PARK STREET BRIEFINGLOCAL RESIDENTS AND COMMUNITY PRESENTATION
CAMBRIDGE PARK STREET
(APARTHOTEL AND
PUBLIC CAR/ CYCLE PARK)
SEPTEMBER 2021
Introduction and Key Dates
• Introduction to the Contractor (Gilbert Ash) https://gilbert-ash.com/
• Design/ project update
• Sequence, programme, logistics and what it means to you
• Ongoing engagement initiatives and communications strategy
Project Milestones Target dates
• Advanced enabling works from October 2021
• Car Park Closure 03 January 2022
• Main Contract commencement 10 January 2022
• Car Park re-opens August 2024
• Hotel opens March 2025
Summary of the Proposals
• Triple basement car park which remains in the ownership of the Council and management under the
Car Park team;
• Consists of 225 parking spaces including 16no. blue badge parking spaces, 270 cycle parking
spaces (inc 18 oversize bikes), 20 motorcycle spaces, improved and enhanced security;
• Publicly accessible courtyard linking Jordan Yard to Park Street; with ecological measures including
bee hotel, planting and artwork;
• Five storey 229 room premium (4*) Aparthotel (C1 use class), which includes a gym, lounge & café;
• Staycity is confirmed as the Aparthotel operator. Upscale brand; Wilde.
Summary of the layout of the scheme
This image provides an illustration
of all of the key ground floor,
publicly accessible areas, and
public artwork locations
When completed there will be a
pleasant shortcut from Bridge
Street to Park Street.
Sustainability and Ecology
Sustainability
• BREEAM ‘Excellent’ targeted
• All electric building, no gas
• 19% improvement on Building Regs Part L• Heating and Cooling recovery systems• Rainwater harvesting • Sustainable drainage and attenuation • LED lighting and Air Source Heat Pumps (ASHP)• 20kWp of photovoltaic (solar) panels on the roofs• Mechanical ventilation and airtightness (windows are not openable
and therefore further mitigates heat/ cooling loss)• Blackout blinds and shading to minimise solar gain through glazing• Good quality and recessed glazing to minimise solar gain • Lifecycle analysis and Carbon Embodiment study has been
undertaken• Minimisation of C02 emissions and pollution • Lifespan and flexibility/ building functionality and consideration of
climate change• 100% electric charging provision for the public car park
Ecology:
• Green roof and bio-diverse planting
• Planting to complement improvements to air quality
• Fragrant and bee friendly planting in the courtyard (publicly
accessible)
• A bee hotel nesting bees
• Insect towers on the roofs
• Bird nesting boxes
Project Update
• Site investigations and ground water and gas site monitoring (6 months) were completed in 2020. 6 boreholes and reference made to 20 number boreholes from records within 250m of the study site boundary. The engineers have confirmed that the results have showed nothing of concern;
• The tender has been completed and Gilbert-Ash have been formally engaged as the Main Contractor;
• Site setup, enabling works and early archaeology are planned to commence October 2021;
• This will require relocation and reduction of some ground floor car park facilities;
• No car park closure until January 2022;
• Main project works and demolition planned to commence January 2022.
Site setup – Phase 1
65
Key1. Site security / Sign-in2. Main Site office / meeting room3. Office toilets 4. Contracts managers office 5. Sub – Contractors office 6. Canteen 7. Drying room / changing room 8. Male / Female toilets 9. Substation10. Material sample area 11. Turn in access provided for
Maypole delivery access.
Key Dates:• December 2021 to• February 2023
(Approx. 63 weeks)
Jesus College car park compound on Park Street
CFA PilingContinuous Flight Auger (CFA) Piling
The use of CFA piling is constructed with partial soil removal by drilling. This generates
lateral soil compression. It is a lower vibration technique and is considered to be
beneficial over driven piles and has a higher pile capacity than piles using bentonite
slurry.
Once the depth of the pile has been achieved with the drill concrete is injected and the
drill is withdrawn and concrete is filled into the required depth with a reinforcement cage
in place.
The drill is then cleaned and the rig can proceed to the next location.
Secant piles are constructed so that there is an intersection of one pile with another.
Secant piling is undertaken by a ‘hit and miss’ pile approach where every other pile
location is undertaken and then the infill piles are revisited later. The secant pile concrete
wall forms a structurally robust and waterproof perimeter to the ‘basement box’.
Secant walls are utilised to transfer lateral, vertical or a combination of both loads
through weak soil layers to a suitable bearing layer. They can be drilled in all types of
configurations that can form an interlocking watertight wall and provide a structural
overlapping wall.
Secant Piles
Source: Soilmec Drilling and Foundation Equipment
M A T E R I A L D I S T R I B U T I O N
Zone A
Zone B
Scaffold Zone
Tower Crane location
Crane Erection Date• December 2022
Crane Dismantle Date• April 2024
Crane & Materials Distribution
Main Works
Key Dates:Completion of BasementLevel 3 – Ground Floor• May 2022 to • October 2023
Ground to Roof• October 2023 to• May 2024
Envelope To Scaffold Dismantle• October 2023 to• February 2024• August 2024 Façade Complete
Car Park Handover• August 2024
Hotel Fit-out• February 2024 to• February 2025
Practical Completion • March 2025
General Construction InformationWorking times:
Working Times - Monday to Friday 08.00 to 18.00*/ Working Times – Saturday 08.00 to 13.00*/ No working on Sundays or Bank
Holidays. C of E Primary School peak times are 8:30 –9am and 15-15:30 (Monday to Friday) vehicle movements will strive to avoid
these periods as much as possible.
Please see table below, this relates to demolition noisy working hours 2022 onwards:
Mon Tues Wed Thurs Fri Sat Sun
0800 to 0900 Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish No works
0900 to 1000 Quieter working Quieter working Quieter working Quieter working Quieter working Noisy - demolish No works
1000 to 1100 Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish No works
1100 to 1200 Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish No works
1200 to 1300 Quieter working Quieter working Quieter working Quieter working Quieter working Quieter working No works
1300 to 1400 Quieter working Quieter working Quieter working Quieter working Quieter working Quieter working No works
1400 to 1500 Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish No works No works
1500 to 1600 Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish No works No works
1600 to 1700 Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish Noisy - demolish No works No works
1700 to 1800 Quieter working Quieter working Quieter working Quieter working Quieter working No works No works
Working Hours
▪ Agree system of monitoring
▪ Agree access requirements and timings
with neighbours
▪ Installation of targets
▪ Baseline readings
▪ Trigger levels set out in Award Docs
▪ Reporting method – who receives
▪ Ensure targets remain clear
Movement Monitoring– Adjacent Buildings
Frequency of readings as per agreed Party Wall Awards:
• During Demolition: 2x monthly
• Post demolition and during grubbing out foundations: 3 times total
• During substructure: weekly
• During superstructure until completion: 2x monthly
Movement Monitoring– Adjacent Buildings
Image examples of monitoring equipment (indicated as blue dots on above drawing) which are adhesive fixed to façade. Final locations and method of install to be agreed
Party Wall / Oversail Management
Maypole & 15 Portugal Place Carpark and abutment wall being removed
8-14 Portugal PlaceGarden wall remaining
8 Portugal Place Underpinning
5-7 Portugal Place Existing Basement -
Curry KingUnder Pinning
Bridge House – 12 Round Church StreetOversail time frames – access provisions
NB - Party wall tracker to monitor compliance against awards
Ongoing Community Engagement
• Site Manager – Martin Douthart:o Single point of contact - day to
day
o Liaison with Client Representative
• Weekly catch-up meetings:o Logisticso Programmeo H&S
• Monthly ‘Information Flyer’
• Daily monitoring by Logistics Manager:o Access / egress / deliverieso Temporary workso Temporary weathering
• Website Information Platform
Supplementary information
The below are further slides on the scheme for those interested in the appearance or
description of the aparthotel offering
Design – Park Street (Verified View 1)
This is the proposed scheme, it has
the Union Society building in the
foreground. Morgan Sindall recently
completed this scheme for Trinity
College.
Design – Park Street (Verified View 1)
This view is taken from Park
Street looking at the corner of
the Aparthotel reception and the
elevations fronting Round
Church Street and Park Street.
The entrance to the centre of
the image is the Aparthotel
entrance. The public car park
entrances are further to the
right along the frontage.
Design - Park Street (Verified View 2)
This view is taken from
Park Street, showing the
proposed building adjacent
to the Maypole Pub
courtyard.
This view looks at the
corner of the car park
vehicle and cycle entrance.
New Jordan Yard
pedestrian entrance and
pedestrian car park
entrance. The Aparthotel is
above.
Staycity ‘Wilde’ Aparthotel
Marick has partnered with the operator, Staycity Group
("Staycity") is the leading independent Aparthotel
operator in Ireland, the UK and Europe:
• Staycity currently operates 3,000 rooms across 20
locations;
• The company launched the Wilde Aparthotel brand
in March 2018 in central London; with other
locations currently in development;
• Staycity has identified Cambridge as one of their
key UK locations;
• This Aparthotel is a Premium brand which is looking
to attract leisure and business guests who will enjoy
the City's many cultural and historic attractions as
well as its restaurants, pubs, cafes, shops, and
businesses.
▪ Hotel style reservation/booking system.
▪ Collection of studios and one bedroom
apartments with lounge area and fitted
kitchen.
▪ Fitted out to a brand standard.
▪ Facilitating guest stays of up to 90 days.
▪ Longer stays than traditional hotels—
typically averaging 5 to 7 days.
▪ 24 hours concierge reception.
▪ On-site dining, gym, guest laundry facilities.
▪ Home from home experience.
WHAT IS ANAPARTHOTEL?
24HR C ONCIERGE, SHARED SPACES
HOME FROM HOME
FULLY-E QUIPPED KITCHENS
▪ Upscale Brand
▪ 4+ Star Category
▪ Short and Extended Stays▪ Design led to a higher standard of
products and material with curation
▪ International Locations:
Capital and Significant Cities.
Prime Locations.
▪ Enhanced F&B Offering.