Upload
oscar-kelly
View
217
Download
1
Tags:
Embed Size (px)
Citation preview
SCHOOL CONSTRUCTION UPDATE November 4, 2015
OVERVIEW
Review of completed projects
Update on large construction projects
Update on remaining projects
COMPLETED PROJECTS Athletic Complexes $12M
Mat-Su Day School $12.4M
Valley Pathways $22.5M
Big Lake ES Reno Ph I $2.2M
Houston/Palmer Jr MS Lockers $335K
Flooring Replacements Ph I $2M
Palmer HS Mechanical Upgrades $5.5M
Trapper Creek ES Roof $1M
Swanson ES Ext Upgrades $200K
Willow ES Roof $1.3M
Joe Redington Sr MS/HS $65M
CTHS Addition $16M
Houston HS Exterior Siding $600K
ADA Upgrades District Wide $1.5M
Washroom Upgrade District Wide $800K
Palmer HS, Palmer Jr MS, Cottonwood Creek ES, Pioneer Peak ES Roofs $3.8M
DENA’INA ES $26.5M Design: Bettisworth North
Construction: FE Const.
44,224 SF
K through 5 school Work started April 2015 Approx. 50% complete
Occupy fall 2016
DENA’INA ES
ExteriorInterior
IDITAROD ES $25.2M Design: MCG
Construction: Collins
50,605 SF replacement school
Work started May 2015 Approx. 55% complete Occupy fall 2016
IDITAROD ES Exterior Interior
FRONTERAS CHARTER SCHOOL $6.9M Contractor: Howdie Const.
Funded by USDA loan and $500K from MSB
Foundation complete and framing is in progress
Access road from Seward Meridian is in place
Construction schedule is to occupy Jul/Aug 2016
FRONTERAS CHARTER SCHOOLFraming in Progress
ATHLETIC FIELD IMPROVEMENTS $6.4M Play court upgrades at Finger Lake, Snowshoe, Larson,
Glacier View and Houston High completed in 2014
Summer 2015 work completed: - Su-Valley HS synthetic track - Palmer Jr MS track and new bleachers - Glacier View ice rink upgrades, softball field upgrades, new water line, fencing and ADA parking- Iditarod ball field improvements
Spring 2016: Install Iditarod softball/baseball turf in-fields
ADDITIONAL PROJECTS Back-Up Generators, District Wide $2.6M - Design: AMC Engineering, 1oo% design - Base bid includes Wasilla MS, Wasilla HS and Palmer HS - MSBSD approved 3 manufactures and will be advertised this month
Big Lake ES Renovation Ph II $800K, and ADA Parking Upgrades $200K
- Work includes flooring, lighting, washroom partitions, and parking lot - Flooring and parking lot were complete prior to school start - Bathroom partitions are near completion - Lighting is currently advertised with bids due December 1
District Wide HVAC Upgrades $7.1M - Design: PDC Engineers, Contractor: Wirtanen Construction - Scope includes upgrading building controls from pneumatic to direct digital controls and is approximately 40% complete - Work will continue into the 2017 school year
ADDITIONAL PROJECTS cont. District Wide Energy Upgrades $3.1M (Gym Lighting and Windows) - Design: Architects Alaska, Construction: Haakenson Electric -- New LED Gym lighting: Wasilla HS, Burchell, Houston MS, Cottonwood Creek, Pioneer Peak, Larsen, Shaw, and Snowshoe, Big Lake, Willow, Swanson, Sherrod, and Goose Bay are complete -- Palmer Jr MS gym lighting will be complete this month - Partial window replacements at 18 schools will be advertised this winter for summer 2016 construction
Flooring Replacements $200K (funded by flooring bond balance) - Scope includes new poured rubber gym flooring at Sherrod, Swanson and Pioneer Peak Elementary Schools - Work will occur over Christmas and spring breaks
Roof Bond Balance $800K - Replace Sutton ES roof summer 2016
QUESTIONS