SCHEDULE OF DISCREPANCY BETWEEN AFC, AS-BUILT, AND ACTUAL ON SITE ITEM LOCATION DESCRIPTION REF. DRAWING REMARK / ACTION 01 BCS / UTILITY AIR COMPRESSOR Toe wall construct half way, grid line A,3-4 missing due to cable conduit fixed inside toe wall line. Without any STQ PDPC cover this portion with steel plate. SSGP-05-BU-S-3313 (AFC) REV X1. Inform verbally to construction team. STQ? NCR? 02 BRO / ADMIN BUILDING If refer to AFC drawing this door (AHU 1 room) shall have vision panel, but install at site none. SSGP-05-BU-S-1306 page 1, 5 and 6 of 9 (AFC) REV X1. Issued letter to PDPC Ref. No. 9000- SSGP-10-01 (L-5298) dated 11 March 2015. To date no action. 03 BRO / AUXILIARY BUILDING Refer to AFC drawing door D17 / D18 at Battery and APU room are excluded panic bar, but on site PDPC install. SSGP-05-BU-S-1305 (AFC) REV X0 Inform verbally to construction team. STQ? NCR? 04 BRO / WAREHOUSE AND WORKSHOP Refer to AFC drawing door type DR06 and DR07 shall have top hung window type WR28 & WR27, actual on site not constructed. SSGP-05-BU-S-1303 (AFC) REV X0 Inform verbally to construction team. STQ? NCR? 05 BRO / ADMIN BUILDING As per AFC drawing, door type DR36 and DR34 shall have vision panel, but install on site not as per AFC. SSGP-05-BU-S-1306 (AFC) REV X1. and STQ 430 Issued letter to PDPC Ref. No. 9000- SSGP-10-01 (L-5298) dated 11 March 2015. To date no action. 06 BRO / WAREHOUSE AND WORKSHOP Gas Store at Warehouse and workshop(BRO), M.S gate and M.S grill not yet install. SSGP-05-BU-S-1303 page 1 of 7 rev X0 (AFC) Inform verbally to construction team. STQ? NCR? 07 BRO / WAREHOUSE AND WORKSHOP Door Type DR12 at A.H.U room install excluded vision panel, not as per AFC drawing with vision panel. SSGP-05-BU-S-1303 (AFC) REV X0 Issued letter to PDPC Ref. No. 9000- SSGP-10-01 (L-5298) dated 11 March 2015. To date no action. 08 BRO / AUXILIARY BUILDING All louvers to have galvanized mild steel hoods. Not install at site. SSGP-05-BU-S-1305 (AFC) REV X0 Inform verbally to construction team. STQ? NCR? 09 BRO / AUXILIARY BUILDING As per AFC drawing door type DO1 at waiting/lounge area is Aluminium type and not pressed steel door type. SSGP-05-BU-S-1305 (AFC) REV X0 Inform verbally to construction team. STQ? NCR? 10 BMS / AUXILIARY BUILDING As per AFC drawing door type DR105 & DR106 are fitted with panic bolt/bar, but on site not yet install. SSGP-05-BU-S-1308 (AFC) REV X0 Inform verbally to construction team. STQ? NCR? 11 BCS AND BMS STATION As per contract document section 11.0 (11.3.9.8) Permanent reference monument / control point (Inclding Elevation, X and Y co-ordinates), as at site not yet install. ITB - SECTION 11.0 (CONSTRUCTION) page 34 of 120 Inform verbally to construction team. STQ? NCR? 12 BCS / INFRONT BV 121 As per AFC, there is a stream in front of BCS/BV121, however after construction completed, PDPC not reinstate back the stream according to AFC drawing. SSGP-05-BU-C-2301 (AFC) REV X2, ITB - SECTION 11.0 (CONSTRUCTION) page 9 of 120 Inform verbally to construction team. STQ? NCR? 13 BRO / SESCO Fencing for SESCO(2m high) , Lower than BCS fencing(2.85m high) SSGP-00-GN-C-1004 (AFC) REV X0. Inform verbally to construction team. STQ? NCR? 14 BCS / BRO JKR ROAD SIDE DRAIN As per AFC, JKR road side drain is a concrete drain, however after widening existing JKR road completed, PDPC re-construct this drain become earth drain and not RCC drain as per AFC drawing. SSGP-05-BU-C-3302 (AFC) REV X1 Inform verbally to construction team. STQ? NCR? 15 BCS / GATE IN FRONT COMPRESSOR STATION 1 Warning sign near gate in front of compressor station 1, the spelling for "stesen pemampat"(compressor station) is wrong. "PEMAMPAT" become "PENAMPAT". PDPC shall make correction. SSGP-00-GN-L-1015 (AFC) REV X0 Inform verbally to construction team. STQ? NCR? 16 BMS Pressurized Fire & water system and Fire Suppression System N/A Awaiting detail engineering from PDPC 17 BCS / COMPRESSOR BUILDING - TURBINE EXAUST STACK Emmision Sampling Port and accordance to EQA 2014 N/A Issued letter to PDPC to do engineering and installation. 18 BMS / AUXILIARY BUILDING Site Notification(SN) - Fuel Gas Creating Hazardous Area and Fire risk in APU room. Ref. No. TR. No. : 9000-ssgp-12-08 (T-6984) Dated : 17 Jan 2014. Drwg No. SSGP-05-BU-P-0501 (AFC) REV X2 PDPC to submit proposal and PCSB to review. C:\Users\localid\Desktop\Overall Discrepancy between asbuilt and actual for BCS and BMS status.xlsx 1 of 1 4/2/2015

Overall Discrepancy Between Asbuilt and Actual for BCS and BMS Status

Embed Size (px)

DESCRIPTION

ok

Citation preview

  • SCHEDULE OF DISCREPANCY BETWEEN AFC, AS-BUILT, AND ACTUAL ON SITE

    ITEM LOCATION DESCRIPTION REF. DRAWING REMARK / ACTION

    01BCS / UTILITY AIR

    COMPRESSOR

    Toe wall construct half way, grid line A,3-4 missing due to

    cable conduit fixed inside toe wall line. Without any STQ PDPC

    cover this portion with steel plate.

    SSGP-05-BU-S-3313 (AFC) REV X1.Inform verbally to construction team.

    STQ? NCR?

    02 BRO / ADMIN BUILDINGIf refer to AFC drawing this door (AHU 1 room) shall have

    vision panel, but install at site none.

    SSGP-05-BU-S-1306 page 1, 5 and

    6 of 9 (AFC) REV X1.

    Issued letter to PDPC Ref. No. 9000-

    SSGP-10-01 (L-5298) dated 11 March

    2015.

    To date no action.

    03 BRO / AUXILIARY BUILDINGRefer to AFC drawing door D17 / D18 at Battery and APU room

    are excluded panic bar, but on site PDPC install.SSGP-05-BU-S-1305 (AFC) REV X0

    Inform verbally to construction team.

    STQ? NCR?

    04BRO / WAREHOUSE AND

    WORKSHOP

    Refer to AFC drawing door type DR06 and DR07 shall have top

    hung window type WR28 & WR27, actual on site not

    constructed.

    SSGP-05-BU-S-1303 (AFC) REV X0Inform verbally to construction team.

    STQ? NCR?

    05 BRO / ADMIN BUILDINGAs per AFC drawing, door type DR36 and DR34 shall have

    vision panel, but install on site not as per AFC.

    SSGP-05-BU-S-1306 (AFC) REV X1.

    and STQ 430

    Issued letter to PDPC Ref. No. 9000-

    SSGP-10-01 (L-5298) dated 11 March

    2015.

    To date no action.

    06BRO / WAREHOUSE AND

    WORKSHOP

    Gas Store at Warehouse and workshop(BRO), M.S gate and

    M.S grill not yet install.

    SSGP-05-BU-S-1303 page 1 of 7 rev

    X0 (AFC)

    Inform verbally to construction team.

    STQ? NCR?

    07BRO / WAREHOUSE AND

    WORKSHOP

    Door Type DR12 at A.H.U room install excluded vision panel,

    not as per AFC drawing with vision panel.SSGP-05-BU-S-1303 (AFC) REV X0

    Issued letter to PDPC Ref. No. 9000-

    SSGP-10-01 (L-5298) dated 11 March

    2015.

    To date no action.

    08 BRO / AUXILIARY BUILDINGAll louvers to have galvanized mild steel hoods. Not install at

    site.SSGP-05-BU-S-1305 (AFC) REV X0

    Inform verbally to construction team.

    STQ? NCR?

    09 BRO / AUXILIARY BUILDINGAs per AFC drawing door type DO1 at waiting/lounge area is

    Aluminium type and not pressed steel door type.SSGP-05-BU-S-1305 (AFC) REV X0

    Inform verbally to construction team.

    STQ? NCR?

    10 BMS / AUXILIARY BUILDINGAs per AFC drawing door type DR105 & DR106 are fitted with

    panic bolt/bar, but on site not yet install.SSGP-05-BU-S-1308 (AFC) REV X0

    Inform verbally to construction team.

    STQ? NCR?

    11 BCS AND BMS STATION

    As per contract document section 11.0 (11.3.9.8) Permanent

    reference monument / control point (Inclding Elevation, X and

    Y co-ordinates), as at site not yet install.

    ITB - SECTION 11.0

    (CONSTRUCTION) page 34 of 120

    Inform verbally to construction team.

    STQ? NCR?

    12 BCS / INFRONT BV 121

    As per AFC, there is a stream in front of BCS/BV121, however

    after construction completed, PDPC not reinstate back the

    stream according to AFC drawing.

    SSGP-05-BU-C-2301 (AFC) REV X2,

    ITB - SECTION 11.0

    (CONSTRUCTION) page 9 of 120

    Inform verbally to construction team.

    STQ? NCR?

    13 BRO / SESCOFencing for SESCO(2m high) , Lower than BCS fencing(2.85m

    high)SSGP-00-GN-C-1004 (AFC) REV X0.

    Inform verbally to construction team.

    STQ? NCR?

    14BCS / BRO JKR ROAD SIDE

    DRAIN

    As per AFC, JKR road side drain is a concrete drain, however

    after widening existing JKR road completed, PDPC re-construct

    this drain become earth drain and not RCC drain as per AFC

    drawing.

    SSGP-05-BU-C-3302 (AFC) REV X1Inform verbally to construction team.

    STQ? NCR?

    15BCS / GATE IN FRONT

    COMPRESSOR STATION 1

    Warning sign near gate in front of compressor station 1, the

    spelling for "stesen pemampat"(compressor station) is wrong.

    "PEMAMPAT" become "PENAMPAT". PDPC shall make

    correction.

    SSGP-00-GN-L-1015 (AFC) REV X0Inform verbally to construction team.

    STQ? NCR?

    16 BMS Pressurized Fire & water system and Fire Suppression System N/AAwaiting detail engineering from

    PDPC

    17

    BCS / COMPRESSOR

    BUILDING - TURBINE

    EXAUST STACK

    Emmision Sampling Port and accordance to EQA 2014 N/AIssued letter to PDPC to do

    engineering and installation.

    18 BMS / AUXILIARY BUILDINGSite Notification(SN) - Fuel Gas Creating Hazardous Area and

    Fire risk in APU room.

    Ref. No. TR. No. : 9000-ssgp-12-08

    (T-6984) Dated : 17 Jan 2014.

    Drwg No. SSGP-05-BU-P-0501

    (AFC) REV X2

    PDPC to submit proposal and PCSB to

    review.