Tendering (CONS6811) Lara Tookey

TENDERING #7

Preliminaries

Page 2: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

ACTIVITY (10 MIN) Working with your peers

So, you have received the SoQ and priced your own work, and you have selected your most competitive subcontractors quotes for inclusion in the tender ….

What other ‘costs’ still need to be considered / included in order to ascertain the tender price?

Page 3: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Tender

Mark Up (Profit)

Head Office Overheads

Preliminaries i.e. Site Overheads

Prime Costs + Provisional Cost + Own Sub-contractors + Own Labour + Materials + Plant

Adjudication

= gross bill

= net bill

Contingencies

Page 4: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Components of a Rate

• Remember, unit rates are a combination of rates for labour, plant, materials & sub-contractors.

• Only the direct site costs are included at this stage.

• Management are able to develop better appreciation for project if indirect costs are dealt with separately.

Page 5: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Pricing Preliminaries & General

Page 6: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Examine documents

Send out material & sub-contractor enquiries

Method statements & schedules

Programmes & Temporary works design

Site visit

PROJECT APPRECIATION & ENQUIRIES

Page 7: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

RESOURCES & PREPARATION OF THE ESTIMATE

Establish outputs for labour & plant

Select material & subbie quotations

Establish rates for labour & plant

Build up rates

Price preliminaries

Prepare estimator’s report

Page 8: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Definition

“The site cost of administering a project and providing general plant, site staff, facilities and site-based services and other items not included in all-in-rates”.

“The cost of providing for the above are not

practical or convenient to include in the unit rate.”

Page 9: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Qui

ck te

st to

see

if an

item

is P

&G

Is the expense incurred part of the permanent structure?

No

If the project did not exist, would the cost still

be incurred?

Yes – overhead

cost

No – P&G Cost

Yes – price in unit rate

Page 10: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

What is the purpose of the preliminaries section? • Make allowance for those costs which are

necessary for the running of the project but are not specifically related to any one item or operation.

Page 11: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

What is the function of the various sections in preliminaries? • Legal & general obligations – the Contract.

• Guarantees, insurance, etc.

• Project overheads & temporary requirements.

• Management of the works, site huts, programming, toilets, telephones, etc.

Page 12: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

What is the function of the various sections in preliminaries? • Special requirements – to meet particular

requirements of specific project. • Specific security requirements, limited access,

etc.

Page 13: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

P&G Clause

• “Tenderer's are referred to the Conditions of Contract, including the Invitation to Tender, Conditions of Tendering Sections and all associated Addendums. Tenderers are to make full allowances in their tender for the content and intent of these documents”

Page 14: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

• The prices and rates throughout the Schedule of Prices shall include (unless otherwise stated) all labour and materials including necessary nails, screws, spikes, plugs, glue or other fixings, waste on materials, conveyance and delivery, storage, unloading, returning packings, preparation, hoisting, lowering, setting, fitting and fixing in position, lapping of materials, square cutting, waste, the forming of fair edges, ends, angles, mitres and junctions between straight and raking or circular work unless specifically measured herein, all taxes payable, transit insurances, import duty and customs charges, awards and conditions payable to workers and also for profit, overheads and establishment charges. The prices and rates shall also include for all overtime and holiday work necessary to ensure delivery of the works on the date stated in the Contract Documents.

Page 15: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

• The words "Allow for Attendance" shall include for the Contractor to attend upon, unload, provide storage space and working space for all Sub-Contractors (except in such respects as the latter definitely undertake to provide their own attendance) and afford all firms or persons engaged upon the Works or requiring to take measurements or other legitimate business all reasonable facilities thereof and the use of such cranage, hoisting facilities, scaffolding, ladders, water, watching, lighting and power as required for the purpose of the Works.

Page 16: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

• Sections further sub-divided into Fixed, Value & Time related costs.

• “Fixed cost” • Those that do not vary with time

• Plant item – transportation to & from site involves two single costs which do not alter irrespective of whether the plant is on site for two or six weeks.

Page 17: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

• “Time related cost” • Those that do vary with time

• Once plant on site, consumer costs directly proportional to time

• “Value related cost”

• Based on the value of the contract

Page 18: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Management / Staffing of the project

Temporary works & services

Construction equipment

Access equipment /

systems

Temporary accommodation & storage

Charges, Levies,

Consultants

Heath & safety

Page 19: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Sequence of events - pricing of the preliminaries: Make notes of general requirements Temporary works, subcontract attendances

Prepare site layout indicating position of: Accommodation, access routes, storage areas,

services. Inspect site features & potential impact!

Use tender programme for planning Staff, plant & temporary works Read client’s specific requirements

Page 20: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Visit & Inspect Site

Take time inspecting site & preparing a report on all aspects of site conditions Inspection of sewers & checking of levels, open up

works for inspection; Location, site conditions i.e. fire risks, security risks,

radiation hazards, underground conditions Transportations costs Accommodation costs Possible cost of employing specialists for reports Provision of bulk bins & dumping of debris & waste.

Page 21: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

P&G Clause

• Allow for visiting and inspecting the Site and its surroundings to ascertain the nature and extent of the Works, the means of access thereto and any other matter or item which may influence the Contractor in making up the tender.

• Allow for uplifting the Building Consent as specified (The Principal has lodged for Consent and paid all fees).

Page 22: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Plant, Tools and Other Equipment

• Schedule of plant should be prepared at outset showing the cost, based on the length of time the plant is required and appropriate charge-out rate.

• Must consider: • Initial capital cost, depreciation, maintenance, loss of

interest on capital, licenses, fuel etc

• If not included in unit rate, plant must be priced in Prelims.

Page 23: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Temporary Facilities & Services

• Definition: Services required for carrying out the project works.

• Inclusion: Installation, operation, maintenance

and removal.

Page 24: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Temporary Facilities & Services

Power / Lighting / Heating Water / Sewer Telephone Stationery & postage Office equipment, desks, chairs, filing cabinets etc Computers (+ consumables) Humidity / temperature control Security & safety measures Perimeter fencing, lighting, alarm systems, cameras. Temporary electrics Waste skips

Page 25: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

• Mess sheds (incl tables, bench seating, vinyl floor covering, sink bench unit)

• Store sheds • Ablutions and latrines • Cost of erection, dismantling & removal, and

cartage to and from site of temporary buildings. • Labour & material for cleaning & general

maintenance incl consumables

Page 26: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Supervision

• Contractors employees partially or wholly on site to carry out general duties.

• Inclusions: Employees in head office carrying out work directly associated with the project. Salaries, overtime, travelling, fares.

• Exclusions: Managers in head office carrying out organization management and the occasional site visit.

Page 27: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Site Personnel (Management & Staff)

• Site Manager • General Foreman • Engineer & Assistants • Planning / Scheduling engineer • Quantity surveyor / Cost Engineer & Assistants • Sub-contract co-ordinator / purchasing office • Clerk / Typist • Security patrols / Night watchman / Guard dogs • Health & safety officer (First Aid) • Overtime payment & bonus;

Page 28: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Site Meetings

• All expenses incurred in organising, accommodating, attending and minuting site meetings must be included

• Generally based on records of similar jobs.

Page 29: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Hoardings & Scaffolding

• Temporary structures installed to protect workers and/or the public, to provide safe access to and around the site and to provide temporary support to existing work being altered or extended.

• Often a quotation is obtained from a specialist firm for supply, erection, hire and removal.

• Area of external wall to be covered usually stated in item description to assist in pricing.

Page 30: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Signboard

• Provision, erection, maintenance and removal.

• Sign writing for Contractor, Arch, principal consultants etc.

Page 31: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Insurance

• Insurance policies taken out in relation to construction site activity and associated items.

Page 32: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Footpath Crossing

• Could involve • Providing temporary protection to footpaths,

grass berms etc • Making good damage caused as required by

Local Authorities

Page 33: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Access Roads, Paths and Carparks

• Could involve • Provision of metal etc for temporary roading • Labour and plant of placing metal • Reinstatement of roads, grassed areas, as

required if damabed • Removal and making good

Page 34: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Temporary Services

• Installation, maintenance and removal of a variety of services, incl cost of all notices, permits & fees not covered in the building permit.

• Water • Drainage for temporary installations • Electricity • Telephones

Page 35: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Keep site free of water

• Dewatering, pumping or some other approved method to ensure site free from water at all times.

Page 36: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Security of the Works

• Night watchman &/or Security firm • Security alarm system

Page 37: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Cleaning Building ready for Occupation • Works carried out at completion of the

project works. • Housekeeping & fire safety on site, cleaning up

& reinstatement of works on completion.

Page 38: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Other things to think about

• Screens, barricades, rails and nightlights • Notices, permits and Fees • Protection of Public & Private Property • Contract Guarantee Bond • Deposit with Tender • Fire fighting equipment • Guarantees, warranties, testing and samples

Page 39: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

How do you think you could reduce preliminaries?!!

Page 40: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

How do you think you could reduce preliminaries?!! • Minimize temporary storage

• deliver to/near installation locations.

• Move materials once only, with cheapest labour possible.

• Maximise handling productivity • Use optimum equipment (capacity, availability,

etc)

Page 41: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Workshop Identification, and pricing of preliminaries.

Page 42: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Brief

• You are : • building a new administration building (159m2

GFA) and;

• Undertaking remedial modifications to 296m2 GFA.

• At a school, which will remain operational.

Page 43: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Page 44: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

• The new building comprises a single story structure with slab-on-ground concrete floor slab over reinforced concrete strip footings and pad foundations. The structure is light timber framed construction generally to NZS3910 (Conditions of Contract for Building and Civil Engineering Construction) and NZS3604 (Timber framed buildings).

Page 45: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

• Siteworks comprises the construction of a staff and visitor's carpark including associated timber retaining walls, hard landscaping elements including fencing, concrete paths, raised planter boxes and exterior lighting. Topsoil and grassing is required to part of the site but other soft landscaping (planting) is by Others.

Page 46: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

• It is envisaged that approximately 200 meters of perimeter security fencing will be required for the full length of the contract to comply with the School's Health and Safety policies and the project's specification. Note that part of the site perimeter is adjacent to existing buildings and it has been determined that there is no need for security fencing to these areas.

Page 47: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

• For the purposes of this brainstorm activity (primarily for determining Preliminary & General costings) you are to assume the contract period will be 8 (eight) calendar months commencing one month after acceptance of Tender.

Page 48: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

What are your initial thoughts?

Page 49: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

What issues do you have to deal with?

Page 50: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

Price out the following key items:

• 28 – 32 • 36, 37 • 39 • 45, 46, 47 • 48 • 58 • 69

Page 51: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

ACTIVITY (60 MIN) Working with your peers

Using the Preliminaries schedule provided, you are required to price out the following clauses:

• 29, 30 • 36, 37 • 39

• 45, 46, 47, 48 • 57, 58, 59 • 62, 63, 69

You will be required to submit your price, and provide details of your sources.

Page 52: Preliminariescons6811.weebly.com/uploads/4/2/6/3/42631959/s07_ppts.pdf · “The site cost of administering a project and providing general plant, site staff, facilities and site-based

Tendering (CONS6811) Lara Tookey

YOUR ASSESSMENTS