Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
PACIFIC AIR FORCES REGIONAL SUPPORT CENTER JOINT BASE ELMENDORF-RICHARDSON, ALASKA PCB-CONTAMINATED SOIL REMOVAL ACTION 2015 INTERIM DATA REPORT SUMMARY
PORT HEIDEN, ALASKA FINAL APRIL 2016
PACIFIC AIR FORCES REGIONAL SUPPORT CENTER JOINT BASE ELMENDORF-RICHARDSON, ALASKA PCB-CONTAMINATED SOIL REMOVAL ACTION 2015 INTERIM DATA REPORT SUMMARY PORT HEIDEN, ALASKA FINAL APRIL 2016
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx i GOV-J07-05DK4801-J22-0005 FINAL 4/28/16
TABLE OF CONTENTS SECTION PAGE
ACRONYMS AND ABBREVIATIONS ..................................................................................iii
1.0 PROJECT OVERVIEW .................................................................................................1-1
2.0 2015 FIELDWORK .......................................................................................................2-1
2.1 EXCAVATION ACTIVITIES ..............................................................................2-2
2.1.1 Radio Relay Station ...............................................................................2-2
2.1.2 Drum Storage Area ................................................................................2-3
2.1.3 Torn and Spilled Bag .............................................................................2-3
2.1.4 Quantities ...............................................................................................2-4
2.1.5 Excavated Soil Transportation and Disposal .........................................2-4
2.2 STORAGE AREA 1 FINAL DECOMMISSIONING ..........................................2-6
2.3 ANALYTICAL SAMPLING ...............................................................................2-6
2.3.1 Soil PCB Analysis ..................................................................................2-7
2.3.2 Equipment Decontamination Confirmation Samples .............................2-8
2.3.3 Soil Lead Analyses .................................................................................2-9
2.3.4 Soil VOC and GRO Analysis .................................................................2-9
2.4 ASBESTOS SAMPLING ...................................................................................2-10
2.5 WINTER STORAGE OF EXCAVATED MATERIALS ..................................2-11
3.0 CONCLUSION AND FUTURE ACTIVITIES .............................................................3-1
4.0 REFERENCES ...............................................................................................................4-1
TABLES
Table 2-1 PCB-Contaminated Soil Loading, Transport, and Disposal Totals for 2015 .. 2-6
Table 2-2 Soil Samples Collected and Submitted for PCB Analysis in 2015 ................. 2-8
Table 2-3 Asbestos Samples Collected and Submitted for Analysis in 2015 ............... 2-11
Table 2-4 LiftPacs Staged Onsite Over Winter 2015-2016 ........................................... 2-12
TABLE OF CONTENTS (Continued) SECTION PAGE
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx ii GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
APPENDICES Appendix A Figures
Appendix B Photograph Log
Appendix C Waste Documentation
Appendix D Data Quality Assessment
Appendix E Asbestos Removal Action Report and Asbestos Sample Summary
Appendix F Estimate of Remaining Quantities of PCB-Contaminated Soil
Appendix G ADEC Approval Letter
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx iii GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
ACRONYMS AND ABBREVIATIONS
ACM asbestos-containing material
ADEC Alaska Department of Environmental Conservation
AFCEC Air Force Civil Engineering Center
bags LiftPacs, or an equivalent containment device
CERCLA Comprehensive Environmental Response, Compensation, and Liability Act
cy cubic yards
DQO data quality objective
DSA drum storage area
ELM ELM Solutions Corporation
EMI Environmental Management, Inc.
GRO gasoline-range organics
Jacobs Jacobs Engineering Group Inc.
KEMRON KEMRON Environmental Services, Inc.
m2 square meters
mg/kg milligrams per kilogram
MS/MSD matrix spike/matrix spike duplicate
NTCRA non-time-critical removal action
PCB polychlorinated biphenyl
ppm parts per million
RCRA Resource Conservation and Recovery Act
RRS Radio Relay Station
SA1 Storage Area 1
SRA2 Soil Removal Area 2
TCB trichlorobenzene
TCE trichloroethene
TCLP toxicity characteristic leaching protocol
TSCA Toxic Substances Control Act
USACE U.S. Army Corps of Engineers
USAF U.S. Air Force
VOC volatile organic carbon
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx iv GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
(intentionally blank)
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 1-1 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
1.0 PROJECT OVERVIEW
This 2015 interim data report summary describes the current status of the removal action of
polychlorinated biphenyl (PCB)-contaminated soil at the former U.S. Air Force (USAF)
Radio Relay Station (RRS) at Port Heiden, Alaska. Removal of PCB-contaminated soil was
initiated in 2009 as part of the Record of Decision for Port Heiden Radio Relay Station
(USAF 2009).
The work described in this report was conducted for the Air Force Civil Engineer Center
(AFCEC) under the U.S. Army Corps of Engineers (USACE), Alaska District Worldwide
Environmental Remediation Services Contract No. W912DY-10-D-0027, Task Order ZJ01.
The work was performed in accordance with the requirements of the Alaska Department of
Environmental Conservation (ADEC), Alaska Administrative Code, Title 18, Section 75.360
(ADEC 2016) and the Comprehensive Environmental Response, Compensation, and Liability
Act (CERCLA). Other regulatory considerations for the project include the Resources
Conservation and Recovery Act (RCRA) and the Occupational Safety and Health
Administration asbestos regulations, as laid out in the Code of Federal Regulations Title 29,
sections 1910 and 1926.
This work was conducted in accordance with the 2013 work plan (USAF 2013), the 2014
sampling and analysis plan (USAF 2014), and the 2015 drum storage area (DSA) work plan
addendum (USAF 2015). The work was conducted by KEMRON Environmental Services,
Inc. (KEMRON), with support from Jacobs Engineering Group Inc. (Jacobs) and ELM
Solutions Corporation (ELM). Asbestos removal at the DSA was conducted according to the
2015 asbestos removal plan prepared by Environmental Management, Inc. (EMI) (EMI 2015).
Excavations of PCB-contaminated soil began in May 2015 at Soil Removal Area 2 (SRA2),
the southern portion of the former RRS site. Maps of the site layout are presented in
Figures A-1 and A-2. Contaminated soil was excavated from locations where PCB
concentrations were greater than 1 part per million (ppm), and was loaded directly into
LiftPacs (also known as Super Sacks), or equivalent containment devices (referred to
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 1-2 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
throughout this document as bags). Filled bags were stored on a liner adjacent to the work
area to await transport and disposal. All bags that had been filled prior to 1 July 2015,
including bags remaining from 2013 and 2014 activities, were transported to, and staged at,
the barge landing at Port Heiden by mid-July.
Excavation of the soil and liner covering the DSA (39.9 tons) was conducted prior to the
hauling operation and was staged at the barge landing. Excavations below the liner at the
DSA began after completing these hauling operations. While awaiting excavation
confirmation samples from the DSA, excavations intermittently continued at the SRA2. A
second hauling operation was performed in mid-August to stage the excavated additional
SRA2 soil at the barge landing in preparation for arrival of the barge. All DSA material
excavated after the initial 39.9 tons remains staged onsite pending final disposal plans.
Previous reports indicated the potential presence of asbestos-containing material (ACM) in
the area. During the initial excavation of the DSA, suspected ACM was discovered, and
excavation activities were halted. EMI conducted the asbestos removal from the DSA area
from 16 through 23 September, 2015.
In total, 1,787 bags of PCB-contaminated soil with weights measured onsite with a wheel
loader’s integrated scale (hereafter referred to as estimated weights) totaling 12,659.6 tons
were generated during the 2015 field effort. A total of 1,632 bags with a certified weight of
11,822.36 tons were transported via truck, barge, and rail to the final disposal facility in
Arlington, Oregon. There are 636 bags with an estimated total weight of 4,203 tons remaining
at Port Heiden. These bags will be transported and disposed of as part of the 2016 field
effort. This interim report is organized as follows:
• Section 1.0 summarizes the project and progress made in 2015.
• Section 2.0 describes the fieldwork and analytical sampling results for PCB-contaminated soil and ACM.
• Section 3.0 summarizes the conclusions from the 2015 efforts and presents recommendations for future activities.
• Section 4.0 lists the supporting documents used in this report.
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 1-3 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
In addition, the following appendices have been provided to supplement the information
presented in this report:
• Appendix A presents project figures. The figures show the grids that have been delineated, characterized, remediated, and targeted for future sampling. Other figures include the locations and results of asbestos sampling, the locations of overwintered bags, and maps of the site layout.
• Appendix B presents photographs of project activities.
• Appendix C presents waste documentation, including certificates of disposal, bag totals, and certified weight totals for all PCB-contaminated soil disposed of in 2015.
• Appendix D presents the data quality assessment, and associated ADEC Laboratory Data Review Checklists.
• Appendix E presents the asbestos removal action report, prepared by EMI, and asbestos sampling summary and results.
• Appendix F presents an estimate of the remaining quantities of PCB-contaminated soil, including a figure, which presents the locations and estimated quantities of PCB-contaminated soil at various areas at Port Heiden.
• Appendix G presents the ADEC approval letter for the draft report.
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 1-4 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
(intentionally blank)
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-1 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
2.0 2015 FIELDWORK
From 14 May to 29 September 2015, Jacobs directed the excavation and removal of an
estimated 12,260 tons of PCB-contaminated soil from the SRA2 in the southern portion of the
former RRS site, from Access Road, from Site Road and Tundra Sections 89 through 92, and
from the DSA (Figure A-2). This soil was excavated directly from targeted grid cells into 8.5
cubic yard (cy) bags. In total, 1,787 bags were generated. The contaminated soil was
characterized under the Toxic Substances Control Act (TSCA) (Title 15 of the U.S. Code,
§2605) as either TSCA (PCB concentrations greater than or equal to 50 milligrams per
kilogram [mg/kg]) or non-TSCA (PCB concentrations less than 50 mg/kg, but greater than or
equal to 1 mg/kg). TSCA bag labels were denoted with a “T” and staged separately from non-
TSCA bags. The TSCA bags contained an extra plastic liner, which was manually placed
inside the bag as a secondary containment barrier.
During the 2015 field season, contaminated soil was transported offsite or staged onsite for
offsite transport and disposal in 2016 as follows:
• A total of 317 bags of TSCA soil, with a certified total weight of 2,145.78 tons, were transferred to barges contracted by ELM, and transported to Chemical Waste Management in Arlington, Oregon for disposal.
• A total of 1,315 bags containing non-TSCA soil with a certified total weight of 9,676.58 tons were transferred to barges contracted by ELM and transported to Columbia Ridge Landfill in Arlington, Oregon. Included in this total were six bags, weighing 10.5 tons, of uncontaminated waste (bags used to build the barge ramp) disposed of by ELM, and approximately 27.9 tons of mistakenly excavated non-contaminated soil, disposed of by Jacobs, which were also transported to Columbia Ridge Landfill (see Section 2.1.1 for additional information).
• A total of 596 bags of non-TSCA soil (weighing an estimated 3,988.2 tons), 35 bags of TSCA soil (approximately 199.8 tons), and all DSA debris were staged onsite for disposal during the 2016 field season. In addition, five bags of dry-decontaminated and crushed barrels removed from the DSA were staged in cells at the DSA that have been confirmed as below cleanup. Five bags of uncontaminated soil and liners (15.1 tons) generated from the decommissioning of Storage Area 1 (SA1) were staged onsite, as well.
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-2 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
2.1 EXCAVATION ACTIVITIES
During 2015 field activities, Jacobs excavated contaminated soil from four areas within the
RRS: SRA2, Access Road, Site Road and Tundra Sections 89-92 and the DSA (Figure A-2).
The DSA is discussed separately in Section 2.1.2 due to the collocated debris and unique
excavation approach. Grids targeted for excavation were selected based on laboratory
sampling results from current and previous field seasons, and excavation instructions were
displayed graphically through use of ArcGIS. Excavation locations and depths for TSCA and
non-TSCA soils are shown on Figures A-3 through A-17 for 2016 removal activities.
Excavation instructions are updated in real time as new analytical results are received.
2.1.1 Radio Relay Station
At the RRS, Jacobs filled 8.5 cy bags directly from excavations of targeted grids utilizing bag
frames positioned adjacent to the active excavation. Bags were manually mounted on the
frames at a central location before being transported to the active excavation site by a loader.
An additional plastic liner was manually installed into bags intended to contain TSCA soil.
Bags were then filled by an excavator, transported back to the central location, unhooked
from the frames, and sealed. Once sealed, the bags were moved to a lined staging area using a
loader and transport rack. RRS area excavations occurred south of Site Road in road sections
89 through 92, along Access Road, and in SRA2 (Figure A-2). The filled bags were staged
and labeled with the general excavation location (e.g., SRA2, DSA), a bag identification
number (with an added “T” for TSCA bags), the weight of the bag, the date of generation, and
the site and owner information. Bags were later transported from the staging areas by semi-
truck and trailer to the barge landing area and then transferred to ELM for disposal.
In early June 2015, approximately 27.9 tons of clean soil was erroneously excavated from
Tundra Section 91 and loaded into bags with contaminated soil. The contaminated and
uncontaminated soil could not be separated. This mistakenly excavated soil was disposed of at
Jacobs’ expense and is not included in the quantities displayed in Table 2-1 below.
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-3 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
2.1.2 Drum Storage Area
Prior to excavations beginning at the DSA, a geotextile fabric covering the area was removed
and disposed of along with some of the soil that had been used to hold the liner down. Soil
that could be removed without disturbing the liner was placed into two suspected clean
stockpiles, and each was sampled according to Table 2A of the ADEC Draft Field Sampling
Guidance (ADEC 2010). All samples from the first stockpile were below cleanup levels, and
the soil from this stockpile was subsequently used for backfill elsewhere on the site. Both
samples collected from the second stockpile were above cleanup levels and this soil was
bagged for disposal.
Due the presence of metallic debris, potentially pressurized gas cylinders, and potential ACM,
additional care was required when excavating at the DSA. Magnetometric screening and hand
digging were performed, and lifts of approximately 2 inches were scraped with the excavator
bucket. In addition, bags used for soil excavated at the DSA had a pre-installed felt liner to
prevent tears and punctures from metallic debris. Large metallic debris, 12 depressurized gas
cylinders, creosote wooden beams, and approximately 100 electronic components including
batteries and transformers were dry-decontaminated and staged onsite. Approximately 100
empty drums were dry-decontaminated, crushed, and stored in five bags separate from the
contaminated soil. Five small plastic jugs and glass bottles with unknown liquid contents were
found during the DSA excavations. The bottles were placed in a 10-gallon overpack drum and
staged onsite. Complete characterization and final disposition of DSA debris is yet to be
determined.
2.1.3 Torn and Spilled Bag
During hauling activities, on 25 June, one previously staged non-TSCA bag ripped as it was
being lifted and spilled its contents onto a liner in the bag storage area at the RRS site. A
portion of the spilled material was observed falling into a berm of clean soil used to hold
down the edge of the liner. The spilled material and torn bag were loaded into a new bag, and
as a precaution, approximately 1,500 pounds of soil were removed from the berm where
mixing could have occurred. Three samples were collected from the area to ensure all
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-4 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
contaminated material had been removed. Two of the three results were nondetect for PCBs
and one result was 0.0564 mg/kg (below the cleanup level of 1 mg/kg).
2.1.4 Quantities
The weight of each bag was measured onsite using uncertified scales integrated into the
loaders. The weight of the bags measured while on site was considered an estimate, and
certified scales at the disposal facilities were used to provide the actual weight. During the
2015 field effort, 1,435 bags of non-TSCA-contaminated material was excavated, weighing
an estimated 10,324.6 tons, and 352 bags of TSCA-contaminated material was excavated,
weighing an estimated 2,335.0 tons.
During barge loading, 1,312 non-TSCA bags and 317 TSCA bags were recorded as loaded.
However, upon arrival in Seattle, 1,315 non-TSCA bags and 317 TSCA bags were unloaded,
weighed, and disposed of. The discrepancy in non-TSCA bags is most likely due to a clerical
error made during loading. The estimated weight for the 1,312 non-TSCA bags that were
recorded as shipped was 10,042.4 tons and the certified weight for the 1,315 bags that arrived
was 9,676.58 tons. The variance on the uncertified site scales and the certified scales for the
non-TSCA material was 365.82 tons lighter, or 3.6 percent difference. However, because of
the disparity in bag counts, the exact percentage could not be calculated. The 317 bags of
TSCA material were estimated at the site to weigh 2,135.3 tons. The weight recorded by
certified scales was 2145.78, heavier by 10.48 tons, or 0.5 percent more, at the certified
scales. The overall variance between the calculated and certified weights of TSCA and non-
TSCA soil in 2015 was 2.92 percent lighter than the estimated weight. Table 2-1 presents the
PCB-contaminated soil loading, transport, and disposal totals for 2015.
2.1.5 Excavated Soil Transportation and Disposal
Two barges belonging to Boyer Towing transported PCB-contaminated waste from Port
Heiden, Alaska in 2015. The first barge, Bainbridge, was loaded with 837 bags containing a
certified weight of 6,206.83 tons of non-TSCA soil from 1 through 4 September 2015. The
second barge, Klinkwan, was loaded from 5 through 9 September 2015 with 478 bags
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-5 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
containing non-TSCA soil with a certified weight of 3,469.75 tons (including six bags
containing 10.5 tons of uncontaminated waste that was used for the construction of the barge
ramp), and 317 bags of TSCA hazardous soil with a certified weight of 2,145.78 tons. The six
bags of uncontaminated waste were disposed of at the expense of ELM. After loading was
complete, the barges travelled to Seattle, Washington.
All bags containing non-TSCA soil were transferred to rail cars in Seattle and transported to
the final disposal facility at Columbia Ridge Landfill in Arlington, Oregon. Weights for the
six bags of barge landing construction materials were included in the waste tracking
documents in Appendix C; however, the estimated weights for these bags (10.5 tons) were
omitted from the calculations of waste generated and waste disposed presented in Table 2-1.
Weights and bag numbers from 2013 and 2014 are included in Table 2-1 for reference. Bags
containing TSCA hazardous soil were loaded into R Transport intermodal containers and
transported via intermodal rail cars to the final disposal facility at Chemical Waste
Management of the Northwest in Arlington, Oregon. Signed certificates of disposal were
issued for the TSCA-generated waste for disposal dates between 13 October and 28 October
2015 (Appendix C).
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-6 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
Table 2-1 PCB-Contaminated Soil Loading, Transport, and Disposal Totals for 2015
Year of Generation
PCB Soil TSCA/Non-TSCA
Total Bags
Generated
Total Estimated
Weight Generated
(tons)
Total Bags Transferred1
Total Estimated
Weight Transferred
(tons)
Total Certified Weight
Disposed (tons)
2013 non-TSCA 1,542 12,089 1,347 10,557 10,422.73 TSCA hazardous 82 334 82 334 348.15
2014 non-TSCA 1,366 10,403.8 1,096 8,228.8 8,718.68 TSCA hazardous 268 2,230.6 268 2,230.6 2,082.11
2015 non-TSCA 1,435 10,324.6 1,3092 10,004.0* 9,638.18* TSCA hazardous 352 2,335.0 317 2,135.3 2,145.78
Total 5,045 37,717.0 4,419 33,489.7 33,355.63 Notes: 1 Six bags weighing a total of 10.5 tons were subtracted from the 2015 non-TSCA figures, as they were uncontaminated
materials used for the barge landing and were disposed of at the expense of waste management subcontractor ELM. A total of 27.9 tons of mistakenly excavated clean soil that was disposed of at the expense of Jacobs were subtracted. The number of bags related to the excavation error is unknown and is not reflected in the bag counts.
2 Bags transferred in 2015 included bags excavated in 2013 and 2014 that were staged onsite. For definitions, refer to the Acronyms and Abbreviations section.
2.2 STORAGE AREA 1 FINAL DECOMMISSIONING
The former stockpiles at SA1 were constructed during the non-time-critical removal action
(NTCRA) conducted in accordance with the 2012 NTCRA decision (USAF 2012). The
stockpiles were decommissioned in 2013 and 2014 and post-construction samples were
collected from the footprints of the stockpiles (USAF 2016). In late-August 2015, Jacobs
directed the final decommissioning of SA1 (Figure A-1). Liners were removed and bagged for
future disposal. Site controls were taken down, and the area was graded with a loader using its
bucket attachment. The post-construction samples collected in 2013 and 2014 did not indicate
PCB contamination, and as such, all garbage collected was disposed of at the Port Heiden
Landfill.
2.3 ANALYTICAL SAMPLING
During the 2015 field season, 1,748 analytical samples were collected at Port Heiden and
submitted for chemical analysis. Of those, 1,735 samples were analyzed for PCBs, eight were
used to screen soil for lead, or volatile organic carbon (VOC) and gasoline-range organics
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-7 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
(GRO), and five were used to assess the effectiveness of equipment decontamination
procedures.
Samples were analyzed by SGS Environmental Services in Anchorage, Alaska. Analytical
data, including the sample summary, analytical results tables, and ADEC laboratory data
review checklists, can be found in Appendix D. Data quality was compared to the objectives
outlined in Worksheet #28 of the 2013 work plan (USAF 2013). The reported data were
considered usable for the soil removal action. Limitations of the analytical results and data
that did not meet project data quality objectives (DQOs) are also noted in Appendix D.
2.3.1 Soil PCB Analysis
Of the 1,735 samples collected in 2015, 1,576 were primary samples and 159 were duplicate
samples. Primary PCB samples consisted of the following:
• Nine-point composite excavation confirmation samples
• Nine-point composite initial surface characterization samples, or step-out grid samples
• Three-point composite excavation sidewall confirmation samples for walls at least 18 inches deep
• Discrete subsurface samples to delineate the vertical extent of PCB contamination in 50 percent of grids with confirmed surface contamination at the DSA
• Eight-point composite North Landfill Road surface samples
• Stockpile decommissioning samples
• Discrete surface samples at the pumice pit (to confirm use as clean backfill), located south of the airport (Figure A-1), and in the vicinity of a torn and spilled bag (Section 2.1.3 above)
The distribution of PCB soil samples is shown in Table 2-2. Samples were collected and
handled in accordance with the 2013 work plan (USAF 2013), the 2014 work plan addendum
(USAF 2014), and the 2015 DSA work plan addendum (USAF 2015). Sample collection
locations include SRA2, Access Road, and Site Road/Tundra Sections 89-92, which are
combined as RRS area; the DSA; Site Road/Tundra Sections 08 and 10 (Figure A-1); soil
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-8 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
stockpiles; the pumice pit (Figure A-1); the area around a spilled bag; and at North Landfill
Road (Figure A-2).
Table 2-2 Soil Samples Collected and Submitted for PCB Analysis in 2015
Source # of Samples
Radio Relay Station Area Grid floor excavation confirmations – nine-point composite 694 Initial grid surface characterizations – nine-point composite 297 Excavation wall confirmations – three-point composite 162 Duplicates 119 Total collected at the Radio Relay Station Area 1,272
Drum Storage Area Grid floor excavation confirmations – nine-point composite 112 Initial grid surface characterizations – nine-point composite 129 Excavation wall confirmations – three-point composite 49 Discrete subsurface delineations of contamination 87 Duplicates 38 Total collected at the Drum Storage Area 415
Site Road and Tundra Sections 08 and 10 Initial grid surface characterizations – nine-point composite 27 Duplicates 2
Total collected at the Road and Tundra Sections 08 and 10 29 Miscellaneous Samples Soil stockpile characterization 8 Pumice pit characterization 5 Spilled bag cleanup confirmations 3 North Landfill Road surface characterization – eight-point composite 3 Total miscellaneous samples collected 19 Total PCB soil analysis samples collected in 2015 1,735
Note: For definitions, refer to the Acronyms and Abbreviations section.
2.3.2 Equipment Decontamination Confirmation Samples
Five equipment decontamination confirmation samples were collected prior to demobilization
from the site. While preparing an excavator for return to its owner, a sample of soil
compacted in the tracks of the excavator was collected, and the PCB result was 1.08 mg/kg.
This soil was removed and bagged for disposal. A hexane wipe of the track confirmed
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-9 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
decontamination was complete. Three additional hexane wipe samples were collected from
excavator buckets, and the PCB results were below the action level of 10 micrograms per for
each.
2.3.3 Soil Lead Analyses
During excavations at the DSA, approximately 100 buried electrical components
(transformers and batteries) were found. Batteries used during the operation period of the
RRS were often lead-acid, and not all the batteries found were completely sealed. As a result,
three discrete targeted samples were collected from areas where batteries were uncovered to
ensure soil from those areas could not be classified as a RCRA hazardous waste. Samples
were submitted for toxicity characteristic leaching protocol (TCLP) analysis of total lead.
Results ranged from 8.06 to 18.0 mg/kg.
2.3.4 Soil VOC and GRO Analysis
Field crews noticed a strong odor originating from soil near a monitoring well (PG1-MW-01)
within SRA2. Trichloroethene (TCE) has been detected at this well in the past. To assess the
potential worker exposure risk, soil from two grids adjacent to the well were tested with TCE-
specific Dräger tubes. Neither test produced a color change in the tube from 2 to 50 ppm or
from 20 to 250 ppm. With consultation from AFCEC and USACE, two primary samples and
one duplicate sample were collected and sent to the analytical laboratory to be analyzed for
VOCs and GRO. The strongest odor was near an antenna pad that had been recently exposed
below the surface, and in an area with PCB concentrations above 3,000 mg/kg. Testing
revealed the presence of 1,2,3-trichlorobenzene (1,2,3-TCB) and 1,2,4-trichlorobenzene
(1,2,4-TCB). One sample had a result of 1.38 mg/kg, above the ADEC Method Two
migration to groundwater cleanup level for 1,2,4-TCB (0.85 mg/kg) (ADEC 2016). The odor
threshold for 1,2,4-TCB is 3 milligrams per cubic meter. As such, the 2015 Explanation of
Significant Differences (currently undergoing internal review) describes 1,2,4-TCB as a new
contaminant of concern for the RRS site. The analyte 1,2,3-TCB has no published exposure or
cleanup levels.
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-10 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
To ensure that material excavated from the area could not be classified as a RCRA hazardous
waste during transport, a sample was collected for TCLP analysis of VOCs from a staged bag
containing soil from the area in question. The results were nondetect for all tested analytes
and the bags from the area were cleared for transport as TSCA waste, as PCB concentrations
were greater than 50 mg/kg.
2.4 ASBESTOS SAMPLING
Because of known asbestos disposal at the DSA and at other former RRS buildings, an onsite
qualified asbestos inspector collected and submitted 79 samples for asbestos analysis during
the 2015 field season. Of the 79 samples, 28 were air monitoring samples, 13 were samples of
soil around known or suspected ACMs, and 38 were samples of bulk materials often
associated with asbestos, such as tiles and pipe insulation (Table 2-3). Of the 38 bulk material
samples, six samples that contained yarn, wool, wire insulation, and baseboard/mastic were
analyzed by transmission electron microscopy, and the remaining 32 were analyzed by
polarized light microscopy. Six samples of bulk material tested positive for chrysotile,
including four floor tiles and mastic and two bags containing thermal system insulation, foam,
and metal at the DSA. The samples collected from these two bags also contained amosite.
Figures A-18 and A-19 depict locations of bulk and soil asbestos sampling, and the associated
results.
The 28 air monitoring samples were collected during initial DSA sampling, while closing
bags, and during the asbestos removal activities as described in the asbestos removal plan
(EMI 2015). Six of the 28 air monitoring samples were negative control field blanks or sealed
blanks. Five of the 28 samples were collected as background air or personal air samples
during soil sampling that occurred after the initial discovery of potential ACM at the DSA.
Field staff were equipped with high-efficiency particulate air filter respiratory protection
during the collection of all air samples. Air monitoring cassettes were analyzed by phase
contrast microscopy. Two of the five personal air monitoring samples collected during
removal activities at the DSA identified airborne asbestos particles, but the results were below
the regulatory personal exposure limit and exclusion limit. The remaining 12 air samples were
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-11 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
collected at the perimeter of the exclusion zones during the removal activities at the DSA.
Three of these samples were upwind of the removal area, and nine samples were downwind;
all were nondetect. Appendix E presents the asbestos removal action summary prepared by
EMI.
Asbestos analyses were submitted to and performed by White Laboratories, LLC in
Anchorage, Alaska; however, White Laboratories outsourced some analyses to Scientific
American Institute in Greensboro, North Carolina. The complete asbestos sample summary
and analytical results can be found in Attachment E-1 of Appendix E.
Table 2-3 Asbestos Samples Collected and Submitted for Analysis in 2015
Sample Type Samples Collected Asbestos Detected
Potentially asbestos-containing soil 13 0 Potentially asbestos-containing bulk materials 38 6 Air monitoring for airborne asbestos fibers 22 2 Negative controls for air monitoring 6 0
Total 79 8
2.5 WINTER STORAGE OF EXCAVATED MATERIALS
As described in Section 2.2, the majority of the materials excavated in 2015 were sent for
disposal, while some remains staged on site. All 277 bags containing non-TSCA soil and
debris and 22 bags containing TSCA soil and debris from the DSA, as well as 324 non-TSCA
bags and 13 TSCA bags from former RRS areas, are still staged in Port Heiden for disposal
during the 2016 field season. Bags being overwintered in Port Heiden are staged on one of
five pads (Figure A-20). Each pad has a liner upon which the bags were set, then the bags and
pads were covered with a second liner. Covers will be inspected monthly throughout the
winter by a local subcontractor. Bags are segregated by PCB level (TSCA or non-TSCA) and
source area (DSA or SRA2). Due to the expected length of storage of TSCA level soil, the
U.S. Environmental Protection Agency was notified. A total of 636 bags weighing
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 2-12 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
approximately 4,203 tons are staged onsite for winter 2015/2016. Table 2-4 presents the
contents of each pad.
Table 2-4 LiftPacs Staged Onsite Over Winter 2015-2016
Pad Number Pad Contents
Pad Area (m2)
# of Bags
Weight (tons)
CA-1A Non-TSCA from RRS areas 646.4
324 2,319.2 CA-1B
Non-TSCA from RRS areas + 5 bags of uncontaminated soil and liners from SA1 decommissioning
797.6
CA-1C TSCA from DSA
777.6 22 109.8
TSCA from RRS areas 13 90.0 CA-1D Non-TSCA from DSA 224.0
277 1,684.1 CA-1E Non-TSCA from DSA 729.8
Total 3,175.4 636 4,203.0 Notes: CA-1A and CA-1B contain the same type of bags from the same source, as do CA-1D and CA-1E. Because the location of each
individual bag is not tracked, only the total weight of both pads combined can be calculated. For definitions, refer to the Acronyms and Abbreviations section.
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 3-1 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
3.0 CONCLUSION AND FUTURE ACTIVITIES
During the 2015 field season, 1,787 bags totaling an estimated 12,659.6 tons (10,324.6 tons
non-TSCA and 2,335.0 tons TSCA) of PCB-contaminated soil were generated from newly
excavated grid cells. A total of 1,632 bags with a certified weight of 11,822.36 tons,
consisting of 9,638.18 tons of non-TSCA soil, 2,145.78 tons of TSCA soil, 10.5 tons of barge
landing construction materials, and 27.9 tons of mistakenly excavated clean soil was
transported to facilities in Arlington, Oregon for disposal.
All remaining waste from 2013 and 2014 and approximately 65 percent of the soil excavated
in 2015 was transported to the disposal facility. All material excavated from the DSA
(299 bags weighing an estimated 1793.8 tons) and 332 bags of soil from SRA2 (weighing an
estimated 2,409.2 tons) remains staged at Port Heiden. Other material staged at the DSA
(within the fenced excavation area) includes a large pile of metal debris, more than
100 transformers and batteries, 12 depressurized gas cylinders, an overpack drum with five
bottles of unknown liquid, and five bags of crushed and dry-decontaminated drums. Complete
characterization and appropriate disposal of DSA debris is yet to be determined. All 636
staged bags will be transported to the disposal facility in 2016 along with the soil excavated
under remaining contract quantities in 2016.
Work at the DSA is anticipated to be completed in spring 2016. Three remaining grid cells
with PCB results above cleanup levels were inaccessible at the end of 2015 due to pooling of
heavy rain in mid-September. End-of-season sampling also delineated five additional
excavation sidewalls with PCB concentrations above cleanup levels. All TSCA materials are
thought to have been removed from the DSA, with only non-TSCA soil remaining. As PCB-
contaminated soil was found collocated with buried metallic debris, a geophysical survey was
performed at the end of the 2015 field season and revealed no remaining buried metallic
debris within 10 feet of the surface.
Levels of 1,2,4-TCB will continue to be screened against ADEC Method Two migration to
groundwater cleanup levels at SRA2. PCBs and 1,2,4-TCB are expected to be collocated at
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 3-2 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
the site, as 1,2,4-TCB was historically used as a dielectric fluid in transformers. Removal of
1,2,4-TCB-contaminated soil is expected to occur during the removal of PCB-contaminated
soil.
The quantities of PCB-contaminated soil remaining at the Port Heiden RRS area are estimated
based on sampling results from previous and current removal activities (2013 through 2015).
These calculations are presented in Appendix F. Approximately 7,800 cy of contaminated soil
remains at Port Heiden. This quantity is based on the current surface characterization results
and estimated results in unsampled areas, and may change based on characterization and
depth delineation sampling planned for the 2016 field season at the former RRS, Septic
Lagoon, North Landfill, and North Landfill Road. The contaminated grids targeted for future
excavation activities and proposed characterization sample locations are presented on figures
in Appendix A.
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 4-1 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
4.0 REFERENCES
ADEC (Alaska Department of Environmental Conservation). 2016 (January). Oil and Other Hazardous Pollution Control Regulations – Discharge Reporting, Cleanup, and Disposal of Oil and Other Hazardous Substances. 18 AAC 75.
ADEC. 2010 (May). Draft Field Sampling Guidance. ADEC Division of Spill Prevention and Response Contaminated Sites Program.
EMI (Environmental Management, Inc.). 2015 (August). Asbestos Removal Plan.
USAF. (U.S. Air Force). 2016 (March). Site Road PCB-Contaminated Soil Removal, 2013/2014 After Action Report. Draft-Final. Prepared by Jacobs Engineering Group Inc.
USAF. 2015 (June). PCB-Contaminated Soil Excavation and Removal Action: Drum Storage Area Work Plan Addendum. Final. Prepared by Jacobs Engineering Group, Inc.
USAF. 2014 (May). PCB-Contaminated Soil Delineation Sampling and Analysis Plan, Work Plan Addendum. Final. Prepared by Jacobs Engineering Group, Inc.
USAF. 2013 (August). PCB-Contaminated Soil Excavation and Removal Action: 2013 Work Plan. Prepared by KEMRON Environmental Services, Inc.
USAF. 2012 (April). Action Memorandum for a Non-Time-Critical Removal Action of PCB-Contaminated Soil. (Draft-Final). Port Heiden Site Road. Port Heiden, Alaska.
USAF. 2009 (February). Record of Decision for Port Heiden Radio Relay Station (Final). Port Heiden RRS, Port Heiden, Alaska. Prepared by Weston Solutions, Inc.
I:\KEMRON\Port Heiden RA\WP\2015 Interim Data Rpt\_Text\2015 Interim Report.docx 4-2 GOV-J07-05DK4801-J22-0005 FINAL 4/28/2016
(intentionally blank)
APPENDIX A
Figures
SITE LOCATION AND VICINITYPORT HEIDEN PCB-CONTAMINATED REMOVAL ACTION
PORT HEIDEN, AK
14 MAR 2016 A-1KELLY McGOVERNP:\Por
tHei
den\
GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R F
ig A
-1.m
xd r
amsa
ybd
Cold Pile Road
NorthLandfillRoad
N RiverRoad
Swan Lake Road
Pit Road
Oil WellRoad
Access
Road
Lower Site Road
Site Road
Airport
Road
o0 0.1 0.2 0.3 0.4 0.5
Miles
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Bering SeaPort Heiden
DATE: PROJECT MANAGER: FIGURE NO:
LegendRoads
ARCTIC OCEAN
Gulf of AlaskaBering Sea
AlaskaCanadaRussia
PACIFIC OCEAN Pumice Pit
Site OfficeStorage Area 1
Road and TundraSections 08 and 10
Former RadioRelay Station
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
1.m
xd r
amsa
ybd
Drum Storage
Area
Black LagoonOutfall Area
Soil RemovalArea 2
AccessRoad
NorthLandfill
NorthLandfillRoad
Site Road andTundra Sections
89 - 92
SepticPipeline
SepticLagoon
oAll Locations Are Approximate
DATE: PROJECT MANAGER: FIGURE NO:
0 150 300 450 600Feet
Below Cleanup, 50 mg/kgUncharacterized
Site_RoadRoad Section LineRRS_Areas
WGS 1984 UTM Zone 4N Imagery: Aerometric 2002
Radio Relay Station Site Overview
Radio Relay Station RemediationPort Heiden, Alaska
26 JAN 2016 Kelly McGovern A-2
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
Soil Removal Area 2 SoutheastRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
Sacking station
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-3
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
Soil Removal Area 2 NortheastRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
Bag Storage Areas
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-4
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
Soil Removal Area 2 NorthwestRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-5
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
Soil Removal Area 2 SouthwestRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-6
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
North Upper Site RoadRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
Bag Storage Areas
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-7
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
South Upper Site RoadRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
Sacking station
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-8
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
Access RoadRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-9
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
Tundra AreaRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-10
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
New Source AreaRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
Sacking station
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-11
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
Drum Storage AreaRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-12
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 20 40 60 80 100
Feet
North LandfillRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-13
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 30 60 90 120 150
Feet
North Landfill RoadRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-14
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-3 to
A-1
5.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
Septic LagoonRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
RRS concrete
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-15
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-16
and
A-1
7.m
xd r
amsa
ybd
0 20 40 60 80 100
Feet
Storage Area 1ARadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-16
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
s A
-16
and
A-1
7.m
xd r
amsa
ybd
0 20 40 60 80 100
Feet
Storage Area 1BRadio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
RRS concrete
Below Cleanup
WERS Legacy DataBelow Cleanup, < 1 mg/kg
Above Cleanup, 1 to 50 mg/kg
TSCA, > 50 mg/kg
Grid To Be Characterized
TSCA Excavation DepthComments
Remove TSCA wall 2.5 feet
TSCA to 36 inches
TSCA to 30 inches
TSCA to 24 inches
TSCA to 18 inches
TSCA to 12 inches
TSCA to 6 inches
PCB 1-50ppm Excavation DepthComments
1-50 mg/kg to wall depth
Remove wall 2.5 feet
1-50 mg/kg at 24 inches
1-50 mg/kg at 18 inches
1-50 mg/kg at 12 inches
1-50 mg/kg at 6 inches
oTrueNorth oProjectNorth
DATE:
A-17
Non-DSA Asbestos Samples Collected in 2015
Radio Relay Station RemediationPort Heiden, Alaska
14 MAR 2016 A-18KELLY McGOVERNP:\Por
tHei
den\
Bac
kup
1208
15\G
IS\M
XD
\Kem
ron\
15P
H_R
epor
ting\
2015
Inte
rim D
ata
Rep
ort\2
015
IDR
figu
re A
-18.
mxd
ram
sayb
d
o0 50 100 150 200FeetAll Locations Are Approximate
WGS 1984 UTM Zone 4N
DATE: PROJECT MANAGER: FIGURE NO:
LegendSoil sample, Nondetect for asbestosBulk sample, Asbestos detected
Bulk sample, Nondetect for asbestos
Access RoadsApproximate DSA boundaryRRS concreteSacking station
SampleID Type ResultH32V15-AD-GWTILE-005 Bulk NondetectH32V15-AD-CONCRETE-006A Bulk NondetectH32V15-AD-CONCRETE-006B Bulk Nondetect
SampleID Type ResultH32V09-AD-PACM-004A Bulk NondetectH32V09-AD-PACM-004B Bulk Nondetect
SampleID Type ResultRRS-DA-BLACKPIPE-017 Bulk NondetectRRS-DA-BLACKPIPE-018 Bulk Nondetect
P:\P
ortH
eide
n\B
acku
p 12
0815
\GIS
\MX
D\K
emro
n\15
PH
_Rep
ortin
g\20
15 In
terim
Dat
a R
epor
t\201
5 ID
R fi
gure
A-1
9.m
xd r
amsa
ybd
0 10 20 30 40 50
Feet
DSA Asbestos Samples Collected in 2015Radio Relay Station Remediation
Port Heiden, Alaska
14 MAR 2016 K. McGovernPROJECT MANAGER: FIGURE NO:
All Locations Are Approximate
WGS 1984 UTM Zone 4N Transverse Mercator
Access Roads
Approximate DSA boundary
Asbestos Samples 2015Soil sample, Nondetect for asbestos
Bulk sample, Asbestos detected
Bulk sample, Nondetect for asbestos
oTrueNorth oProjectNorth
DATE:
A-19
SampleID Type Result15PH-DSA-H17V22-AS-12 Soil Nondetect
SampleID Type Result15PH-DSA-H19V24-AS-12 Soil Nondetect
SampleID Type Result15PH-DSA-H17V21-AS-12 Soil Nondetect
SampleID Type Result15PH-DSA-H20V27-AS-12 Soil Nondetect
SampleID Type Result15PH-DSA-H11V26-AS-12 Soil Nondetect
SampleID Type Result15PH-DSA-H12V25-AS-12 Soil Nondetect
SampleID Type ResultDSA-AD-UNKFRI-017 Bulk NondetectDSA-AD-WIREINS-018 Bulk Nondetect
SampleID Type Result15PH-DSA-H15V25-AS-12 Soil Nondetect
SampleID Type Result15PH-DSA-H15V24-AS-12 Soil Nondetect
SampleID Type Result15PH-DSA-H13V27-AS-12 Soil NondetectDSA-AD-FBGINSULATION-006C Bulk NondetectDSA-AD-GRNTILE-010B Bulk Chrysotile detected
SampleID Type ResultDSA-AD-WALLBOARD-003E Bulk NondetectDSA-AD-GREYWTTILE-014 Bulk NondetectDSA-AD-CLEARTILE-015 Bulk NondetectDSA-AD-YARN-016 Bulk NondetectDSA-AD-COVEBASE-019 Bulk NondetectDSA-AD-WOOL-020B Bulk Nondetect
SampleID Type ResultDSA-AD-WOOL-020 Bulk Nondetect
SampleID Type Result15PH-DSA-H16V27-AS-12 Soil Nondetect
SampleID Type ResultDSA-AD-WTFOAM-009 Bulk Nondetect
SampleID Type ResultDSA-AD-YARN-016B Bulk Nondetect
SampleID Type ResultDSA-AD-WALLBOARD-003B Bulk NondetectDSA-AD-WALLBOARD-003C Bulk NondetectDSA-AD-WALLBOARD-003D Bulk NondetectDSA-AD-TANTILE-005 Bulk Chrysotile detectedDSA-AD-FBGINSULATION006 Bulk NondetectDSA-AD-FBGINSULATION006B Bulk NondetectDSA-AD-LMTIME-007 Bulk NondetectDSA-AD-WTGRNTILE-008 Bulk NondetectDSA-AD-WTGRNTILE-008B Bulk NondetectDSA-AD-GRNTILE-010 Bulk Chrysotile detectedDSA-AD-BEIGETILE-011 Bulk NondetectDSA-AD-TILE-012 Bulk NondetectDSA-AD-GRNFOAM-013 Bulk Nondetect
SampleID Type Result15PH-DSA-H14V26-AS-12 Soil NondetectDSA-AD-GREYTILE-001 Bulk NondetectDSA-AD-BROWNTILE-002 Bulk 8% Chrysotile,
6% ChrysotileDSA-AD-WALLBOARD-002 Bulk Nondetect
SampleID Type Result15PH-DSA-H16V22-AS-12 Soil Nondetect
SampleID Type Result15PH-DSA-H18V25-AS-12 Soil Nondetect
SampleID Type ResultDSA-AD-BAGS-004A Bulk 5% Amosite,
20% ChrysotileDSA-AD-BAGS-004B Bulk 5% Amosite,
20% Chrysotile
APPENDIX B
Photograph Log
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-i
TABLE OF CONTENTS
PHOTO NUMBER PAGE
Photo No. 1 May 14 2015 Bagging operations at TU92-L9-E. View facing southwest. ........................................................................................................ B-1
Photo No. 2 26 May 2015 Transferring the contents of a bag with a failed zipper to a new bag. View facing west........................................................................... B-1
Photo No. 3 28 May 2015 Excavating along the southern end of Access Road. View facing west. ............................................................................................ B-2
Photo No. 4 30 May 2015 Loading excavated soil into hopper along south end of Access Road. View facing west. ................................................................. B-B-2
Photo No. 5 30 May 2015 Digging through overlying vegetation to collect nine-point composite surface samples. View facing southeast. ............................. B-3
Photo No. 6 2 June 2015 Placing a new liner and weighting the corners at a bag storage area. View facing southwest. .............................................................. B-3
Photo No. 7 4 June 2015 Collecting initial asbestos samples at the DSA in level C PPE. View facing north. .................................................................................. B-4
Photo No. 8 13 June 2015 Overview of the DSA as equipment operators prepare to remove the cover to begin excavations. View facing northeast. ..................... B-4
Photo No. 9 15 June 2015 Operators continue removing the cover from the DSA in a thick fog. View facing west. ......................................................................... B-5
Photo No. 10 18 June 2015 Decontaminating the excavator bucket prior to commencement of hauling activities. View facing northwest. ...................... B-5
Photo No. 11 18 June 2015 Placing a liner at the barge landing to begin staging full bags for transfer and disposal. View facing south. ........................................ B-6
Photo No. 12 19 June 2015 Unloading a bag for staging at the barge landing. View facing northeast. .............................................................................................. B-6
Photo No. 13 23 June 2015 The village provided a watering truck to help with dust suppression through town. View facing northeast. ........................................ B-7
Photo No. 14 24 June 2015 Picking up a bag at the RRS storage to haul to the barge landing. View facing north. ............................................................................. B-7
Photo No. 15 27 June 2015 Hand auguring for subsurface samples at the DSA. View facing north. ........................................................................................... B-8
Photo No. 16 3 July 2015 Strong easterly winds caused a plume of pumice particles to be blown from the Aniakchak crater towards the RRS site and the village of Port Heiden and forced an early work stoppage. View facing northeast. .............................................................................................. B-8
Photo No. 17 8 July 2015 Guiding the loader operator while placing a bag on the flatbed. View facing east. ................................................................................ B-9
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
TABLE OF CONTENTS (Continued)
Photo Number Page
Photograph Log B-ii
Photo No. 18 8 July 2015 Hooking a bag to the loader rack to load onto the flatbed. View facing west. ............................................................................................ B-9
Photo No. 19 9 July 2015 Employee sampling in level C PPE preparing to collect a sample of a potentially asbestos-containing material. View facing north. ............................................................................................................. B-10
Photo No. 20 – 9 July 2015 Debris encountered at the DSA. Contents of a clear plastic bag labeled “WASTE ONLY” were sampled for asbestos. Two buried drums are also in view. View facing down. ....................................... B-10
Photo No. 21 13 July 2015 Loader operator guiding a full hopper into the sacking station bay. View facing west. ...................................................................... B-11
Photo No. 22 13 July 2015 View of DSA prior to excavation. View facing north. ........... B-11
Photo No. 23 14 July 2015 Two fire suppression cylinders located at the DSA. View facing down. ........................................................................................ B-12
Photo No. 24 16 July 2015 Excavating PCBs at concentrations greater than 50 mg/kg at the RRS area. Note the clear plastic liner lining the bag and folded over the outside. View facing southwest. .......................................... B-12
Photo No. 25 21 July 2015 A buried drum collocated with household garbage at the DSA. View facing down. .............................................................................. B-13
Photo No. 26 21 July 2015 Metallic debris staging area and decontamination area at the DSA. View facing north. ......................................................................... B-13
Photo No. 27 21 July 2015 An empty small chemical drum with two chemical safety warning signs located in excavations at the DSA. View facing down. ............................................................................................................. B-14
Photo No. 28 21 July 2015 A large piece of electrical equipment (likely a transformer). View facing down. .................................................................. B-14
Photo No. 29 22 July 2015 Tangled steel cable excavated from the DSA. View facing northwest. ........................................................................................... B-15
Photo No. 30 23 July 2015 Collection of five transformers pulled from early excavations at the DSA. View facing down.................................................. B-15
Photo No. 31 13 August 2015 Debris at the southwest corner of the DSA with 18-inch excavation instructions painted on the ground in pink. View facing south. .................................................................................................. B-16
Photo No. 32 13 August 2015 Amber 2 liter bottle with unknown contents recovered from DSA excavations. View facing down. ................................. B-16
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
TABLE OF CONTENTS (Continued)
Photo Number Page
Photograph Log B-iii
Photo No. 33 13 August 2015 A large bundle of electrical conduit was uncovered in the DSA. Conduit was multi-layered and approximately 4 inches in diameter. View facing west. .......................................................................... B-17
Photo No. 34 22 August 2015 Debris excavated at the DSA. View facing west. .............. B-17
Photo No. 35 22 August 2015 Cleaning the excavator bucket into a bag prior to returning the unit at the end of its rental term. View facing east. ................ B-18
Photo No. 36 28 August 2015 Post-decommissioning photo of Storage Area 1. View facing east. ........................................................................................... B-18
Photo No. 37 1 September 2015 All bags staged at the barge landing for disposal. View facing east. ........................................................................................... B-19
Photo No. 38 16 September 2015 A liner bag was placed over the excavator bucket to prevent contaminated soil from dripping off while relocating the excavator during heavy rains. View facing southwest. ................................. B-19
Photo No. 39 18 September 2015 Overview of DSA regulated exclusion zone for asbestos removal activities. View facing northwest. .................................... B-20
Photo No. 40 19 September 2015 Hand-digging friable asbestos material and placing into asbestos waste bags. View facing down. .................................. B-20
Photo No. 41 19 September 2015 During asbestos removal activities, approximately 50 empty drums were encountered. At least nine are visible in this photo. View facing northeast. ....................................................................... B-21
Photo No. 42 19 September 2015 Asbestos removal crew members wet the affected areas with water before removal while the excavator removes a drum obstructing their access. View facing northwest. .......................................... B-21
Photo No. 43 25 September 2015 A geophysicist conducts a geophysical survey of the DSA to find any remaining buried metallic debris after excavations were complete. View facing north. ............................................................... B-22
Photo No. 44 26 September 2015 Two of the grids with sample results above cleanup levels remain under water and could not be excavated. View facing north. .................................................................................................. B-22
Photo No. 45 27 September 2015 Cylinders and electrical equipment are staged overwinter at the DSA awaiting final disposition orders. View facing southeast. ....................................................................................................... B-23
Photo No. 46 27 September 2015 Metal debris staged overwinter at the DSA awaiting final disposition orders. View facing south. ................................... B-23
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
TABLE OF CONTENTS (Continued)
Photo Number Page
Photograph Log B-iv
Photo No. 47 27 September 2015 Batteries, transformers, and fire suppression cylinders staged for overwintering at the DSA while awaiting final disposition orders (left half). View facing down. ......................................... B-24
Photo No. 48 27 September 2015 Batteries, transformers, and fire suppression cylinders staged for overwintering at the DSA while awaiting final disposition orders (right half). View facing down. ....................................... B-24
Photo No. 49 30 September 2015 Decontaminating the excavator bucket before returning it to the owner. View facing west. ................................................. B-25
Photo No. 50 1 October 2015 A bag storage pad covered by a liner for overwintering and weighted with clean fill. View facing north.................... B-25
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-1
Photo No. 1 – May 14 2015
Bagging operations at TU92-L9-E. View facing southwest.
Photo No. 2 – 26 May 2015
Transferring the contents of a bag with a failed zipper to a new bag. View facing west.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-2
Photo No. 3 – 28 May 2015
Excavating along the southern end of Access Road. View facing west.
Photo No. 4 – 30 May 2015
Loading excavated soil into hopper along south end of Access Road. View facing west.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-3
Photo No. 5 – 30 May 2015
Digging through overlying vegetation to collect nine-point composite surface samples. View facing southeast.
Photo No. 6 – 2 June 2015
Placing a new liner and weighting the corners at a bag storage area. View facing southwest.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-4
Photo No. 7 – 4 June 2015
Collecting initial asbestos samples at the DSA in level C PPE. View facing north.
Photo No. 8 – 13 June 2015
Overview of the DSA as equipment operators prepare to remove the cover to begin excavations. View facing northeast.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-5
Photo No. 9 – 15 June 2015
Operators continue removing the cover from the DSA in a thick fog. View facing west.
Photo No. 10 – 18 June 2015
Decontaminating the excavator bucket prior to commencement of hauling activities. View facing northwest.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-6
Photo No. 11 – 18 June 2015
Placing a liner at the barge landing to begin staging full bags for transfer and disposal. View facing south.
Photo No. 12 – 19 June 2015
Unloading a bag for staging at the barge landing. View facing northeast.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-7
Photo No. 13 – 23 June 2015
The village provided a watering truck to help with dust suppression through town. View facing northeast.
Photo No. 14 – 24 June 2015
Picking up a bag at the RRS storage to haul to the barge landing. View facing north.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-8
Photo No. 15 – 27 June 2015
Hand auguring for subsurface samples at the DSA. View facing north.
Photo No. 16 – 3 July 2015
Strong easterly winds caused a plume of pumice particles to be blown from the Aniakchak crater towards the RRS site and the village of Port Heiden and forced an early work stoppage.
View facing northeast.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-9
Photo No. 17 – 8 July 2015
Guiding the loader operator while placing a bag on the flatbed. View facing east.
Photo No. 18 – 8 July 2015
Hooking a bag to the loader rack to load onto the flatbed. View facing west.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-10
Photo No. 19 – 9 July 2015
Employee sampling in level C PPE preparing to collect a sample of a potentially asbestos-containing material. View facing north.
Photo No. 20 – 9 July 2015
Debris encountered at the DSA. Contents of a clear plastic bag labeled “WASTE ONLY” were sampled for asbestos. Two buried drums are also in view. View facing down.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-11
Photo No. 21 – 13 July 2015
Loader operator guiding a full hopper into the sacking station bay. View facing west.
Photo No. 22 – 13 July 2015
View of DSA prior to excavation. View facing north.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-12
Photo No. 23 – 14 July 2015
Two fire suppression cylinders located at the DSA. View facing down.
Photo No. 24 – 16 July 2015
Excavating PCBs at concentrations greater than 50 mg/kg at the RRS area. Note the clear plastic liner lining the bag and folded over the outside. View facing southwest.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-13
Photo No. 25 – 21 July 2015
A buried drum collocated with household garbage at the DSA. View facing down.
Photo No. 26 – 21 July 2015
Metallic debris staging area and decontamination area at the DSA. View facing north.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-14
Photo No. 27 – 21 July 2015
An empty small chemical drum with two chemical safety warning signs located in excavations at the DSA. View facing down.
Photo No. 28 – 21 July 2015
A large piece of electrical equipment (likely a transformer). View facing down.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-15
Photo No. 29 – 22 July 2015
Tangled steel cable excavated from the DSA. View facing northwest.
Photo No. 30 – 23 July 2015
Collection of five transformers pulled from early excavations at the DSA. View facing down.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-16
Photo No. 31 – 13 August 2015
Debris at the southwest corner of the DSA with 18-inch excavation instructions painted on the ground in pink. View facing south.
Photo No. 32 – 13 August 2015
Amber 2 liter bottle with unknown contents recovered from DSA excavations. View facing down.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-17
Photo No. 33 – 13 August 2015
A large bundle of electrical conduit was uncovered in the DSA. Conduit was multi-layered and approximately 4 inches in diameter. View facing west.
Photo No. 34 – 22 August 2015
Debris excavated at the DSA. View facing west.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-18
Photo No. 35 – 22 August 2015
Cleaning the excavator bucket into a bag prior to returning the unit at the end of its rental term. View facing east.
Photo No. 36 – 28 August 2015
Post-decommissioning photo of Storage Area 1. View facing east.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-19
Photo No. 37 – 1 September 2015
All bags staged at the barge landing for disposal. View facing east.
Photo No. 38 – 16 September 2015 A liner bag was placed over the excavator bucket to prevent contaminated soil from dripping off
while relocating the excavator during heavy rains. View facing southwest.
Former Port Heiden RRS – PCB-Contaminated Soil Removal 2015 Interim Data Report
Photograph Log B-20
Photo No. 39 – 18 September 2015
Overview of DSA regulated exclusion zone for asbestos re