractor.
30″ MIN CAUTION TAPE
(SECONDARIESAND/OR OTHERUTILITIES WITH ORWITHOUT CONDUIT)
ÂÂ
ÂÂÂÂ CONDUIT FOR PRIMARY CABLE
(SCHEDULE 40 PVC)
CROSS SECTION OF JOINT TRENCH
FINISHED GRADE
NATIVE BACKFILLNOTE 1
FUEL ORWATER LINE
CLEAN FILL
30″
12″
6/24/98
04/10/06
5
DIRECT−BURIED IN CONDUIT − INSTALLATION OF HANDHOLE SINGLE−PHASE CABLE − LOADBREAK JUNCTION CONNECTOR
FIBERGLASS COVERNOTE 1
APPROVED
ORIGINAL
Notes1. Install 36″ D x 36″ H round handhole, SPC H−020, and fiberglass cover, SPC C−710.2. Install conduit, with all joints cemented, through knockout to 4 inches inside handhole. Terminate conduit run with
end bell (e.g., SC 0177110 for 3−inch diameter). Conduit destination to be permanently marked on conduit end.Conduit shall be minimum 3−inch−diameter, Schedule 40 PVC. Limit four 4−inch−diameter conduits perknockout.
3. Gaps around conduit at knockout openings shall be sealed with cement mortar to prevent backfill from enteringhandhole.
4. Install a 1/4−inch−diameter nylon pull line in each duct, including 10 feet of slack, and secure to conduit plug(e.g., SC 0434785 for 3−inch diameter). Plugged conduit to be left accessible.
5. Install on virgin or well tamped gravel. Where poor soil exists, remove to 6 inches below bottom of handhole andbackfill with compacted clean gravel, free of foreign matter and debris, and extending 12 inches past edge ofstructure. Remaining backfill shall not contain ashes, frozen material, debris or stones larger than 2 inches inmaximum dimension.
6. When installing cable, utilize pulling eyelets provided in handhole.7. Galvanized steel ground rods to be installed in trench adjacent to handhole. See DTR 56.221.8. For loadbreak junction connector installation, refer to DTR 50.111 for pad−mounted or DTR 50.269 for
submersible.
PULL LINE IN CONDUITNOTE 4 12″
LIMIT FOUR CONDUITS MAXIMUMPER KNOCKOUT
COMPACTED FREEDRAINING GRAVEL
12″
DTR 50.107 38/10/06
10/22/99
NORTHEAST UTILITIES CONSTRUCTION STANDARD
6″ NOTE 5
FINISHED GRADE
8′ GROUND RODNOTE 7
SECTION A−A
36″
8′ GROUND RODNOTE 7
1/2″ : 1′
A A
8′ GROUND RODNOTE 7
8′ GROUND RODNOTE 7
PRIMARY
PRIMARY
PRIMARY
30″CABLE WARNING TAPE
CONDUIT PLUGNOTE 4
PRIMARYOPTIONAL SPARE FOR FUTURE USEOPTIONAL SPARE FOR FUTURE USE
12″
A
COMPACTED FREEDRAINING GRAVEL
″3
12″
DTR 58.185 38/10/06
10/22/99
NORTHEAST UTILITIES CONSTRUCTION STANDARD
APPROVED
ORIGINAL DIRECT−BURIED IN CONDUIT − INSTALLATION OF CONCRETE PADFOR SINGLE−PHASE PAD−MOUNTED TRANSFORMERS
Notes1. Install 42″ x 48″ x 4″ pad, SPC P−009 and 36″ D x 36″ H round handhole, SPC H−020.2. Install conduit, with all joints cemented, through knockout to 4 inches inside handhole. Terminate conduit run with
end bell (e.g., SC 0177110 for 3−inch diameter). Conduit destination to be permanently marked on conduit end.Conduit shall be minimum 3−inch−diameter, Schedule 40 PVC. Limit four 4−inch−diameter conduits per knockout.a. Primaries and secondaries in conduit to be installed at 30 inches below grade.b. Services in conduit to be installed at 24 inches below grade.c. Install a 1/4−inch−diameter nylon pull line in each duct, including 10 feet of slack, and secure to conduit plug
(e.g., SC 0434785 for 3−inch−diameter). Plugged duct to be left accessible.d. Gaps around conduit at knockout openings shall be sealed with cement mortar to prevent backfill from entering
handhole.3. Install on virgin or well tamped gravel. Where poor soil exists, excavate to 6 inches below bottom of handhole and
backfill with compacted clean gravel, free of foreign matter and debris, extending 12 inches past edge of structure.Remaining backfill shall not contain ashes, frozen material, debris, or stones larger than 2 inches in maximumdimension.
4. Galvanized steel ground rods to be installed in trench adjacent to handhole. See DTR 56.221.5. Refer to DTR 58.107 for transformer connections.6. Refer to DTR 54.203 for details on conduit stubs.
6″ NOTE 3
FINISHED GRADE
PULL LINEIN CONDUITNOTE 2c
8′ GROUND RODNOTE 4
SECTION A−A
36″
GROUND RODNOTE 4
1/2″ : 1′
A
GROUND RODNOTE 4
8′ GROUND RODNOTE 4
SECONDARIES AND/OR SERVICES
PRIMARIES AND/OR SECONDARIES
SECONDARIES AND/OR SERVICES
PRIMARIES AND/OR SECONDARIES
LIMIT FOUR CONDUITS MAXIMUMPER KNOCKOUT
CABLE WARNING TAPE30″
CONDUIT PLUGNOTE 2c
______________________________________________________________________________________________________________________________________________________
| CONSTRUCTION STANDARD VARIATION | CONSTRUCTION UNIT IDENTIFIER |
|____________________________________________________________________________________________________________________________________________________|
| A NO PAD/HH 15 KV 25-167KVA XF-4POS CONN-SVC FROM XF | DTR58.185.3A |
| B NO PAD/HH 15 KV 25-167KVA XF-6POS CONN-SVC FROM XF | DTR58.185.3B |
| C NO PAD/HH 23 KV 25-167KVA XF-4POS CONN-SVC FROM XF | DTR58.185.3C |
| D NO PAD/HH 23 KV 25-167KVA XF-6POS CONN-SVC FROM XF | DTR58.185.3D |
| E NO PAD/HH 15 KV 25-167KVA XF-4POS CONN-SVC-PRI DE | DTR58.185.3E |
| F NO PAD/HH 15 KV 25-167KVA XF-6POS CONN-SVC-PRI DE | DTR58.185.3F |
| G NO PAD/HH 23 KV 25-167KVA XF-4POS CONN-SVC-PRI DE | DTR58.185.3G |
| H NO PAD/HH 23 KV 25-167KVA XF-6POS CONN-SVC-PRI DE | DTR58.185.3H |
| I 15 KV 25-167KVA XF-4 POS-SVC FROM XF W/PAD TOP | DTR58.185.3I |
| J 15 KV 25-167KVA XF-6 POS-SVC FROM XF W/PAD TOP | DTR58.185.3J |
| K 23 KV 25-167KVA XF-4 POS-SVC FROM XF W/PAD TOP | DTR58.185.3K |
| L 23 KV 25-167KVA XF-6 POS-SVC FROM XF W/PAD TOP | DTR58.185.3L |
| M 15 KV 25-167KVA XF-1PH FUT EXT/LOOP OPEN-USE W/A&B | DTR58.185.3M |
|____________________________________________________________________________________________________________________________________________________|
| STOCK CODE QUANTITY | | | U=UNIT OF PROPERTY STOCK |
|________________________________________________________________| | | |
| M | L | K | J | I | H | G | F | E | D | C | B | A |UM| STOCK CODE DESCRIPTION | M=MINOR L=LOBBY CODE |
|____________________________________________________________________________________________________________________________________________________|
| | | | | | | | | | | | | |EA| HANDHOLE CONCR PCST 36 IN DIA X 36 IN HIGH | U M017498800 |
| | 1| 1| 1| 1| | | | | | | | |EA| PAD CONCRETE PRECAST 42 X 48 X 4 IN | U M017510900 |
| | | | | | 1| 1| | | | | | |EA| ARRESTER DISTR MOV ELBOW 18 KV | M M018071500 |
| 1| | | | | | | 1| 1| | | | |EA| ARRESTER SURGE 13.2 KV & 13.8 KV MGY SYS VOLT 12 KV RATING | M M040860800 |
| | | | 2| 2| | | 2| 2| | | 2| 2|EA| BUSHING CONN LBK 15 KV | M M017754700 |
| | 2| 2| | | 2| 2| | | 2| 2| | |EA| BUSHING CONN LBK 25 KV | M M017754800 |
| | | | 2| 2| | | 1| 1| | | 2| 2|EA| CONN ELBOW LBK 15 KV AL 1 STR 175 MIL POLY | M M017894600 |
| | 2| 2| | | 1| 1| | | 2| 2| | |EA| CONN ELBOW LBK 25 KV AL 1 STR 260 MIL POLY | M M017894800 |
| | | 3| | 3| | 3| | 3| | 3| | 3|EA| CONN TERMINAL AL 4 POS 4-500 TO 2H PAD | M M017922300 |
| | 3| | 3| | 3| | 3| | 3| | 3| |EA| CONN TERMINAL AL 6 POS 4-500 TO 2H PAD | M M017921200 |
| | | | | | | | | | | | | |EA| COVER HANDHOLE SOL FG 42 IN DIA | M M017481900 |
| | 2| 2| 2| 2| 2| 2| 2| 2| 2| 2| 2| 2|EA| COVER INSULATING HOOD VINYL 6.75 IN H X 2.25 IN DP X 10 IN | M M041661700 |
| 1| | | | | | | | | | | | |EA| PLUG STANDOFF FDTHR 15 KV F/LBK ELB CONN | M M017979500 |
| | | | | | | | | | | | | |EA| PLUG STANDOFF FDTHR 25 KV F/LBK ELB CONN | M M017979700 |
| 1| | | | | | | | | | | | |EA| RECEPTACLE DEADEND 15 KV F/LBK BSHG | M M017985400 |
| | | | | | | | | | | | | |EA| RECEPTACLE DEADEND 25 KV F/LBK BSHG | M M017985700 |
| | | | | | | | | | | | | |EA| STAND PARKING F/160 SERIES ESNA FITTINGS | M M018027100 |
| | 6| 6| 6| 6| 6| 6| 6| 6| 6| 6| 6| 6|EA| BOLT MACHINE STS 1/2 X 1-3/4 IN | L M017443500 |
| | 1| 1| 1| 1| 1| 1| 1| 1| 1| 1| 1| 1|EA| CONN VISE BRZ 13-35 #14 SHEAR HEAD BOLT | L M017928600 |
| | | | | | | | | | | | | |EA| CONNECTOR CABLE GROUNDING COPPER #8-1/0 | L M017895700 |
| | 1| 1| 1| 1| 1| 1| 1| 1| 1| 1| 1| 1|EA| LOCK EQUIP T-P 2.5 IN RING AW SHEAR SCREW | L M018997800 |
| | 6| 6| 6| 6| 6| 6| 6| 6| 6| 6| 6| 6|EA| NUT HEX STS 18-8 1/2-13 | L M017507300 |
| | | | | | | | | | | | | |EA| NUT PENTA S.S. UNC THEAD F/3/8 IN BOLT | L M017506100 |
| | | | | | 1| 1| 1| 1| 1| 1| 1| 1|EA| PROTECTOR CABLE VIR NYL FOR 3-6 IN DUCT | L M017533500 |
| | | | | | | | | | | | | |EA| ROD GROUND G 5/8 IN X 8 FT | L M017536200 |
| | 1| 1| 1| 1| 1| 1| 1| 1| 2| 2| 2| 2|EA| SEAL CABLE JACKET KIT F/SOLID DIELECTRIC CABLES 0.95-1.63 IN| L M018145600 |
| | | | | | | | | | | | | |EA| STUD HEX SHOULDER S.S. 3/8 IN UNC THREAD | L M017667000 |
| | 6| 6| 6| 6| 6| 6| 6| 6| 6| 6| 6| 6|EA| WASHER LOCK STS 18-8 1/2 IN | L M017680100 |
| | 12| 12| 12| 12| 12| 12| 12| 12| 12| 12| 12| 12|EA| WASHER ROUND FLAT STS 18-8 1/2 IN BOLT | L M017702500 |
| | 1| 1| 1| 1| | | | | | | | |LB| WIRE TIE BARE CU #6 SOLID | L M018034900 |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
|____________________________________________________________________________________________________________________________________________________|
| PAGE DTR58.185.3A / M | ORIGINAL ISSUE 02 / 14 / 00 |
| |__________________________________________________|
| 1 OF 1 | REVISION DATE 11 / 04 / 03 |
| |__________________________________________________|
| NORTHEAST UTILITIES CONSTRUCTION STANDARD ESTIMATING UNITS | APPROVED BY |
|____________________________________________________________________________________________________________________________________________________|
40
______________________________________________________________________________________________________________________________________________________
| CONSTRUCTION STANDARD VARIATION | CONSTRUCTION UNIT IDENTIFIER |
|____________________________________________________________________________________________________________________________________________________|
| N 23 KV 25-167KVA XF-1PH FUT EXT/LOOP OPEN-USE W/C&D | DTR58.185.3N |
| O HANDHOLE & FIBERGLASS COVER & GROUND RODS | DTR58.185.3O |
| P 15 KV 25-167 KVA FUTURE TRANSFORMER | DTR58.185.3P |
| Q 23 KV 25-167 KVA FUTURE TRANSFORMER | DTR58.185.3Q |
| R 15 KV HANDHOLE WO/XF F/LOOP FEED | DTR58.185.3R |
| S 23 KV HANDHOLE WO/XF F/LOOP FEED | DTR58.185.3S |
| T 15 KV HANDHOLE WO/XF F/FUTURE DE | DTR58.185.3T |
| U 23 KV HANDHOLE WO/XF F/FUTURE DE | DTR58.185.3U |
| V HANDHOLE 36 IN W/CONCRETE PAD TOP & GROUND RODS | DTR58.185.3V |
| | |
| | |
| | |
| | |
|____________________________________________________________________________________________________________________________________________________|
| STOCK CODE QUANTITY | | | U=UNIT OF PROPERTY STOCK |
|________________________________________________________________| | | |
| Z | Y | X | W | V | U | T | S | R | Q | P | O | N |UM| STOCK CODE DESCRIPTION | M=MINOR L=LOBBY CODE |
|____________________________________________________________________________________________________________________________________________________|
| | | | | 1| | | | | | | 1| |EA| HANDHOLE CONCR PCST 36 IN DIA X 36 IN HIGH | U M017498800 |
| | | | | 1| | | | | | | | |EA| PAD CONCRETE PRECAST 42 X 48 X 4 IN | U M017510900 |
| | | | | | 1| | | | | | | 1|EA| ARRESTER DISTR MOV ELBOW 18 KV | M M018071500 |
| | | | | | | 1| | | | | | |EA| ARRESTER SURGE 13.2 KV & 13.8 KV MGY SYS VOLT 12 KV RATING | M M040860800 |
| | | | | | | | | | | | | |EA| BUSHING CONN LBK 15 KV | M M017754700 |
| | | | | | | | | | | | | |EA| BUSHING CONN LBK 25 KV | M M017754800 |
| | | | | | | 1| | 2| | 2| | |EA| CONN ELBOW LBK 15 KV AL 1 STR 175 MIL POLY | M M017894600 |
| | | | | | 1| | 2| | 2| | | |EA| CONN ELBOW LBK 25 KV AL 1 STR 260 MIL POLY | M M017894800 |
| | | | | | | | | | | | | |EA| CONN TERMINAL AL 4 POS 4-500 TO 2H PAD | M M017922300 |
| | | | | | | | | | | | | |EA| CONN TERMINAL AL 6 POS 4-500 TO 2H PAD | M M017921200 |
| | | | | | | | | | | | 1| |EA| COVER HANDHOLE SOL FG 42 IN DIA | M M017481900 |
| | | | | | | | | | | | | |EA| COVER INSULATING HOOD VINYL 6.75 IN H X 2.25 IN DP X 10 IN | M M041661700 |
| | | | | | | 1| | 1| | 1| | |EA| PLUG STANDOFF FDTHR 15 KV F/LBK ELB CONN | M M017979500 |
| | | | | | 1| | 1| | 1| | | 1|EA| PLUG STANDOFF FDTHR 25 KV F/LBK ELB CONN | M M017979700 |
| | | | | | | | | | | | | |EA| RECEPTACLE DEADEND 15 KV F/LBK BSHG | M M017985400 |
| | | | | | | | | | | | | 1|EA| RECEPTACLE DEADEND 25 KV F/LBK BSHG | M M017985700 |
| | | | | | 2| 2| 2| 2| 2| 2| | |EA| STAND PARKING F/160 SERIES ESNA FITTINGS | M M018027100 |
| | | | | | | | | | | | | |EA| BOLT MACHINE STS 1/2 X 1-3/4 IN | L M017443500 |
| | | | | | | | | | | | | |EA| CONN VISE BRZ 13-35 #14 SHEAR HEAD BOLT | L M017928600 |
| | | | | 2| | | | | | | 2| |EA| CONNECTOR CABLE GROUNDING COPPER #8-1/0 | L M017895700 |
| | | | | | | | | | | | | |EA| LOCK EQUIP T-P 2.5 IN RING AW SHEAR SCREW | L M018997800 |
| | | | | | | | | | | | | |EA| NUT HEX STS 18-8 1/2-13 | L M017507300 |
| | | | | | | | | | | | 4| |EA| NUT PENTA S.S. UNC THEAD F/3/8 IN BOLT | L M017506100 |
| | | | | | | | | | | | | |EA| PROTECTOR CABLE VIR NYL FOR 3-6 IN DUCT | L M017533500 |
| | | | | 2| | | | | | | 2| |EA| ROD GROUND G 5/8 IN X 8 FT | L M017536200 |
| | | | | | 1| 1| 2| 2| 2| 2| | |EA| SEAL CABLE JACKET KIT F/SOLID DIELECTRIC CABLES 0.95-1.63 IN| L M018145600 |
| | | | | | | | | | | | 4| |EA| STUD HEX SHOULDER S.S. 3/8 IN UNC THREAD | L M017667000 |
| | | | | | | | | | | | | |EA| WASHER LOCK STS 18-8 1/2 IN | L M017680100 |
| | | | | | | | | | | | | |EA| WASHER ROUND FLAT STS 18-8 1/2 IN BOLT | L M017702500 |
| | | | | 8| | | | | | | 8| |LB| WIRE TIE BARE CU #6 SOLID | L M018034900 |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
|____________________________________________________________________________________________________________________________________________________|
| PAGE DTR58.185.3N / V | ORIGINAL ISSUE 02 / 14 / 00 |
| |__________________________________________________|
| 1 OF 1 | REVISION DATE 11 / 04 / 03 |
| |__________________________________________________|
| NORTHEAST UTILITIES CONSTRUCTION STANDARD ESTIMATING UNITS | APPROVED BY |
|____________________________________________________________________________________________________________________________________________________|
41
DTR 54.201 38/10/06
10/22/99
NORTHEAST UTILITIES CONSTRUCTION STANDARD
APPROVED
ORIGINAL DIRECT−BURIED IN CONDUIT − HANDHOLE ACROSS STREETSINGLE−PHASE CABLE − SECONDARY/SERVICE
Notes1. Install 36″ D x 36″ H round handhole, SPC H−020, and fiberglass cover, SPC C−710.2. Install conduit, with all joints cemented, through knockout to 4 inches inside handhole. Terminate conduit run
with end bell (e.g., SC 0177110 for 3−inch diameter). Conduit destination to be permanently marked on conduitend. Conduit shall be minimum 3−inch−diameter, Schedule 40 PVC. Limit four 4−inch−diameter conduits perknockout.
3. Gaps around conduit at knockout openings shall be sealed with cement mortar to prevent backfill from enteringhandhole.
4. Install 1/4−inch−diameter nylon pull line in each duct, including 10 feet of slack, and secure to conduit plug (e.g., SC 0434785 for 3−inch diameter). Plugged conduit to be left accessible.
5. Install on virgin or well tamped gravel. Where poor soil exists, remove to 6 inches below bottom of handhole andbackfill with compacted clean gravel, free of foreign matter and debris, and extending 12 inches past edge ofstructure. Remaining backfill shall not contain ashes, frozen material, debris or stones larger than 2 inches inmaximum dimension.
6. When installing cable, utilize pulling eyelets provided in handhole.7. Refer to DTR 54.203 for details on conduit stubs.
1/2″ : 1′
COMPACTED, FREEDRAINING GRAVELNOTE 5
12″
6″
FINISHED GRADE
PULL LINEIN CONDUITNOTE 4
SECTION A−A
36″ 30″CABLE WARNING TAPE
CONDUIT PLUGNOTE 4
12″
FIBERGLASS COVERNOTE 1
LIMIT FOUR CONDUITS MAXIMUMPER KNOCKOUT
A A
SECONDARY FROM TRANSFORMER
SERVICES
SERVICE
SERVICE
______________________________________________________________________________________________________________________________________________________
| CONSTRUCTION STANDARD VARIATION | CONSTRUCTION UNIT IDENTIFIER |
|____________________________________________________________________________________________________________________________________________________|
| A STD SERVICE CONCRETE HANDHOLE | DTR54.201.1A |
| B STD SERV BUS CONN 4 POS 4-500 MCM | DTR54.201.1B |
| C STD SERV BUS CONN 6 POS 4-500 MCM | DTR54.201.1C |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
|____________________________________________________________________________________________________________________________________________________|
| STOCK CODE QUANTITY | | | U=UNIT OF PROPERTY STOCK |
|________________________________________________________________| | | |
| M | L | K | J | I | H | G | F | E | D | C | B | A |UM| STOCK CODE DESCRIPTION | M=MINOR L=LOBBY CODE |
|____________________________________________________________________________________________________________________________________________________|
| | | | | | | | | | | | | 1|EA| HANDHOLE CONCR PCST 36 IN DIA X 36 IN HIGH | U M017498800 |
| | | | | | | | | | | | | 1|EA| COVER HANDHOLE SOL FG 42 IN DIA | M M017481900 |
| | | | | | | | | | | | 3| |EA| CONN BUS INS 600V AL 4 POS 4-500MCM | L M017849900 |
| | | | | | | | | | | 3| | |EA| CONN BUS INS 600V AL 6 POS 4-500MCM | L M017850000 |
| | | | | | | | | | | | | 4|EA| NUT PENTA S.S. UNC THEAD F/3/8 IN BOLT | L M017506100 |
| | | | | | | | | | | | | 4|EA| STUD HEX SHOULDER S.S. 3/8 IN UNC THREAD | L M017667000 |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
|____________________________________________________________________________________________________________________________________________________|
| PAGE DTR54.201.1A / C | ORIGINAL ISSUE 02 / 15 / 00 |
| |__________________________________________________|
| 1 OF 1 | REVISION DATE 11 / 04 / 03 |
| |__________________________________________________|
| NORTHEAST UTILITIES CONSTRUCTION STANDARD ESTIMATING UNITS | APPROVED BY |
|____________________________________________________________________________________________________________________________________________________|
43
PRIMARY CONDUITS BYPASSSECONDARY HANDHOLE
TEMPORARY DEADENDNOTE 7
LIMIT FOUR CONDUITSMAXIMUM PER KNOCKOUT
DTR 54.203 3NORTHEAST UTILITIES CONSTRUCTION STANDARD
APPROVED
ORIGINAL DIRECT−BURIED IN CONDUIT − INSTALLATION OF HANDHOLE600 VOLTS AND BELOW − SINGLE−PHASE − SECONDARY/SERVICE
Notes1. Install 36″ D x 36″ H round handhole SPC H−020, SC 0174988, and fiberglass cover SPC C−710, SC 0174819.2. Install on virgin or well tamped gravel. Where poor soil exists, remove to 6 inches below bottom of handhole and
backfill with compacted clean gravel, free of foreign matter and debris, and extending 12 inches past edge ofstructure.
3. Install conduit, with all joints cemented, through knockout to 4 inches inside handhole. Conduit destination to bepermanently marked on conduit end. Conduit shall be minimum 3−inch−diameter, Schedule 40 PVC. Limit four4−inch−diameter conduits per knockout.
4. Gaps around conduit at knockout openings shall be sealed with cement mortar to prevent backfill from enteringhandhole.
5. Install a 1/4−inch−diameter nylon pull line in each duct, including 10 feet of slack, and secure to conduit plug(e.g., SC 0434785 for 3−inch diameter). Plugged conduit to be left accessible.
6. When installing cable, utilize pulling eyelets provided in handhole.7. Refer to DTR 54.118 for details on installation of temporary deadend.
1/2″ : 1′
SERVICES
SECONDARY
SERVICES
TO COMPLETE SERVICE − MATECUSTOMER CONDUIT TO EXISTING, JOINPULL LINES, SLIDE CONDUIT SLEEVE OVERBOTH ENDS AND SECURE WITH CONDUITCEMENT.
CONTRACTOR NOTE − FOR EASE INMATCHING CONDUIT LOCATION ANDELEVATION, START LAYING CONDUIT ATEASEMENT END AND WORK TOWARDCUSTOMER END.
22−1/2°
NOTE 5
CONDUIT SLEEVE COUPLING
STREET TAKING LINE
PR
OP
ER
TY
LIN
E
10′ E
AS
EM
EN
T
10′ LENGTH OF CONDUIT
THIS AREA FOR OTHER UTILITIES
8/10/06
10/22/99
______________________________________________________________________________________________________________________________________________________
| CONSTRUCTION STANDARD VARIATION | CONSTRUCTION UNIT IDENTIFIER |
|____________________________________________________________________________________________________________________________________________________|
| A HANDHOLE WITH 42 IN FG COVER | DTR54.203.0A |
| B STD SERVICE BUS CONN 4 POS 4-500MCM | DTR54.203.0B |
| C STD SERVICE BUS CONN 6 POS 4-500MCM | DTR54.203.0C |
| D 42 IN FIBERGLASS COVER ONLY | DTR54.203.0D |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
|____________________________________________________________________________________________________________________________________________________|
| STOCK CODE QUANTITY | | | U=UNIT OF PROPERTY STOCK |
|________________________________________________________________| | | |
| M | L | K | J | I | H | G | F | E | D | C | B | A |UM| STOCK CODE DESCRIPTION | M=MINOR L=LOBBY CODE |
|____________________________________________________________________________________________________________________________________________________|
| | | | | | | | | | | | | 1|EA| HANDHOLE CONCR PCST 36 IN DIA X 36 IN HIGH | U M017498800 |
| | | | | | | | | | 1| | | 1|EA| COVER HANDHOLE SOL FG 42 IN DIA | M M017481900 |
| | | | | | | | | | 4| | | |EA| BOLT MACHINE PNHD STS 3/8 X 1 IN | L M017438800 |
| | | | | | | | | | | | 3| |EA| CONN BUS INS 600V AL 4 POS 4-500MCM | L M017849900 |
| | | | | | | | | | | 3| | |EA| CONN BUS INS 600V AL 6 POS 4-500MCM | L M017850000 |
| | | | | | | | | | | | | 4|EA| NUT PENTA S.S. UNC THEAD F/3/8 IN BOLT | L M017506100 |
| | | | | | | | | | | | | 4|EA| STUD HEX SHOULDER S.S. 3/8 IN UNC THREAD | L M017667000 |
| | | | | | | | | | 4| | | |EA| WASHER ROUND FLAT G 3/8 IN BOLT | L M017683800 |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
|____________________________________________________________________________________________________________________________________________________|
| PAGE DTR54.203.0A / D | ORIGINAL ISSUE 02 / 14 / 00 |
| |__________________________________________________|
| 1 OF 1 | REVISION DATE 11 / 04 / 03 |
| |__________________________________________________|
| NORTHEAST UTILITIES CONSTRUCTION STANDARD ESTIMATING UNITS | APPROVED BY |
|____________________________________________________________________________________________________________________________________________________|
45
1/24/06
6/24/98
NORTHEAST UTILITIES CONSTRUCTION STANDARD
APPROVED
ORIGINAL
DTR 54.118
ËËËËËËËË
DEPTHNOTE 4
UNDERGROUND CABLE SIGN,TO BE INSTALLED BYNORTHEAST UTILITIES
3″ PVC DEAD−END CAP
WELL TAMPED EARTH
FINISHED GRADE
LOCATION TAG, TO BE INSTALLED BYNORTHEAST UTILITIES
1/4″ NYLON PULL LINE
PLASTIC CONDUIT PLUG CONDUIT, SCHEDULE 40 PVC
3
WARNING TAPECT/MA − LOCATE 12″ABOVE TOP OF CONDUIT.NH − LOCATE 12″ BELOWFINISHED GRADE.
Notes1. Install temporary dead−end cap where customer’s trench ends on private property if customer is not ready
for service.2. Remove PVC dead−end cap, extend conduit, and pull cable when service is extended to future building, vault,
or transformer.3. The contractor is responsible for all material shown, unless noted otherwise. Location tag and underground cable
sign to be supplied and installed by Northeast Utilities.4. Minimum burial depth shall be as follows: CT/MA − 24 inches for secondary cable and 30 inches for primary
cable. NH − 30 inches for secondary cable and 36 inches for primary cable.
DIRECT−BURIED CONDUIT SYSTEM − TEMPORARY DEAD−END CAP
– SPC C–710 –
COVER – HANDHOLE – HEXAGONS AND ROUND42–INCH DIAMETER
3NORTHEAST UTILITIES
APPROVED
ORIGINAL
MATERIAL SPECIFICATION6/14/97
5/13/86
ELECTRIC
Notes1. Cover shall conform to ASTM D790.2. DESIGN LOADING shall be 4,500 pounds applied at the center of the cover over a 6″ X 6″ area. The cover will
be supported by a 36–inch ID ring. The total deflection of the cover shall not exceed 4 inches with load appliedfor 5 minutes.
3. Plywood core designs shall be encapsulated in a fiberglass–reinforced polyester laminate a minimum of 1/8 inchthick on all surfaces, consisting of a spray up of chopped glass and resin totaling 5 ounces per square foot ofsurface. The glass content will be a minimum of 25 percent on the top, and will be increased on the bottom ifnecessary to meet the design loading specified in NOTE 1. The plywood core will comply with the AmericanPlywood Association Standard PS 1–1974, DFPA GRADE, GROUP 1, EXTERIOR C–C or better.
4. The cover shall be permanently embossed with both manufacturer’s name and the word “ELECTRIC” as shown.5. The resin and the gel coat will be pigmented dark green, and there shall be no exposed glass on any surface.6. A stainless steel or brass washer, 1–3/8 inch OD with a 5/8–inch hole, will be epoxied into the pentahead
recess. There should be no exposed wood in the recess.
5/8″ MAX1/4″ MIN
NON–SKIDSURFACE4″
SEE DETAIL A
AA
5/8″
38–1/2″42″
SECTION A–A
DETAIL A
42″ DIAMETERCOVER
38–1/2″ BOLTCIRCLE NOTE 3
1–1/2″ DIA5/8″ DIA
ELECTRIC
– SPC E–953 –
EXTENSION – HANDHOLE/VAULT – PRECAST CONCRETE180 DEGREE SEGMENT X 36″ DIAMETER X 4″ HIGH
8NORTHEAST UTILITIES
APPROVED
ORIGINAL
MATERIAL SPECIFICATION6/1/91
8/5/70
NOTES1. Two zinc alloy iron inserts 3/8 inch – 16 x 1–1/2 inches on 38–1/2 inch bolt circle.2. Two holes equally spaced on 38–1/2 inch bolt circle.3. Final 28 day concrete strength 4000 psi.4. Concrete and concrete design shall be in accordance with ACI 318–1986 latest revision thereof.5. Manufacturer’s identification and month/year when manufactured shall be legibly marked in/on concrete on the
inner side. 6. Construction tolerances shall allow for the mating of two 180 degree segments, on NU SPC’s H–020 and V–025,
to achieve a 360 degree extension.
18″
45°
NOTE 1
67–1/2°
A
A
22–1/2°
NOTE 2
#4 REBAR
NOTE 1
3″
4″
ÇÇÇÇÇÇ
3″3/4″
2″
38–1/2″ DIAMETER BOLT CIRCLE
NOTE 2
1″GALVANIZED WASHER1–3/4″ DIAMETER11/16″ HOLE
SECTION A–A
HANDHOLE/VAULT EXTENSION(FOR GRADE ADJUSTMENT)
22–1/2°
22–1/2°
NOTE 2
SPC H–020
HANDHOLE – ROUND – PRECAST CONCRETE36″ DIAMETER x 36″ HIGH
6NORTHEAST UTILITIES
APPROVED
ORIGINAL
MATERIAL SPECIFICATION6/9/00
5/13/86
NOTE 9
3″ x 6″–W2.9 x W2.9, WELDED STEELWIRE FABRIC, AS PER ASTM A–185(ALTERNATE – 6″ x 6″–W1.4 x W1.4, W/TWO 1/4″ DIA REBAR HOOPS CENTERED AT 6″ AROUND EYELETS)
10″
Notes1. Concrete and concrete design shall be in accordance with ACI 318–1995.2. Concrete strength 5000 psi at 28 days. Air entrainment 6 to 8 percent.3. Four zinc alloy inserts 3/8″ – 16 x 1–3/8″ equally spaced on 38–1/2″ bolt circle. 4. Four zinc alloy inserts 5/8″ – 11 x 1–11/16″ equally spaced on 38–1/2″ bolt circle. 5. Eight zinc alloy inserts 3/8″ – 16 x 1–3/8″.6. Four eyelets, for use as pulling points, shall be installed adjacent to and centered above knockouts as shown.7. Manufacturer’s identification and month/year when manufactured shall be legibly marked in/on concrete on the
outside upper part. 8. Location of each knockout shall be identifiable from exterior of handhole by providing a 3″ diameter circle
imprinted 1/4″ deep into the concrete. Center of the imprinted circle shall be located at center of each knockout.9. All knockouts shall have a web thickness not to exceed 3/4″ ±1/8″. Knockouts to be free of reinforcement.
10. The two recesses 12″ from top are for use with adjustable lifter tool only. 11. Eyelets and zinc alloy inserts not to be used for lifting.
4″
22–1/2°
c
22–1/2°
NOTE 4
45°
NOTE 3
NOTE 5
NOTE 9
A A
36″
NOTE 7
NOTE 4 NOTE 3
NOTE 5
3″
10″
15″
12″3″
9″
12″
9″
SECTION A–A
NOTE 6
18″
NOTE 8
3″
3″ x 3″ x 1/4″ CURVED SQUARE WASHER, GALV, W/13/16″ HOLE, AS PER EEI TDJ10
3″ x 6″–W2.9 x W2.9, WELDED STEELWIRE FABRIC, AS PER ASTM A–185(ALTERNATE – 6″ x 6″–W1.4 x W1.4, W/TWO 1/4″ DIA REBAR HOOPSCENTERED AT 6″ AROUND EYELETS. SEE SECTION B–B)
5/8″–11, 5″ LONG, MACHINE BOLT, GALV,W/SQUARE NUT, AS PER ANSI C135.1–1979,FOR USE W/EYELET, STANDARD, LONG,GALV, AS PER ANSI C135.5–1987
SECTION B–B
1/4″ REBAR
(SHOWS ALTERNATE REBAR LOCATION)
B
B
6″
NOTE 8
NOTE 4
B
B
36″
6″
8″
ML 1245 D
– SPC P–009 –
PAD – PRECAST CONCRETE – TRANSFORMER167 KVA MAXIMUM – 42 ″ X 48″ X 4″
11NORTHEAST UTILITIES
APPROVED
ORIGINAL
MATERIAL SPECIFICATION8/1/91
4/23/70
NOTES1. Final 28 day concrete strength to be 5000 psi.2. A 3/4 inch coil loop insert (Dayton F63) with an insert locator plug (Dayton T21) for lifting the pad at the center
of gravity with a swivel plate.3. Manufacturer’s identification and month/year when manufactured shall be legibly marked in/on concrete in the
top near the center.4. Concrete and concrete design shall be in accordance with ACI 318–1986.
c
28″
26–1/2″
NOTES 2&3
A A
42″
48″
2″2″
2″
16″
6″
28″
2″
14–1/2″
6″ X 6″ 10 GAUGEWIRE MESH REINFORCEMENT
#4 BAR
36″
36″
26–1/2″
7″ 7″
4″
1/4″
SECTION A–A
3/4″
ML 1245
PAD – PLUG – PRECAST CONCRETE – 16 ″ X 28″ X 4″FOR THE 42″ X 48″ X 4″ PAD
2NORTHEAST UTILITIES
APPROVED
ORIGINAL
MATERIAL SPECIFICATION8/1/91
5/13/86
SPC P–010
NOTES1. Final 28 day concrete strength to be 3500 psi minimum.2. A 3/4 inch coil loop insert (Dayton F–63) with an insert locator plug (Dayton T–21) for lifting the pad at the center of gravity with a swivel plate.3. Threaded insert shall be plastic capped to stop dirt buildup.4. Threaded inserts shall be greased on inside to prevent corrosion.5. Manufacturer’s name and month/year of construction shall be legibly marked in concrete on the bottom.
B
B
A A
25″ #3 REBAR
26″
28″
4″
13″ #3 REBAR
1–1/4″
13–3/4″
16″
1/8″
SECTION A–A SECTION B–B
ML 145 D
– SPC P–017 –
PAD – ENCLOSURE – PRECAST CONCRETE48″ X 48″ X 4″
9NORTHEAST UTILITIES
APPROVED
ORIGINAL
MATERIAL SPECIFICATION11/1/94
2/17/76
9″
NOTES1. Final 28 day concrete strength to be 5000 psi.2. Manufacturer’s identification and month/year when manufactured shall be legibly marked in/on concrete in the
top within 4 inches of the opening.3. Concrete and concrete design shall be in accordance with ACI 318–1986.4. Two 3/4 inch coil loop inserts (Dayton F63) with an insert locator plug (Dayton T21) for lifting the pad with a
swivel plate.
30″
48″
NOTE 4
9″
A A
BB
27″
48″
37–3/4″
24″
39–1/2″
32″
5–1/8″
24″ 24″
9″9″ 30″
38–1/2″
EIGHT ZINC ALLOY INSERTS5/8″–11 X 1–1/2″
5–1/8″
8–1/2″ 8–1/2″
#4 REBAR 40″ X 40″1/4″ 3/4″
4″
4–3/4″ 4–3/4″
24″
SECTION B–B
SECTION A–A
3/4″
2″1″
GALVANIZEDWASHER1–3/4″ DIA11/16″ HOLE
DTR 50.341 211/2/99
6/22/90
NORTHEAST UTILITIES CONSTRUCTION STANDARD
APPROVED
ORIGINAL
HILL HOLDER – DIRECT–BURIED SYSTEM
Notes1. Use with any single–phase pad–mounted or submersible transformer or single–phase switchgear.2. Depending on steepness of the grade, select either 16– or 32–inch–high model.3. Always place hill holder with the back toward the grade. Do not install with the side of the hill holder facing the
grade; this product is not designed to support side loads.4. Make sure that 2–inch flange is properly secured with an adequate amount of soil to prevent the hill holder from
being removed or vandalized.
______________________________________________________________________________________________________________________________________________________
| CONSTRUCTION STANDARD VARIATION | CONSTRUCTION UNIT IDENTIFIER |
|____________________________________________________________________________________________________________________________________________________|
| A HILLHOLDER 16" GRADE ADJUSTMENT | DTR50.341.0A |
| B HILLHOLDER 32" GRADE ADJUSTMENT | DTR50.341.0B |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
|____________________________________________________________________________________________________________________________________________________|
| STOCK CODE QUANTITY | | | U=UNIT OF PROPERTY STOCK |
|________________________________________________________________| | | |
| M | L | K | J | I | H | G | F | E | D | C | B | A |UM| STOCK CODE DESCRIPTION | M=MINOR L=LOBBY CODE |
|____________________________________________________________________________________________________________________________________________________|
| | | | | | | | | | | | | 1|EA| HOLDER HILL FG 16 X 44 X 52 IN | M M018340600 |
| | | | | | | | | | | | 1| |EA| HOLDER HILL FG 32 X 44 X 52 IN | M M018340700 |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
|____________________________________________________________________________________________________________________________________________________|
| PAGE DTR50.341.0A / B | ML | ORIGINAL ISSUE 4 / 13 / 91 |
| |__________________________________________________|
| 1 OF 1 | REVISION DATE 1 / 1 / 97 |
| |__________________________________________________|
| NORTHEAST UTILITIES CONSTRUCTION STANDARD ESTIMATING UNITS | APPROVED BY |
|____________________________________________________________________________________________________________________________________________________|
54
DTR 50.401 512/18/00
5/25/88
NORTHEAST UTILITIES CONSTRUCTION STANDARD
APPROVED
ORIGINAL COVER AND GRADE EXTENSIONSROUND HANDHOLE
Notes1. Fiberglass cover – Install stud with 1–1/4–inch end down and 1–inch end up. 2. Use extensions for grade adjustments only. 3. Use stud and penta nut with fiberglass cover.
PENTA NUTSC 0175061
HANDHOLE COVERSC 0174819(SEE SPC C–710)
HEX–SHOULDER STUDSC 0176670
4″ EXTENSIONSC 0174870(SEE SPC E–953)
HANDHOLE, 36″ x 36″SC 0174988(SEE SPC H–020)
4″ BOLT FOR ONE EXTENSIONSC 0174355(8″ BOLT FOR TWO EXTENSIONSSC 0174356)
ÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏÏ
______________________________________________________________________________________________________________________________________________________
| CONSTRUCTION STANDARD VARIATION | CONSTRUCTION UNIT IDENTIFIER |
|____________________________________________________________________________________________________________________________________________________|
| A HANDHOLE WITH 42IN FIBERGLASS COVER | DTR50.401.1A |
| B 4 INCH CONCRETE EXTENSION | DTR50.401.1B |
| C 8 INCH CONCRETE EXTENSION | DTR50.401.1C |
| D FIBERGLASS 42" COVER DB | DTR50.401.1D |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
|____________________________________________________________________________________________________________________________________________________|
| STOCK CODE QUANTITY | | | U=UNIT OF PROPERTY STOCK |
|________________________________________________________________| | | |
| M | L | K | J | I | H | G | F | E | D | C | B | A |UM| STOCK CODE DESCRIPTION | M=MINOR L=LOBBY CODE |
|____________________________________________________________________________________________________________________________________________________|
| | | | | | | | | | | | | 1|EA| HANDHOLE CONCR PCST 36IN DIA X 36IN HIGH | U M017498800 |
| | | | | | | | | | 1| | | 1|EA| COVER HANDHOLE SOL FG 42 IN DIA | M M017481900 |
| | | | | | | | | | | 4| 2| |EA| EXTENSION VLT/HH CONCR 1/2 SEG 36IN X 4IN | M M017487000 |
| | | | | | | | | | | | 4| |EA| BOLT MACHINE G 5/8 X 4 IN | L M017435500 |
| | | | | | | | | | | 4| | |EA| BOLT MACHINE G 5/8 X 8 IN | L M017435600 |
| | | | | | | | | | | | | 4|EA| NUT PENTA S.S. UNC THEAD F/3/8" BOLT | L M017506100 |
| | | | | | | | | | | | | 4|EA| STUD HEX SHOULDER S.S. 3/8" UNC THREAD | L M017667000 |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
|____________________________________________________________________________________________________________________________________________________|
| PAGE DTR50.401.1A / D | | ORIGINAL ISSUE 9 / 3 / 88 |
| |__________________________________________________|
| 1 OF 1 | REVISION DATE 2 / 15 / 01 |
| |__________________________________________________|
| NORTHEAST UTILITIES CONSTRUCTION STANDARD ESTIMATING UNITS | APPROVED BY |
|____________________________________________________________________________________________________________________________________________________|
56
GRADE ADJUSTMENTSINGLE–PHASE – PAD–MOUNTED TRANSFORMER
Notes1. Make sure that there is enough slack in the primary and secondary cables to allow for raising the transformer.2. The split pad is to be placed on top of the existing concrete pad.3. For additional height, a second or third split pad can be installed, one over the other.4. The transformer can be secured to the split pad with transformer clips installed in the adjustable struts with
3/8″ x 1–1/2″ bronze bolts, SC 0174429.
DTR 58.195 311/2/99
9/28/87
NORTHEAST UTILITIES CONSTRUCTION STANDARD
APPROVED
ORIGINAL
4″
SECURE HALVES OFSPLIT PAD WITHSUPPLIED BOLTS
______________________________________________________________________________________________________________________________________________________
| CONSTRUCTION STANDARD VARIATION | CONSTRUCTION UNIT IDENTIFIER |
|____________________________________________________________________________________________________________________________________________________|
| A 4" GRADE ADJ FOR 1 PH PAD TRANS DB | DTR58.195.0A |
| B 4" GRADE ADJ FOR 1 PH PAD TRANS UG | DTR58.195.0B |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
| | |
|____________________________________________________________________________________________________________________________________________________|
| STOCK CODE QUANTITY | | | U=UNIT OF PROPERTY STOCK |
|________________________________________________________________| | | |
| M | L | K | J | I | H | G | F | E | D | C | B | A |UM| STOCK CODE DESCRIPTION | M=MINOR L=LOBBY CODE |
|____________________________________________________________________________________________________________________________________________________|
| | | | | | | | | | | | 1| 1|EA| PAD TOP SPLIT FG/CONC 42X48X4" | M M017509900 |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
| | | | | | | | | | | | | | | | |
|____________________________________________________________________________________________________________________________________________________|
| PAGE DTR58.195.0A / B | ML | ORIGINAL ISSUE 4 / 13 / 91 |
| |__________________________________________________|
| 1 OF 1 | REVISION DATE 1 / 1 / 97 |
| |__________________________________________________|
| NORTHEAST UTILITIES CONSTRUCTION STANDARD ESTIMATING UNITS | APPROVED BY |
|____________________________________________________________________________________________________________________________________________________|
58