Upload
sundaram1783
View
233
Download
0
Embed Size (px)
Citation preview
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 1/89
Pipecoating Part 2
MODULE 4
APPLICATION of COATING
ELEMENTS IN THIS MODULE:
FBE Application
3 Layer Polyethylene and Polypropylene.
Application
INTRODUCTION PIPE COATING
Module “4” describes the process and the requirements for inspection andecording the identity of pipes when being processed in anti corrosion
oating facilities. Coatings described within this module include Fusion
Bonded Epoxy (FBE), 3 Layer Polyethylene and Polypropylene.
.0 FUSION BONDED EPOXY COATING (FBE)
usion Bonded Epoxy (FBE) is a fairy hard thermosetting material that is
ommonly used for corrosion control of steel surfaces. For pipe coating the
material can be used as a stand alone coating or it can be used as a primer
or multi layer coatings. For greater protection (Mechanical) sometimes two
ayers of FBE are applied simultaneously, this is commonly known as dual
oat FBE
FBE Coating
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 2/89
Prior to the commencement of FBE coating all incoming materials should
e checked against the material manufacturer’s certification and any other
pecification requirements. The Incoming receipt form IRF stipulates the
ncoming material testing requirements that are to be verified prior to using
he material. Incoming test that are typically Gel Time, Cure Time, Thermal
Analysis and Moisture Content. "See section 3.11 off line tests"
.1 INCOMING PIPE
Pipes are received at the incoming racks. Any contamination or pipe
efects that prevents acceptable coating and cannot be repaired at the
ncoming rack or grinding area shall be cause to hold the pipe. The held
ipe shall be removed from the process and clearly marked (HOLD or
REJECT) and placed into an appropriate holding area for adjudication by
he client representative as to its disposition.
he criteria for steel defects shall be generally in accordance with API (The
ractical detail to be agreed by both parties). See steel defects "Module 2"
Responsibilities:
he incoming Tally man shall be responsible for the recording and
raceability of all the incoming bare pipes. He shall also be responsible in
nsuring that the task is conducted in the safest possible manner.
he incoming Inspector shall be responsible for the release or quarantining
f the incoming bare pipe.
.2 COATING PROCESS
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 3/89
Preheat & Blast Cleaning:
Pipes are be placed onto the incoming blast line rack where bevel
rotectors (if fitted) are removed and end plugs fitted. The pipes are then
e indexed and lowered onto a blast line conveyor and conveyed through a
re-heat oven set to allow for the required preheat temperature to be
chieved.
he pipe surface temperature shall be monitored prior to blast cleaning
sing a hand held surface roller contact pyrometer, optical thermometer or
melt sticks.
he preheat temperature shall be checked as a minimum each hour and
he temperatures recorded. The steel surface temperatures for blast
leaning shall be above the required local dew point requirement, the dew-
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 4/89
oint should be checked twice per shift and recorded on an agreed Climatic
Conditions Report.
After preheating he pipes are then progressed through the first centrifugal
brasive cleaning machine; the blast machine operator shall continually
monitor the blast effectiveness via visual inspection. Abrasive samples (100
ml) shall be taken from the working mix(s) once per shift: the sample shalle passed through 1.18 mm & 0.425-mm mesh sieves. No more than 16%
hall pass the 0.425-mm sieve.
Should the amount of fines exceed this figure, fresh grit shall be added to
he working mix. Each abrasive sample shall be tested for chlorides and
ther contaminants. The results of the analysis shall be recorded on an
greed Abrasive Contamination Test Report
Responsibilities:
he Abrasive Line Supervisor shall be responsible for ensuring that the end
lugs are positioned correctly and that the specified preheat temperature is
onstantly maintained. He shall also ensure that the conveyor line speed is
onstant and that the surface amplitude and pipe cleanliness is maintained
within the specified tolerances. He shall also be responsible in ensuring
hat the task is conducted in the safest possible manner.
he QC Inspector/Auditor shall be responsible for verifying that end plugs
ave been positioned correctly and that the specified preheat temperature
s maintained. He shall also perform climatic conditions testing at the
pecified intervals and review laboratory testing of abrasive materials.
he Laboratory Technician shall be responsible for taking samples of the
brasive and analysing.
.3 Grinding Area:
On completion of the first abrasive blasting the pipes shall be indexed onto
he transfer holding rack (grinding area) and inspected. All pipes are to be
hecked for any steel imperfections i.e. sliver, scabs, lamination's, burrs or
ristles. Defects shall be repaired by grinding or by hand filing. Pipes that
annot be repaired and fail to meet the specified requirements shall be
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 5/89
learly marked (HOLD or REJECT), removed from the process and placed
n a reject rack for adjudication by the client as to its disposition.
Details of pipe defects shall be recorded on an agreed Grinding Inspection
Report.
A salt contamination check of the blasted pipe surface is checked using anSCM 400 salt contamination instrument and the results recorded. Typically
he first pipe then further two pipes per shift are checked, the results are
ecorded on an agreed Salt Contamination Test Report.
On completion of surface defect and salt contamination checks, the pipes
re lowered onto the second centrifugal abrasive cleaning line where the
ipes receive a second blasting process.
After the second blasting operation the blasted surfaces are checked for
urface profile (using Testex Press-O-Film) replicating tape or other agreed
methods and the profile recorded. Typically pipes are checked at
he commencement of each shift then twice more during the shift.
A surface contamination check is typically performed at the commencement
f each shift and twice more during the shift.
o check contamination clear cellotape strips are used and compared
gainst a contamination table. The results of both the surface profile and
ontamination checks are recorded on an agreed Surface Blast Cleaning
nspection Report. Both the Testex film and the dust contamination films
re normally attached to the report.
he blasted surface shall meet or exceed the requirement of the blast
rade as specified by comparing the blasted surface to a pictorial standard
.g. ISO 8501-1. The blast standard shall be monitored and recorded every
hours.
he elapsed time shall between surface preparation and the
ommencement of coating shall be monitored, the maximum elapsed time
hall be 4 hours, no rust blooming shall be apparent prior to the application
f the coating.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 6/89
Responsibilities:
he Blast Line Supervisor shall ensure that all repairs grinding and filing is
arried out under controlled conditions. If unsure about the disposition of
ipe defects, the QA department should be contacted to assist with any
ueries. The supervisor should also ensure that the pipe has been cleaned
f residue blasting matter both internally and externally. He shall also beesponsible in ensuring that the task is conducted in the safest possible
manner.
he QC Inspector/Auditor shall be responsible for recording disposition of
ipe exhibiting defects and raising NCR report. He shall also perform
eriodic testing in accordance with the agreed project ITP.
he Tally Man shall maintain pipe traceability and ensure that correct
ecords of defective pipe, movement and disposition.
.4 Surface Conditioning
is often a requirement that after abrasive blasting the pipe surfaceshould receive a surface conditioning (chemical treatment), particularly for tandalone FBE coatings.A typical chemical treatment is a Phosphoric Acidreatment: below you will find a typical application procedure.
Note: Any chemical treatments must be applied strictly in accordance with
he chemical supplier’s recommendations.
Phosphoric acid is applied immediately on completion of the blast cleaning;he acid is typically applied using an acid concentration of 10% ± 3% (byolume). The concentration is normally measured and recorded using atration method.
deally the pipes shall be uniformly heated to between 40 and 70 C. Theeating is usually provided a residual heat from the blasting line preheatingystem.
he Phosphoric Acid solution has to be applied in a uniform manner:ormally gravity fed from above the pipe and spread on the pipe surfacesing a brush arrangement. The acid has to remain on the pipe surface for period of time (Dwell time) that allows the reaction process to take place.
is critical that the dwell time is strictly adhered to and is related to the pipeemperature at the time of application. The acid manufacturer normallyrovides a dwell time table for this purpose.
ypical dwell time chart:
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 7/89
8 C - 37 sec’s3 C - 27 sec’s9 C - 25 sec’s4 C - 21 sec’s0 C - 17 sec’s
Note: It is essential that the pipe surfaces remain wet at all times during thePhosphoric Acid treatment.
After the dwell time has elapsed, the pipe surface shall be thoroughlynsed with deionized water having a conductivity of 10µmhos/cm max.
he pressure of the water used shall be sufficient to thoroughly remove allcid residues. The minimum specified pH of the wet surface after rinsinghall be determined by directly touching the pipe surface with a pH paper.he pH paper shall have measurement units of 0.5 pH or less.
On completion of the surface conditioning the appearance of the steelubstrate should be similar to that of the freshly blasted surface (apart fromlight water streaking).
Note: Normally A maximum of four (4) is permitted between the acid prereatment an the coating application
.5 Preheat FBE:
Prior to FBE coating the previously installed end plugs should be removed
nd the internal bore of the pipes checked for contamination. The pipes are
hen preheated prior to the application of the Fusion Bonded Epoxy powder
y passing through an Induction coil heating system.
Induction Heating Coils
he preheat temperatures are controlled so that the pipe is within the
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 8/89
orrect manufacturers recommended temperature range when the epoxy
owder is applied. The pipe temperature is continuously monitored
mmediately prior to the powder application booth by using a calibrated
urface temperature probe, infrared sensor or "Tempil" sticks. The latter
owever, may not be a permissible method due to oily residues left on the
ipe surface.
Infra Red Thermometer
Infra Red Temperature Read Out
Tempil Stick
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 9/89
Responsibilities:
he Blast Line Supervisor should ensure that the induction heating
quipment is maintained in satisfactory operating condition and that the
ettings are commensurate to the required heating range for the particular
ipe size and wall thickness being heated. He should also ensure that the
onveyor line speed is constantly maintained to allow even pipe preheatnd coating to be achieved. He should also be responsible in ensuring that
he task is conducted in the safest possible manner.
he QC Inspector is responsible for monitoring preheat temperatures at the
pecified periodic intervals.
he Tally Man should ensure that pipe traceability and correct records of ipe movement and disposition.
Coating Parameters:
is always advisable that the production line operating parameters be
ecorded for internal analysis on an internal coating operations parameter
eport..
.6 FUSION BONDED EPOXY POWDER INSPECTION
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 10/89
Each container of epoxy powder is inspected prior to loading into the
owder delivery systems. (Where dual coat powders are used, the
eparate powders are loaded into the appropriate delivery systems, i.e.
rimer in one system and the top coat in the other. The powders shall not
e mixed or interchanged).
Note: With FBE powder it is advisable to check production material for moisture content and gel time on at least a daily basis. A high moisture
ontent can cause porosity and cure problems with the coating.
he inspection should also confirm that the epoxy powder is listed on the
Approved IRF". Only powder with current, valid approval shall be used.
Batch numbers shall be recorded on all the relevant inspection and
aboratory test reports. Once the approved status of the epoxy powders are
onfirmed, the powders are loaded into the delivery systems.
Reclaim:
Subject to client approval the amount of reclaim powder applied in any
iven interval shall not exceed 20 % of the total powder application. (When
sing dual coat the reclaim powders shall be controlled separately and
lended with the top coat virgin powder. Reclaim shall not be blended with
he primer powder).
FBE Reclaim
.7 Coating Application
he Fusion Bond Epoxy Powder is applied to the heated pipe using a
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 11/89
eries of electrostatic spray guns. (When using a dual coat system using a
ingle fluid bed, the primer and top coat guns should be set apart in a
manner that allows the correct amount of separation of the two FBE layers.
Alternatively two separate fluid beds may be used).
By balancing the conveyor line speed and the settings of the electrostatics
nd guns, flow rate and pressure of the material feed the material
pplication is controlled to achieve the correct applied coating thickness.he coating should be continuous over the entire length (coating area) of
ach pipe joint. The minimum/maximum thickness shall be as indicated in
he agreed Inspection Project ITP.
FBE Application
On completion of coating and allowing sufficient flow out and set up time of
he powder, the coated pipes continue on through a water quenching
tation where the coating is cooled down using a continuously application
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 12/89
f water. The pipes are cooled until the pipe is safe to be handled.
Typical FBE Quenching
Caution: The pipe coating should not be quenched to early or the FBE
ure may be compromised.
Note; If and when required, a friction coating shall be sintered (Sinter coat)
nto the FBE surfaces immediately after the FBE application process.
Responsibility:
he Coating Line Supervisor is responsible for maintaining the correct pipereheat temperatures for the line speed being used and ensuring that the
ne speed is at an even rate. Information required to perform this function
s obtained from the coating line controller. He is also responsible in
nsuring that the task is conducted in the safest possible manner.
he QC Inspector/Auditor is responsible for monitoring of all the coating
arameters.
he Powder Booth Operator is responsible for maintaining the application,un settings, flow rates of materials, feed line pressures for the particular
ne speed and pipe diameter and the electrostatics.
he Coating Line Controller is responsible for all line activities for material
oating line. This includes maintaining the correct line speed and pipe
reheat by monitoring inspection reports, control room instrumentation and
hat all the powder coating parameters are maintained.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 13/89
.8 COOLING BOARDS & INSPECTION
mmediately after cooling the coated pipe is transferred to the outgoing
padded" pipe rack where the coating is visually inspected for any
etrimental coating defects the pipes are then positioned on end cleaning
otators where the cutbacks are correctly established.
After end cleaning the entire coated surface of each length of pipe shall be
nspected for holidays using a high voltage (pulse type) holiday detector
hat has been previously set and calibrated to the correct test voltage. The
ircumferential search electrode shall maintain intimate contact around the
ntire circumference of the coated pipe at all times. The voltage shall be
hecked and recorded hourly.
he travel speed for holiday detection is a rate of 300 mm per second
maximum. Any holidays or surface defects are clearly marked on the pipe
nd details recorded on an agreed Coating Application Report.
Random adhesion testing are carried out using the St. Andrews cross
method where coating is inscribed through to the metal substrate using a
Stanley knife the coating is prized off to check the coating adherence to the
ubstrate,
St Andrews Cross
he system coating thickness is typically determined by taking the 4
quidistant measurements, 3 on the body and 1 on the weld (if applicable)
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 14/89
ocations at the lead end middle and tail end of each pipe ( a total of 12
measurements). The measurement shall be conducted using an
lectromagnetic thickness gauge. Records of the thicknesses shall be
ecorded on an agreed Coating Application Report.
Thickness Check
Responsibility
he Cooling Board Supervisor is responsible for ensuring that the holiday
etection of each pipe is carried out in a correct manner and at the correct
oltage. Also he should ensure that the pipe cutbacks are correctly
stablished and that the pipe ends and pipe internals are sufficiently
leaned. He should also be responsible in ensuring that the task is
onducted in the safest possible manner.
he QC Inspector/Auditor should be responsible for visual inspection of the
oating and physical testing, monitor the holiday detection and cut back
ength, calibration of the holiday detection equipment prior to the start of
ach shift. He shall also ensure that coating thickness checks are being
arried out and being recorded correctly for each pipe
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 15/89
Note: In some coating facilities an "in line" holiday detector is used.
he Load Out Tally man is responsible for checking the pipe identity and
maintaining pipe traceability on the computerized pipe tracking system
where used).
.9 PIPE MARKING AND IDENTIFICATION:
he identity markings of each pipe shall be established and the details
ntered into the pipe tracking system such that traceability is maintained
fter which the accepted pipes are released for transportation to the
tockpiles or other processes.
Responsibility
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 16/89
he Load Out Tally Man shall ensure that the correct pipe markings are
pplied in accordance with the agreed marking system. He shall also be
esponsible in ensuring that the task is conducted in the safest possible
manner.
.10 Repairs:
Repairs to the coatings are carried out in accordance with an agreed
Repair Procedure. Coated pipes that cannot be repaired are rejected,
tripped and re coated. Unacceptable pipe are marked up with Red/White
azard tape and recorded on the NCR system.
he maximum allowable holidays that may be repaired are to be agreed
nd should form part of the project ITP. Typically the allowable numbers of
oliday repairs allowed is 1 per metre of pipe length.
Note: In the event that ongoing extensive numbers of holidays are
pparent the coating line should be shut down and the cause of the
roblem investigated.
A typical FBE repair procedure:
Pin hole holidays should be repaired with a melt stick.
he coating surface must be abraded and clean. To ensure good adhesion,
oughen area-using sandpaper and wipe to remove all dust.
Care must be taken when using hot melt sticks as preheat of the FBE
oating surface is required. Heat should be applied to the repair area in a
manner that avoids burning or charring of the epoxy coating. Slight
rowning of the parent coating is acceptable, but charring or blistering is
ot. The use of a noncontaminating heat source, such as portable hand
eld butane torch is required.
Holding the melt stick on or near the repair area continue to heat theleaned area until the coating surface is at the desired temperature at
which point the patch stick begins to melt. The heat source maintains the
emperature of the coating and melts the stick. While continuing to expose
he melt stick to the heat source, apply the patch material by rubbing the
tick in a circular motion on the area to be repaired until the a thickness of
he repair is at least 15 mils (380 microns) greater than the parent coating
hickness. Allow the repair to cool before handling.
arger repairs should be made using a 2 part liquid epoxy patching
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 17/89
ompound.
arger defect repairs.
he defective area should be cleaned and abraded by using abrasive
aper. The exposed steel surface should be power brushed to give a
urface cleanliness equal to St 3 . All surface dust should be removed and
he surface wiped with solvent saturated lint free cloth and the solventllowed evaporate.
Using a 2-part epoxy repair material the two constituent parts should be
horoughly hand mixed in the correct proportions according to the
manufacturers’ written instructions.The material shall be carefully applied to
he abraded area of the steel and FBE. Finally, the surface of the repair
hould be allowed to cure. For neatness and containment of the repair area
masking tape border can be applied around the repair area that is
emoved prior to the repair compound curing
he repaired area should be visually inspected to ensure no voids and/or
ir entrapment.and shall be holiday detected using a portable holiday
etector.
All repairs should be recorded on an agreed repair Quality form
Responsibility
he Repair Foreman is responsible for coating repairs and should ensure
he correct equipment and repair method is used for coating repair. He
hould also be responsible in ensuring that the task is conducted in the
afest possible manner.
he QC Inspector/Auditor is responsible for checking the preparation and
he completed repairs.
.11 OFFLINE TESTING
Besides online testing and inspection requirements there are a series of
Off Line” tests that have to carried out to confirm compliance of the coating
ystem against the specified requirements which include the following
ractices:
Back Side Contamination Checks
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 18/89
Coating Thickness Measurement
Differential Scanning Calorimeter
Gel Time Determination
Holiday Detection
hickness Measurement
Porosity both Inter facial and Cross Sectional
lexibility (Bend) Test
Pull Off Adhesion TestCathodic Disbondment Test
Hot Water Resistance Test
mpact Resistance
Determination of Coating Hardness
----------------------------------------------------------------------------------------
-----------------
Back Side Contamination - CAN/CSA Z245.20-2
Scope
o determine the extent of backside contamination at the bottom side of an
BE coating chip sample.
Equipment
Sample freezer
Bending machine
0 X microscope
Procedure
A sample section of coated pipe shall be removed from a test ring. Theample section shall be approximately 200 x 50 mm
he sample cut out shall then be placed into a freezer and cooled down to
ear freezing point. After freezing the sample shall be removed from the
reezer and rapidly bent around a suitably sized mandrel causing the FBE
o flake off of the substrate.
Evaluation
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 19/89
Pry off the flake sample, The then examine the sample using a 40 X
microscope and the percentage of contamination is rated
Acceptance cr iteria: The backside contamination shall be within the
pecified tolerance. Typically 30 % max.
Report
Record
Date
ime
Pipe number
Batch number
Backside Contamination expressed in %
Backside Contamination
----------------------------------------------------------------------------------------
----------------
COATING THICKNESS MEASUREMENT BS 3900 Part C5 1992
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 20/89
Scope
Determine the coating thicknesses of anti corrosion coatings.
Equipment
Calibrated electronic Thickness Gauge
Procedure
he pipe should be suitably cooled immediately after anti corrosion coating
efore measuring the coating thickness.
he coating thickness of the coated pipe is checked by using a calibratedlectronic thickness gauge. The checking position of the inspection probe
hould be in vertical position and at right angles to the coating being
hecked. The coating thickness is measured at the specified locations
long the body of the pipe and on the weld seam where applicable.
Calibration of the measuring instrument
Switch on thickness gauge
Select "CAL" button
Place the probe on top of a certified standard thickness shim which has
een placed on a blast cleaned bare steel area and read the measurement.
Adjust the up or down button to give the actual reading according the
oating thickness standard or certified shim.
Press the "CAL" button again for confirmation calibration.
Report
Record
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 21/89
Date of coating
Pipe number
hickness gauge reading
Report the individual coating thicknesses on both body and weld seam.
Report the minimum average thickness of the coating.
Record instrument calibration details
----------------------------------------------------------------------------------------
--------------------------------------
DIFFERENTIAL SCANNING CALORIMETER - CAN/CSA Z245.20-2
Note: This practice may be modified by the requirements of the customer’s
pecification,see relevant Project Inspection Test Plan (ITP)
Scope
his test is to determine the glass transition temperature (Tg) and the
mount of exothermic heat of reaction (DH) of epoxy powder or fusion-
onded epoxy cured coating.
Equipment
Differential scanning calorimeter (DSC) and accessories
Analytical balance accurate to 0.1mg
Knife or file
Procedure
Obtain a 10+/-1-mg sample of epoxy powder or coating aspplicable. Place the sample in a pre-weighed aluminum pan and put lid in
lace. Crimp the lid into place with the encapsulating press and obtain the
ample weight by subtracting pan and lid weight from the total weight.
Place a small vent hole (pierce) in the lid without damaging the pan.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 22/89
Place sample and reference (as suggested by the instrument supplier) in
he DSC furnace.
Use nitrogen gas to purge the cell.
or epoxy powder sample, obtain thermal scans for the following cycles in
rder:
a) heat the sample from 25 ± 5ºC to 70 ± 5ºC at a rate of 20ºC/min,
hen immediately cool the sample to 25
5ºC
b) heat the sample from 25 ± 5ºC to 285 ± 10ºC at a rate of 20ºC/min, then
mmediately cool the sample to
5 ± 5ºC; and
c) heat the sample from 25 ± 5ºC to 150 ± 10ºC at a rate of 20ºC/min. For
oating samples, obtain thermal
cans for the following cycles in order:
d) heat the sample from 25 ± 5ºC to 110 ± 5ºC at a rate of 20ºC/min, hold
t 110 ± 5ºC for 1.5 min, then
mmediately cool the sample to 25 ± 5ºC;
e) heat the sample from 25 ± 5ºC to 285 ± 10ºC at a rate of 20ºC/min, then
mmediately cool the sample to
5 ± 5ºC; and
f) heat the sample from 25 ± 5ºC to 150 ± 10ºC at a rate of 20ºC/min.
Evaluation
he Tg is taken as the point of intersection of the extrapolated baseline of
he low temperature end and the tangents to the curve at the inflection
oint (onset) Calculate the residual exothermic heat of reaction (DH)
ollowing the instructions provided by the manufacturer of the DSC
quipment.DTg = Tg4 – Tg3
Report
Record
Date
Date of coating
Product code for epoxy powder only
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 23/89
Batch number, and date tested.
Pipe number where applicable,
Report Tg1, Tg2 and DH, for epoxy powder
Report Tg3, Tg4, DTg and DH, for coating, including units
ndicate the type of differential scanning calorimeter.
DSC Sample Preparation
DSC Machine
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 24/89
----------------------------------------------------------------------------------------
----------------
GEL TIME DETERMINATION - CAN/CSA Z245.20.02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
o determine the gel time of fusion bonded epoxy powder coating material.
Equipment
Hot plate (accurate to ± 3° C)
Stopwatch or electronic timer
Spatula
Stiff wire
Procedure
Gel time shall be determined by placing approximately 1g of coating
material in a hot plate stabilized at 205±3°C. In a smooth motion, deposit
nd draw the epoxy powder across the metal plate while holding the tool at
n angle of approximately 45° to the metal plate. This motion will create a
ongue of epoxy powder approximately 25mm wide. The target thickness of
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 25/89
he cured film is 300 – 400µm. Start the time as soon as the coating
material becomes molten. Stir the coating with a stiff wire or spatula, and
top the watch when the coating becomes resistant to stirring and
elatinous.
Evaluation
he elapsed time to reach this condition is the gel time.
Report
Record
Date
Product
Batch number
Gel time in seconds.
Testing Gel Time
----------------------------------------------------------------------------------------
----------------
MOISTURE CONTENT - CAN/CSA Z245.20.02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 26/89
Determine the moisture content of FBE powder using the mass loss
method
Equipment
Oven controllable within 3°CBalance accurate to 0.001g
Desiccators; and
Sample container
Procedure
Weigh the sample container to the nearest 0.001g. Transfer approximately
0 g of epoxy powder into the sample container. Weigh the sample
ontainer and epoxy powder to the nearest 0.001g. Place the sample
ontainer with the epoxy powder into the oven for a maximum of two hours
t 105 ± 3°C. Remove the container from the oven and place in the
esiccators to cool. Weigh the sample container when it has cooled to
0 ± 3°C
Evaluation
Calculate the percentage of moisture using the following formula:
M = (B-C)/(B-A) x 100
Where
M = percentage of moisture
B = initial mass of sample container and epoxy powder, g
C = final mass of sample container and epoxy powder, g
A = mass of sample container, g
Acceptance criteria, Typically 0.5 % max
Report
Record
Date
Material Code
Batch number
Moisture expressed in %
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 27/89
Moisture Content
----------------------------------------------------------------------------------------
----------------
POROSITY INTERFACE & CROSS SECTIONAL - CAN/CSA Z245.20.02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
) To determine the extent of inter facial porosity at the bottom side of an
BE coating.
B) To determine the extent of cross sectional porosity within an FBE
oating
Equipment
Sample freezer or dry ice & container
Bending machine
0-40 X microscope
Mandrel
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 28/89
Procedure
A sample specimen of coated pipe shall be removed from a test ring. The
ample section shall be approximately 300 x 50 mm. The sample cut out
hall then be placed into a freezer or dry ice and cooled down to near or
elow freezing point. After freezing the sample shall be removed from the
reezer or dry ice and rapidly bent around a suitably sized mandrel causing
he FBE to flake from the substrate. Pry off the flake sample of FBE coatingo allow observation of both the cross section and underside of the coating
ample to be examined.
Evaluation
he sample shall then be viewed both in inter facial and cross sectional
levations using a 40 X microscope and assessed for porosity.
Acceptance cri ter ia, Typically rating 3 max.
Report
Record
Date
Pipe number
nterface Rating 1-5
Cross sectional rating 1-5
Ratings Chart
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 29/89
----------------------------------------------------------------------------------------
----------------
LEXIBILITY (BEND) TEST - NACE RP 0394-94 CAN/CSA Z 245.20-02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
his test is to determine the flexibility of coating for field bending.
Equipment
Hydraulic Press
Bending mandrels of fixed radii
Microscope
reezer
Procedure
Specimens shall be removed from test rings (approx. 300mm long x 50mm
wide x pipe wall thickness, with the 300mm dimension parallel to the axis of
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 30/89
he pipe.
Ensure that the specimen edges have all stress raisers removed and that
ubstrate is exposed along the edges. Test temperatures shall be 0ºC and
3ºC +/-2ºC. Typical, Calculate the required mandrel radius (R) using the
ollowing formula:
R= ((57.3)(t)/s))– t/2
Where:
R = mandrel radius, t= effective strap thickness, and
s = strain (deflection) in degrees per pipe diameter (°/PD).
Determine the effective strap thickness (t), which includes the specimen
hickness and any curvature, by placing the specimen on a flat surface and
measuring the thickness as shown in Figure K1 of NACE RP0394-94
Standard. Where a mandrel of the calculated radius is not available; the
mandrel of the next smaller radius shall be used.
Bend the test specimens over the radius so that the uncoated side is in
ontact with the mandrel, completing the bend within 30 seconds. The
end test shall take a minimum of 10 seconds for completion.
Measure the residual bend radius by matching the outer curve of the test
pecimen to the nearest arc from Figures K2, K3, K4 or K5 of NACE
RP0394-94 Standard.
Evaluation
Visually inspect the specimens for cracks, tears in the coating, and
isbonding of the coating after the specimen has warmed to room
emperature. The presence of any such defect within 2.5mm of the strap
dge does not constitute failure. The presence of strain marks alone does
ot constitute failure.
Acceptance cri ter ia, Typically equal to 2° PD (No cracking)
Report
Record
Date
Date tested
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 31/89
Manufacturer code
Batch number
Pipe number
est Temperature
Defect {s} if any Specimen effective strap thickness, permanent (residual)
train radius, angle of deflection in degrees per pipe diameter for passing
end test.
Bend Test
----------------------------------------------------------------------------------------
----------------
PULL OFF ADHESION TEST
Note: This practice may be modified by the requirements of the customer’specification,see relevant Project Inspection Test Plan (ITP)
Scope
o determine either the greatest perpendicular force (intension) that a
urface area can be bear before a plug of material is detached or whether
he surface remains intact at a prescribed force (pass/fail)
Equipment
Hydraulic Adhesion Tester 108
Dolly/Loading Fixture
Adhesive
Procedure
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 32/89
he selected test area must be a flat surface to accommodate the specified
umbers of replicate tests. (Test panel : 300 mm x 450 mm)
oading fixture shall be detach with test panel using adhesive and hold for
day. After 1 day. Insert a decreased FE-fluorocarbon plug into the dolly
ntil the tip protrudes from the surface of the dolly. When applying adhesiveo the dolly, avoid getting adhesive on the plug. Remove plug after holding
he dolly in place for 10 s. Ensure that the black needle of the tester is
eading zero. Connect a test dolly to the head and increase the pressure by
urning the handle clockwise until the pin protrudes from the dolly.
Decrease pressure to zero and remove the test dolly. Connect the head to
he dolly to be tested, by pulling back the snap on ring, pushing the head
nd releasing the snap-on ring. Ensure the tester is held normal to the
urface to be tested and that the hose is straight. Increase the pressure
lowly by turning the handle clockwise until either the maximum stress or
ailure is reached.
Evaluation
Record the force attained at failure or the maximum force applied.
Report
Record
Date
ype and date coating
Sample ID
Maximum Pressure and thickness coating
Batch Number
Pull Off Adhesion Test
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 33/89
----------------------------------------------------------------------------------------
----------------
CATHODIC DISBONDMENT - CAN/CSA Z245.20-02 & CAN/CSA
245.21-02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
o assess the comparative resistance of damaged coatings to loss of be
erformed on a test specimen taken from a pipe or pup piece previously
ubjected to holiday detection, and in which an artificial defect of a defined
ize has been drilled.
Equipment
Stabilized DC Power supply unit with controlled voltage output.
A Cathodic polarization potential of –1.500mV to a saturated
alomel reference electrode (equivalent to UH = -1.260mV, where UH
means the potential of the standard hydrogen electrode shall be
maintained). “E” potential of the “working electrode” with regards to the
reference electrode”. “V” difference of potential between the “working
lectrode” and the “counter electrode”.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 34/89
Electrolyte cell consisting of rigid plastic tube or PVC of with an internal
iameter of 75 ± 3 mm. The height shall be 120 mm.
A rigid plastic cover in which 3 holes shall be drilled to allow the passage of
he electrodes and any other measuring instruments deemed necessary,
nd to allow the escape of hydrogen.
Reference electrodes- the saturated calomel reference electrode or uitable type of reference electrode to give an equivalent potential shall be
laced in an electrode holder situated in a glass tube with a porous end
lug. The end of this assembly shall be placed approx. 10mm from the
urface of the coating and approximately 20mm from the coating defect.
Counter electrode or platinum wire.
Working electrode (cathode)- is represented by the artificial defect, which
hall be 3.2 mm in diameter for FBE & 6.4 mm in diameter for 3 Layer,
which shall penetrate through the coating to expose steel substrate.
Calomel reference electrode
Utility knife
est Specimen
est- Ring Specimen
he test plate specimen shall be a 100mm x 100 mm (square) segment cut
rom the representative test ring.
Procedure
Drill a 3.2 mm (FBE) or 6.4 mm (3 Layer) diameter holiday through the
oating at the center of the specimen.
Glue a plastic cylinder onto the specimen using a sealant to form a water esistant seal. Ensuring the pre drilled holiday is at the center of the
ylinder.
Pour approximately 300ml of Sodium Chloride Solution into the
lastic cylinder.
When testing specimens cut from the pipe, a heat- transfer medium shall
e employed to provide uniform heating of the specimen.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 35/89
Use a metal pan/tray partially filled with a heat transfer medium (sand) into
which the specimen is implanted. Place on a hot plate or in an oven to
maintain the test temperature as required according to the duration of tests
pecified in the specification.
Connect the negative lead (working electrode) from the power supply to the
pecimen ( Cathode) and the positive lead (Counter electrode) to thenode after the test temperature is reached.
urn on the power supplies and applies voltage to the test specimen:
egative 1.5V or 3.5V with respect to the calomel reference electrode for
he 24 hr, 48-hr (only on accelerated production test) and/or 28-day tests.
Monitor the voltage, temperature and electrolyte level at the start and at
very 24-hr interval thereafter.
or the 28-day test, the electrolyte level need not be monitored on
weekends provided a cover plate is loosely fitted over the test cell. Distilled
water shall be added as required to maintain the electrolyte level.
Evaluation
After 24hrs or 48 hrs (on accelerated production test), dismantle the test
ell and remove the test sample cell from the hot plate or oven.
mmediately drain the electrolyte and air-cool the sample to 20 ± 3° C. The
valuation shall be performed within one hour of removal from the hot plate.
or 28 day test, remove the 28-day test cell using the same procedure.
Using a utility knife, make radial cuts from the edge of the holiday outward
hrough the coating to the substrate. The radial cuts shall be at least 20mm
n length from the centre of the holiday.
nsert the blade of the utility knife under the coating. Using a levering
ction, chip off the coating. Continue until the coating demonstrates aefinite resistance to the levering action.
Measure the radius of the disbonded distance from the holiday edge along
ach radial cut and average the measured results. Maximum allowed CD
adius as measured, is detailed in the controlled ITP drawn for this project.
Acceptance criteria:- Typically 3-4 mm radial disbondment for FBE
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 36/89
Report
Record
Date tested.
Pipe number Coating date.
CD Equipment set up
Cathodic Disbondment sample
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 37/89
----------------------------------------------------------------------------------------
-------------
HOT WATER RESISTANCE - CAN/CSA Z245.20.02
Note: This practice may be modified by the requirements of the customer’s
pecification,see relevant Project Inspection Test Plan (ITP)
Scope
Determine the hot water resistance (Adhesion) of FBE coating.
Equipment
emperature controlled water bath
ap water
hermometer
Utility Knife
Procedure
A coated sample of approximately 100 mm x 100 mm removed from a pipeest ring be fully immersed in a tap water filled bath, previously warmed to
he required test temperature of 75°± 3°C. The sample shall remain in the
ath for a minimum period of 24 hrs and the test temperature of the water
hall be controlled throughout the duration of the test.
After 24 hours the test sample shall be removed from the water bath and
whilst still warm, a rectangle 30 x 15 mm shall be incised in the coating
hrough to the steel substrate. The sample shall be air cooled to the
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 38/89
est temperature of 20 ± 3°C
At the correct test temperature insert the tip of a utility knife under the
oating at one of the corners of the incised rectangle. Used a continuing,
evering action in an attempt to remove the coating. Continue the levering
ction until either all the coating is removed from the rectangle or the
oating demonstrates a resistance to the levering action.
On completion of the test, record the rate of adhesion as follows:
Rating 1 Coating cannot be removed cleanly
Rating 2 Less than 50 % of the coating can be removed
Rating 3 More than 50 % can be removed, but the coating demonstrates a
efinite resistance to
the levering action.
Rating 4 The coating can be easily removed in strips or chips
Rating 5 The coating can be completely removed as a single piece.
Acceptance cr iteria, Typically rating 3 however sometimes rating 2 is
equired.
Report
Record
Date
Batch number
Rating 1-5
----------------------------------------------------------------------------------------
------------------------------------
MPACT RESISTANCE - DIN 30670, DIN 30678 & CAN/CSA Z 245.20-02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 39/89
Scope
Equipment
mpact Tester having)
alling masses 1-kg FBE, 3.5-kg 3LPE, 6-kg 3 LPP
5.8mm (FBE) or 25 mm (3 Layer) diameter ball bearing tup piece (tup
shall have a
Hardness of 50 to 55 HRC)
meter long graduated slotted tube
A wood block measuring approx. 610mm on each side and have a topacing of
Hardwood (for laboratory controlled test procedure).
DC holiday detector
est Specimens
Laboratory test) Shall be approximately 25mm x 200mm x pipe W.T., with
he 200mm dimension parallel to the axis of the pipe.(Field test) Test pipe.
Procedure
he impact test shall be carried at room temperature with the relevant
weight housed within a 1-meter graduated slotted tube. The ball bearing
hall be rotated every 10 impacts to a new location and replaced after 200
mpacts. The distance between each impact shall be 30 mm minimum.
Evaluation
Each pipe shall receive 10 impacts, each impact indentation on the test
pecimen shall be checked for substrate exposure using a holiday detector
et at 5V/micron (FBE) or 7900volts per mm (3 Layer).
Acceptance cr iteria, Typically the impact energy shall be 15 joules (For
BE)
o determine the impact resistance of coating (this practice can be adopted
n both FBE & Three Layer coating systems). The test can be carried out
oth, in a controlled laboratory environment and as a field test (directly on
est pipe surface).
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 40/89
Report
Record
Date
Batch number
Pipe number Coating date.
he applied impact energy (joules)
Holiday detection voltage setting
Impact Resistance
----------------------------------------------------------------------------------------
--------------
DETERMINATION OF HARDNESS - ASTM D 2240
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
est to measures the coating hardness using a Shore D hardness gauge.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 41/89
Specimen
Applied coating or a free film sample usually 3mm or more in thickness.
he surface of the specimen shall be flat and parallel over a sufficient area
o permit the presser foot of the gauge to suitably contact the test area.
Equipment
Shore D Hardness gauge.
Procedure
a free film specimen is used, the specimen shall be placed on a hard, flat
orizontal surface. The Shore D Hardness gauge shall be held in a vertical
osition with the point of indenter at least 12mm from any edge of the
pecimen. Apply the presser foot to the specimen as rapidly as possible,
without shock, keeping the foot parallel to the surface of the specimen.
Apply just sufficient pressure to obtain firm contact between presser foot
nd specimen.
Evaluation
When the presser foot is in firm contact with specimen, the scale reading is
o be recorded within 5 seconds’
Note: The hardness reading may progressively decrease with any time
elay.
Acceptance cri ter ia, Typically Shore 60
Report
Record
Date
Manufacturer code
Batch number
Coating date .
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 42/89
Pipe Number or sample ID if applicable, shall be recorded
Record hardness value obtained.
ype and Serial Number meter
Shore D Hardness Test
.0 POLYETHYLENE & POLYPROPYLENE COATINGS
Polyethylene and Polypropylene coatings are commonly used as an outer
ayer for multi layer coating systems. Due to the nature of these materialshey are suitable for giving coated pipe added mechanical protection.
Polyethylene and Polypropylene coatings are usually applied over an FBE
rimer and have a bonding material (Polymer Adhesive) between the
rimer and outer layer. (Three Layer System).
ypically Polyethylene is used for moderate temperature conditions and
Polypropylene for higher temperature applications. Polymer coating are
ormally applied using a side extrusion method however, the cross headxtrusion method can also be used for pipe diameters up to 26". In this
module i will be describing the side extrusion method of coating.
Typical PE Coating
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 43/89
Typical PP Coating
Prior to the commencement of three layer coating all incoming materials
re checked against the material manufacturer’s certification and any other
pecification requirements. The Incoming receipt form (IRF) should
tipulate the incoming material testing requirements that are to be verified
rior to using the material.
ncoming test are typically Gel Time, Cure Time, Thermal Analysis and
Moisture Content for the FBE and Melt Flow Index MFI and moisture
ontent for the Polymers."See off line tests section 4.5 below"
.1 INCOMING PIPE
Pipes received at the incoming racks are checked for contamination or pipe
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 44/89
efects that prevents acceptable coating and cannot be rectified at the
ncoming rack or grinding area. Any held pipes shall be removed from the
rocess and clearly marked (HOLD or REJECT) and placed into an
ppropriate holding area for adjudication by the client representative as to
s disposition.
he criteria for steel defects shall be generally in accordance with API (Theractical detail to be agreed by both parties).
See steel defects "Module 2"
Responsibilities:
he incoming rack supervisor should ensure that pipe is handle in a
manner that prevents pipe damage during the load in to the coating facility,
e should also supervise any rectification work required. The supervisor is
esponsible in ensuring that tasks are conducted in the safest possible
manner.
he incoming Inspector shall be responsible for the release or quarantining
f the incoming bare pipe
he incoming Tally man shall be responsible for the recording and
raceability of all the incoming bare pipes.
.2 COATING PROCESS
Preheat & Blast Cleaning
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 45/89
Pipes are be placed onto the incoming blast line rack where bevel
rotectors (if fitted) are removed and end plugs fitted to the pipe internals
o prevent the ingress of blasting media. The pipes are then indexed and
owered onto a blast line conveyor and conveyed through a pre-heat oven
Usually gas) set to allow for the required preheat temperature to be
chieved. The pipe surface temperature shall be monitored prior to blast
leaning using a hand held surface contact pyrometer, optical thermometer
r melt sticks.
he preheat temperature shall be checked as a minimum each hour and
he temperatures recorded. The steel surface temperatures for blast
leaning shall be above the required local dew point requirement, the dew-
oint (typically 3 C above local dew point) should be checked twice per shiftnd recorded on an agreed Climatic Conditions Report.
After preheating he pipes are then progressed through the first of two
entrifugal abrasive cleaning machine; the blast machine operator shall
ontinually monitor the blast effectiveness via visual inspection.
Abrasive samples (100 ml) shall be taken from the working mix(s) once per
hift: the sample shall be passed through 1.18 mm & 0.425-mm meshieves. No more than 16% should pass the 0.425-mm sieve. In the event
hat the amount of fines exceed this figure, fresh grit shall be added to the
working mix. Each abrasive sample shall be tested for chlorides and other
ontaminants. The results of the analysis shall be recorded on an agreed
Abrasive Contamination Test Report
See Module 2
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 46/89
Responsibilities
he Abrasive Line Supervisor shall be responsible for ensuring that the end
lugs are positioned correctly and that the specified preheat temperature is
onstantly maintained. He shall also ensure that the conveyor line speed is
onstant and that the surface amplitude and pipe cleanliness is maintained
within the specified tolerances. He shall also be responsible in ensuringhat the task is conducted in the safest possible manner.
he QC Inspector/Auditor is responsible for verifying that end plugs have
een positioned correctly and that the specified preheat temperature is
maintained. He shall also perform climatic conditions testing at the
pecified intervals and review laboratory testing of abrasive materials.
see Module 2)
he Laboratory Technician shall be responsible for taking samples of the
brasive and analysing.
.3 Grinding Area:
On completion of the first abrasive blasting operation the pipes shall be
ndexed onto the transfer holding rack (grinding area) and inspected. All
ipes are to be checked for any steel imperfections i.e. sliver, scabs,
amination's, burrs dents or bristles. Defects shall be repaired by grinding or
y hand filing.
Pipes that cannot be repaired and fail to meet the specified requirements
hall be clearly marked (HOLD or REJECT), removed from the process and
laced on a reject rack for adjudication by the client as to its disposition.
Details of pipe defects shall be recorded on an agreed Grinding Area
nspection Report.
A salt contamination check of the blasted pipe surface is checked using an
SCM 400 salt contamination instrument and the results recorded. Typically
he first pipe then further two pipes per shift are checked, the results are
ecorded on an agreed Salt Contamination Test Report.
See Module 2
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 47/89
On completion of surface defect and salt contamination checks, the pipes
re lowered onto the second centrifugal abrasive cleaning line where the
ipes receive a second blasting process.
After the second blasting operation the blasted surfaces are checked for
urface profile (using Testex Press-O-Film) replicating tape or other agreed
methods and the profile recorded. Typically pipes are checked at
he commencement of each shift then twice more during the shift.A surface contamination check is typically performed at the commencement
f each shift and twice more during the shift. To check contamination
lear cellotape strips are used and compared against a contamination
able.
See Module 2
he results of both the surface profile and contamination checks are
ecorded on an agreed Surface Blast Cleaning Inspection Report. Both the
estex film and the dust contamination films are normally attached to the
eport.
he blasted surface shall meet or exceed the requirement of the blast
rade as specified by comparing the blasted surface to a pictorial standard
.g. ISO 8501-1. The blast standard shall typically be a minimum Sa, 2.5
nd be monitored continuously and recorded every 4 hours.
he elapsed time between surface preparation and the commencement of
oating should also be monitored, the maximum elapsed time should be a
maximum of 4 hours, or before any rust blooming apparent.
Responsibilities
he Blast Line Supervisor is responsible for ensuring that all repairs,
rinding and filing is carried out under controlled conditions. If unsure about
he disposition of pipe defects, the QA department should be contacted tossist with any queries. The supervisor should also ensure that the pipe
as been cleaned of residue blasting matter both internally and externally.
He shall further be responsible in ensuring that the task is conducted in the
afest possible manner.
he QC Inspector/Auditor is responsible for recording the disposition of
ipe exhibiting defects and raising NCR report if required. He shall also
erform periodic testing in accordance with the agreed project Inspection
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 48/89
est Plan (ITP).
he Tally Man shall maintain pipe traceability and ensure that correct
ecords of defective pipe movement and disposition.
.4 Preheat FBE:
Prior to FBE coating the previously installed end plugs should be removednd the internal bore of the pipes checked for contamination. The pipes are
hen preheated prior to the application of the Fusion Bonded Epoxy powder
y passing through an Induction coil heating system.
Induction Heating Coils
he preheat temperatures are controlled so that the pipe is within the
orrect manufacturers recommended temperature range when the epoxy
owder is applied. The pipe temperature is continuously monitored
mmediately prior to the powder application booth by using a calibrated
urface temperature probe, infrared sensor or "Tempil" sticks. The latter
owever, may not be a permissible method due to oily residues left on the
ipe surface.
Infra Red Thermometer
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 49/89
Infra Red Temperature Read Out
Tempil Stick
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 50/89
Cutback taping
Cut back areas are sometimes applied to avoid excessive time on the end
leaning station after coating, the paper used must be flame resistant.
apes have been known to inflame during pre heating and have the
otential to cause a coating booth explosion?
Responsibilities:
he Blast Line Supervisor should ensure that the induction heating
quipment is maintained in satisfactory operating condition and that the
ettings are commensurate to the required heating range for the particular
ipe size and wall thickness being heated. He should alsoensure that the
onveyor line speed is constantly maintained to allow even pipe preheat
nd coating to be achieved. He should also be responsible in ensuring that
he task is conducted in the safest possible manner.
he QC Inspector is responsible for monitoring preheat temperatures at thepecified periodic intervals.
he Tally Man should ensure that pipe traceability and correct records of
ipe movement and disposition.
Coating Parameters:
is always advisable that the production line operating parameters be
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 51/89
ecorded for internal analysis on an internal coating operations parameter
eport.
.5 MATERIAL INSPECTION
usion Bonded Epoxy Powder
Each container of epoxy powder is inspected prior to loading into the
owder delivery system.
Note: With FBE powder it is advisable to check production material for
moisture content and gel time on at least a daily basis. (A high moisture
ontent can cause coating irregularities.
he inspection should also confirm that the epoxy powder is listed on the
Approved IRF".Only powder with current, valid approval shall be used.
Batch numbers shall be recorded on all the relevant inspection and
aboratory test reports.
Polymers
Each container Polymer shall be inspected prior to loading into the Extruder
opper systems.
Note: With Polymers it is advisable to check for moisture of the pellets
very two hours when in production. A simple way to check for moisture is
o push your bare hand into the box of pellets. If when you withdraw your
and you find pellets adhering to your skin it is an indication that excessive
moisture is present.
he inspection shall also confirm that the Polymers are listed on the
Approved IRF. Only Polymers with current, valid approval shall be used.
Batch numbers shall be recorded on all the relevant inspection andaboratory test reports.
Reclaim:
Subject to client approval the amount of reclaim powder applied in any
iven interval shall notexceed 20 % of the total powder application.
FBE Reclaim
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 52/89
.6 Coating Application
Powder application
he Fusion Bond Epoxy Powder is applied to the heated pipe using a
eries of electrostatic spray guns. By balancing the conveyor line speed
nd the settings of the electrostatics, guns, FBE flow rate and pressure of
he material feed the material application is controlled to achieve the
orrect applied coating thickness. The coating should be continuous over
he entire length of each pipe joint. The minimum thickness shall be asndicated in the agreed Project Inspection Test Plan ( ITP.)
Polymer Application
mmediately after the FBE primer, the co polymer adhesive (intermediate
oat) is applied. The application shall take place within the gel time window
f the FBE to ensure adequate adhesion to the primer. The minimumhickness is as indicated in the agreed project Inspection Test Plan (ITP)
ollowing the adhesive side extrusion application, the Polyethylene or
Polypropylene topcoat is applied by side extrusion process in a single sheet
ayer over the adhesive. Both polymer layers are applied with an overlap.
During the application of the polymers, a pressure roller is applied against
he pipe behind the polymer sheet that presses against the the applied
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 53/89
heet that eliminates air bubbles and ensures intimate contact between the
ayers. The minimum thickness of the PE/PP is as indicated in the agreed
roject Inspection Test Plan (ITP).
PE Application
PP Application
Responsibilities:
he coating line Supervisor shall be responsible for the strict control of all
he heating to maintain the correct pipe preheat temperatures in
ccordance with line speed, pipe diameter and material preheat
equirements. Information required to perform this function is received from
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 54/89
he coating line controller. He shall also be responsible in ensuring that the
ask is conducted in the safest possible manner.
he QC, inspector/auditor shall be responsible for monitoring of the coating
arameters.
he Powder booth foreman shall be responsible for maintaining the
pplication, gun settings, flow rates of materials, feed line pressures for the
articular line speed and pipe diameter and the electrostatics.
he coating line controller shall be responsible for all line activities for
material coating line. This includes maintaining the correct line speed and
ipe preheat by monitoring inspection reports and control room
nstrumentation and that all powder coating and Polymer extrusion
arameters are maintained.
On completion of coating the coated pipe is progressed through a water
uenching tunnel where copious amounts of water is sprayed onto the
nished coating and to cool the pipe for safe handling.
Water Quench
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 55/89
.3 COOLING BOARDS & INSPECTION
mmediately after cooling the coated pipes are transferred to an outgoing
added pipe rack where the pipes are positioned on end cleaning rotators
he end cleaner brushes remove the coatings from the cut back areas of
he pipe. The entire coating surface is visually inspected for coating quality
nd detrimental coating defects. The cutback distance at both ends of the
ipe are also checked..
After end cleaning and visual inspection the entire coated surface of each
ength of pipe is inspected for holidays using a high voltage (pulse type)oliday detector previously set and calibrated to the correct voltage. The
ircumferential search electrode shall maintain intimate contact around the
ntire circumference of the coated pipe at all times. The voltage shall be
hecked and recorded hourly. The travel speed for holiday detection shall
e at a rate of 300 mm per second maximum. Any holidays or surface
efects shall be clearly marked and recorded on the agreed Coating
Application Report.
Holiday Detector
he coating thickness is usually determined by taking the 4 equidistant
measurements (3 on the body and 1 on the weld) at the lead end middle
nd tail end of each pipe (a total of 12 measurements). The measurement
hall be conducted using an electromagnetic thickness gauge. Records of
he thicknesses shall be recorded on the agreed Coating Application
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 56/89
Report
Thickness Check
Responsibilities
Cooling board supervisor shall be responsible for ensuring that the holiday
etection of each pipe is carried out in a correct manner and at the correct
oltage. Also he shall ensure that the pipe cutbacks are correctly
stablished and that the pipe ends and pipe internals are sufficiently
leaned. He shall also be responsible in ensuring that the task is conducted
n the safest possible manner.
he QC, inspector/auditor shall be responsible for visual inspection of the
oating and physical testing. He shall also monitor the holiday detection
nd cut back length. He shall also be responsible for calibration of the
oliday detection equipment prior to the start of each shift.
oad out Tally man, shall be responsible for checking the pipe identity and
maintaining pipe trace ability on the computerized pipe tracking system. He
hall also ensure that coating thickness checks are being carried out andeing recorded correctly for each pipe.
.4 REPAIRS:
Repairs to the coatings shall be carried out in accordance with an approved
Repair Procedure. Coated pipes that cannot be repaired shall be rejected,
tripped and re coated. Unacceptable pipe shall be marked up with
Red/White hazard tape and recorded on the NCR system.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 57/89
ypical Repair Procedure
his procedure describes methods that enable repairs to be made to the 3
ayer Coating System after the completion of the in line process. This
method statement describes three repair methods and is presented in three
arts:
Part 1: - Repairs using a Hand Held Extruder Gun.
Part 2: - Repairs using Melt sticks.
Part 3: - Repairs using Sleeves.
Part 1: Hand Extruder
here are two types of repair
ype A: - Repairs to the total three layer system.
ype B: - Repairs to the Polyethylene layer only.
YPE A - The defective area shall be removed and the surrounding sound
oating shall be abraded to allow a "key" for the system repair material. An
rea of at least 50 mm diameter will be removed to facilitate the effective
leaning of the steel and FBE. The repair area substrate shall then be
ently preheated to remove surface moisture.
he FBE shall then be feathered using abrasive paper at the FBE/substrate
nterface.The exposed substrate shall then be mechanically roughened,
masking tape (if used) and surface dust shall be removed and two pack
poxy material applied. Mixing/application of the two pack epoxy shall be in
ccordance with manufacturer's data sheet and shall be applied to the
repared area using a clean brush (or pallet knife if compound is used).
After the Epoxy coating has cured, Polymer (as used in the parent coating)
s then extruded from a hand held extruder onto the repair area taking care
hat no air entrapment at the FBE/Polymer interface occurs. The Polymer is
xtruded in layers to bring the repair thickness up to and in excess of thearent coating thickness. Once cool, the repair shall be blended with the
arent coating, any excess Polyethylene removed by scraper and/or rasp.
he completed repair areas shall then be holiday detected.
Hand Extruder
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 58/89
YPE B - The damaged Polymer is removed using a chisel and the
urrounding area roughened using a mechanical burr. Extruded Polymer as used in the parent coating) is then introduced into the prepared area.
Once cool, the repair area shall be blended with the parent coating and any
xcess removed by scraper and rasp. The completed repair areas shall
hen be holiday detected. For repairs of Pinholes and minor defects to the
Polymer coating repairs shall be by using melt sticks.
Any loose or defective coating shall be removed from the damaged area
nd any sharp edges eliminated. The area and adjacent coating is then
leaned thus removing all foreign materials.
he prepared area is then preheated, at the same time the end of the melt
tick is heated such that it becomes “glossy”. The molten adhesive is then
pread onto the damaged area.
Melt stick
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 59/89
On hardening, the repair shall be smoothed with a rasp such that the repair
rea becomes flush with the existing parent coating.
Part 3: WPC Sleeves
Heat shrinkable sleeves shall be used as an alternative for larger repairs.
he defective coating area shall be removed from the defect area. The full
ircumference around the pipe at the defect locality shall be thoroughly
leaned of surface dust, grease, oil etc using Xylene or bio -degradable
mulsifier. The full circumference of the pipe surface where the sleeve is to
e applied plus 100 mm either side shall be abraded.
he steel substrate at the defect area shall be mechanically roughened and
he repair area warmed slightly to drive off surface moisture. On completion
f preparation a two pack epoxy shall be applied to the steel surface. Mixing
nd application of the two pack epoxy shall be in accordance with the
manufacturer's data sheet. The epoxy shall be applied to the prepared
rea using a clean brush (or pallet knife if compound used).
When the Epoxy compound has cured, a filler shall be applied to the repair
rea to increase the coating thickness at the repair area location. A shrink
leeve shall be prepared to the correct dimensions and made ready for
pplication. When prepared the protective release plastic shall be removed
rom the mastic coating and the sleeve centred over the repair area. The
leeve shall be loosely wrapped around the pipe with ends overlapping by
pproximately 75-100 mm. The overlap shall be in approximately the 11
’clock position of the pipe with the edge of the overlap pointing
ownwards. The ends shall be aligned evenly.
Using a propane gas torch one end of the closure patch shall be heated
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 60/89
ntil the reinforcing fabric is visible or the thermo-chromic paint has
hanged colour. With a gloved hand, the closure shall be patted down
rmly to the pipe and any wrinkles or bubbles shall be smoothed out. This
rocedure shall be repeated moving across the closure until the opposite
nd is completed. Whilst the closure is still hot and soft, a hand roller shall
e used to smooth out any trapped air and the edges and corners shall be
rmly bonded down.
he heating procedure shall continue around the pipe by heating in the
entre of the sleeve and continue towards the edges. Occasionally the
dhesive flow shall be checked by using finger pressure. After the sleeve
as shrunk and is still hot and soft, use a hand roller over the sleeve to
emove any entrapped air. Re heating of the sleeve is permissible to
omplete the repair.
Responsibilities:
he repair foreman shall be responsible for coating repairs and shall ensure
he correct equipment and repair method is used for coating repair. He shall
lso be responsible in ensuring that the task is conducted in the safest
ossible manner.
QC, Inspector/auditor shall be responsible for checking the preparation and
he completed repairs.
.5 OFFLINE TESTING
Besides online testing and inspection requirements there are a series of
Off Line” tests that have to carried out to confirm compliance of the coating
ystem against the specified requirements which include the following
ractices:
Back Side Contamination Checks
Coating Thickness Measurement
Differential Scanning Calorimeter
Gel Time DeterminationHoliday Detection
hickness Measurement
lexibility (Bend) Test
Cathodic Disbondment Test
mpact Resistance
Melt Flow Index
Moisture content
Adhesion Test
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 61/89
ensile Elongation Test
Determination of Coating Hardness
----------------------------------------------------------------------------------------
----------------------------------
Back Side Contamination - CAN/CSA Z245.20-2
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
o determine the extent of backside contamination at the bottom side of an
BE coating chip sample.
Equipment
Sample freezer
Bending machine
0 X microscope
Procedure
A sample section of coated pipe shall be removed from a test ring. The
ample section shall be approximately 200 x 50 mm
he sample cut out shall then be placed into a freezer and cooled down to
ear freezing point. After freezing the sample shall be removed from the
reezer and rapidly bent around a suitably sized mandrel causing the FBE
o flake off of the substrate.
Evaluation
Pry off the flake sample, The then examine the sample using a 40 X
microscope and the percentage of contamination is rated
Acceptance criteria: The backside contamination shall be within the
pecified tolerance. Typically 30 % max.
Report
Record
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 62/89
Date
ime
Pipe number
Batch number
Backside Contamination expressed in %
ackside Contamination
------------------------------------------------------------------------------
----------------------------------------
COATING THICKNESS MEASUREMENT
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
Determine the coating thicknesses of anti corrosion coatings.
Equipment
Calibrated electronic Thickness Gauge
Procedure
he pipe should be suitably cooled immediately after anti corrosion coating
efore measuring the coating thickness.
he coating thickness of the coated pipe is checked by using a calibrated
lectronic thickness gauge. The checking position of the inspection probe
hould be in vertical position and at right angles to the coating being
hecked. The coating thickness is measured at the specified locationslong the body of the pipe and on the weld seam where applicable.
Calibration of the measuring instrument
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 63/89
Switch on thickness gauge
Select "CAL" button
Place the probe on top of a certified standard thickness shim which has
een placed on a blast cleaned bare steel area and read the measurement.
Adjust the up or down button to give the actual reading according the
oating thickness standard or certified shim.
Press the "CAL" button again for confirmation calibration.
Report
Record
Date of coating
Pipe number hickness gauge reading
Report the individual coating thicknesses on both body and weld seam.
Report the minimum average thickness of the coating.
Record instrument calibration details
----------------------------------------------------------------------------------------
------------------------------
DIFFERENTIAL SCANNING CALORIMETER - CAN/CSA Z245.20-2
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
his test is to determine the glass transition temperature (Tg) and the
mount of exothermic heat of reaction (DH) of epoxy powder or fusion-
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 64/89
onded epoxy cured coating.
Equipment
Differential scanning calorimeter (DSC) and accessories
Analytical balance accurate to 0.1mg
Knife or file
Procedure
Obtain a 10+/-1-mg sample of epoxy powder or coating as applicable
Place the sample in a pre-weighed aluminum pan and put lid in place.
Crimp the lid into place with the encapsulating press and obtain the sample
weight by subtracting pan and lid weight from the total weight.
Place a small vent hole (pierce) in the lid without damaging the pan.
Place sample and reference (as suggested by the instrument supplier) in
he DSC furnace.
Use nitrogen gas to purge the cell.
or epoxy powder sample, obtain thermal scans for the following cycles in
rder
a) heat the sample from 25 ± 5ºC to 70 ± 5ºC at a rate of 20ºC/min,
hen immediately cool the sample to 25
5ºC
b) heat the sample from 25 ± 5ºC to 285 ± 10ºC at a rate of 20ºC/min, then
mmediately cool the sample to
5 ± 5ºC; and
c) heat the sample from 25 ± 5ºC to 150 ± 10ºC at a rate of 20ºC/min. For
oating samples, obtain thermal
cans for the following cycles in order:
d) heat the sample from 25 ± 5ºC to 110 ± 5ºC at a rate of 20ºC/min, holdt 110 ± 5ºC for 1.5 min, then
mmediately cool the sample to 25 ± 5ºC;
e) heat the sample from 25 ± 5ºC to 285 ± 10ºC at a rate of 20ºC/min, then
mmediately cool the sample to
5 ± 5ºC; and
f) heat the sample from 25 ± 5ºC to 150 ± 10ºC at a rate of 20ºC/min.
Evaluation
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 65/89
he Tg is taken as the point of intersection of the extrapolated baseline of
he low temperature end and the tangents to the curve at the inflection
oint (onset) Calculate the residual exothermic heat of reaction (DH)
ollowing the instructions provided by the manufacturer of the DSC
quipment.DTg = Tg4 – Tg3
Report
Record
Date
Date of coating
Product code for epoxy powder only
Batch number, and date tested.
Pipe number where applicable,
Report Tg1, Tg2 and DH, for epoxy powder
Report Tg3, Tg4, DTg and DH, for coating, including units
ndicate the type of differential scanning calorimeter.
DSC Sample Preparation
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 66/89
DSC Machine
----------------------------------------------------------------------------------------
---------------------------------
GEL TIME DETERMINATION - CAN/CSA Z245.20.02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 67/89
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 68/89
Date
Product
Batch number
Gel time in seconds.
----------------------------------------------------------------------------------------
---------------------------------
MOISTURE CONTENT - CAN/CSA Z245.20.02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
Determine the moisture content of FBE powder using the mass loss
method
Equipment
Oven controllable within 3°C
Balance accurate to 0.001g
Desiccators; and
Sample container
Procedure
Weigh the sample container to the nearest 0.001g. Transfer approximately
0 g of epoxy powder into the sample container. Weigh the sample
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 69/89
ontainer and epoxy powder to the nearest 0.001g. Place the sample
ontainer with the epoxy powder into the oven for a maximum of two hours
t 105 ± 3°C. Remove the container from the oven and place in the
esiccators to cool. Weigh the sample container when it has cooled to
0 ± 3°C
Evaluation
Calculate the percentage of moisture using the following formula:
M = (B-C)/(B-A) x 100
Where
M = percentage of moisture
B = initial mass of sample container and epoxy powder, g
C = final mass of sample container and epoxy powder, g
A = mass of sample container, g
Acceptance criteria, Typically 0.5 % max.
Report
Record
Date
Material Code
Batch number
Moisture expressed in %
----------------------------------------------------------------------------------------
--------------------------------
POROSITY INTERFACE & CROSS SECTIONAL - CAN/CSA Z245.20.02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
o determine the extent of inter facial porosity at the bottom side of an FBEoating.
o determine the extent of cross sectional porosity within an FBE coating
Equipment
Sample freezer or dry ice & container
Bending machine
0-40 X microscope
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 70/89
Mandrel
Procedure
A sample specimen of coated pipe shall be removed from a test ring. The
ample section shall be approximately 300 x 50 mm. The sample cut out
hall then be placed into a freezer or dry ice and cooled down to near or
elow freezing point. After freezing the sample shall be removed from thereezer or dry ice and rapidly bent around a suitably sized mandrel causing
he FBE to flake from the substrate. Pry off the flake sample of FBE coating
o allow observation of both the cross section and underside of the coating
ample to be examined.
Evaluation
he sample shall then be viewed both in inter facial and cross sectional
levations using a 40 X microscope and assessed for porosity.
Acceptance cri ter ia, Typically rating 3 max.
Report
Record
Date
Pipe number
nterface Rating 1-5
Cross sectional rating 1-5
----------------------------------------------------------------------------------------
-------------------------------
DETERMINATION OF HARDNESS - ASTM D 2240
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
est to measures the coating hardness using a Shore D hardness gauge.
Specimen
Applied coating or a free film sample usually 3mm or more in thickness.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 71/89
he surface of the specimen shall be flat and parallel over a sufficient area
o permit the presser foot of the gauge to suitably contact the test area.
Equipment
Shore D Hardness gauge.
Procedure
a free film specimen is used, the specimen shall be placed on a hard, flat
orizontal surface.The Shore D Hardness gauge shall be held in a vertical
osition with the point of indenter at least 12mm from any edge of the
pecimen. Apply the presser foot to the specimen as rapidly as possible,
without shock, keeping the foot parallel to the surface of the specimen.
Apply just sufficient pressure to obtain firm contact between presser foot
nd specimen.
Evaluation
When the presser foot is in firm contact with specimen, the scale reading is
o be recorded within 5 seconds’
Note: The hardness reading may progressively decrease with any time
elay.
Acceptance criteria, Typically Shore 60
Report
Record
Date
Manufacturer code
Batch number
Coating date .
Pipe Number or sample ID if applicable, shall be recorded
Record hardness value obtained.ype and Serial Number meter
Shore D Hardness Test
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 72/89
----------------------------------------------------------------------------------------
---------------------------------
Melt Flow Index - (ASTM D1238)
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
his test is primarily useful to raw material manufacturers as a method of
ontrolling material uniformity. While the data from this test is not directly
ranslatable into relative end-use processing characteristics, the melt index
alue is nonetheless strongly indicative of relative “flow ability” of various
ind and grades of Polymer. The property measured by this test is basically
melt viscosity or rate of shear. In general, the materials that are more
esistant to flow are those with higher molecular weight.
Equipment
Extrusion Plastometer (ASTM D1238)
Stopwatch or electric timer
Spatulahermometer
Procedure
he apparatus is preheated to 190°C . Material is put into the cylinder and
he loaded piston is put into place. After 10-15 minutes, the extrudite
ispensing from the orifice is cut off flush, and again one minute later.
hese cuts are discarded. Cuts for the test are taken at 1, 2, 3, or 6
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 73/89
minutes, depending on the material or its flow rate. The melt flow index is
alculated and recorded in grams/10 minutes. For adhesive the test
ondition load is 2.16 kg test for 1 minute only at 230° C.
Calculation
Weigh 4 samples and take average reading; A
Melt Flow Index, g/10min = Aktest is 1 minute, the factor k is 10
test is 3 minutes, the factor k is 3.33
test is 6 minutes, the factor k is 1.67
Report
he following information shall be reported:
Manufacturer, product code, batch number, and date tested.
Pipe size identification
Report MFI results in g/10 min.
ndicate time, and weight used.
----------------------------------------------------------------------------------------
------------------------------
HOLIDAY DETECTION - NACE RP 0188-99/DIN 30670/CAN/CSA
45.20+21-02
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 74/89
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
o determine the anti corrosion coating is without any coating defects that
llow continuity between the test electrode and the substrate e.g. pinholes,oids, cracks and/or foreign matter inclusions.
Equipment
n-Plant Holiday Detector (e.g. SPY) which is an electrical device that
ocates discontinuities in the protective coating.
A calibrated Jeep meter crest-void meter which is used to calibrate the In-
Plant Holiday Detector.
Calibration Procedure
he In-Plant Holiday Detector is connected to the Jeep meter. Then both
oliday detector and jeep meter are switched on.
he In-Plant holiday detector is adjusted to the required test voltage and
he voltage value on the Jeep meter checked. The readings shall be of
qual value. Should the value on the jeep meter differ from that as set on
he holiday detector, the holiday detector shall be adjusted to allow the jeep
meter value to be obtained.
Calibration of holiday detector shall be performed at the beginning of each
hift and after any long term pause in production.
est Procedure
he pipe shall be in dry condition before holiday detection to avoid
ppreciable High Voltage DC leakage through the holiday detector circuitwhich can potentially produce a false signal.
he test voltage setting shall be dependant on the coating thickness. The
minimum testing voltage for a particular coating thickness shall be in
ccordance with the specified requirements for the coating being tested,
.g. 3LPP/PE 5 Kv/mm and FBE 5 V/µm.
he holiday detector electrode shall travel along the pipe surface at a
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 75/89
maximum travel speed of 300mm per/sec.
Where a holiday is detected, the defect area shall be clearly marked using
permanent marker and recorded on the appropriate inspection report.
Report
he following information shall be reported:
Date
Pipe Identification
Number and type of defect
Holiday detection speed
Calibration details
Holiday Detector
----------------------------------------------------------------------------------------
--------------------------------
LEXIBILITY BEND TEST - NACE RP 0394-94 CAN/CSA Z 245.20-02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 76/89
Scope
his test is to determine the flexibility of coating for field bending.
Equipment
Hydraulic Press
Bending mandrels of fixed radii
Microscope
reezer
Procedure
Specimens shall be removed from test rings (approx. 300mm long x 50mm
wide x pipe wall thickness, with the 200mm dimension parallel to the axis of he pipe.
Ensure that the specimen edges have all stress raisers removed and that
ubstrate is exposed along the edges. Test temperature shall be 23+/-2ºC.
Calculate the required mandrel radius (R) using the following formula
R= ((57.3)(t)/s))– t/2
Where
R= mandrel radius, t= effective strap thickness, and
= strain (deflection) in degrees per pipe diameter (°/PD).
Determine the effective strap thickness (t), which includes the specimen
hickness and any curvature, by placing the specimen on a flat surface and
measuring the thickness as shown in Figure K1 of NACE RP0394-94
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 77/89
Standard. Where a mandrel of the calculated radius is not available; the
mandrel of the next smaller radius shall be used.
Bend the test specimens over the radius so that the uncoated side is in
ontact with the mandrel, completing the bend within 30 seconds. The bend
est shall take a minimum of 10 seconds for completion.
Measure the residual bend radius by matching the outer curve of theest specimen to the nearest arc from Figures K2, K3, K4 or K5 of NACE
RP0394-94 Standard. Visually inspect the specimens for cracks, tears in
he coating, and disbonding of the coating after the specimen has warmed
o room temperature. The presence of any such defect within 2.5mm of the
trap edge does not constitute failure. The presence of strain marks alone
oes not constitute failure.
Report
he following information shall be reported :
Manufacturer, product, batch number, and date tested.
Pipe number, coating date.
Specimen effective strap thickness, permanent (residual) strain radius,
ngle of deflection in degrees per pipe diameter for passing bend, and test
rocedure used.
est Temperature
Defect {s} if any
----------------------------------------------------------------------------------------
--------------------------------
ADHESION TESTING - CAN/CSA Z245.20.02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
o determine Peel Adhesion of Polyeofins (Constant rate of peel method)
o determine Peel Adhesion of Polyeofins (Hanging weight method)
Equipment (Constant Rate of Peel Method)
ensile testing machine able to measure a load to an accuracy of 1%
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 78/89
Utility Knife
Attachment Clamp
Equipment (Hanging Weight Method)
Masses 0.3, 2.0, 15.3 kg
Attachment clamp
Utility Knife
Stop watch
Procedure (Constant Peel Method)
Cross head speed 10 +/- 1 mm/min
Normal specimen length of peel 75 mm for test
Normal specimen width 25 +/- 1 mm
Peel orientation shall be circumferential
Procedure
Prior to conducting the test condition the sample to test temperature for a
eriod of 1 hour minimum. Cut the required dimension test strip through to
he steel substrate. Make a cut at right angle to the test strip to enable
fting of the start tab. On the bonded area of the test strip mark the
equired test length
Attach the pull clamp to the tab of the test strip and proceed to peel the
trip at the prescribed 10 +/- 1 mm/min. Record the load required to peel
he sample. If more than 5 % of the total peeled length has a peeling load
elow the specified minimum value, the sample fails the test. If a small
ortion (less than 5 %) of the total peeled load is below the specified
minimum, accept the test as satisfactory. If the polyeofin breaks more than
hree times during the test, terminate the test and accept as being
atisfactory’
Calculate the minimum peel strength as follows:
P = Lp x 9.81
Where
P = minimum peel strength, N
p = minimum peel load, kg
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 79/89
Report (Constant Rate Test)
Sample ID
est date
Minimum peel strength
est temperature
Procedure (Hanging weight method)
Width of peel sample 25 +/- 1 mm
Peel orientation shall be circumferential
Make two cuts 25 +/- 1 mm apart through the coating to the substrate and
ircumferential from the 90° position to the 180° position. The coating shall
e cut at right angle at the 90° position and the peel shall be down towards
he 135° position.
he appropriate mass shall be attached to the free end of the peel strip
Mass for System
A1 0.3 kg
A2 2.0 kg
B 15.3 kg
he peeling time in minutes from the 135° position terminating at the 180°
osition shall be measured. The peeling may also be terminated when theest time calculated by using the following formula has been exceeded.
= 0.125 x 3.14 x D ÷ 10
Where
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 80/89
= test time in minutes
D = Nominal pipe outside diameter in mm
Measure the distance peeled in mm from the time the test was initiated
ntil it was terminated. Calculate the peeling speed using the following
ormula;
PS = d ÷ t
Where
PS = peeling speed in mm/min
= distance peeled in mm
= peeling time in min
the peeling speed is in excess of 10 mm/min at the test temperature the
est shall be considered a failure.
Report (Hanging Weight Test)
Sample ID
est date
est temperature
Pipe OD
Mass used in kg
Distance peeled mm
Peeling time minutesPeeling speed mm/min
Peel Adhesion Machine
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 81/89
Peel Adhesion Sample
----------------------------------------------------------------------------------------
----------------------------------
ENSILE at BREAK & ELONGATION - ASTM D 638
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
Scope
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 82/89
o assess of the tensile and elongation properties in material. The force
ecessary to pull the specimen apart is determined, along with how much
he material stretches before breaking. The elastic modulus (modulus of
lasticity or tensile modulus) is the ratio of stress to strain below the
roportional limit of the material.
Specimen
Specimen can be machined from compression molded plaques or
xtrudate. Samples to be suitably conditioned prior to testing.
Specimen is typically 1/8” thick (3mm) and made up to a type 5 barbell
onfiguration test piece.
Equipment
Universal Testing Machine, or equivalent
Computer complete with printer to plot graphical result
Procedure
Both ends of the specimen are firmly clamped in the jaws of a tensile
esting machine. The jaws may move apart at rates of 5, 12, 50 or 500 mm
er minute, pulling the sample from both ends.
Prior to starting the test, the original area (to be stretched) of the test
pecimen is measured and recorded.
he applied yield load is first recorded. After the yield load is obtained, the
nstrument is reset to get a second reading for the break point.
he stretched area of the sample is then measured to use in calculating the
reaking or stress at break of the specimen.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 83/89
or the elongation of specimen, the stress is automatically plotted against
train (elongation) on graph paper.
Note : In case there is no graphical plotter is available, the elongation shall
e recorded as a percentage using the equation
A0, % = (L1 – L0)/L0 x 100
Where
0 = initial free length between gauge length.
1 = distance between gauge length at the time of breaking
he arithmetic mean of 5 results (A0) shall be determined.
Report
he following information shall be reported :
Manufacturer, product, batch number and date tested.
Pipe number, coated date.
Report Yield and Ultimate strength results in MPa.
Report Elongation in Percentage, %
Record results on relevant laboratory test report.
----------------------------------------------------------------------------------------
---------------------------------
CATHODIC DISBONDMENT- CAN/CSA Z245.20-02 & CAN/CSA
245.21-02
Note: This practice may be modified by the requirements of the customer’s
pecification, see relevant Project Inspection Test Plan (ITP)
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 84/89
Scope
o assess the comparative resistance of damaged coatings to loss of
dhesion by disbondment when exposed to Cathodic polarization. The test
hall be performed on a test specimen taken from a pipe or pup piece
reviously subjected to holiday detection, and in which an artificial defect of
defined size has been drilled.
Equipment
Stabilized DC Power supply unit with controlled voltage output.
A Cathodic polarization potential of –1.500mV to a saturated calomel
eference electrode (equivalent to UH = -1.260mV, where UH means the
otential of the standard hydrogen electrode shall be maintained). “E”
otential of the “working electrode” with regards to the “referencelectrode”. “V” difference of potential between the “working electrode” and
he “counter electrode”.
Electrolyte cell consisting of rigid plastic tube or PVC of with an internal
iameter of 75 ± 3 mm. The height shall be 120 mm.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 85/89
A rigid plastic cover in which 3 holes shall be drilled to allow the passage of
he electrodes and any other measuring instruments deemed necessary,
nd to allow the escape of hydrogen.
Reference electrodes- the saturated calomel reference electrode or
uitable type of reference electrode to give an equivalent potential shall be
laced in an electrode holder situated in a glass tube with a porous endlug. The end of this assembly shall be placed approx. 10mm from the
urface of the coating and approximately 20mm from the coating defect.
Counter electrode or platinum wire.
Working electrode (cathode)- is represented by the artificial defect, which
hall be 3.2 mm in diameter for FBE & 6.4 mm in diameter for 3 Layer,
which shall penetrate through the coating to expose steel substrate.
Calomel reference electrode
Utility knife
est Specimen
est- Ring Specimen
he test specimen shall be a 100mm x 100 mm (square) segment cut from
he representative test ring.
Procedure
Drill a 3.2 mm (FBE) or 6.4 mm (3 Layer) diameter holiday through the
oating at the center of the specimen.
Glue a plastic cylinder onto the specimen using a sealant to form a water
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 86/89
esistant seal. Ensuring the pre drilled holiday is at the center of the
ylinder.
Pour approximately 300ml of Sodium Chloride Solution into the plastic
ylinder.
When testing specimens cut from the pipe, a heat- transfer medium shall
e employed to provide uniform heating of the specimen.
Use a metal pan/tray partially filled with a heat transfer medium (sand) into
which the specimen is implanted. Place on a hot plate or in an oven to
maintain the test temperature as required according to the duration of tests
pecified in the specification.
Connect the negative lead (working electrode) from the power supply to the
pecimen ( Cathode) and the positive lead (Counter electrode) to the
node after the test temperature is reached.
urn on the power supplies and applies voltage to the test specimen:
egative 1.5V or 3.5V with respect to the calomel reference electrode for
he 24 hr, 48-hr (only on accelerated production test) and/or 28-day tests.
Monitor the voltage, temperature and electrolyte level at the start and at
very 24-hr interval thereafter. For the 28-day test, the electrolyte level
eed not be monitored on weekends provided a cover plate is loosely fitted
ver the test cell. Distilled water shall be added as required to maintain the
lectrolyte level.
Evaluation Procedure
After 24hrs or 48 hrs (on accelerated production test), dismantle the test
ell and remove the test sample cell from the hot plate or oven.
mmediately drain the electrolyte and air-cool the sample to 20 ± 3° C. The
valuation shall be performed within one hour of removal from the hot plate.
or 28 day test, remove the 28-day test cell using the same procedure.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 87/89
Using a utility knife, make radial cuts from the edge of the holiday outward
hrough the coating to the substrate. The radial cuts shall be at least 20mm
n length from the centre of the holiday.
nsert the blade of the utility knife under the coating. Using a levering
ction, chip off the coating. Continue until the coating demonstrates aefinite resistance to the levering action.
Measure the radius of the disbonded distance from the holiday edge along
ach radial cut and average the measured results. Maximum allowed CD
adius as measured, is detailed in the controlled ITP drawn for this project.
Report
he following information shall be reported:
Date tested.
Pipe number and coating date.
Average disbonded radius.
PE CD SAMPLE
----------------------------------------------------------------------------------------
----------------------------------- -
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 88/89
MPACT TEST - DIN 30670, DIN 30678 & CAN/CSA Z 245.20-02
ote: This practice may be modified by the requirements of the customer’s specification,
ee relevant Project Inspection Test Plan (ITP)
cope
o determine the impact resistance of coating (this practice can be adopted on both FBE &
hree Layer coating systems). The test can be carried out both, in a controlled laboratory
nvironment and as a field test (directly on test pipe surface).
quipment (Impact Tester having)
alling masses 1-kg FBE, 3.5-kg 3LPE, 6-kg 3 LPP
5.8mm (FBE) or 25 mm (3 Layer) diameter ball bearing tup piece (tup shall have a
ardness of 50 to 55 HRC)
meter long graduated slotted tube
wooden block measuring approx. 610mm on each side and have a top facing of
ardwood (for laboratory controlled test procedure).
C holiday detector
est Specimens
Laboratory test) Shall be approximately 25mm x 200mm x pipe W.T., with the 200mm
mension parallel to the axis of the pipe.
Field test) Test pipe.
rocedure
he impact energy shall be 15 joules (FBE) or 5 joules/mm (3 Layer)
he impact test shall be carried at room temperature with the relevant weight housed
ithin a 1 -meter graduated slotted tube. The ball bearing shall be rotated every 10 impacts
o a new location and replaced after 200 impacts. The distance between each impact shall
e 30 mm minimum.
8/10/2019 Painting Coating 2
http://slidepdf.com/reader/full/painting-coating-2 89/89
ach pipe shall receive 10 impacts, each impact indentation on the test specimen shall be
hecked for substrate exposure using a holiday detector set at 5V/micron (FBE) or
900volts per mm (3 Layer).
eport
he following information shall be reported:
roduct batch number and date tested.
ipe number and coating date.
he applied impact energy (joules)
oliday detection voltage setting according to the type of coating being tested.
Impact Test