Partnering to Rebuild after the Oso Landslide
By Janice Fahning, Megan Slater, Jason Smith, and Becki Kniveton
4/12/2016
2
SR 530 Slide
Emergency Response Phase 2: Reconstruction/RestorationApril 29, 2014 to Present
Six projects totaling $43 million
• Emergency Temporary Berm Constructionand Dewatering
• North Fork Stillaguamish River Pilot Channel
• SR 530 Access Road Maintenance and Traffic Control
• SR 530 Roadway Clearing
• SR 530 Emergency Roadway Reconstruction– Streams/drainage restoration
– Flood protection
– Mitigation for environmental impacts
• SR 530 Incident Debris Removal
4/12/2016
3
Emergency Temporary Berm Construction and Dewatering | $300,000 U.S. Army Corps of Engineers and Snohomish County
North Fork Stillaguamish River Pilot Channel | $480,000BCI Contracting Inc. – Amphibious Excavation
4/12/2016
4
SR 530 Access Road Maintenance and Traffic Control | $3.4 million WSDOT and Granite Construction
SR 530 Roadway Clearing Project $5.0 million
4/12/2016
5
SR 530 Emergency Roadway Reconstruction Project $21.0 million WSDOT – Atkinson - Jacobs
SR 530 Incident Debris Removal Project $13.0 million
4/12/2016
6
Procurement
• Traffic Impacts
• Schedule
• Earthwork Movement
• Community Impacts
• Environmental Impacts
SR 530 Project Limits
4/12/2016
10
Reducing Environmental Impacts• Fish Passage Design with Tribal Agencies
• Wetland Delineation
• Stream Delineation
• Marbled Murrelet & Spotted Owl Assessment
• Coordination between WSDOT, County, and different contractors (IMCO, Granite, Atkinson)
• Reducing Impacts to Wetlands with design refinement (2:1 Slopes, Roadway Alignment, Roadway Elevation)
Key Partners• FEMA• Snohomish County
• Public Works• Parks• Community Development
• Stillaguamish Tribe of Indians• Washington Dept. of Fish and
Wildlife• US Army Corps of Engineers• Washington State Ecology• Atkinson Construction• Jacobs
Reducing Community Impacts
• Local contractors and people hired from the surrounding community to work on the reconstruction and debris removal.
• Creation of on-site mitigation (instead of using proposed mitigation bank) reduced project costs, created open space for the County, and preserved high-quality wetlands.
• One-on-one coordination with adjacent property owners.
4/12/2016
11
SR 530 Landslide Recovery Timeline
Reconstructed SR 530 Open To TrafficSeptember 22nd
Two-Lane Detour OpenedJune 20th
Design & Reconstruct SR 530 - June 13th to September 22nd
DB Team Controls SR 530June 16th
Contract AwardedMay 30th
WSDOT Releases RFP April 29th
FEMA Rescue and Recovery – March 22nd to June 22nd
Landslide March 22nd
3 months6 months
Comparison of Project Delivery Models
Typical Design-Bid-Build Project Delivery
2.5-3 years
• Endangered Species Act (ESA)
• Section 106• NEPA• SEPA
• Section 404/401 Permitting• Mitigation Plan/Design• State and Local Permitting
• Environmental Construction and Commitment Monitoring
SR 530 Design-Build Project Delivery
18 months
• Agency Coordination• Culvert design/sizing• Mitigation Coordination• Emergency Permits• Construction Monitoring
• ATF Section 404/401 Permitting• Mitigation Plan/Design• ATF Endangered Species Act
Consultation
• NHPA Section 106 Consultation• Snohomish County Local Permitting• Environmental Construction and
Commitment Monitoring
RoadConstruction3-4 months
MitigationConstruction
2 months
MitigationConstruction
2 months
Preliminary Design/NEPA12 months
Final Design/Permitting12 to 18 months
After-the-fact Permitting/Mitigation
12 months
Design and Construction
4 months
4/12/2016
12
Emergency Permitting & Restoration
SR 530 Restoration & Permitting Timeline
Sept. 2014 Roadway open to public
Sept. 2014 - March 2015 Restore roadside/staging areas
July 2014 - March 2015 Design mitigation site
July 2014 – Sept. 2015 Complete regulatory permitting
Sept. – Oct 2015 Construct Linda Lee McPhersonMitigation Site
4/12/2016
14
Wetland, Stream, & Buffer Mitigation
soil stockpile
area
existing wetland
Endangered Species Act ReviewPotential Marbled Murrelet/Northern Spotted Owl Habitat
Drains to Stillaguamish River(salmon-bearing stream)
WDFW In-Water Work Window:August 1-15Marbled Murrelet
Nesting Season:April 1 – Sept. 23
Northern Spotted Owl Early Nesting Season:March 1- July 15
4/12/2016
15
SR 530 Landslide Recovery Timeline
construction planting
Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov Dec
X X X X X
X X X X X
X X X X X X X X X X X X
Allowed
Allowed with restrictions/Not likely to adversely affect
X Likely to adversely affect
Construction – Grading and Soil Amendment
4/12/2016
17
Environmental Successes/Design Build Innovations
• Collaboration focused on the community and environment allowed flexibility by the contractor, designer, and agencies as the project progressed
• Right-sizing culverts and the onsite wetland and stream mitigation site saved money, restored streams and wetlands, is a memorial to Linda McPherson, and was transferred to Snohomish County Parks as a protected natural area
• Extraordinary construction water quality management by Atkinson
• Reuse of excavated soil on Snohomish County’s White Horse Trail reconstruction
• Contractors shared security costs
Successful Project Outcomes• Completed reconstruction of SR 530 in just 6
months after the landslide — construction lasted only 13 weeks.
• Opened two-way temporary road within days of contract award.
• Coordinated, designed, and constructed six fish passage culverts.
• Designed and restored wetlands at two staging areas.
• Designed, permitted, and constructed the Linda Lee McPherson wetland and stream mitigation site on 36.3 acres.
• Saved WSDOT $5.4 million over the engineer’s estimate.
4/12/2016
18
McPherson Mitigation Site“The goal of putting a high price tag on the use of the existing mitigation site was to incentivize the DB to minimize impacts to aquatic resources but it had an unexpected—but extraordinary—result. The DB decided that it was a better value to purchase and develop their own mitigation site, McPherson. This is unprecedented in my experience with the agency and it resulted in the acquisition and protection of a really high quality property in the immediate impact area, the McPherson site.”
-Linda Cooley, WSDOT Environmental
Tips to share
• Start planning now• Bringing your A Team• Assign areas of responsibility • Have extra people on hand• Start tracking – daily logs, dollars expended, labor
hours.• Communicate, Communicate, Communicate• Use internal and external resources• Recognize and tend to emotions • Give grace to people