PACS SVR3 8/9 Nov 2007
System Testing 1
Tests on Satellite Level
H. Feuchtgruber
PACS SVR3 8/9 Nov 2007
System Testing 2
PACS SVR3 8/9 Nov 2007
System Testing 3
Layout of Integration
Facility at EADSAstrium GmbH Friedrichshafen
CCS
PACS SVR3 8/9 Nov 2007
System Testing 4
Instrument EGSE Room during IST@ASED
HIFI SPIRE
PACS
S2K
QLACUS
Remote Control for Air-conditioning
Portable Phone
PACS SVR3 8/9 Nov 2007
System Testing 5
Schedule
PACS SVR3 8/9 Nov 2007
System Testing 6
System Test Elements (1)
• SFT warm (1st run on 19-Oct) (PACS-ME-TP-017) 1-2x• SFT HeI & HeII (PACS-ME-TP-017) 5-7x• IST program incl. RMS (PACS-ME-TP-021)• TB/TV Tests (PACS-ME-TP-021)
X
PACS SVR3 8/9 Nov 2007
System Testing 7
System Test Elements (2)
• SVT-1 System Validation Test (PT-HMOC-OPS-PL-6204-OPS-OAH):“The purpose of the System Validation Tests is to test and validate the external interfaces from the MOC to the satellite, in closed loop, and to validate the satellite TM and TC database definition. The contents of the SVTs are designed to test these interfaces and the database with an increasing level of realism and complexity from one SVT to the next, making use of the satellite nominal and contingency flight operations procedures in the performance of the tests. Replacement or additional SVT specific procedures may also be required.” consists for PACS at present of all manual procedures from the IUM, however it is unlikely that the “to-be-translated” mechanism and SFT procedures can make it into SVT-1(is expected to be run be run at HeI, will require ICC participation)
PACS SVR3 8/9 Nov 2007
System Testing 8
System Test Elements (3)
• EMC Tests (PACS-ME-TP-032)• SOVT-1 System Operational Validation Test (PT-CMOC-OPS-PL-
6212-OPS-OAH, draft 0.1) :This will be a spacecraft End-to-End test of routine operations. It will involve the entire PACS ICC. Observations will be similar as for RMS test, but extended by selected AORs (RV & BA). Requires ICC@MOC and ICC@MPE.
MTL-OD Validity Upload DTCP Contents
MTL-0 D1/06:00 - D1/18:00
DTCP-0(D1/06:00)
Leading to DTCP-1
MTL-1 D1/18:00 - D2/18:00
DTCP-1(D1/12:00)
PACS photometer (50%) and spectrometer (50%)
MTL-2 D2/18:00 - D3/18:00
DTCP-1(D1/12:00)
HIFI operations
MTL-3 D3/18:00 - D4/18:00
DTCP-2(D2/12:00)
SPIRE/ PACS scenarios (PACS photometer, SPIRE photometer, parallel mode)
MTL-4 D4/18:00 - D5/18:00
DTCP-3(D3/12:00)
SPIRE/ PACS scenarios (PACS photometer, SPIRE photometer, parallel mode)
PACS SVR3 8/9 Nov 2007
System Testing 9
System Test Elements (4)
• SVT-2 will be similar to SVT-1, but with lessons learnt, possible extensions and/or new procedures: Emphasis on “Extended Instrument Interface Validation and Extended Database Validation”
• SOVT-2 will include eventually also more non-routine operations and eventually also more delivery processes.
• Launch Campaign content and PACS contribution TBD (i.e. just SFT like or more IST like ?)