19
SOLDIER CREEK ENGINEERING t TECHNICAL SERVICES, LLC Calculation SCE-FRNP-2019-M001 Rev. 0 Originated By: K.L. Kaylor Checked By: T. Fletcher Soldier Creek Engineering & Technical Services Document No. SCE-FRNP-2019-M001 Page 1 of 19 Title: Nitrogen Piping Project Pressure Loss-Longest Run FRNP ESQ: FA5270 Responsible Engineer: K.L. Kaylor, P.E. Date: 03/07/2019 Checked By: Terry Fletcher/ P.E. Contents of Calculation _Page Number 1.0 Summary 1 2.0 Detailed Problem Statement 1 3.0 Assumptions 1 4.0 References 1 5.0 Design Inputs 1 6.0 Analysis 2 7.0 Conclusions 2 Attachments 3 1.0 Summary This calculation will determine the pressure drop of the longest run of the 6-in natural gas supply header, from the tie-in to the 6-in natural gas supply at the package boiler area, to the 2- in feed to C-300 for supply of natural gas for the HVAC Service Replacement project. 2.0 Detailed Problem Statement This calculation is the first step in determining the expected pressure at each of the new header takeoff feeds for suppling natural gas for the HVAC Replacement Service projects at C-100/ C- 200, and C-300. It is expected that the pressure drop from the supply to the feeds is small. Thus the first calculation is for the longest run using conservative inputs (using total flow rate from start to end, and a conservative length of pipe). If the calculated pressure drop is negligible/ then the pressure at each take-offfeed will be considered to be the same as the starting supply pressure and calculating the pressure drop for each section of the header will not be required. 3.0 Assumptions See Attachment 1. All assumptions are noted in the various sections of the calculation. 4.0 References See Attachment 1. References are noted in the attachment. 5.0 Design Inputs See Attachment 1. All inputs are noted in the various sections of the calculation. Page 1 of 19

Page 1 of 19 Contents of Calculation Page Number

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Page 1 of 19 Contents of Calculation Page Number

SOLDIER CREEK ENGINEERING

t TECHNICAL SERVICES, LLC Calculation SCE-FRNP-2019-M001

Rev. 0

Originated By: K.L. Kaylor

Checked By: T. Fletcher

Soldier Creek Engineering & Technical Services Document No.

SCE-FRNP-2019-M001 Page 1 of 19

Title: Nitrogen Piping Project Pressure Loss-Longest Run FRNP ESQ: FA5270

Responsible Engineer: K.L. Kaylor, P.E.

Date: 03/07/2019 Checked By: Terry Fletcher/ P.E.

Contents of Calculation _Page Number1.0 Summary 1

2.0 Detailed Problem Statement 1

3.0 Assumptions 1

4.0 References 1

5.0 Design Inputs 1

6.0 Analysis 2

7.0 Conclusions 2

Attachments 3

1.0 Summary

This calculation will determine the pressure drop of the longest run of the 6-in natural gas

supply header, from the tie-in to the 6-in natural gas supply at the package boiler area, to the 2-

in feed to C-300 for supply of natural gas for the HVAC Service Replacement project.

2.0 Detailed Problem Statement

This calculation is the first step in determining the expected pressure at each of the new header

takeoff feeds for suppling natural gas for the HVAC Replacement Service projects at C-100/ C-

200, and C-300. It is expected that the pressure drop from the supply to the feeds is small. Thus

the first calculation is for the longest run using conservative inputs (using total flow rate from

start to end, and a conservative length of pipe). If the calculated pressure drop is negligible/

then the pressure at each take-offfeed will be considered to be the same as the starting supply

pressure and calculating the pressure drop for each section of the header will not be required.

3.0 Assumptions

See Attachment 1. All assumptions are noted in the various sections of the calculation.

4.0 References

See Attachment 1. References are noted in the attachment.

5.0 Design Inputs

See Attachment 1. All inputs are noted in the various sections of the calculation.

Page 1 of 19

Page 2: Page 1 of 19 Contents of Calculation Page Number

SOlDB)Cfi££KE»GW££R)NG

irecHWALSCTviusLic Calculation SCE-FRNP-2019-M001

Rev. 0

Originated By: K.L. Kaylor

Checked By: T. Fletcher

6.0 Analysis

See Attachment 1 for calculation details.

7.0 Conclusions

The calculated pressure drop of the longest run, supply tie-in connection to the 2-in feed to C-

300, is negligible, less than 0.04 psi. Thus the pressure at C-100 and C200 supply take-off feeds

will be considered to be the same as the starting supply pressure.

Responsible Engineer ^. L /^^u^ 03/07/19

Checker _\CU^^--- 2\?r\\^

Approverrtl^/^&U^ 3/^7, (9

Page 2 of 19

Page 3: Page 1 of 19 Contents of Calculation Page Number

Calculation: SCE-FRNP-2019-M001 Rev. 0

Attachment 1

Calculation-NG Supply-Pressure Drop 1-Longest Run (2019-0213) 5 - pagesAttachment A - Calculation References 11 - pages

Page 3 of 19

Page 4: Page 1 of 19 Contents of Calculation Page Number

Natural Gas Supply-Pipe Pressure Drop Calculation 1-Longest Run02/13/19 By: KL Kaylor

Using Crane example calculation 7-10

Crane Flow of Fluids-Technical Paper 410 - 2018 pg 7-6

Inputs

Outputs

Calculate pressure drop:

Longest Run-total flow from package boiler NG tie-in to C300 2-in supply takeoff from 6-in nitrogen piping header

Refl 6-4 Eqn6-22

Using: Darcy Weisbach equation - pressure drop in units of pounds per square inch (psi)

2.799xlQ~7KW2VAP=

d4

where:

K= resistance coefficient (unitless)

W= rate of flow (pph)

V= specific volume of fluid (cuft/lb)

d= internal diameter (in)

psi (Pressure loss)

Ref3.1

Assume:

Ref3.3

Ref3.2

Ref3.2

Ref3.2

Ref5

Given:

Fluid: Natural Gas

Sect 1.0 pl=

Pl=

Note 3 t=

Sg=

NG flow rate=

NG flow rate=

NG flow rate=

60 psig14.7 psia

74.7 psia

70 °F

0.59

99.0 cfm

37.1 cfm

12.4 cfm

Calculate total natural gas flow rate in pph:

Printouts

W,ioo=

wc-200=

W,300=

0.051 Ibs/cuft

302.9 pph

113.5 pph

37.9 pph

pressure (Ranges from 58-67)

barometric pressure

pressure

temperature

specific gravityC-100

C-200

C-300

density Note 6

C-100 flow rate

C-200 flow rate

C-300 flow rate

\N= 454.3 pph

Given: Pipe DetailsNom Size= 6 in

Material ASS CS

Sch= 40

Refl 6-2 Eqn6-3

Calculate reynolds number

6.3151^Re =

d[i

Refl

Refl

Refl

where:

W= rate of flow (pph)

d= internal diameter (in)

\i= absolute viscosity (centipoise)

B-14 d= 6.065 in

A-6 |j= 0.0106 centipoise

(linear interpolation & Note 2 )

solving:

A-26

Re= 4.46E+04

f= 0.0225

flow total

pipe size

pipe typepipe schedule

Reynolds number (unitless)

pipe IDabsolute viscosity

@ 74.7 psia70 OF

0.59 Sg hydrocarbon vapor

Reynolds number

friction factor (from Moody Chart)

Calculation-NG Supply-Pressure Drop 1-Longest Run (2019-0213) Page 4 of 19

Page 5: Page 1 of 19 Contents of Calculation Page Number

Ref5 Printoutl

Refl

Refl

1-8

6-2 Eqn6-2

Calculate total resistance coefficient K

From Worksheet "K Calcs" below - Sum all K values for pipe, valves, and fittings

K= 154.00 resistance coefficient (total)

V= 3.902 cuft/lb specific volume

@ 60 psig70 OF

Calculate pressure loss

AP=| 0.03]psi Pressure loss

pressurep2=

% Change

59.97 psig

0.0% ( If ~ 10% less than inlet absolute pressure Pl, "OK", see Note 1)

(If not- see Refl pg 1-8 for correction directions)

Calculate velocity and compare to recommended

0.050931^v =

pd2 ft/s (Velocity)

where:

W= rate of flow (pph)p= density of fluid (Ib/cuft)

d= internal diameter (in)

Ref2

from above:

from above:

solving:

w=d=

p=

v=

v=\

454.3 pph6.065 in

1/specific volume (\3.902 cuft/lb

2.45|ft/s

Recommended velocity in pipes

100 ft/s

specific volume

velocity

Natural gas

References

Refl

Ref2

Crane Flow of Fluids-Technical Paper 410 - 2018

Internet-EngineeringToolbox-Liquids, gases and vapors - suggested fluid velocities in pipes

http://www.engineeringtoolbox.com/fluid-velocities-pipes-d_1885.html

RefS.l Project SOW

Ref3.2 NG Consumption (Handout at 12/20/18 meeting-draft)

Ref3.3 ATMOS ENERGY Gas Chemistry Report dated 12/11/18

Ref4 Sketch (20181221KLK)

Ref5 Internet-GlobalSpec-Gas Density and Specific Volume Calculator

http://www.globalspec.com/calculators/gas-density

Ref6 Reducer dimension chart

Ref7 Cameron Hydraulic Data - 16th Addition, 2nd Printing 1981

Notes:

1 From Refl page 1-8.

If the calculated pressure drop (AP ) is ~ 10% less than inlet absolute pressure Pl,

reasonable accuracy will be obtained if the specific volume (V) used in the

equation is based upon either the upstream or downstream conditions.

2 Graph values are gases at 14.7 psia; it's note states that for gas on this page, correction of viscosity for

pressure is <10% for pressures up to 500 psia; therefore assumed no correction in this calculation.

3 Assume 70F for convenience for initial calculation; gas source is underground at ~50F,

4 In K Calcs below, for convenience, used L/D's from Cameron Hydraulics Ref7. Crane 2018 is fairly

complicated and with negligible pressure drop, not worth all the calculations described in

pages 2-14 thru 2-16 as referred in A-30 for standard tees and wyes.

5 Not used.

6 Density at 14.73 psia (0 psig) and 60F, conditions used to estimate volumetric flow rate provided in reference 3.2.

Calculation-NG Supply-Pressure Drop 1-Longest Run (2019-0213) Page 5 of 19

Page 6: Page 1 of 19 Contents of Calculation Page Number

Worksheet

Refl

"K Calcs"

Calculate resistance coefficient (K) values for pipe, valves,

From above

A27

Nom Size=

MaterialSch=

d=

D=

f=

fr=

6 in

ASS CS

40

6.065 in

0.5054 ft

0.0225

0.0150

and fittings

pipe ID

pipe IDfriction f,

Ref4 (Estimated quantities below)

K values based in pipe size and schedule

Qty Component

3000 pipe

2 ball valve (full port)

53 ell-90 deg-LR (r/d=1.5)

2 tee-run

1 tee-branch

1 enlarger 6"x3" (gradual reducer)

1 enlarger3"x2" (gradual reducer)

K Calc-Reducer 6"x3" schedule 40

Refl A-27 Equations for determining reducer & enlargement Ks

where: dl=smaller pipe ID; d2=larger pipe ID (in)

L/D/unit forfy K(ea) K(Total)

Note 4

Note 4

Refl

Refl

Refl

Ref7

Ref7

2-7 Eqn2-4

A-29

A-30

Pg3-113

Pg3-113

(See K calculation below)

(See K calculation below)

K=fL/D

K=3fT

K-14fT

K=20f

K=60f

1.9786

3

1420

60

0.0225

0.0150

0.0150

0.0225

0.0225

0.0445

0.0450

0.2100

0.4500

1.3500

2.3899

4.5847

133.56

0.09

11.13

0.90

1.35

2.39

4.58

resistance coefficient (total) K=| 154.001

Refl

Refl

Ref6

First calculate angle theta (9)Reducer/Enlargersize:

B-13/14 dl(nom)=

B-13/14 d2(nom)=

Chart 1=

3 in

6 in

5.5 in

dl= 3.068 in

d2= 6.065 in

length (end-end)

let: 1= adjacent side

0= opposite side=(d2-dl)/2

h= hypotenuse

Using Pythagorean theorem (a2 + b2 = c2)

then: h2=12+o2

0= 1.4985 in

h= 5.7005 in

sin(6/2)= o/hsin(9/2)= 0.262872

(Q/2)= 0.265997 radians

(Q/2)= 15.2 degrees(9)= 30 degrees

(6)=<45degrees | YES |

Then from:

Refl A-270.8 sm^-(I-/?2) K,

^1)="—"2^ ")=^- resistance coefficient (larger dia pipe)

Where:

KzfFl)^ K;,(Formulal)

P= ratio of diameters of the smaller to larger pipe

subscript l=smaller end; subscript 2=larger end

Calculation-NG Supply-Pressure Drop 1-Longest Run (2019-0213) Page 6 of 19

Page 7: Page 1 of 19 Contents of Calculation Page Number

letting :

then:

Calculate P:

2-12 Eqn2-28

A=

A=

p=

the constant

0.8

(areal/area2)°-5=(dl/d2)Refl

P= 0.5059

solving: K2<F1)= 2.3899 resistance coefficient (larger dia pipe)

from above: 1<2(F1)= Ki/(34

then: Ki= KZ (F1)(P4) resistance coefficient (smaller dia pipe)

solving: l<i= 0.1565 resistance coefficient (smaller dia pipe)

K Calc-Reducer 3"x2" schedule 40

Refl A-27 Equations for determining reducer& enlargement Ks

where: dl=smaller pipe ID; d2=larger pipe ID (in)

First calculate angle theta (6)

Reducer/Enlarger size:

Refl B-13/14 dl(nom)= 2 in dl- 2.067 in

Refl B-13/14 d2(nom)= 3 in d2= 3.068 in

Ref6 Chart 1= 3.5 in length (end-end)

let: 1= adjacent side

0= opposite side=(d2-dl)/2

h= hypotenuse

Using Pythagorean theorem (a + b = c )

then: h2=12+o2

0= 0.5005 in

h= 3.5356 in

sin(6/2)= o/hsin(Q/2)= 0.14156

(6/2)= 0.142037 radians

(6/2)= 8.1 degrees(9)= 16 degrees

(9)=<45degrees | YES |

Thenfrom:.__ 0.8 sin^ (l-/^) ^Refl A-27 K^Ff} = —^——:——')= '— resistance coefficient (larger dia pipe)

p* •' p4

Where:

K2(F1)= ^(Formulal)

P= ratio of diameters of the smaller to larger pipe

subscript l=smaller end; subscript 2=larger end

letting :then:

Calculate?:

2-12 Eqn2-28

solving:

A=

A=

p=

p=

K,(F1)-

the constant

0.8

(areal/area2)°'5-(dl/d2)

0.6737

0.3002

Refl

resistance coefficient (larger dia pipe)

from above: 1<2(F1)= Ki/P4

then: Ki= K; (Fl)((3'>) resistance coefficient (smaller dia pipe)

solving: Ki= 0.0619 resistance coefficient (smaller dia pipe)

Calculation-NG Supply-Pressure Drop 1-Longest Run (2019-0213) Page 7 of 19

Page 8: Page 1 of 19 Contents of Calculation Page Number

Convert calculated K^ (larger dia of reducer) to 1< relative to 6-in piping

Refl 2-9Eqn2-9 K.= ^ [(d^/dt,)4]

Where:

d= inside diameter

subscript a relates to size with reference to which all resistances are to be expressed

subscript b relates to any other size

therefore: a=6" pipe and b=3"pipe

from above: dg= 6.065 in for 6" pipe

d[,= 3.068 in for 3" pipe

K;,(Fl)=Kb= 0.3002 for 3" pipe

solving: Kg= 4.5847 for 6" pipe

Calculate Equivalent Length (Le) from K (total)

fLRefl 2-7 Eqn 2-4 K=

DResistance coefficient (ft/ft)

where:

f= friction factor (unitless)

L= length of pipe (ft)

D= internal diameter (ft)

then:

from above:

solving:

Le=L=

K=

D=

f=

Le=

KD/f154.00

0.5054

0.0225

3459

ft

ft

ft

Ktotal

Friction factor (f) check (compare calculated f to Moody chart lookup value)

Calculate friction factor f using Swamee-Jain formula:

Refl

Refl

6-2 Eqn6-7 f=0.25

£ , 5.74 \V.[lo9[3^D+-R^

Friction factor (unitless)

for: 5000< Re <3xlOA8, 10A-6< e/D <0.01

where:

e= absolute roughness (ft)

D= internal diameter (ft)

Re= reynolds number (unitless)

A-24

from above:

from above:

solving:

from above:

E=

D=

6/D=Re=

f=

0.00015

0.5054

0.000297

4.46E+04

0.0224

0.0225

ftft2.97E-04

commercial steel

meets criteria

from Moody Chart%error= -0.44% calculated factor vs chart factor

Calculation-NG Supply-Pressure Drop 1-Longest Run (2019-0213) Page 8 of 19

Page 9: Page 1 of 19 Contents of Calculation Page Number

Calculation: Natural Gas Supply-Pipe Pressure Drop Calculation 1-Longest Run

Attachment A

Ref2 Internet-Engineering Toolbox-Liquids, gases and vapors - suggested fluid velocities in pipes

http://www.engineeringtoolbox.com/ftuid-velocities-pipes-d_1885.html

Ref3.1 Project SOW

Ref3.2 NG Consumption (Handout at 12/20/18 meeting-draft)

Ref3.3 ATMOS ENERGY Gas Chemistry Report dated 12/11/18

Ref4 Sketch (20181221KLK)

Ref5 Internet-GlobalSpec-Gas Density and Specific Volume Calculator

http://www.globalspec.com/calculators/gas-density

-Printoutl (NG density at GOpsig 70F)

-Printout6 (NG density at Opsjg 60F)

Ref6 Reducer dimension chart

Ref7 Cameron Hydraulic Data - 16th Addition, 2nd Printing 1981

Page 9 of 19

Page 10: Page 1 of 19 Contents of Calculation Page Number

Fluid Velocities in Pipes Page 1 of 2

fjmeEnoineerinBm^Fome

Resources, Tools and Basic Information for Engineering and Design of Technical Applications! - adapts seamiessiy to phones, pads and desktops!

AdChofees (t> ^ pjoes ^_Eluid > Fluid in Pipe l>_EJfig§j2L^3M

TheEnaineeringTuolBoxwww.Engineerifl8TooiBox.com

i I Search - "Search is the most efficient way to navigate the Engineeiing ToolBox!"

F I uid Velocities in Pipes

Liquids, gases and vapors -su^

Thanks for the feedback! BackWe'll review this ad to improve your experience in the future.

Help us show you better ads by updating your ads settings.

Sponsored Linl

[&

Co.-^k-

Fluid

Acetylene, steel pipe

Air, 0-30 psi, steel pipe

Ammonia, liquid, steel pipe

Ammonia, gas, steel pipe

Benzene, steel pipe

Bromine, liquid, glass pipe

Bromine, gas, glass pipe

Calcium Chloride, steel pipe

Carbon Tetrachloride, steel pipe

Chlorine, liquid, steel pipe

Chlorine, gas, steel pipe

Chloroform, liquid, steel or copper pipe

Chloroform, gas, steel or copper pipe

Ethylene, gas, steel pipe

Ethylene Dibromide, glass pipe

Ethylene Dichloride, steel pipe

Ethylene Glycol, steel pipe

Hydrogen, steel pipe

HydrogenchloricAcid, liquid, rubber linedpipe

Hydrogenchloric Acid, gas, rubber lined pipe

Methyl Chloride, liquid, steel pipe

Methyl Chloride, gas, steel pipe

-9 Natural gas,, steel pipe

Oil lubricating, steel pipe

Oxygen, stainless steel

Propylene Glycol, steel pipe

Perchlorethylene, steel pipe

Steam, 0-30 psi, saturated, steel pipe

Sulfuric acid

Sulfur Dioxide, steel pipe

Styrene, steel pipe

Trichlorethylene, steel pipe

Vinyl Chloride, steel pipe

Vinylidene Chloride, steel pipe

Water, steel pipe

Velocity

(ft/min)4000400036060003602402000240360300

2000 - 5000

36020006000240360360

4000

300

4000300

40006000300

1800-4000

300360

4000 - 6000

2404000360360360360

180-480

(m/s)20201.8

301.8

1.2

101.2

1.8

1.5

10-25

1.8

10301.2

1.8

1.8

20

1.5

201.5

20301.5

9-20

1.5

1.8

20-30

1.2

201.8

1.8

1.8

1.8

0.9 - 2.4

low pressures up to 50 ps/ (3.5 bar)temperatures 50 - 100PF (10 - 3SPC)

Thanks for the feedback! BackWe'll review this ad to improve your experience in the future.

Help us show you better ads by updating your ads settings.

Go^lc

Sponsored t-inlti>

Page 10 of 19

http://www.engineeringtoolbox.com/fluid-velocities-pipes-d_l 885.html 12/1/2014

Page 11: Page 1 of 19 Contents of Calculation Page Number

PERFORMANCE STATEMENT OF WORKDESIGN OF A NATURAL GAS UNE USING EXISTING MTKOGEN LINES

1.0 Description ofServices/Introduction: Four Rivers Nuclear Partnership, LLC, hereinafter referredto as the Contractor, is soliciting a bid for subcontracted engineering services to provide completedesign of natural gas piping to support installation of new heating equipment (i.e. boilers, gasheaters, etc.) for HVAC that wiU be located at C~ 100, C-200/205 and C-300. Natural gascurrently services five (5) package boilers on the east side ofC-600, however, new HVAC servicereplacement equipment will require natural gas supply to the areas mentioned above and notcurrently serviced by natural gas. Additionally, the Contractor requires the design of the naturalgas piping to use existing nitrogen piping, where applicable. An evaluation is currently beingcompleted to verity that the existing nitrogen line is suitable for reuse. This evaluationencompasses both integrity and thickness checks of the exiting line and well as a seismicevaluation. The evaluation will provide background study for use of the existing sections of Aenitrogen line to be repurposed for use as a natural gas line and in compliance with NFPA 54,ASME B31.8, and ASME B3 IE.

The subcontracted engineering firm shall use this evaluation, along with Contractor's conceptualrouting of the new natural gas line (provided in this Performance Statement of Work, see figures 1,

2, & 3) and all applicable codes and standards to complete the Work. Currently, design isunderway for new equipment installations at the C-100 complex and gas demand and volume isknowiL Exact demands for C-200/205 and C-300 are not known at this time, but can beapproximated. The Contractor does not expect a larger demand on the natural gas supply thanwhat it is currently designed to be available. The Contractor will provide the subcontractor withthis information as the information becomes available and will expect the subcontractor to workwith other Contractor subcontractors and suppliers as needed to collect design information. At thecompletion of this design, new equipment installed at C-100, C-2007205 and C-300 shall beserviced by the new gas supply.

The vendor or supplier, hereinafter referred to as the subcontractor, shall provide all requiredengmeering disciplines, equipment, supplies, facilities, transportation, tools, materials,supervision, and other items and non-personal services necessary to perform engineering design

services for natural gas piping desigp in support ofHVAC installation projects as defined in thisPerformance Statement of Work.

General project design considerations: Existing valve replacements or removal, removal/air gapfrom existing facilities that will be non-users of the natural gas service, new pipe construction andsupports, existing pipe supports with additional restraining to design for seismic rating,underground pipe runs of new construction to C~ 100 complex, potential for gas meters design,venting for operational maintenance, additional valves for isolations and pressure relief valves,grade of existing pipe (nitrogen piping 2-inch and greater is seamless or lap welded black steel,schedule 40, ASTM A53 carbon steel), grade of new construction pipe, coating material for pipingand supports, and other necessary design requirements. " - .

General Natural Gas service consideration: Existing supply line is 6 inch, underground service tothe existing package boiler location, pressures vary from 58-67 psig, overpressure protection fromthe supplier, natural gas supply is considered dry, vent location exists at the package boilerlocation. „/

^___ ___„ -..-..... . ..^._... ,^..^—--•- .. .. ..,_,.,. ...^^-^..—.•.^--^

2.0 Specific tasks: Subcontractor shall provide:

• 60%/90%/CFC Design Packages for Contractor review and approval

o Design packages shall be prepared by subcontractor using subcontractor designprocesses and procedures. Drawings shall be generated using the Contractor'sdrawing template in AutoCAD, Design packages shall contain design drawingsand specifications that provide complete and thorough instructions for allfabrication, construction, testing procedures and acceptance requirements for acomplete, safe and acceptable installation meeting all applicable codes andstandards and Contractor and industry requirements. The 60%/90% designpackages shall include appropriate level of design detail that matches the percentcomplete progression expected as agreed to by the Contractor project team. The

2 //(ei-s. I

Page 11 of 19

7

Page 12: Page 1 of 19 Contents of Calculation Page Number

F&M r^r/y Af /2y4>/^ 5c^^

Estimates on natural gas consumption (maximum)

Natural gas cost $5.3174/mcf

BuildingC-757

C-752-A

C-600

C-100 Complex

C-200

C-300

TOTAL

Description

Gas Powered Heaters (UH-1 and UH-2)

Qty 5-107,900 BTU/hr

Qtyl-45,650 BTU/hr

Gas Powered Heaters (2 heaters)

Assume same as C-757 (until I can confirm)

Packaged Boilers (19,500 Ibs/hr steam each max, and 2 used max)

Assume 15,000 Ibs/hr max use

This may get decreased with installation at 100/200/300

New hot water boilers

New heating equipment (may be reduced by electric heat install)

New hot water boilers

BTU/hr

5395001456501

585,150

15,000,000

6,000,000

2,250,000

750,000

cfm

8.9|

0.8|

9.7|

247.5|

99.0|

37.1|

12.4|

MCF/day

415.4|

131

14

356

1435318

598

Cost/day

$$$$

$

$$$

$

686

74

1,895

75828495

3,180

MCF/month

38533

417

10,693

4,277

1,604

535

17943

DRAFT

Page 12 of 19I f?ep 5.z

"^

Page 13: Page 1 of 19 Contents of Calculation Page Number

Current Report

Device ID: 82055Location: Location of Stream 1

Stream: JOP 36

Cal Date: 12/11/2018Cal Time: 9:59:00

Signature:

Detector-t-

Comrt62409355347848286341224734163227101720040212978759171-11444.82059

0.

C1

C 02JL

C2

00 50.00 100.00 150.00 200.00 250.00BBF: 112 - C2 Device: 82055 Date: •I2.-I1/2018 09:26:04

Seconds

DetectorCount

1259565111145096333581521966710451898937087422275974643-73472

-2215870

C2-

C3 109C4

fi "PTIC5 NC5

U-+-4-L

00 50.00 100.00 150.00 200.00 250.00BBK: C3 - C6+ Device: 82055 Date: 12.>-M.'2018 09:26:04

Seconds

Components

PropaneHydrogen Sulfide

IsoButaneButane

NeoPentaneIsoPentane

Pentane

Hexane+

NitrogenMethane

Carbon DioxideEthyleneEthaneHexaneHeptaneHeptaneOctane

Nonane

Nonane'

Decans

Undecane

Ethane-

' Propane +

OxygenWater

HeliumHydrogen

&^S-ft3iU<p'AcTiOS.

RF2.745560,000002.033308.835190.000000.357391.708570.226863.353021.300051.418750.000001.027570.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000.000000 000000.00000

Contract Settings

2843190

2577139288

09576114438764

5702811169939840

10525310

1515823700000000

145211568433134

0000

Unnormalized0.084600.000000.006170.009270.000000.002080.002440.001641.76173

92.586720.404160.000004.645320.000000.000000.000000.000000 000000.000000.000000.000000,000000.000000.000000.000000.000000.0000099.50413

Normalized0:085030.000000.006200.009310.000000.002090.002460.001651.77050

93.048120.406180.000004.668470.000780.000000.000580.000280.000000.000000.000000.000000.000000.000000.000001.740670.000000.00000

101.74232

cy2.139350.000000.201700.303840.000000.08347•0.09845

0.000000.00000

939.786010.000000.0000082.617840.037160.000000.032010,017690.000000 000000.000000.000000,000000.000000.000000.000000.000000.00000

Calculated Results

.,iaui€s_.

0.023470.000000.002030.002940.000000.000760.000890.000000.1951615.804480.069450.000001.250900.000320.000000.000270.000150.000000.000000.000000.000000.000000.000000.000000.000000.000000.0000017.35082

SG0.001290.000000.000120.000190.000000.000050.000060.000000.017120.515400.006170.000000.048470.000020.000000.000020,000010.000000.000000 000000.000000.000000.000000.000000.000000.000000.00000

Pressure: 14.73000 psinTemperature: 60.00000 deg F

Humidity: 100%Contract Hour: 0

Ideal CV; 1025.31750 Btu/SCF 6'7~^ Superior Wobbe: 1340.83398 Btu/SCFSuperior CV: 1029.90649 Btu/SCF RiZ.y Inferior Wobbe: 1316.87585 Btu/SCF ^ .. . ,»Inferior CV: 1012 01764 Btu/SCF t0e+-Relative Density: 0.58999 Ibm/tU •s? ^€0-'^^- ^^

Compressibility: 0.99785 Normal Density: 0.04515 lbm/tt3Methane Number: 95.77462 Speed of Sound: 427.25092 m/s

Page 13 of 19 /jf!EE^U

Page 14: Page 1 of 19 Contents of Calculation Page Number

-iOl-loj.

,- -t?H-L+- 7%

^ M.6

t ^6L£$

^ i-^^ro.(."^^^

[//JCE^fcOff.MPFftOtJi ft^M05

^

3^ ^tU^. -fb ^ML^ ^Li^. C[\ff^j?

s

©^ ^

--77^-/A/ -TO ^"^'rWEt^ p'pi^fAf MoPf?/ ^5 roe or ^fzj^f- ^f^-L

^T 5^6 ^Pb&/^ ^^^ fk{:.£lflTA.-TO^

^) ^5a^s ^- fo^^ie ^ c^A»46,c<^,

--'-TIE Ar

'^-- - ~(€ ^17:

^£-f^

K-~f?£-fy AT (Jf^of^f ^ ^.^/T^J- C^hs^i-5

\s(S>

>^/

^<s>

^(D

i—-^-^ . c .".-.-^~

@-^-

t-2,^MS-IN Peep C-\oo

^e^N f£?Page 14 of 19

£ir/ M ^r^ (^ (p ^ tt° t'£>lULxiLer^ -^-TSP

^o/ - 6>^^'^^t^(5£)

^3 ^b ^ q^Qj^^ 0c 3 —. ^£LLS a

Z — ^U-VAU=5?p1 —^E-^MJ^^_ ^-^u.^-^I>^l^J — 'R€T>UX-&1S. (^^-s

\^ ^e^u-c.^ 3X^

^E^f ^0(g(ZZ|^L^.

^5; ^ M6°6J.^ Co^urepM^5j^=iu4 B^? oM ^^ F6txC^^

?,, f 5 ^e-n^t- ^^^ /

c-ww&iuffeep L-d) r^£> ^K.3^$^/£^Wfi^.

Page 15: Page 1 of 19 Contents of Calculation Page Number

^ https:/7ww\v.globalspec,com/calculator5/gas-dens P " A C j% Gas Density and Specific Vo... x j

Fii-'ontei TL'I:;!^ Heip

;ted Sites ^ g Toshiba App Place ^ g Web Slice Gallery ^ g WildTangent Games

lr^ iiylU.l-a-l.li.iiyy

M Engineering 360Engineering Calculator Disclaimer

Results

Reference Library ^ Search Reference Library

OBOOKNftRK gifcE3.

Below are the results of your calculation. To run a different calculation, you may change yourvalues on the form betow and resubmit-

Density:

Specific Volume;

0.256 Ib/ft

3.902 ft'/lb

Pressure: (psig)

Temperature: (F)

Compressibility Factor: (Hsia)

^Molecular Weight: (Ib/lbmol) (Typical vstues)/'**

F-»^M t-\€t.£. -.-....-- .

^.ATTAC^CP u^on-rzl^

/'

|60

i70

i1

119.5

[_Submit | [Reset]

Related Product Areasfi.-l< ^t»n<,r»r<; CU1 rwnn»n»t\i»<\

Page 15 of 19

MA-pMAL ^

'^^\%.^f?c/r/A-

j^/rffQ

Page 16: Page 1 of 19 Contents of Calculation Page Number

ps: /ww^.globa1spec.com calculators^gss-dens P ^ fi C jm Gas Density and Specific Vo... x

»ites ^ B^ Toshiba App Place v .§) '^Veb Slice GsSlery ^ jj V/ildTangent Games ^

r^ ••--rt^'c-ij tn 5t£.L <^'-i:-£...-t!OS:C

Engineering 360Csteutetor

Pressure i.cyss in

Straight Gas Lines

Catcutetor

Pressure Loss m

SSra^ht Uquid LinesCalcutetor

Setf-Ventiing Row Line

Calculator

Tanks & Vessels

Electrical Cafcuiators

UW~TOP

calculations is:

PV = nZRT

This equation is sometimes reThis caiculator has been scale

weights for acetylene; air, amrhydrogen, natural gas» nitrogeEngineering Calculator Disclai

Pressure: (psig)

Temperature: (F)

Compresstbility Factor (HC^)

Molecular Weight (INIbmd)

Reference Library ^ Search Reference Library

Typical Molecular Weight Values

ACETfLENE

AIR

AMMONIA

ARGON

CARBONDIOXIDE

CARBONMONOXIDE

CHLORINE

HYDROGEN

26ib/lbmol

29Sb/lbmol

17Sb/lbmol

39.9Ib/Ibmo!

44Ib/lbmol

28Ib/Sbmol

70.9

!b/ibmol

2Sb/lbmol

NITROGEN28ib/lbmol

^D^^\V^lnfi&

Page 17: Page 1 of 19 Contents of Calculation Page Number

Gas Density and Specific Volume Calculator at GlobalSpec Page 1 of 2

Reference Library Search Reference Library Subrr

TOSH IBA Toshiba Motor Control Products - ® EBVE!ektronik>;

Make Your Motor SmarterWebinar On-Demand Until April 22nd

HOME REF ERENCE UBRARY CALCULATORS GAS DENSIPC AND SPECIFIC VOLUME CALCULATOR

Other Calculatore

S General Engineering

Q Flow Control & FluidTransfer

Compressible Flow

Pressure Loss

Calculator

Loss In Fluid Lines

Calculator

Open Channel Flow

Calculator

Pressure Loss in

Straight Gas Lines

Calculator

Pressure Loss in

Straight Liquid Lines

Calculator

Sdf-Venting Row Line

Calculator

a Tanks & Vessels

B Electrical Calculators

Gas Density and Specific Volume CalculatorThe Gas Density and Specific Volume Calculator calculates the density and specific volume ofgas based on a modified version of the Ideal Gas Law;

PV=nRT where:P is the absolute pressure of the gas,V is the volume of the gas,n is the number of moles of gas,T is the absolute temperature of the gas,R is the universal gas constant

The Ideal Gas Law assumes the existence of a gas with no volume and no interactions withother molecules. Therefore, the Compressibility Factor (Z) can be used for a slight alteration tothe ideal gas law to account for real gas behavior. Therefore the equation used for thesecalculations is:

PV = fiZRT where:P is the absolute pressure of the gas,V is the volume of the gas,n is the number of moles of gas,T is the absolute temperature of the gas,R is the universal gas constantZ is the gas compressibility factor

This equation is sometimes referred to as the Non-ldeal Gas LawThis calculator has been scaled to use English units for temperature and pressure. Molecularweights for acetylene, air, ammonia, argon, carbon diou'de, carbon monoxide, chlorine,hydrogen, natural gas, nitrogen, oxygen, propane and steam are all provided.Engineering Calculator Disclaimer

.OBOOKMRRK B " B.,Results

Toshiba MotorControl Products -

Make Your Motor SmarterWebinar On-Demand

Until April 22nd

TOSH I BA © EBVEIektronik

Below are the results of your calculation. To run a different calculation, you may change yourvalues on the form belcw and resubmit.

Density:

Specific Volume:

0.051 Ib/ft'

19.452 ft3/lb

Pressure: (psig)

Temperature: (F)

Compressibility Factor (Help)

Molecular Weight; (Ib/lbmol) (Typical values)

p

^0-_

'1

[fsTif

I Submit | j Reset |

Related Product Areas

Gas SenSOrS (54< companies)

Gas sensors interact with a gas to initiate the measurement of its concentration. The sensorthen provides output to an instrument to display the measurements- Search By Specification |Leam More about Gas Sensors

Gas Instruments (927 companies)

Gas instruments detect, monitor or analyze gases present in an environment. Search BySpecification | Learn More aboul Gas Instruments

Industrial Gases (324 companies)

Industrial gases are pure elements, molecular compounds or mixtures that are gaseous orvaporous at room temperature and pressure. Search By Specification | Learn More aboutIndustrial Gases

Welding Gases and Thermal Process Gases (124 companies)

Welding gases and thermal process gases are specialized gases for welding, cutting or otherthermal processing applications. Search By Specification | Learn More about Welding Gasesand Thermal Process Gases

Electronic and Semiconductor Gases (M companies/

<7£f5

Page 17 of 19

https://www.globalspec.com/calculators/gas-density

f^i»4-ToaT"<p

2/13/2019

Page 18: Page 1 of 19 Contents of Calculation Page Number

FITTINGS

*o IOKC n*DWtldttl.

NFS

1<23/4

1r/4r/22

2'k

33*/24568101214161823243036®)42(D|

PipeO.D.

.8401.0501.3151.6601.9002.3752.87S3.5004.0004.5005.5636.6258.62510.75012.75014.00016.00018.00020.00024.00030.00036.00042.000

~Qu-s

w.

.OE

.06

.1C

.1C

.1C

.1C

.12

.12

.12

.12

,12

.12

.V

.16

.1£

.2E

,2£

3S..2C

.2£

.31

.31

w nEouci»«cI II WtldEll

iCHI20

250?50250312312312375i75sOO500

SCH30

.277

.307

.330

.375

.375.438.500.562.625.625

-@-

STD

.109

.113

.133

.140

.145

.154

.203216.226

237258-280.322.365.375.375.375.375.375.375.375.375.375

SCH40

.109

.113

.133

.140

.145

.154203.216.??fi

.237

.258-280.322.365.406.438.soo.562,594.668

.750

WAUL THICKNESS

SCHGO

.406

.500

.562

.594

.656

.750

.812

.969

.147

.154

.179

.191

.200218.276.300.318.337.375.432.500.500.500.500.500.500.500.500.500.500.500

SCHso

.147

.154

.179

.191200,218276.300.318.337.375.432.500.594.688.750.844.9381.0311.219

ONC •AOIUS*»Ktt-i

SCH100

.594

.719

.844

.9381.0311.1561.2811.531

SCH120

.438

.500-562.719.8441.0001.0941.2191.3751.5001.812

SCH140

.8121.0001.1251.2501.4381.5621.7502.062

SCH160

..188

.219250.250.281.344.375.438

.531

.625

.719

.9061.1251.3121,4061.5941.7811.9692.344

XXStg

.294.308.358.382.400.436.552.600.636

.674

.750

.864

.S751.0001.000

A

1'/2

r/a11/217/.21/,333/44'/25V<67',291215182124273036455463

II

B

s/«7/,6

7/»11V.13/.13/4221/42*/23',.33/<

56'/47'/283/<10

m<w,15

'2221/4

23

IMOIImeWrldCLt.

K

17/a1"/,«

y/i623/<3V,4'/,e53/,6

6V<7V.i

8'/<105/,,

m,6165/,c203/iWtt283236434860

D

111/<r/222'/23

'2

4568101214

Page 19: Page 1 of 19 Contents of Calculation Page Number

Note: Fittings are standard with full openings.

Fittlnfl

l."<-':' T'. '7v..fi'^:vr'xfn'r~°^.

";=^-"s^,a?5B5S*t>_fSiisnsss

^<0

Butterfly Valve

-Jpd̂

-^rir-Plug Valve stralghtway

^Sr"^

^rPlug Valve 3-way thru-fto

Plug Valve branch-flo

Standard albow

longradiusso"

UD

^,(8"<t+

(fl^

30

Nominal pipe size

m 2t/z-3 8-10 | 12-16 | 18-24

K value

^

0.81

2.43 2.25

0.40

0.41

0.35

1.89

0.86

0.30

0.81

1.62

0.29

0.31

0.51

0.27

0.68

0.27

0.45

0.63

0.25

0.42

1.26

0.22

0.23

0.39

1.17

0.39

0.21

?w

I3 "?2 ?• 3*® 0 2:

I?!-I s &Iw

©(ft

w S'S 35" "O

I?7S

Mlo I '2

?a:

c<pA

(0

0,30

0.19

0.19

@s3Di?0

IIIx

s?\

Calculated from data in Cram Co; Technical Paper No. 410.

Note: Fittings are standard with full openings.

w

Fitting

Closa Return Bend

r.\Standard Tee

-J L,

90° Bends. Pipe bends, Hangedelbows, butt welded elbows

A,'r/

dJ "

Mltrs Bends

—d-

^^^"

Type ofbend

thru flo

thru branch

r/d= 1

r/d= 2

r/d- 3

r/d= 4

r/d= 6

r;d= 8

r/d=10

r/d == 12

r/d = 14

r/d = 16

r;d=-18

r/d == 20

a » 15°

a « 30°

a =45°

a =60°

u=7S°

a =90°

L/D

50

20

60

20

12

1214

17

24

30

34

38

42

46

so

2

4

8

15

25

40

60

Nominal pipe size

'',2

1.35

0.54

1.62

0.54

0.32

0.32

0.38

0,48

0.65

0.81

0.92

1.03

1.13

1.24

1.35

0.05

0.11

0.22

0.41

o.es

1.09

1.62

V4

1.25

0,50

1.50

0.50

0.30

0,30

0.35

0.43

0.60

0.75

0.85

0.95

1.05

1.15

1.25

0.05

0.-10

0.20

0.38

0.63

1.00

1.50

1

1.15

0,46

1.38

0.48

02S

0.28

0.32

0.39

0,55

0.69

0.78

0.87

0.97

1.06

1.15

0.05

0,09

0.18

0.35

0.58

0.92

1,38

iv<

1.10

0.44

1.32

0.44

0.26

0.26

0.31

0.37

0.63

0.66

0.75

0.84

0-92

1.01

1.10

0.04

0.09

0.18

0.33

0.55

0.88

1.32

11A

1.05

0.42

1.26

0.42

0.25

0.25

0.29

0.36

0,50

0.63

0.71

0.80

0.88

0.97

1.05

0,04

0,08

0.17

0.32

0.53

0.84

1.26

2

0.95

0.38

1.14

0.38

0.23

0.23

0.27

•0.32

0.46

0.57

0.85

0.72

0.80

0.87

0.95

0.04

0.08

0.15

.0.29

0.48

0.76

1.14

2^-3

value

0.90

0.36

1.08

0.36

0.22

0.22

0.25

0.31

0.43

0.54

0.61

0.68

0.76

0.83

0.90

0.04

0.07

0.14

0.27

0.45

0.72

i.oa

4

0,85

0.34

1.02

0.34

0.20

0.20

0.24

0.29

0.41

0.51

0.58

0.65

0.71

0.78

0.85

0.03

0.07

0.14

0.26

0.43

0.68

1.02

6

0.75

0.30

0.90

0.30

0.18

0.18

0.21

0.26

0.36

0.45

0.51

0.57

0.63

0.69

0.75

0.03

0.06

0.12

0.23

0.38

0.60

0.90

8-10

0,70

0.28

0.84

0.28

0.17

0.17

0.20

0.24

0.34

0.42

0.48

0.53

0.59

0.64

0.70

0.03

0.06

0.11

0,21

0.35

0.56

0.84

12-16

0.65

0.26

0.78

0,26

0.16

0.16

0.18

0.22

0.31

0.39

0.44

0.49

0.55

0.60

0.65

0.03

0,05

0,10

0.20

0.33

0.52

0.78

18-24

0.60

0.24

0.72

0.24

0.14

0.14

0.17

0.20

0.29

0.36

0.41

0.46

0.50

0.55

.0.60

0.02

0.10

0.18

0.30

0.48

0.72

r»3.

S ipmiQ.<Ba

^cs303aa=F

11^

<s?b

03r-0w<fl®w

35"0<t»"n

?3(0co

w. i

0§?*5'

IA

I!sn

§

Im3>-a

nm

@01Calculated from data in Crane Co. Technical Paper No, 410,

Page 19 of 19 \^Yrl ,