PandID Sheets of a Process Plant

Embed Size (px)

Citation preview

  • 7/27/2019 PandID Sheets of a Process Plant

    1/36

    P&ID sheets of a process plant

    Basic theory

    and

    Utilization of P&ID data

  • 7/27/2019 PandID Sheets of a Process Plant

    2/36

    P&ID preliminaries

    Piping and instrumentation digrams is designers road map whichshows all the equipment,pumps,valves,instrumentation,and otherpiping items in sequence for proper system function.

    The primary element of a piping design is the piping and

    instrumentation diagram (P&ID).

    Both the process engineer and the instrument and controls engineerprovide design information

    P&ID shows all of piping including the physical sequence of

    branches, reducers, valves, equipment, instrumentation, etc.

    The P&IDs are used to operate the process system.

  • 7/27/2019 PandID Sheets of a Process Plant

    3/36

    A P&ID should include

    Instrumentation and designations

    Mechanical equipment with names and numbers

    All valves and their identifications

    Process piping, sizes and identification Miscellaneous - vents, drains, special fittings,sampling lines, reducers, increasers andswagers

    Permanent start-up and flush lines

    Flow directions

    Interconnections references

  • 7/27/2019 PandID Sheets of a Process Plant

    4/36

    A P&ID should include (continued).

    Control inputs and outputs, interlocks

    Interfaces for class changes

    Seismic category

    Quality level

    Computer control system input

    Vendor and contractor interfaces

    Identification of components andsubsystems delivered by others

  • 7/27/2019 PandID Sheets of a Process Plant

    5/36

  • 7/27/2019 PandID Sheets of a Process Plant

    6/36

  • 7/27/2019 PandID Sheets of a Process Plant

    7/36

  • 7/27/2019 PandID Sheets of a Process Plant

    8/36

  • 7/27/2019 PandID Sheets of a Process Plant

    9/36

  • 7/27/2019 PandID Sheets of a Process Plant

    10/36

  • 7/27/2019 PandID Sheets of a Process Plant

    11/36

  • 7/27/2019 PandID Sheets of a Process Plant

    12/36

  • 7/27/2019 PandID Sheets of a Process Plant

    13/36

  • 7/27/2019 PandID Sheets of a Process Plant

    14/36

  • 7/27/2019 PandID Sheets of a Process Plant

    15/36

  • 7/27/2019 PandID Sheets of a Process Plant

    16/36

  • 7/27/2019 PandID Sheets of a Process Plant

    17/36

  • 7/27/2019 PandID Sheets of a Process Plant

    18/36

  • 7/27/2019 PandID Sheets of a Process Plant

    19/36

    An example of a Process Flow Diagram (PFD)

    P&ID for this PFD

  • 7/27/2019 PandID Sheets of a Process Plant

    20/36

    P&ID for this PFD

  • 7/27/2019 PandID Sheets of a Process Plant

    21/36

  • 7/27/2019 PandID Sheets of a Process Plant

    22/36

    P&ID should not include :-

    Instrument root valves control relays

    manual switches

    equipment rating or capacity

    primary instrument tubing and valves

    pressure temperature and flow data

    elbow, tees and similar standard fittings

    extensive explanatory notes

    & G

  • 7/27/2019 PandID Sheets of a Process Plant

    23/36

    P&ID Guidelines The P&ID should utilize industry recognized symbols

    and abbreviations.

    A schedule should be presented on the P&ID orother referenced drawing, identifying all symbols,abbreviations and instrumentation functionidentifiers.

    System directional flow arrows should be utilized onthe P&ID.

    Design flow quantities and temperature and pressureset points are to be presented on the P&ID orcorresponding schedule.

    P&ID components are to be labeled with unique tagsor identifiers.

    Piping system lines are to be labeled at regularintervals to better facilitate the following of the lines

    on the drawing. Where P&ID lines extend tosubse uent drawin s.

    P&ID Guidelines (Continued)

  • 7/27/2019 PandID Sheets of a Process Plant

    24/36

    P&ID Guidelines (Continued)

    The P&ID may be used to present line sizes andtype information, insulating requirements, heattracing requirements, etc. where scale or complexity

    prohibit such presentation on the plans. The HVAC P&ID is intended to depict the Facilities

    Services systems including the distribution andgeneration of all HVAC water and steam systems.

    All heat addition and rejection components are to beincorporated into the P&ID as well as heatexchanger components.

    Terminal devices or multiple air handling equipmentheat exchangers are appropriately presented intypical form to communicate expectations forrepetitive component types.

    Instrument identifiers are intended to be crossreferenced to the Sequence of operation

    descriptions presented on the drawings or thes ecifications.

  • 7/27/2019 PandID Sheets of a Process Plant

    25/36

    P&ID data is used for - Design of plot plan and plant layout.

    For counting bill of materials. For piping specifications

    For pipe connecter and piperack specifications

    For detail piping layout. For pipe stress analysis.

    Material take-off (MTO) and bill of quantity

    (BOQ). Checking of isometrics and piping layouts.

    Checking regulation rules and practices.

  • 7/27/2019 PandID Sheets of a Process Plant

    26/36

    What is Material Take Off (MTO)?

    What is Bill of Material (BOM)?

    What is Bill of Quantity (BOQ)?

  • 7/27/2019 PandID Sheets of a Process Plant

    27/36

    1. Material takeoff( MTO):-

    A Material Take off (MTO) is the process ofanalyzing the drawings and determining all

    the materials required to accomplish the

    design. We then use the material takeoff to

    create a Bill of Materials. Inspection does not

    aid in creating a Bill of Material. Procurement

    and requisition are activities that occur after

    the Bill of Materials is complete.

  • 7/27/2019 PandID Sheets of a Process Plant

    28/36

    MTO= Material Take Off

    This can be a noun and a verb. The MTO is the

    finished product of a work activity (i.e.: Let me

    see the Material Take Off). In this case the

    "MTO" is a rather thick stack of computer print-

    outs that reflect all of the (piping) material

    requirements for the Area, Unit or total jobdepending on how the "MTO" was executed.

    MTO is also the activity itself (i.e.: Okay lets

    start the Material Take Off). In this case the

    "MTO" is the action of doing a mass download ofall the material from the computer models

    design data base.

  • 7/27/2019 PandID Sheets of a Process Plant

    29/36

    2. Bill of Materials (BOM):-

    A Bill of Material (B.O.M.) is a hierarchical list

    of materials (components, subassemblies,ingredients.) required to produce an item,showing the quantity of each required item.Other information such as scrap factors mayalso be included in the BOM for use inmaterials planning and costing.

    An engineering BOM represents theassembly structure implied by the parts listson drawings and drawing tree structure. Amanufacturing BOM represents the assemblybuild-up the way a product is manufactured.

  • 7/27/2019 PandID Sheets of a Process Plant

    30/36

    Bill of material reflecting the product as

    designed by engineering, referred to as theas-designed" bill of material.

    BOM= Bill of Material

    This is a noun. A Bill of Material is (normally)

    the listing of material required for one pipeline or segment thereof, such as an Isometric.

    Each Isometric should have a BOM attached.

  • 7/27/2019 PandID Sheets of a Process Plant

    31/36

    3. Bill of Quantities ( BOQ):-

    Bill of quantities is used as a form of cost

    planning and mapping to monitor andcontrol the construction cost during the

    execution or post-contract period of

    construction. These documents originated historically as

    non-contractual measurements, taken off

    drawings to assist tenderers in quotinglump sum prices.

  • 7/27/2019 PandID Sheets of a Process Plant

    32/36

    Bills of quantities are drawn up and specified by a costprofessional called a quantity surveyor and prepared in

    advance to take into account the works required for aproject, and then later used as a tender document toacquire bidding from the contractors who would beinterested in winning the job.

    There are different styles of bills of quantities, mainly the

    Elemental BOQ and Trade Bills. BOQ= Bill of Quantities

    This would be a noun. I have never used this term.Where I worked we used the term "Material Summaries."These documents were the result of taking all the

    material collected in the "MTO" and after sorting it bytype, material, size, etc. it is printed out in a form thatwould be forwarded to the purchasing department for theactual purchase.

  • 7/27/2019 PandID Sheets of a Process Plant

    33/36

    Bill of Material (BOM) Mainly Contains:-

    SR No Tag No Descriptio

    n

    Size Quantity

  • 7/27/2019 PandID Sheets of a Process Plant

    34/36

    Tag No is given to the Mainly to the :-

    Pipes

    Valves

    All types of fittings

    Gasket material used

    Type of bolt and nut used

    All types of valves

  • 7/27/2019 PandID Sheets of a Process Plant

    35/36

    Description Mainly Contains:-

    Standard used (i.e. ASME ,BIS,DIN etc)

    Material of Construction (MOC)

    Schedule No

    Grade of Material

    Pressure-temperature Rating Class

    Quantity:- Quantity gives the number of items .

  • 7/27/2019 PandID Sheets of a Process Plant

    36/36

    Example :-

    Prepare the bill of Material for following

    isometric Drawing ?