P6Ch4BCP&DRPPart4

Embed Size (px)

Citation preview

  • 8/10/2019 P6Ch4BCP&DRPPart4

    1/48

    PAPER-6 PART-4 OF5

    CA A.RAFEQ, FCA

    Chapter-4: Business Continuity Planningand Disaster Recovery Planning

    1

  • 8/10/2019 P6Ch4BCP&DRPPart4

    2/48

    Learning Objectives2

    To understand the concept of Business Continuity Management

    To understand the key phases and components of a Business

    Continuity Plan

    To understand the key aspects of Business Continuity Planimplementation

    To learn about Back-up and Disaster Recovery Planning

    To learn how to audit a Business Continuity Plan

  • 8/10/2019 P6Ch4BCP&DRPPart4

    3/48

    Topics Covered3

    PART-4

    4.13 Types of Plans

    4.14 Types of Back-ups

    4.15 Alternate Processing Facility Arrangements

    4.16 Disaster Recovery Procedural Plan

  • 8/10/2019 P6Ch4BCP&DRPPart4

    4/48

    4.13 Types of Plans4

    Emergency Plan

    Back-up Plan

    Recovery Plan

    Test Plan

  • 8/10/2019 P6Ch4BCP&DRPPart4

    5/48

    Emergency Plan5

    Emergency plan specifies the actions

    Management must identify situations

    Actions to be initiated

    Security review program

  • 8/10/2019 P6Ch4BCP&DRPPart4

    6/48

    Four aspects of the emergency plan6

    Plan must show who is to be notified immediatelywhen the disaster occurs

    Plan must show actions to be undertaken

    Any evacuation procedures required must bespecified

    Return procedures

  • 8/10/2019 P6Ch4BCP&DRPPart4

    7/48

    Back-up Plan

    7

    Type of backup

    Could be complex

    Difficult to specify

    Backup plan needscontinuous updating

    Key responsibilities

    Backup task

    Hardware and software mustbe updated

  • 8/10/2019 P6Ch4BCP&DRPPart4

    8/48

    Recovery Plan8

    Backup plan is intended to restore operations

    Recovery plan should identify a recovery committee

    Indicate Applications

    Recovery committee must understand theirresponsibilities

    Review and practice executing their responsibilities

    Committee members

  • 8/10/2019 P6Ch4BCP&DRPPart4

    9/48

    Test Plan9

    Final component of a disaster recovery plan is a test plan

    Identify deficienciesEnable a range of disasters

    Test plans must be invoked

    Top managers

    Real disaster

  • 8/10/2019 P6Ch4BCP&DRPPart4

    10/48

    4.14 Types of Back-ups10

    Typesof Back-

    ups

    Full Backup

    IncrementalBackup

    DifferentialBackup

    Mirrorback-up

  • 8/10/2019 P6Ch4BCP&DRPPart4

    11/48

    Full Backup11

    Backup captures all files

    Backup generation containsevery file

    Realistic proposition for backingup a large amount of data

  • 8/10/2019 P6Ch4BCP&DRPPart4

    12/48

    Incremental Backup12

    Incremental backup captures files

    Economical method

    Saves a lot of backup time and space

    Incremental backup are very difficult torestore

  • 8/10/2019 P6Ch4BCP&DRPPart4

    13/48

    Differential Backup13

    Differential backup stores files that havechanged

    Differential backup is obviously faster

    Differential backup is a two-stepoperation

    Restoring from the last full backup

    Differential backup probably includes filesthat were already included

  • 8/10/2019 P6Ch4BCP&DRPPart4

    14/48

    Mirror back-up14

    Mirror backup is identical to

    a full backup.

    Backup is most frequently

    used to create an exactcopy.

  • 8/10/2019 P6Ch4BCP&DRPPart4

    15/48

    Question

    4. Briefly explain the various types ofsystems back-up for the system anddata together.(5 Marks) (Nov 2008)

    15

  • 8/10/2019 P6Ch4BCP&DRPPart4

    16/48

    Answer

    Types of systems Back-ups

    When the back-ups are taken of the system and data together,they are called total systems back-up.

    System back-up may be

    Full Backup

    Differential

    Backup

    Incremental

    Backup

    Mirror

    back-up

    16

  • 8/10/2019 P6Ch4BCP&DRPPart4

    17/48

    Answer

    Full Backup: Every backup generation contains every file in the backup set.

    However, the amount of time and space such a backup takes prevents it frombeing a realistic proposition for backing up a large amount of data.

    This is the simplest form of backup with a single restoring session for restoringall backed-up files.

    Differential Backup: It contains all the files that have changed since the last

    full backup.This is in contrast to incremental backup generation, which holds all the filesthat were modified since the last full or incremental backup.

    It is faster and more economical in using the backup space, as only the filesthat have changed since the last full backup are saved.

    17

  • 8/10/2019 P6Ch4BCP&DRPPart4

    18/48

    Answer

    Incremental Backup: Only the files that have changed since the last fullbackup / differential backup / or incremental backup are saved.

    This is the most economical method, as only the files that changed sincethe last backup are backed up.

    This saves a lot of backup time and space. Normally, it is difficult torestore as you have to start with recovering the last full backup, and thenrecovering from every incremental backup taken since.

    Mirror back-up: It is identical to a full backup, with theexception that the files are not compressed in zip files andthey cannot be protected with a password.

    A mirror backup is most frequently used to create an exactcopy of the backup data.

    18

  • 8/10/2019 P6Ch4BCP&DRPPart4

    19/48

    4.15 Alternate Processing Facility

    Arrangements19

    Coldsite

    Hot site

    Warm

    site

    Reciprocal

    agreement

  • 8/10/2019 P6Ch4BCP&DRPPart4

    20/48

    Cold site20

    Organisation cantolerate

    some

    downtime

    Cold sitehas all thefacilities

    Establish itsown cold-site facility

  • 8/10/2019 P6Ch4BCP&DRPPart4

    21/48

    Hot site21

    Organisationmight need hot

    site backup

    Hardware andoperations

    facilities

    A hot site is

    expensive tomaintain

    Shared with

    otherorganisations

  • 8/10/2019 P6Ch4BCP&DRPPart4

    22/48

    Warm site22

    A warm siteprovides anintermediate

    level

    Cold-sitefacilities inaddition

    Warm site mightcontain selected

    peripheralequipment

  • 8/10/2019 P6Ch4BCP&DRPPart4

    23/48

    Reciprocal agreement23

    Two or more

    organisations

    Backup option isrelatively cheap

  • 8/10/2019 P6Ch4BCP&DRPPart4

    24/48

    Reciprocal agreement24

    What controls will be in place and working at the off-site facility

    The facilities and services the site provider agrees to make available

    The conditions under which the site can be used

    The period during which the site can be used

    The priority to be given to concurrent users of the site in the event of acommon disaster

    The number of organizations that will be allowed to use the site concurrentlyin the event of a disaster

    How soon the site will be made available subsequent to a disaster

  • 8/10/2019 P6Ch4BCP&DRPPart4

    25/48

    Question

    A company has decided to outsource a thirdparty site for its alternate back-up and recovery

    process.

    What are the issues to be considered by thesecurity administrator while drafting the contract?

    (5 Marks) (May 2010)

    25

  • 8/10/2019 P6Ch4BCP&DRPPart4

    26/48

    Answer

    If a third party site is to be used for backup andrecovery purposes, security administrators must ensurethat a contract is written to cover the following issues

    How soon the site will be made availablesubsequent to a disaster

    The number of organizations that will be allowed to

    use the site concurrently in the event of a disaster The priority to be given to concurrent users of thesite in the event of a common disaster

    The period during which the site can be used

    26

  • 8/10/2019 P6Ch4BCP&DRPPart4

    27/48

    Answer

    The conditions under which the site can be used

    The facilities and services the site provider agrees to makeavailable

    What controls will be in place and working at the off-site

    facility

    The above are the main issues that should be covered while drafting acontract. These issues are often poorly specified in reciprocal

    agreements. Moreover, they can be difficult to enforce under areciprocal agreement because of the informal nature of the agreement

    27

  • 8/10/2019 P6Ch4BCP&DRPPart4

    28/48

    Question

    Discuss the various backup optionsconsidered by a security administratorwhen arranging alternate processingfacility.

    (4 Marks) (May 2011)

    28

  • 8/10/2019 P6Ch4BCP&DRPPart4

    29/48

    Answer

    Security administrators shouldconsider the following backup options

    while arranging alternate processingfacility:

    Cold site

    Hot site Warm site

    Reciprocal agreement

    29

  • 8/10/2019 P6Ch4BCP&DRPPart4

    30/48

    Answer

    Cold site

    If an organization can tolerate some down time, cold site backup mightbe appropriate

    A cold site has all the facilities needed to install a mainframe system,raised floors, air conditioning, power, communication lines, and so on

    An organization can establish its own cold site facility or enter into anagreement with another organization to provide a cold site facility

    30

  • 8/10/2019 P6Ch4BCP&DRPPart4

    31/48

    Answer

    Hot site

    If fast recovery is critical, an organization might

    need hot site backup

    All hardware and operations facilities will beavailable at the host site

    In some cases, software, data and supplies mightalso be stored there

    A hot site is expensive to maintain

    They are usually shared with other organizationsthat have hot site needs

    31

  • 8/10/2019 P6Ch4BCP&DRPPart4

    32/48

    Answer

    Warm site

    It provides an intermediate level of backup

    It has all cold site facilities in addition with hardware that might

    be difficult to obtain or install

    For example, a warm site might contain selected peripheralequipment plus a small mainframe with sufficient power tohandle critical applications in the short run

    32

  • 8/10/2019 P6Ch4BCP&DRPPart4

    33/48

    Answer

    Reciprocal agreement

    Two or more organizations might agreeto provide backup facilities to each otherin the event of one suffering a disaster

    This backup option is relatively cheap,but each participant must maintain

    sufficient capacity to operate another'scritical system

    33

  • 8/10/2019 P6Ch4BCP&DRPPart4

    34/48

    4.16 Disaster Recovery Procedural Plan

    Conditions for activating the plans

    Emergency procedures

    Fall-back procedures

    Resumption procedures

    Maintenance schedule

    Awareness and education activities

    Responsibilities of individuals

    34

  • 8/10/2019 P6Ch4BCP&DRPPart4

    35/48

    Disaster Recovery Procedural Plan

    35

    Resumption procedures, which describe the actions to be taken toreturn to normal business operations

    A maintenance schedule, which specifies how and when theplan will be tested, and the process for maintaining the plan

    Awareness and education activities, which are designed tocreate an understanding of the business continuity, process and

    ensure that the business continues to be effective

    The responsibilities of individuals describing who is responsible forexecuting which component of the plan. Alternatives should benominated as required

  • 8/10/2019 P6Ch4BCP&DRPPart4

    36/48

    Disaster Recovery Procedural Plan

    36

    List of phone numbers of employees in the event of an emergency

    Checklist for inventory taking and updating the contingency plan on aregular basis

    List of vendors doing business with the organization, their contact numbersand address for emergency purposes

    Contingency plan testing and recovery procedure

    Detailed description of the purpose and scope of the plan

    Contingency plan document distribution list

  • 8/10/2019 P6Ch4BCP&DRPPart4

    37/48

    Disaster Recovery Procedural Plan

    37

    Emergency phone listfor fire, police,

    hardware, software,suppliers, customers,back-up location, etc

    Medical procedure tobe followed in case of

    injury

    Back-up locationcontractual agreement,

    correspondences

    Insurance papers andclaim forms

    Primary computercentre hardware,

    software, peripheralequipment and

    software configuration

  • 8/10/2019 P6Ch4BCP&DRPPart4

    38/48

    Disaster Recovery Procedural Plan

    38

    Location of data and program files, data dictionary,documentation manuals, source and object codes and back-

    up media.

    Alternate manual procedures to be followed such aspreparation of invoices.

    Names of employees trained for emergency situation, firstaid and life saving techniques.

    Details of airlines, hotels and transport arrangements.

  • 8/10/2019 P6Ch4BCP&DRPPart4

    39/48

    Questions

    3. What do you understandby the term Disaster? What

    procedural plan do you

    suggest for disaster recovery?(10 Marks) (Nov 2008)

    4. (A) Explain the variousgeneral components of

    Disaster Recovery Plan

    (8 Marks) (Nov. 2011)

    39

  • 8/10/2019 P6Ch4BCP&DRPPart4

    40/48

    Answer

    The term disastercan be defined as anincident which jeopardizes business

    operations and/or human life. It could bedue to sabotage (human) or natural.

    Following is the procedural plans for disasterrecovery.

    Disaster Recovery Procedural Plan:Normally disaster recovery procedural plan

    is made when the system is normally working.After visualizing the disaster the action to be

    taken by different people of theorganization are to be documented.

    40

  • 8/10/2019 P6Ch4BCP&DRPPart4

    41/48

    Answer

    This recovery and planning document may includethe following areas

    The conditions for activating the plans, which describe the

    process to be followed before each plan, are activated.

    Emergency procedures, which describe the actions to betaken following an incident which jeopardises businessoperations and/or human life.

    This should include arrangements for public relationsmanagement and for effective liaison with appropriatepublic authorities e.g. police, fire, services and localgovernment.

    41

  • 8/10/2019 P6Ch4BCP&DRPPart4

    42/48

    Answer

    Fall-back procedures which describe the actions to be taken to moveessential business activities or support services to alternate temporarylocations, to bring business process back into operation in the requiredtime-scale

    Resumption procedures, which describe the actions to be taken to returnto normal business operations

    A maintenance schedule, which specifies how and when the plan will betested, and the process for maintaining the plan

    42

  • 8/10/2019 P6Ch4BCP&DRPPart4

    43/48

    Answer

    Awareness and education activities, which are designed to create anunderstanding of the business continuity, process and ensure that thebusiness continues to be effective

    The responsibilities of individuals describing who is responsible forexecuting which component of the plan. Alternatives should benominated as required

    Contingency plan document distribution list

    Detailed description of the purpose and scope of the plan

    43

  • 8/10/2019 P6Ch4BCP&DRPPart4

    44/48

    Answer

    Contingency plan testing and recoveryprocedure.

    List of vendors doing business with theorganization, their contact numbers and

    address for emergency purposes.

    Checklist for inventory taking andupdating the contingency plan on a

    regular basis.

    List of phone numbers of employees inthe event of an emergency.

    44

  • 8/10/2019 P6Ch4BCP&DRPPart4

    45/48

    Answer

    Emergency phone list for fire, police, hardware, software,suppliers, customers, back-up location, etc.

    Medical procedure to be followed in case of injury

    Back-up location contractual agreement, correspondences

    Insurance papers and claim forms

    Primary computer centre hardware, software, peripheralequipment and software configuration

    45

  • 8/10/2019 P6Ch4BCP&DRPPart4

    46/48

    Answer

    Location of data and program files, data dictionary,documentation manuals, source and object codes andback-up media

    Alternate manual procedures to be followed such aspreparation of invoices

    Names of employees trained for emergency situation,first aid and life saving techniques

    Details of airlines, hotels and transport arrangements

    46

  • 8/10/2019 P6Ch4BCP&DRPPart4

    47/48

    Summary47

    PART-4

    4.13 Types of Plans

    4.14 Types of Back-ups

    4.15 Alternate Processing Facility Arrangements

    4.16 Disaster Recovery Procedural Plan

  • 8/10/2019 P6Ch4BCP&DRPPart4

    48/48

    Thank you!

    48