18
PACMAN Simulation II

PACMAN Simulation 2 Report

Embed Size (px)

Citation preview

  1. 1. PACMAN Simulation II
  2. 2. PACMAN Chief Engineer Peiyi Huo Chief Operations Manager Chirag Agarwal Chief Architect Abide Masaraure Team Strategy: Identify the enemies, befriend them and then stealthily attack .
  3. 3. Overview 1 & 2 Choosing the Contract Ordering machines Choosing the safety stock Selecting the reorder point Selecting the order quantity I and II Maintaining contracts The unmanned spacecraft Lessons Learned Acknowledgment and thanks Agenda
  4. 4. This was an exciting and a highly contested simulation Our goals were to: increase the team revenue with minimal risk increase our team position in the overall standings learn more about purchasing, lot sizing and how to maintain supplier contracts Overview 1 gg pacman maniacs ads123 kgs ideaco csuite Closing cash balance $2 406 931
  5. 5. Overview 2- Changes Summary
  6. 6. Switched to contact 2 on Day 54 Contract 2 offered better revenues compared to contract 1 Choosing the contracts
  7. 7. Machines were ordered the same day we entered into Contract 2 We had enough cash to purchase the machines One more machine was added to each of the three stations Ordering machines
  8. 8. Safety Stock (Max Daily Usage Avg Daily Usage) Lead Time* Service Factor Used the safety stock to calculate the optimal order quantity Determining safety stock
  9. 9. Point was changed on day 55 Job queues were increasing because the inventory was out of stock Choosing the reorder point
  10. 10. Calculated the optimal order quantity to minimize costs On day 63 order quantity was changed to 14400 kits by doubling current order quantity Selecting the order quantity I
  11. 11. Selecting the order quantity II The optimal solution is was to order for 3 times in the next 81 days. So the order quantity was be changed to 12.5*27=337.5338batches=20280 kits
  12. 12. Utilization station under each station was well under 0.5 This enabled us to choose contract three which paid $1250 per job Contracts were interchanged between 2 and 3 according to the changes in queue sizes through the rest of the simulation Maintaining the contracts
  13. 13. Ceased to use contract 1 and 2 after day 132 Revenue averaged 1200 from day 80 using contract three Revenue Analysis
  14. 14. On day 70 scheduling rule of station 2 was set to priority step 4 This was due to a number of jobs queuing on station 1 2 days later priority was changed back to FIFO and the queue size of station 1 was well close to 0.1 in the next coming days Scheduling Analysis Station 2 QueueStation 1 Queue Station 3 Queue
  15. 15. Last 50 days in space - Getting the right fuel The unmanned Spacecraft
  16. 16. Accurately forecasting demand Calculating the the reorder point Determining the reorder quantity Minimizing inventory costs Maintaining supplier and service contracts Lessons Learned
  17. 17. Thanks to the Professor for her efforts in delivering the course. Thanks to the PACMAN team for your hard work. To the MBE class. It was fun to be in the program with you. And thumbs up to our enemy, team gg. Acknowledgment and thanks
  18. 18. Question and Answer Session