SCHEDULE OF DISCREPANCY BETWEEN AFC, AS-BUILT, AND ACTUAL ON SITE
ITEM LOCATION DESCRIPTION REF. DRAWING REMARK / ACTION
01BCS / UTILITY AIR
COMPRESSOR
Toe wall construct half way, grid line A,3-4 missing due to
cable conduit fixed inside toe wall line. Without any STQ PDPC
cover this portion with steel plate.
SSGP-05-BU-S-3313 (AFC) REV X1.Inform verbally to construction team.
STQ? NCR?
02 BRO / ADMIN BUILDINGIf refer to AFC drawing this door (AHU 1 room) shall have
vision panel, but install at site none.
SSGP-05-BU-S-1306 page 1, 5 and
6 of 9 (AFC) REV X1.
Issued letter to PDPC Ref. No. 9000-
SSGP-10-01 (L-5298) dated 11 March
2015.
To date no action.
03 BRO / AUXILIARY BUILDINGRefer to AFC drawing door D17 / D18 at Battery and APU room
are excluded panic bar, but on site PDPC install.SSGP-05-BU-S-1305 (AFC) REV X0
Inform verbally to construction team.
STQ? NCR?
04BRO / WAREHOUSE AND
WORKSHOP
Refer to AFC drawing door type DR06 and DR07 shall have top
hung window type WR28 & WR27, actual on site not
constructed.
SSGP-05-BU-S-1303 (AFC) REV X0Inform verbally to construction team.
STQ? NCR?
05 BRO / ADMIN BUILDINGAs per AFC drawing, door type DR36 and DR34 shall have
vision panel, but install on site not as per AFC.
SSGP-05-BU-S-1306 (AFC) REV X1.
and STQ 430
Issued letter to PDPC Ref. No. 9000-
SSGP-10-01 (L-5298) dated 11 March
2015.
To date no action.
06BRO / WAREHOUSE AND
WORKSHOP
Gas Store at Warehouse and workshop(BRO), M.S gate and
M.S grill not yet install.
SSGP-05-BU-S-1303 page 1 of 7 rev
X0 (AFC)
Inform verbally to construction team.
STQ? NCR?
07BRO / WAREHOUSE AND
WORKSHOP
Door Type DR12 at A.H.U room install excluded vision panel,
not as per AFC drawing with vision panel.SSGP-05-BU-S-1303 (AFC) REV X0
Issued letter to PDPC Ref. No. 9000-
SSGP-10-01 (L-5298) dated 11 March
2015.
To date no action.
08 BRO / AUXILIARY BUILDINGAll louvers to have galvanized mild steel hoods. Not install at
site.SSGP-05-BU-S-1305 (AFC) REV X0
Inform verbally to construction team.
STQ? NCR?
09 BRO / AUXILIARY BUILDINGAs per AFC drawing door type DO1 at waiting/lounge area is
Aluminium type and not pressed steel door type.SSGP-05-BU-S-1305 (AFC) REV X0
Inform verbally to construction team.
STQ? NCR?
10 BMS / AUXILIARY BUILDINGAs per AFC drawing door type DR105 & DR106 are fitted with
panic bolt/bar, but on site not yet install.SSGP-05-BU-S-1308 (AFC) REV X0
Inform verbally to construction team.
STQ? NCR?
11 BCS AND BMS STATION
As per contract document section 11.0 (11.3.9.8) Permanent
reference monument / control point (Inclding Elevation, X and
Y co-ordinates), as at site not yet install.
ITB - SECTION 11.0
(CONSTRUCTION) page 34 of 120
Inform verbally to construction team.
STQ? NCR?
12 BCS / INFRONT BV 121
As per AFC, there is a stream in front of BCS/BV121, however
after construction completed, PDPC not reinstate back the
stream according to AFC drawing.
SSGP-05-BU-C-2301 (AFC) REV X2,
ITB - SECTION 11.0
(CONSTRUCTION) page 9 of 120
Inform verbally to construction team.
STQ? NCR?
13 BRO / SESCOFencing for SESCO(2m high) , Lower than BCS fencing(2.85m
high)SSGP-00-GN-C-1004 (AFC) REV X0.
Inform verbally to construction team.
STQ? NCR?
14BCS / BRO JKR ROAD SIDE
DRAIN
As per AFC, JKR road side drain is a concrete drain, however
after widening existing JKR road completed, PDPC re-construct
this drain become earth drain and not RCC drain as per AFC
drawing.
SSGP-05-BU-C-3302 (AFC) REV X1Inform verbally to construction team.
STQ? NCR?
15BCS / GATE IN FRONT
COMPRESSOR STATION 1
Warning sign near gate in front of compressor station 1, the
spelling for "stesen pemampat"(compressor station) is wrong.
"PEMAMPAT" become "PENAMPAT". PDPC shall make
correction.
SSGP-00-GN-L-1015 (AFC) REV X0Inform verbally to construction team.
STQ? NCR?
16 BMS Pressurized Fire & water system and Fire Suppression System N/AAwaiting detail engineering from
PDPC
17
BCS / COMPRESSOR
BUILDING - TURBINE
EXAUST STACK
Emmision Sampling Port and accordance to EQA 2014 N/AIssued letter to PDPC to do
engineering and installation.
18 BMS / AUXILIARY BUILDINGSite Notification(SN) - Fuel Gas Creating Hazardous Area and
Fire risk in APU room.
Ref. No. TR. No. : 9000-ssgp-12-08
(T-6984) Dated : 17 Jan 2014.
Drwg No. SSGP-05-BU-P-0501
(AFC) REV X2
PDPC to submit proposal and PCSB to
review.