Page 1 of 22 BID DOCUMENT FOR Design and Construction of Formation in Embankments/Cuttings including blanketing, Viaducts, Rail Flyover, Bridges (Major, Minor & RUBs), Supply and Spreading of Ballast and other related infrastructural works for double track electrified railway line on Design Build Lump Sum Basis from Howrah end approach of DFC Sone bridge to Chirailapathu station of IR towards Howrah & to New Sonnagar station towards Garhwa and at Dehri-on-Sone yard from Km. 3.16 to Km. 5.38 in connection with Eastern Dedicated Freight Corridor in the state of Bihar in India. CIVIL AND STRUCTURES CONTRACT PACKAGE Issued on: 12.10.2015 Bid Document No.: HQ/EN/EC/SEB JN.Works PART-5 Employer: DEDICATED FREIGHT CORRIDOR CORPORATION OF INDIA LIMITED A GOVERNMENT OF INDIA ENTERPRISE under MINISTRY OF RAILWAYS COUNTRY: INDIA

PART-5 - Dedicated Freight Corridor Corporation of India Doc Sone Junction Arrangement Part-5... · Design Build Lump Sum Basis from Howrah end approach of DFC ... PART-5 Employer:

Embed Size (px)

Citation preview

Page 1 of 22

BID DOCUMENT FOR

Design and Construction of Formation in Embankments/Cuttingsincluding blanketing, Viaducts, Rail Flyover, Bridges (Major, Minor &RUBs), Supply and Spreading of Ballast and other relatedinfrastructural works for double track electrified railway line onDesign Build Lump Sum Basis from Howrah end approach of DFCSone bridge to Chirailapathu station of IR towards Howrah & to NewSonnagar station towards Garhwa and at Dehri-on-Sone yard fromKm. 3.16 to Km. 5.38 in connection with Eastern Dedicated FreightCorridor in the state of Bihar in India.

CIVIL AND STRUCTURES CONTRACT PACKAGE

Issued on: 12.10.2015

Bid DocumentNo.: HQ/EN/EC/SEB JN.Works

PART-5

Employer:DEDICATED FREIGHT CORRIDOR CORPORATION OF INDIA LIMITED

A GOVERNMENT OF INDIA ENTERPRISEunder

MINISTRY OF RAILWAYSCOUNTRY: INDIA

Page 2 of 22

PART – 5

Price Schedules

Page 3 of 22

CONTENTS

PART – 5 -Price Schedules

1. Preamble

2. PRICE PROPOSAL SUBMISSION SHEET (BDF-10)

3. Schedule – A (Form for Lump sum cost of the Bid)

4. Schedule – B Apportionment of contract Price for payments according to cost centres. Price Weightage for interim Payment (B-1 to B-13).

Page 4 of 22

PREAMBLE

1. The Price Schedules shall be read in conjunction with the “Instructions toBidders”, “General Conditions”, “Particular Conditions”, “Employer’sRequirement”, ”Technical Specifications”, and “Drawings”.

2. The bidder shall quote lump sum cost in INR for the entire project “Design andConstruction of Formation in Embankments/Cuttings including blanketing,Viaducts, Rail Flyover, Bridges (Major, Minor & RUBs), Supply and Spreading ofBallast and other related infrastructural works for double track electrified railwayline on Design Build Lump Sum Basis from Howrah end approach of DFC Sonebridge to Chirailapathu station of IR towards Howrah & to New Sonnagar stationtowards Garhwa and at Dehri-on-Sone yard from Km. 3.16 to Km. 5.38 inconnection with Eastern Dedicated Freight Corridor in the state of Bihar in India”in Schedule-A. The cost shall cover all the items of the work as detailed in the“Employer’s Requirement” contained in Part-2 Section-V of the Bid document aswell as conforming to all specifications and stipulations laid down in the BidDocument including all addenda/corrigenda thereof till the date of submission ofBids. The lump sum cost shall be inclusive of all costs on Design, Drawings,Reports, Survey, Site Facilities, Construction Equipment, Plants, Instruments,Labour, Supervision, Materials, Erection, Testing, Maintenance, TemporaryWorks, Site Access, Safety, Security, Defect Rectification, Insurance, Profit,duties, Taxes, Levies, Royalties as per applicable law together with all generalrisks, liabilities and obligations set out or implied in the contract.

3. To facilitate stage payments during execution for which Lump sum Cost shall bequoted in Schedule A, the entire work has been divided into Thirteen (13) CostCenters along with their respective percentages of the quoted lump sum of costin Schedule `B’. The value of each cost centre can thus be worked out basedon lump sum quote. For further facilitating stage/on account payment, each of thecost centres have been divided into cost sub centres with percentageapportionment of the cost attached to each cost centres as indicated inSchedule B-1 to B-13.On account payments would be made on prorate basis for work done againsteach Cost Centre/Sub-Centre. There are certain items which are not included inCost centres/Sub-centres, these works shall also be carried out by Contractor, noextra/additional payment shall be done on account of these works.

For the purpose of stage/on account payment, the successful Bidder needs toindicate quantities assessed on the basis of preliminary/Final designs/drawingsfor each Cost Centres/Sub-Centers. However, on approval of detailed designsand drawings by Engineer/Employer against, each Cost Centre/Sub Centre, thefinal quantities for each Cost Centre/Sub Centre would be considered andpayment done will be adjusted accordingly.

Page 5 of 22

4. Filling of Bid document

The Cost shall be filled in with indelible ink or be type written. The personauthorized to sign on behalf of the Bidder shall sign in full with the date at thebottom of all pages and at the end of schedules.

Page 6 of 22

BDF- 10

PRICE PROPOSAL SUBMISSION SHEET(To be submitted with Financial Proposal only)

Date: ……………………………….Invitation for Bid No. HQ/EN/EC/SEB JN.Works, dated : 09.10.2015

To: ...........................................................................................................................

We, the undersigned, declare that:(a) We have examined and have no reservations to the Bidding Documents,

including Addenda issued in accordance with Instructions to Bidders (ITB) 7;(b) We offer to execute the Work in conformity with the Bidding Documents;(c) The total price of our Bid is as per schedule- A (Attached).(d) We understand that this bid, together with your written acceptance thereof

included in your notification of award, shall constitute a binding contract betweenus, until a formal contract is prepared and executed; and

(e) We have not made any tampering or changes in the bidding documents onwhich the bid is being submitted and if any tampering or changes are detectedat any stage, we understand the bid will invite summery rejection and forfeitureof bid security/the contract will be liable to be terminated along with forfeitureof performance security, even if LOA has been issued.

(f) We understand that you are not bound to accept the lowest bid or any other bidthat you may receive.

Name ......................................................................................................................In the capacity of ....................................................................................................Signed ....................................................................................................................Duly authorized to sign the Bid for and on behalf of ...............................................

Date ........................................................................................................................................................................................................................................................

Page 7 of 22

PRICE SCHEDULESchedule A

(Sub-clause 14.1 of GCC)Name of Work :- “Design and Construction of Formation in Embankments/Cuttingsincluding blanketing, Viaducts, Rail Flyover, Bridges (Major, Minor & RUBs), Supplyand Spreading of Ballast and other related infrastructural works for double trackelectrified railway line on Design Build Lump Sum Basis from Howrah end approach ofDFC Sone bridge to Chirailapathu station of IR towards Howrah & to New Sonnagarstation towards Garhwa and at Dehri-on-Sone yard from Km. 3.16 to Km. 5.38 inconnection with Eastern Dedicated Freight Corridor in the state of Bihar in India.”S No. Description of Schedule Lump Sum cost in INR

In Figures In Words1 2 3 41 Design and Construction of Formation in

Embankments/Cuttings including blanketing,Viaducts, Rail Flyover, Bridges (Major,Minor & RUBs), Supply and Spreading ofBallast and other related infrastructuralworks for double track electrified railway lineon Design Build Lump Sum Basis fromHowrah end approach of DFC Sone bridgeto Chirailapathu station of IR towardsHowrah & to New Sonnagar station towardsGarhwa and at Dehri-on-Sone yard fromKm. 3.16 to Km. 5.38 in connection withEastern Dedicated Freight Corridor in thestate of Bihar in India.

Total Amount Rs.

Note:-1) The cost shall be filled in with indelible ink or be type written.2) The above quoted cost covers all items of the work as detailed in the

“Employer’s Requirement” contained in Part 2 – Section-V as well asconforming to all specifications and stipulations laid down in the BidDocument including all addenda/corrigenda thereof till the date ofsubmission of Bids.

3) It is inclusive of all costs on Design, Drawings, Reports, Survey, SiteFacilities, Construction, Equipment, Plants, Instruments, Labour,Supervision, Materials, Erection, Testing, Maintenance, TemporaryWorks, Site Access, Safety, Security, Defect Rectification, Insurance,Profit duties, Taxes, Levies, Royalties as per applicable law togetherwith all general risks, liabilities and obligations set out or implied in thecontract.

SIGNATURE OF BIDDER

Page 8 of 22

Price Schedule

Schedule - B

Apportionment of Contract Price for Payments According to Cost Centres

(Sub-clause 14.4, GC)

SN

Cost Centre Percentage ofContract Price

(1) (2) (3)

1 Survey, investigation, Design, Setting out and As Builtdrawings

2.0

2 Construction of Viaduct 33.0

3 Bridge Portion of Rail Fly Over and its approach spans(excluding approach earth work which will be covered in“Earthwork”).

13.0

4 Earthwork 13.05 Minor Bridges, Road Under Bridges, LHS & RCC Buried

Boxes6.3

6 Major Bridges 5.07 Ballast Supply and Spreading 4.08 Construction of Station Building at New Sonnagar, Cabin at

Chirailapathu and Cabin at Sonnagar.0.7

9 Construction of quarters (162 units) and construction of one50,000 gallon capacity RCC water tank with tubewell 15000GPH capacity & pump at Sonnagar/approved location.

7.0

10 Construction of 100000 gallon capacity RCC tank withtubewell 15000 GPH capacity with pump & pump house,Electrical Sub-station, Electrical office, Carriage & Wagonoffice ( 317.50Sqm plinth area) at Dehri-on-Sone.

2.0

11 Construction of new ROB, dismantling of existing structures,regrading of road including construction of return walls & REpanel for restoration of traffic at NH-2 at DFC Ch.4900.

8.0

12 Shifting of Chartered Utilities: Civil & Electricaland dismantling of Water Tank, Boundary Walls, Buildings(sub-station, electrical office, carriage & wagon office,quarters, Temple etc.) falling on DFC alignment.

2.0

13 Miscellaneous works & Final Taking Over 4.0Total- 100%

The percentage figures as filled in column 3 by the Employer for the apportionment ofthe Contract Price for completion of the Works corresponding to the items given aboveare fixed and payment will be released for different cost centre as per above percentagebreak-up of contract price. Refer Sub-Clause 14.4 – Particular Conditions of Contractfor further details.

Page 9 of 22

Price Schedule B-1

Contract Price Weightage for Interim Paymentsfor

Survey, Investigation, Design, Setting Out and As Built Drawing(Sub-clause 14.4 of GC)

CostCentre Item of Work Stage Payment Weigh

tage Cost PaymentProcedure

Survey,Investigation,Design,SettingOut andAs BuiltDrawing

1 Survey 1(a) Site survey andfinalization ofalignment

05%

2%

of t

he C

ontr

act P

rice

Unit ofmeasurement

is linearlength alongalignment.Payment ofeach stage

will be madeon prorata

completion oflinear length

as perweightage

given in thisSchedule

Geotechnical/HydrologicalInvestigations

1(b) Site data collection,Detailed Geotechnicaland Hydrologicalinvestigations reportsubmission, andacceptance of Reportby Engineer.

10%

PreliminaryDesign

1(c) Preliminary Design ofthe formation, bridges,culverts, Viaduct,Flyovers / RUB, LHS,fencing, drains,buildings, and allother structures.

20%

2 DefinitiveDesign

2 Definitive Design ofthe formation,bridges, culverts,Viaduct, Flyovers,RUB, LHS, fencing,drains, buildings, andall other structures.

30%

3 Setting Out 3 Setting out of theFinal Alignment withlocation of allstructures

15%

4 CompletionDrawings

4 As Built Drawings20%

Total: 100%

Note :Payment will be made on certification of the Engineer for various items.

Page 10 of 22

Price Schedule B-2

Contract Price Weightage for Interim Paymentsfor

Construction of Viaduct(Sub-clause 14.4 of GC)

CostCentre Item of Work Stage Payment

Weightage

Cost PaymentProcedure

Construction ofViaduct

Construction ofViaduct.

1 On ground clearance,ground improvement ifrequired to improve thebearing capacity andtesting, completion ofthe foundation worksetc.

10%

33%

of t

he C

ontr

act P

rice

Unit ofmeasurementis linear lengthalongalignment.Payment ofeach stage willbe made onproratacompletion oflinear lengthas perweightagegiven in thisSchedule.

2 On completion of RCCBoxes/abutment &piers in case ofslab/girder.

50%

3 On completion ofbalance works as perdrawing like –wearingquote/deck slab,walkway/foot path,cable duct, railings,wing walls, returnwalls, Ballast Retainer,hand railing, trolleyrefuges, drainagearrangement, earthingarrangement, pedestalfor OHE mast, alltypes of protectionworks, pitching, backfilling at approaches,painting/finishing etc.complete in all respect.

40%

Total: 100%Note-

1. Payment will be made on certification of the Engineer for various items.

Page 11 of 22

Price Schedule B-3

Contract Price Weightage for Interim Paymentsfor

Bridge Portion of Rail Fly Over and its approach spans (excluding approachearthwork which will be covered under “Earthwork”)

(Sub-clause 14.4 of GC)Cost

CentreItem ofWork Stage Payment Weigh

tageCos

tPayment

ProcedureBridgeportionof RailFlyOverand itsapproachspans(excludingapproachearthworkwhichwill becovered under“Earthwork”)

Construction ofBridgePortion ofRailFlyoversand itsapproachspans(excludingapproachearthworkwhich willbecoveredunder“Earthwork”

1 On ground clearance, preparation ofbase below the pile cap for pilefoundations or below the well capfor well foundation or below the pierbase for open foundation asapplicable, ground preparation work,completion of the foundation worksand testing work.

20%

13%

of t

he C

ontr

act P

rice Payment of

each stagefor RFO willbe paid oncompletion ofthe relevantstage as pertheWeightagegiven in thisschedule.

2 On Completion of abutment/piersincluding pile caps or well caps asapplicable, work up to the bottom ofsuper-structure (without bearings)including pier/abutment cap.

15%

3 On completion of super structures,bearings, walkways, hand rails,testing.

40%

4 On completion of balance works asper drawing like - wing walls, returnwalls, back filling, all protectionworks, Painting of Girders, pitching,turfing, if any, etc. complete in allrespects.

25%

Total: 100%Note :

1. Payment will be made on certification of the Engineer for variousitems.

2. For Rail Flyover and its approach spans – the stage 1 & 2 above will befurther subdivided, into Number of piers + 2 abutments as per theapproved drawing of RFO and stage payment for completion of work foreach pier and abutment shall be made as per the requirement of thesestages.

3. For Stage-3: Stage payment for completion of work of superstructure shallbe made on completion of each span on prorate completion of linearlength.

Page 12 of 22

Price Schedule B-4Contract Price Weightage for Interim Payments

forEarthwork

(Sub-clause 14.4 of GC)Cost

CentreItem ofWork Stage Payment Weig

htage Cost PaymentProcedure

Earthwork

Earthwork informationincludingblanketing, drains,retainingstructures, turfing,pitchingand otherincidentalworks.

1

1(a)

1(b)

1(c)

Earthwork in embankment/cuttingincluding compaction so as toachieve 50% of desired heightbelow bottom of blanketing layer:For Sonnagar-New Sonnagaralignment (Ch.225.975 to Ch.8460),

For Sonnagar-Chirailapathualignment (Ch. 225.975 to Ch.7270),

For Km 3.16 to Km 5.38 (NearDOS).

13%

13%

4%

13%

of t

he C

ontr

act P

rice

Unit ofmeasurement is linearlength alongalignment.Payment ofeach stagewill be madeon proratacompletionof linearlength asperweightagegiven in thisSchedule.

2

2(a)

2(b)

2(c)

Balance earthwork in embankment/cutting including compaction uptobottom of blanketing layer:For Sonnagar-New Sonnagaralignment (Ch.225.975 to Ch.8460),

For Sonnagar-Chirailapathualignment (Ch. 225.975 to Ch.7270),

For Km 3.16 to Km 5.38 (NearDOS).

11%

11%

3%

3 Earthwork in Blanketing layercomplete in all respect

35%

4 Longitudinal/cross drains includingcable ducts on either side of drain,retaining structures, pitching, turfingand other incidental works,complete.

10%

Total: 100%Note :

i) Payment will be made on certification of the Engineer for various items.ii) In case of UP & DN lines to / from Chirailapathu on both sides of viaduct

where UP and DN line are separate, each line will be considered halflinear length separately for the purpose of payment.

iii) Track center, Ground level, formation level etc. shown in indicative planand profile are indicative which may change as per design and Employer’srequirements. However stage payment shall be made as per approveddefinitive plan and profile.

Page 13 of 22

Price Schedule B-5

Contract Price Weightage for Interim Paymentsfor

Minor Bridges, Road Under Bridges, LHS and RCC Burried Boxes(Sub-clause 14.4 of GC)

CostCentre Item of Work Stage Payment

Weightage

Cost PaymentProcedure

MinorBridges,RUBs,LHS andRCCBurriedBoxes.

Construction ofMinor Bridges,Road UnderBridge, LHS andRCC BurriedBoxes etc.

1 On ground clearance,ground improvement ifrequired to suit designbearing capacity andtesting, completion ofthe foundation worksetc.

10%

6.3

% o

f the

Con

trac

t Pric

e

Cost of eachminorbridge/RUB/LHS/BurriedBoxes will bedetermined onthe basis oftotal linearlength, alongalignment, ofthe minorbridges/RUB/LHS/BurriedBoxe on pro-rata basis.Payment ofeach stage fora bridge/RUBwill be madeon thecompletion ofthe relevantstage as perthe weightagegiven in thisschedule.

2* On completion of RCCBoxes, abutment, piersfor slab/girder bridges.

47%

3 On completion ofbalance works as perdrawing like -deckslab, walkway,footpath, cable duct,railings, wing walls,return walls, BallastRetainer, hand railing,all types of protectionworks, pitching, turfing,back filling andapproaches, rivertraining works, if any,etc. complete in allrespects.

43%

Total: 100%Note-

1. Payment will be made on certification of the Engineer for various items.2* If a bridge is constructed using precast elements, then 75 % payment

against sub cost centre 2 shall be released upon finishing casting ofelements and transporting all such elements to the site of bridgeconstruction. Balance 25% shall be released after completion of stage 2.

3. In case of UP & DN lines to / from Chirailapathu on both sides of viaductwhere UP and DN lines are separate, each line will be considered halflinear length separately for the purpose of payment.

Page 14 of 22

Price Schedule B-6

Contract Price Weightage for Interim Paymentsfor

Major Bridges(Sub-clause 14.4 of GC)

CostCentre Item of Work Stage Payment Weig

htageCost Payment Procedure

MajorBridges

Construction ofMajor Bridges

1 On ground clearance,preparation of base belowthe pile cap or below thewell cap for wellfoundation or below thepier base for openfoundation as applicable,ground preparation work,completion of thefoundation works andtesting work.

25%

5%

of t

he C

ontr

act P

rice Cost of each bridge will

be determined on thebasis of total linearlength along thealignment, of the bridgeson prorata basis.Payment of each stagefor a bridge will be madeon completion of therelevant stage as per theweightage given in thisschedule.

2 On Completion ofabutment, piers includingpile caps or well caps asapplicable, work up to thebottom of super-structure(without bearings)including pier/abutmentcap.

20%

3 On completion of superstructure, bearings,walkway footpath, cableduct, hand rails, testingetc.

30%

4 On completion of balanceworks as per drawing like -wing walls, return walls, allprotection works, pitching,completion of approachesincluding back filling,turfing, if any, testing oncompletion etc. completein all respects.

25%

Total: 100%NOTE :1.Payment will be made on certification of the Engineer for various items.

Page 15 of 22

Price Schedule B-7

Contract Price Weightage for Interim Paymentsfor

Ballast Supply and Spreading(Sub-clause 14.4 of GC)

CostCentre

Item ofWork Stage Payment Weigh

tage Cost Payment ProcedureBallastSupplyandSpreading

BallastSupplyandSpreading

1 Supply andSpreading of Ballast :

4%

of t

he C

ontr

act P

rice

1(a) Supply of Ballast(Quantity: 44,000Cum)

32% Stage payment underthis cost centre willbe regulated basedon pro-rata volumetricmeasurement (stackmeasurements) ofBallast Supply.

1(b) Spreading of Ballast(Quantity: 44,000Cum) includinglevelling and rollingon Formation/SoneBridge/Viaduct/Ballasted deck Bridgesalong DFC trackalignment to makeinitial neat Ballastcushion of approx.200mm after requiredrolling to facilitatelaying of track overthe ballast bed.

10% Stage payment underthis cost centre shallbe regulated onprorate linearmeasurement basisof compacted/rolledprofile of Ballast onbed.

2 Supply of Ballast instacks (Quantity:66,000 Cum) atspecified locations forthe use by trackcontractor.

58% Stage payment underthis cost centre willbe regulated basedon pro-rata volumetricmeasurement (stackmeasurements) ofBallast Supply.

Total: 100%

Note:Payment will be made on certification of the Engineer for various items.

Page 16 of 22

Price Schedule B-8

Contract Price Weightage for Interim Paymentsfor

Construction of Station Building at New Sonnagar, Cabin at Chirailapathu andCabin at Sonnagar

(Sub-clause 14.4 of GC)

CostCentre

Item ofWork Stage Payment

Weightage

Cost Payment Procedure

ConstructionofStationBuilding atNewSonnagar,CabinatChirailapathuandCabinatSonnagar

Construction of StationBuilding at

NewSonnagar,Cabin at

Chirailapathu and Cabinat Sonnagar

1 On completion offoundation upto plinthlevel as perEmployer’srequirement.

20%

0.7

% o

f the

Con

trac

t Pric

e

For the purposestage payment, costof each building willbe determined onpro-rata basis of totalarea of building inSqm. For buildingshaving more than onestorey the total areaof each such buildingwould be found outby adding the area ofeach storey to arriveat the total area.

Payment of eachstage under this costcentre will be madeas per weightagegiven in thisschedule.

2 On Completion ofBrick work upto rooflevel including doorand window framesas per Employer’srequirement.

40%

3 On completion of roofcasting, plastering,fixing doors/windowshutters, paintingdoor/window shutters,sanitary/water supplyworks, internalelectrical wiring worksin the buildings andfinal finishing with allworks complete asper Employer’srequirement.

25%

4 Boundary wall,approach road,drainage outsidebuildings.

15%

Total: 100%

Note:Payment will be made on certification of the Engineer for various items.

Page 17 of 22

Price Schedule B-9

Contract Price Weightage for Interim Paymentsfor

Construction of Quarters(Sub-clause 14.4 of GC)

CostCentre

Item ofWork Stage Payment Weigh

tageCos

t Payment ProcedureConstruction

ofquarter

Construction of

quarters(162units)and

Construction of50000gallon

capacityRCC tank

withtubewell15000GPH

capacitywith

pump atSoneNagarand 8units

quartersat New

Sonnagar.

1 On completion offoundation upto plinthlevel as per Employer’srequirement.

20%

7 %

of t

he C

ontr

act P

rice

For the purposestage payment, costof each building willbe determined onpro-rata basis of totalarea of building/blockin Sqm. For buildingshaving more than onestorey the total areaof each such buildingwould be found outby adding the area ofeach storey to arriveat the total area.

Payment of eachstage under this costcentre will be madeas per weightagegiven in thisschedule.

2 On Completion of Brickwork upto roof levelincluding door andwindow frames as perEmployer’s requirement.

34%

3 On completion of roofcasting, plastering, fixingdoors/window shutters,painting door/windowshutters, sanitary/watersupply works, internalelectrical wiring works ineach unit in the buildingsand final finishing with allworks complete as perEmployer’s requirement.

22%

4 On completion WaterTank of about 50,000Gallon capacity forRailway.

9%

5 On completion PumpHouse and 15000 GPHtube well with pump &connection of Rising andDelivery pipe etc.

5%

4 Boundary wall, approachroad, drainage outsidebuildings.

10%

Total: 100%

Note:Payment will be made on certification of the Engineer for various items.

Page 18 of 22

Price Schedule B-10

Contract Price Weightage for Interim Paymentsfor

Construction of 100000 gallon capacity RCC tank with tubewell 15000 GPHcapacity with pump & pump house and Electric Sub Station, Electrical Office,Carriage & Wagon office ( 317.50 Sqm ) plinth area at Dehri on sone.

(Sub-clause 14.4 of GC)

Note:1. Payment will be made on certification of the Engineer for various

items.2. Further distribution for stage payment of item 2 & 3 above will be

decided by Engineer

Cost Centre Item ofWork Stage Payment Weight

age Cost PaymentProcedure

Construction of 100000galloncapacityRCC tankwithtubewell15000 GPHcapacitywith pump &pumphouse,connectionof rising anddelivery pipeetc. andElectric substation &Electrical,Carriage &Wagonoffice (317.50Sqm )plinth areaat Dehri onsone.

Constructionof WaterTank in lieuof existingWater Tankat DOS

1. On completion WaterTank of about100,000 Galloncapacity for Railway.

40%

2 %

of t

he C

ontr

act P

rice

Payment will bemade oncompletion of theseactivities as perWeightage given inthis Schedule.

Pump Houseand 15000GPH tubewell withpump&PumpHouse,connection ofRising andDelivery pipe

2. On completion PumpHouse and 15000GPH tube well withpump & connection ofRising and Deliverypipe

20%

Electric substationbuilding &Electrical,Carriage &Wagon office( 317.50Sqm) plinth areaat Dehri onsone.

3. On completion ofElectric sub station &Electrical, Carriage &Wagon office (317.50Sqm) plintharea at Dehri onsone..

40%

Total: 100%

Page 19 of 22

Price Schedule B-11Contract Price Weightage for Interim Payments

forConstruction of new ROB, dismantling of existing structures, regrading of roadincluding construction of return walls & RE panel for restoration of traffic at NH-2at DFC Ch.4900.

(Sub-clause 14.4 of GC)Cost

Centre Item of Work Stage PaymentWeightage

Cost

PaymentProcedur

eConstructionof newROB,dismantling ofexistingstructures,regrading ofroadincludingconstruction ofreturnwalls &REpanelforrestoration oftrafficat NH-2at DFCCh.4900

Dismantling of RE Panel,return wall, etc. in lengthrequired to pass DFCCILtrack and for construction ofnew abutments as perapproved plan andprotection of RE panel wallincluding removing of filledup sand etc. in between REpanel wall.

1(a) Dismantling of RE Panel,return wall, existingabutments etc. in lengthrequired to pass DFCCILtrack and for constructionof new abutments as perapproved plan andprotection of RE panelwall including removing offilled up sand etc. inbetween RE panel wall.

3.5%

8%

of t

he C

ontr

act P

rice

Paymentof eachstage willbe madeoncompletionof therelevantstage asper theWeightagegiven inthisschedule.

Dismantling of existingabutments, return wall,beam under traffic andpower block(as perrequirement) and slab,removing of fill materials tofacilitate construction of newabutment of 60 m Bow stingGirder

1(b) Dismantling of existingabutments, return wall,beam and slab, removingof fill materials to facilitateconstruction of newabutment of 60 m Bowsting Girder

3.5%

Ground clearance,preparation of base belowthe pile cap for pilefoundations or below thepier/abutment base for openfoundation as applicable,ground preparation work,completion of the foundationworks and testing work forConstruction of new ROBopening for DFC tracks inexisting Road (NH-2).

1(c) On completion of groundclearance, preparation ofbase below the pile capfor pile foundations orbelow the pier base foropen foundation orbottom slab of box asapplicable, groundpreparation work,completion of thefoundation works andtesting work forConstruction of new ROBopening for DFC tracks inexisting Road (NH-2).

3%

Page 20 of 22

Construction ofabutment/piers for two Nos.two Lane RDSO standard60 M Bow string Girderincluding pile caps asapplicable, work up to thebottom of super-structure(without bearings) includingpier/abutment cap for newROB opening for DFC andIR tracks in lieu of existingROB on NH-2.

2. On Completion ofabutment/piers includingpile caps as applicable,work up to the bottom ofsuper-structure (withoutbearings) includingpier/abutment cap fornew ROB opening forDFC tracks in existingRoad (NH-2).as perapproved GAD

30%

Completion of balanceworks of super structures(02nos. 2lane Bow sting RDSOstandard Girders), bearings,walkways, hand rails, crashbarriers testing, wearingcoat, wing walls /returnwalls, back filling, allprotection works etc.complete in all respect fornew ROB opening for DFCand IR tracks in lieu ofexisting 4 lane ROB on NH-2.

3. On completion of balanceworks of super structures,bearings, walkways, handrails, testing, wearingquote, wing walls /returnwalls, back filling, allprotection works etc.complete in all respect fornew ROB opening forDFC tracks in existingRoad (NH-2).

40%

Completion of regrading ofRoad (NH-2) on both side ofROB for the purposerestoration of traffic onexisting NH-2 afterconstruction of new ROBopening complete includingearthwork, WBM, blacktopping etc. as per NHspecifications.

4. On completion ofregrading of Road (NH-2)towards Aurangabad sideof ROB for the purposerestoration of traffic onexisting NH-2 afterconstruction of new ROBopening completeincluding earthwork,WBM, black topping etc.as per NH specifications.

20%

Total: 100%

Note :1. Payment will be made on certification of the Engineer for various

items.2. Further distribution for stage payment of item 2 & 3 above will be decided

by Engineer.3. Traffic block will be arranged as per Appendix – 13, Volume-6, Section-V,

Part-2 Employer’s Requirement. Expected duration of each block will belimited to maximum 3 – 4 hours in a stretch as per convenience of IR.

Page 21 of 22

Price Schedule B-12

Contract Price Weightage for Interim Paymentsfor

Shifting of Chartered Utilities: Civil & Electrical and dismantling of Water Tank,Boundary walls, Buildings (Sub-station, Electrical Office, Carriage and

Wagon Office, Quarters, Temple etc.) falling on DFC alignment.(Sub-clause 14.4 of GC)

Note:1. Payment will be made on certification of the Engineer for various

items.2. Further distribution for stage payment of item 2 & 3 above will be

decided by Engineer.

CostCentre

Item ofWork Stage Payment

Weightage

Cost Payment Procedure

Shifting ofCharteredUtilities:Civil &Electricalanddismantlingof WaterTank,Boundarywalls,Buildings(Sub-station,ElectricalOffice,Carriageand WagonOffice,Quarters,Templesetc.) fallingon DFCalignment.

CivilUtilities

1. Removal andreconstruction ofchartered civil utilitiesas mentioned inBidding Document.

25%

2%

of t

he C

ontr

act P

rice

Payment will bemade on completionof these activities asper Weightage givenin this Schedule.

Dismantling ofwork ofWaterTank,SubStation,Offices,Godownetc.

2. On completion ofdismantling of WaterTank, Quarters,Temples, Sub StationBuilding, Offices,Godown etc.

35%

ElectricalUtilities

3. Relocation ofchartered Electricalutilities as mentionedin Bidding Document.

40%

Total: 100%

Page 22 of 22

Price Schedule B-13

Contract Price Weightage for Interim Paymentsfor

Miscellaneous Works and Final Taking Over(Sub-clause 14.4 of GC)

Note: Payment will be made on certification of the Engineer for various items.

CostCentre

Item ofWork Stage Payment

Weightage

Cost Payment Procedure

Miscellaneous Worksand Final

Taking Over

LevelCrossing

1. On completion ofheight gauge (Drg.No.TI/DRG/HGAUGE/RDSO/00002/05/0),road correction atunmanned LC.

5%

4%

of t

he C

ontr

act P

rice

Payment will bemade on completionof these activities.

FinalTakingOverActivities

2. Completion of allother finishing itemslike Bridge nameboard, bridge plaque,flood gauges, trolleyrefuge, railing forinspection platform,ladders etc.

40% Payment will bemade on completionof these activities.

3. Final Taking Over 55% Lump Sum.

Total: 100%