Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1. chilled / mixed water to counting houses 2. cooling station transfer lines 3. stations construction Future works 4. VELO concentric lines construction 5. rack cooling and fire extinction network

Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed

Embed Size (px)

Citation preview

Page 1: Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed

Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

LHCb - Install Meeting 12/10/05

TS/CV/DC Installations STATUS

Ongoing works

1. chilled / mixed water to counting houses

2. cooling station transfer lines

3. stations construction

Future works

4. VELO concentric lines construction

5. rack cooling and fire extinction network

Page 2: Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed

1. Primary systems around barracks

CRIOTEC

-installation of pneumatic lines and actuators finished

(cabling to valves and control components from DSS)

-pressure tests performed successfully

(one leak detected, connection repaired)

-not fully tight valve changed today, system ready for operation, commissioning to TS/CV/OP asap

Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

Page 3: Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed

Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

2. DC stations transfer lines under construction

INEO ALPES

-transfer lines for IT, TT, OT, RICH stations under construction, to be finished in week 43 (before the 28th)

-piping to IT/TT safety chiller to be soon designed and installed according to same schedule

-on LHCb demand: isolation valves on four lines installed on RB84 side, bypass dismantled on same side, brackets near to barracks stairs on RB86 modified

-cavern wall on RB86 to be tidied up for pipes installation

(neon light, cables)

Page 4: Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed

3. DC stations constructionINEO ALPES

Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

Page 5: Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed

4. VELO concentric lines constructionSIMIND

Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

-schedule:

beginning Nov 28th or Dec 05th

duration 10 working days

-preliminary yard visit on 14/10

-PPSPS drawing up ongoing

-requests to LHCb: crane truck with operator, 2/3 nights for pressure tests (pneumatic, 125 bar)

Page 6: Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed

5. Rack cooling lines at mixed water, fire extinction network, chilled/mixed

water pipes modification on RB84

IT to be drawn up

Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

Fire prevention lines integration completed, on RB84 spurs almost defined, lines drawing up on RB86 priority. Tests on rack exchangers

and Wiener power supplies ongoing (Detraz, Bobillier)

Page 7: Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005 LHCb - Install Meeting 12/10/05 TS/CV/DC Installations STATUS Ongoing works 1.chilled / mixed

Others

Paolo Guglielmini - TS / CV LHCb Install Meeting - 12/10/2005

- ventilation system for Muon station M1/3

design under definition, ES approval in 3 weeks, TS/CV to supply components, installation from Muon collaboration

TS1

FS1

Mechanicalfilter

Blower

Post coolingbattery

Mixed watersupply (13 - 18 C)

Pressure manualregulator

Temperature andflow safety switches

Dividing manifold witheight outlet channels

- CV works required in SX8/R-003 (007, 008)

to be defined with F.Levrier

- air conditioners maintenance around barracks

performed by R.Mollay in week 42