Upload
jack-pearson
View
223
Download
2
Tags:
Embed Size (px)
Citation preview
Outsourcing Desktop Initiative for NASA
Lessons Learned and Critical Success Factors
A Thought Leadership Forum: University of Maryland
Center for Public Policy and Private EnterpriseQueenstown, Maryland
Darryl A. SmithDeputy Program Manager
Monday, November 15, 2004
2
Outsourcing Desktop Initiative for NASA
Why Outsource?
Share/transfer risks.
Increased need for system and product interoperability across the enterprise.
Need to improve corporate focus. Recruitment and retention of skilled personnel. No leverage to introduce world-class capabilities. Lack of insight into true operating costs
3
Outsourcing Desktop Initiative for NASA
Established Agencywide team that took a corporate perspective
Worked closely with other major Agency initiatives to ensure coordination and appropriate interfaces.
Examined other “Seat Management” endeavors. Conducted Market Research Developed Center Cost Baseline Concept Requested that vendors propose both
heterogeneous and homogeneous solutions. Established an aggressive schedule. Ensured availability to other Agencies through
partnership with GSA Communicated, Communicated, Communicated
NASA Strategy
4
Outsourcing Desktop Initiative for NASA
Structuring the Contract
Invest heavily in requirements definition A delicate balance of specifics and ambiguities A “Keep it Simple” approach to metrics Make it Performance-Based Incentives for good performance Fixed price Perform due diligence before award Establish a baseline commitment
5
Outsourcing Desktop Initiative for NASA
The Implementation Challenges Insufficient change management strategy; magnitude of
cultural changes underestimated– Change from cost-plus to fixed price contracting– “Loss of control” by the customers
•Ownership, level-of-effort personal support, “buy what you want, when you want it”
– Strong emotional issue with the customer– Limited and inconsistent business processes to
interface with ODIN No Agencywide policy on ODIN implementation
– Inconsistent scope across the Centers Lack of authority in the ODIN Program Office Inconsistent expectations among Agency, ODIN
Program, ODIN contractors, and customers Contractor performance and service delivery issues at
the Centers
The Implementation Challenges - Continued
Ames Research Center - ARC
Stennis Space Center - SSC
Glenn Research Center - GRC
NASA Headquarters - HQ
Dryden Flight Research Center - DFRC
Goddard Space Flight Center - GSFC
Langley Research Center - LaRC
Johnson Space Center - JSC
Marshall Space Flight Center - MSFC
Kennedy Space Center - KSC
6
7
NASA Chief Information Officer (CIO)(Code V)
NASA/GSFC CIO
NASA CIO Board
Agency ODIN Program
Manager and CO
NASA CFO
CommunityThird Party
Testing (IV&V)
Contractor (Alterion)
ODIN VENDORS:*Lockheed Martin
*OAOSAICCSC
DynCorpNorthrup Gruman
Diginet(*)Denotes Active Delivery
Orders
GSA (GWAC)
NASA Enterprise/
Center DOCOTRs,
TMRs & DOCOs
Tier One Original Equipment Manufacturers (OEMs) e.g., Apple, HP, Dell, Toshiba
ODIN Organizational Structure
LegendCFO – Chief Financial OfficerCIO – Chief Information OfficerCO – Contracting OfficerDOCO – Delivery Order Contracting OfficerDOCOTR – Delivery Order Contracting Officer Technical RepresentativeGSA – General Services AdministrationGWAC – Government-wide Acquisition ContractTMR – Technical Management Representative
Outsourcing Desktop Initiative for NASA
5/25/2000
Lockheed Martin OAO*
GSFC DFRC GRC ARC LaRC HQ JSC KSC MSFC SSC
GSFC awarded seven performance based, fixed-price, Indefinite Delivery/Indefinite Quantity (IDIQ) contracts in June 1998
Contracts have a 12-year period of performance. Centers award delivery orders up to 3-year period of
performance Current ODIN contractor and supported centers represented
below:
* Wholly owned subsidiary of Lockheed Martin
Contract Overview
8
Lockheed Martin
9
Outsourcing Desktop Initiative for NASA Roles and Responsibilities ODIN contractor is responsible for:
Selecting systems, products and services; Establishing staffing levels; Establishing SLAs with non-ODIN contractors; Meeting the requirements for interoperability, functionality,
and maintaining configuration control; Complying with all applicable Agency IT standards; and Asset/Resource Tracking
Government is responsible for: Establishing IT standards; Establishing Center-level Configuration Control boards
(CCB); Approving and funding infrastructure upgrades; Maintaining “Smart Buyer” capability.
10
Outsourcing Desktop Initiative for NASA
Desktop: General Purpose Scientific and Engineering Hardware Maintenance Network Attached Device
Server Web, Application, Computational, File
Intra-Center Communications Phone, Administrative Radio, Public Address, Local
Video, FAX, Remote Communications, Virtual Team Meeting Seat
For each seat category, functionality and both standard and optional service levels
are defined; catalogue options allow complete flexibility to tailor the seat to
meet the end user’s requirements
ODIN Seat Categories
11
Outsourcing Desktop Initiative for NASA What do I get for my monthly seat payment?
Standard services include: Hardware and both application and system software
acquisition, licensing, installation and maintenance Periodic hardware and software technology refreshment,
synchronized with current commercial offerings Shared peripheral services (e.g., file, print, e-mail, etc.) Asset management IT Security Help Desk support, training, system administration and
other services Network access and support, including network
engineering, management, and upgrade planning Local backup and restore Moves, adds and changes
12
Outsourcing Desktop Initiative for NASA
Help Desk
ODIN vendor is required to provide integrated customer support/help desk for all ODIN-managed services
Service includes: Problem ticket initiation, tracking and resolution Providing customer and service providers with system
status and alerts Monitoring systems to proactively determine, diagnose
and resolve problems Providing access to ODIN service offerings Providing consultation services for all Triage level 1
software packages
13
Outsourcing Desktop Initiative for NASA
Desktop Support and Refreshment
Desktop Hardware 2 hr. contiguous to 3 working days Return to Service
(RTS) 1.5, 3, 4, or 5 year refresh cycle Tier 1, Third-party certified equipment
Desktop Software 2 hr. contiguous to 3 working days RTS 6 or 12-month system and application software refresh 3 levels of support
Triage Level 1 – Full Support Triage Level 2 – Installation and pass-through Triage Level 3 – ‘Drop/Ship’
14
Outsourcing Desktop Initiative for NASA
Catalogue of Services and Commercial Components (CSCC)
Designed to augment the seat Additional memory, larger monitor, etc.
Can include stand-alone services Personal Digital Assistant (PDA’s – ie: Palm, Blackberry,
etc..) Additional Moves, Adds and Changes
Generally a one-time charge Service/support for 3 years
15
Outsourcing Desktop Initiative for NASA
Desktop Technology Refreshment
“Lemon Law” ensures reliable equipment Technology Refresh Plan is based on inventory at
beginning of delivery order Third Party Testing Facility (Alterion)
Alterion performance ratings drive technology refreshment under ODIN
NASA/Alterion Partnership Quarterly commercial market survey/benchmarking
process establishes top performer for desktop seats (NASA funded)
NASA/Alterion web site publishes survey data ODIN vendors work with OEMs to develop offerings Alterion validates vendor-proposed systems
– ODIN Vendor pays cost of validation benchmarking– System offerings are not acceptable until validated by Alterion
16
Outsourcing Desktop Initiative for NASA
Infrastructure Management
Different from standard seats! Title for all infrastructure (including replacements or
upgrades) remains with the Government. Infrastructure refresh requirements proposed/priced
after due diligence. Management of the necessary LAN communications
infrastructure is expected to be bundled with each service offered.
Infrastructure upgrades approved and funded separately (by the Government).
Infrastructure inventory managed by the ODIN vendor.
17
Outsourcing Desktop Initiative for NASA
Incentives Transition Bonus
– Up to $100k set aside for successful 180-day transition Performance Retainage Pool (PRP)
– 3% of sum of monthly seat prices
•Available on 1st anniversary, then semi-annually
•Tied to successful implementation of the ODIN Operating Model
•Meets/Fails to Meet/Discretionary Metric Performance Retainage Pool (MPRP)
– 1% of sum of monthly seat prices
– Tied to Level 1 Metrics
– Meets/ Fails to Meet
18
Outsourcing Desktop Initiative for NASA
Desktop Performance Metrics Level 1
– Service Delivery (98%)• Frequency of action requests being responded to and successfully
completed within the allotted time.– Availability (98%)
• Unscheduled outages and # users affected– Customer Satisfaction (agreed to at DOSP and/or during Delivery
Order Negotiations)• Measured using commercial/broad industry-accepted practices
Level 2– Contractor Specific Metrics
• 1st call resolution, hardware failure rate, switch latency, backbone utilization, etc. (the vendor determines the measurement in an effort to improve their performance)
Level 3– Trend Metrics
• Trend views of Level 1 and Level 2 metrics in 3-month or greater increments. (Measuring the contractor’s service level trends)
19
Outsourcing Desktop Initiative for NASA
Features SummaryODIN is a flexible contract vehicle that includes:
Automatic technology refreshment requirements, Standards and architecture management mechanisms, Government managed change control procedures, Allowance for government ownership of assets where it’s
determined to be in the Government’s best interest, “Unwinding” provisions to allow transition of contractor
owned assets at termination (to government or another contractor),
Allowances for installation and use of non-outsourcer provided hardware and software, and
Accommodations for unplanned requirements.
Outsourcing Desktop Initiative for NASA
Current Status
20
21
Outsourcing Desktop Initiative for NASA
Current Status - Continued
NASA– NASA’s 10 sites are operational
– Delivery Order values ~$315 million– ~36,543 “fully supported” seats– ~8,322 network only– ~1056 Admin Radio seats– ~48,699 phones
– 10 sites reviewing strategy for follow-on delivery orders– GSFC awarded their follow-on Delivery Order effective
February 1, 2004– ARC, DFRC, GRC and LaRC awarded their follow-on
Delivery Order effective April 1, 2004– HQ awarded their Delivery Order effective September
1, 2004– JSC, KSC, MSFC, and SSC are currently negotiating
their follow-on Delivery Orders
22
Outsourcing Desktop Initiative for NASA
ARC DFRC GSFC GRC HQ JSC KSC LaRC MSFC SSC
Seat/Service Type:
Desktop Seats X X X X X X X X X X
Server Seats X X X X n/a X n/a X X X
Phones(*=includes cell
phones) n/a X*
Cell Phones Only X* n/a X n/a X* n/a X
Facsimile n/a X X X X n/a n/a X n/a
Local Video n/a X n/a X n/a n/a n/a X n/a X
Admin Radio n/a X n/a X n/a n/a n/a n/a X
Network n/a
Email Services
Only n/a X n/a X
Email Services
Only X X X
Remote Comm n/a X n/a X n/a X X X X X
Public Address n/a X n/a X n/a n/a n/a n/a n/a n/a
Cable Plant n/a X n/a X n/a n/a n/a X n/a X
VTM X X X X X X X X X X
Printer Seats n/a n/a X n/a X X X n/a X X
ODIN Delivery Order services selected reflect flexibility of interfacing with existing contracts and/or support requirements.
23
Outsourcing Desktop Initiative for NASA
Current Status - Continued Established a very strong ODIN team
– Partnerships between Contractors, between Centers and between the Centers and Contractors
– Annual face-to-face workshops, functional tiger teams, regularly scheduled telecons and meetings
Traceable and continuous improvements in the Delivery Order (DO) process resulted from successive lessons-learned– e.g., Center-unique DO mods used to overcome Master
Contract ambiguities and to meet new Agency and customer requirements
Now have consistent and documented processes and procedures– Shared best practices, International Standards
Organization (ISO) certifications ODIN’s flexibility further demonstrated through the catalog
– Enhanced Systems Administration– Latest technology monitors– Specialized processors
Outsourcing Desktop Initiative for NASA
Performance Against the Objectives
24
25
Outsourcing Desktop Initiative for NASA
Performance Against the Objectives - Continued
Focus NASA civil service personnel on core research and development activities
• Reduced the amount of procurement involvement with securing ODIN services
• Greatly reduced the level of civil servants involved with Asset Management
26
Outsourcing Desktop Initiative for NASA
27
Outsourcing Desktop Initiative for NASA
Performance Against the Objectives - Continued
Promote information technology systems and product interoperability
– Over 36,000 desktops replaced since 1998.
– No additional investment by NASA (acquisition, logistics, integration, data removal, disposal)
Enhance and optimize service delivery– No method of performance measurement was in place prior to
ODIN
– ODIN has implemented monthly and quarterly performance metrics to track vendor performance
28
On a scale of 1-5, with 5 being “Excellent,” only responses marked 4 or 5 are counted toward achieving this metric
29
30
31
Outsourcing Desktop Initiative for NASA
Performance Against Objectives - Continued Reduce cost and improve cost management
and cost containment
– ODIN seat costs are better than predicted and comparable to industry
– Prior to ODIN• No established baseline
• Total cost of ownershipunknown
• IT costs hidden in programbudgets
• Investments made on
available funding basis
• Unequal access to technology
– With ODIN• Documented asset
baseline
• Known, visible, reliablecosts
• Predictable and “fixed”costs for future planning
• No more “haves” vs.“have nots” effect
– Before and after cost model is very different
32
Outsourcing Desktop Initiative for NASA
Seat Cost Comparison
* Data from ODIN Business Case** From State of Texas Study*** University of Texas**** Navy Marine Corp Intranet
Data from ODIN Program Post Implementation Business AssessmentKelly, Anderson & Associates, November 2001
NASA BenchmarkKSC*Gartner Average*Chevron*ODIN Business Case (low)ODIN Business Case (high)Update to Business Case (low)Update to Business Case (high)Gartner (low)**Gartner (high)**GSAHUDVDOTUTMB Baseline***UTNB Contract***NMCI General PurposeNMCI High End Business***ODIN Average
$500
450
400
350
300
250
200
150
100
50
0
MonthlySeatCost
1996 2001
33
Outsourcing Desktop Initiative for NASA
ODIN Accomplishments Established a very strong ODIN team
– Partnerships between Contractors, between Centers and between the Centers and Contractors
– Annual face-to-face workshops, functional tiger teams, regularly scheduled telecons and meetings
Traceable and continuous improvements in the DO process resulted from successive lessons-learned
– e.g., Center-unique DO mods used to overcome Master Contract ambiguities and to meet new Agency and customer requirements
Now have consistent and documented processes and procedures
– Shared best practices, ISO certifications ODIN’s flexibility further demonstrated through the
catalog – Enhanced Systems Administration– Latest technology monitors– Specialized processors
34
Outsourcing Desktop Initiative for NASA
Civil Servant refocusingTech refresh
Over 36,000 desktops replaced since 1998. No additional investment by NASA (acquisition, logistics, integration, data removal, disposal)
Interoperability and Security of SystemsInfrastructure support & upgradesCurrent technologyCommon metric and data reportingFlexibilityVendor Relationships!
What’s Working
35
Outsourcing Desktop Initiative for NASA
What’s Working - Continued Predictable cost baseline for ODIN provided services
(Budget Management) Filling the gaps 508 Compliancy (CAP Support) Seat Prices ODIN has helped the Agency meet Presidential Management
Agenda (PMA) goals
Outsourcing Desktop Initiative for NASA
Lessons Learned
36
37
Outsourcing Desktop Initiative for NASA
What Needs Work
Asset Management Upgrade/New Product Rollouts Help Desk Attachment R Process Consistency Customer Satisfaction Consistency Catalog
38
Outsourcing Desktop Initiative for NASA
Successful Management Techniques
Use Common Sense! Involve your outsourcer in strategic planning
(Partnership and Communication) Be Flexible Be Patient Approach each problem with a “Win-Win” attitude Don’t hold back information from your outsourcer Trust, but verify Limit line manager’s ability to circumvent the
contract
Outsourcing Desktop Initiative for NASA
Additional Questions?
Please contact
or call
(301) 286 – 5250
http://www.odin.nasa.gov
39