1 ARTISAN 1st ARTISAN 1st Plenary Plenary Meeting Meeting May 8th – 9th 2012 Overview of activities of the first six months and of the next six months Angelo Frascella

Overview of activities of the first six months and of the next six months

  • Upload
    keaira

  • View
    32

  • Download
    2

Embed Size (px)

DESCRIPTION

Overview of activities of the first six months and of the next six months. Angelo Frascella. We are here !. Ended Tasks. Running Tasks. Starting Tasks. In synthesis. Data Structure Scenarios and use case/services at good point 7 technical deliverable has to be delivered within M12 - PowerPoint PPT Presentation

Citation preview

Page 1: Overview of activities  of  the first six months  and of the next six months

1ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

Overview of activities of the first six months

and of the next six months Angelo Frascella

Page 2: Overview of activities  of  the first six months  and of the next six months

2ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

2

We are here!

Page 3: Overview of activities  of  the first six months  and of the next six months

3ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

Task Respons. Foreseen End Deliverable Status

1.1 User Requirements

DITF M6 → April 30th Results in D1.2 (M9)

Available excel file with scenarios,

1.3 Mapping of enterprise data

DOMINA M6 → April 30th D1.1 (M6) Deliverable available (to review)

T1.4 Services and tools definitions

AUEB M6 → April 30th D1.3 (M9) Deliverable at good point of preparation

T2.1 Infrastructure capturing and storing energy data

AUEB M5 → March 31th Results in D2.1 (M7)

Draft deliverable available (to review)

Ended Tasks

Page 4: Overview of activities  of  the first six months  and of the next six months

4ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

Task Respons. Foreseen End Deliverable Status

T2.2 Consumption of supply chain processes…

DITF M7 → May 31th Results in D2.1 (M7)

Index under construction

T3.1 Energy-driven algorithms

AUEB M8 → June 30th D3.1 (M8) Running (no working draft available)

T1.2 Energy Efficiency Indices

ENEA M9 → July 31th Results in D1.2 (M9)

Energy audit under analysis. Deliverable under construction (still not distributed)

T5.1 Overall Architecture

INTRA M11 → September 30th

D5.1 (non official interim: M11 and M16)

Running (index and some parts available)

T2.3 Energy Consumption reduction tool

ENEA M12 → October 31th

D2.2 (M12) Running (no working draft available)

Running Tasks

Page 5: Overview of activities  of  the first six months  and of the next six months

5ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

Task Respons. Start date Foreseen End Deliverable

T3.2 Optimized operations Tools

ATC M5 → March 1st

M10 → August 31th

D3.2 (M10)

T2.4 Energy Monitoring Tools Design

ATC M6 → April 1st M12 → October 31th

D2.2 (M12)

T2.5 Energy Monitoring Tools Development

INTRA M8 → June 1th M12 → October 31th

D2.4

Task 4.1 Energy Forecasts and Energy Trading Services

ENEA M8 → June 1th M12 → October 31th

D4.1 (M12 interim version)

Task 4.2 Carbon Trading Services

AUEB M9→ July 1th M13 → November 30th

D4.2 (M10 interim version)

Starting Tasks

Page 6: Overview of activities  of  the first six months  and of the next six months

6ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

• Data Structure Scenarios and use case/services at good point

• 7 technical deliverable has to be delivered within M12 One is almost ready (D1.1 – M6) An incoming one (D2.1 – M7) collecting results from T2.1

and T2.2 seems in at good point for T2.1, still not available for T2.2 part

Next deliverables: D3.1 – M8 (AUEB), D1.2 – M9 (DITF), D1.3 – M9 (AUEB), D3.2 –

M10 (ATC), D2.2 – M12 (ATC)

In synthesis

Page 7: Overview of activities  of  the first six months  and of the next six months

7ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

Some general results required in the first months

• First needed results inside the project (from KoM decisions)– WP1:

• Scenarios definition - DITF => done• Services and tools definitions – AUEB => done• Identification of machine and processes - DOMINA=> running• Assessment of scenarios with Piacenza – ENEA => done• Definition of parameter that have been optimized – ENEA => running• Collecting and analysis of consumption data – ENEA => running• Validation of Scenarios by IIG – EURATEX => ongoing

– WP2:• Needed data and meters - AUEB-RC => to do?• Available data and meters – DOMINA => to do

Page 8: Overview of activities  of  the first six months  and of the next six months

8ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

Some general results required in the first months

– WP 3:• Set of real data about production scheduling and routing collected in the

space of two weeks – DOMINA and DITF => To do

– WP 5:• Definition of questions that need an answer in order to allow to define

the architecture requirements – INTRA => done?• Decision about UML tool to use – INTRA => done• First analysis about data format for interfacing ERP and MES (from

TEXWIN) and supply chain partners (MODA-ML) (ENEA and DOMINA) => to do

– WP 8• Wiki structure and content about ARTISAN Architecture => done (and,

up to now, not used)

Page 9: Overview of activities  of  the first six months  and of the next six months

9ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

Deliverable dashboard on the web site

Please, watch the dashboard: http://www.artisan-project.eu/artisan/imple/pgcl.asp?lingua=en&p=462&node_id=7.4 Or, by menu, RESERVED AREA -> DELIVERABLE LIST

Page 10: Overview of activities  of  the first six months  and of the next six months

10ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

ARTISAN 1st ARTISAN 1st Plenary MeetingPlenary MeetingMay 8th – 9th 2012

• Don’t forget to send me filled templates about:

– Activities reporting for the first six months

– Periodic Progress report for the first six months

– Timesheet for the first six months

A remainder

Page 11: Overview of activities  of  the first six months  and of the next six months