SCHOOL CONSTRUCTION UPDATE November 4, 2015

OVERVIEW Review of completed projects Update on large construction projects Update on remaining projects

Embed Size (px)

Citation preview

Page 1: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

SCHOOL CONSTRUCTION UPDATE November 4, 2015

Page 2: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

OVERVIEW

Review of completed projects

Update on large construction projects

Update on remaining projects

Page 3: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

COMPLETED PROJECTS Athletic Complexes $12M

Mat-Su Day School $12.4M

Valley Pathways $22.5M

Big Lake ES Reno Ph I $2.2M

Houston/Palmer Jr MS Lockers $335K

Flooring Replacements Ph I $2M

Palmer HS Mechanical Upgrades $5.5M

Trapper Creek ES Roof $1M

Swanson ES Ext Upgrades $200K

Willow ES Roof $1.3M

Joe Redington Sr MS/HS $65M

CTHS Addition $16M

Houston HS Exterior Siding $600K

ADA Upgrades District Wide $1.5M

Washroom Upgrade District Wide $800K

Palmer HS, Palmer Jr MS, Cottonwood Creek ES, Pioneer Peak ES Roofs $3.8M

Page 4: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

DENA’INA ES $26.5M Design: Bettisworth North

Construction: FE Const.

44,224 SF

K through 5 school Work started April 2015 Approx. 50% complete

Occupy fall 2016

Page 5: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

DENA’INA ES

ExteriorInterior

Page 6: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

IDITAROD ES $25.2M Design: MCG

Construction: Collins

50,605 SF replacement school

Work started May 2015 Approx. 55% complete Occupy fall 2016

Page 7: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

IDITAROD ES Exterior Interior

Page 8: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

FRONTERAS CHARTER SCHOOL $6.9M Contractor: Howdie Const.

Funded by USDA loan and $500K from MSB

Foundation complete and framing is in progress

Access road from Seward Meridian is in place

Construction schedule is to occupy Jul/Aug 2016

Page 9: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

FRONTERAS CHARTER SCHOOLFraming in Progress

Page 10: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

ATHLETIC FIELD IMPROVEMENTS $6.4M Play court upgrades at Finger Lake, Snowshoe, Larson,

Glacier View and Houston High completed in 2014

Summer 2015 work completed: - Su-Valley HS synthetic track - Palmer Jr MS track and new bleachers - Glacier View ice rink upgrades, softball field upgrades, new water line, fencing and ADA parking- Iditarod ball field improvements

Spring 2016: Install Iditarod softball/baseball turf in-fields

Page 11: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

ADDITIONAL PROJECTS Back-Up Generators, District Wide $2.6M - Design: AMC Engineering, 1oo% design - Base bid includes Wasilla MS, Wasilla HS and Palmer HS - MSBSD approved 3 manufactures and will be advertised this month

Big Lake ES Renovation Ph II $800K, and ADA Parking Upgrades $200K

- Work includes flooring, lighting, washroom partitions, and parking lot - Flooring and parking lot were complete prior to school start - Bathroom partitions are near completion - Lighting is currently advertised with bids due December 1

District Wide HVAC Upgrades $7.1M - Design: PDC Engineers, Contractor: Wirtanen Construction - Scope includes upgrading building controls from pneumatic to direct digital controls and is approximately 40% complete - Work will continue into the 2017 school year

Page 12: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

ADDITIONAL PROJECTS cont. District Wide Energy Upgrades $3.1M (Gym Lighting and Windows) - Design: Architects Alaska, Construction: Haakenson Electric -- New LED Gym lighting: Wasilla HS, Burchell, Houston MS, Cottonwood Creek, Pioneer Peak, Larsen, Shaw, and Snowshoe, Big Lake, Willow, Swanson, Sherrod, and Goose Bay are complete -- Palmer Jr MS gym lighting will be complete this month - Partial window replacements at 18 schools will be advertised this winter for summer 2016 construction

Flooring Replacements $200K (funded by flooring bond balance) - Scope includes new poured rubber gym flooring at Sherrod, Swanson and Pioneer Peak Elementary Schools - Work will occur over Christmas and spring breaks

Roof Bond Balance $800K - Replace Sutton ES roof summer 2016

Page 13: OVERVIEW  Review of completed projects  Update on large construction projects  Update on remaining projects

QUESTIONS