OptiX OSN 7500 Commissioning Guide Contents
T2-040439-20060320-C-1.50 Huawei Technologies Proprietary i
Contents
1 Preparations for Equipment Commissioning .................................................................................1-1 1.1 Instruments and Tools.................................................................................................................... 1-2 1.2 Engineering Information................................................................................................................ 1-3 1.3 Connection Points Position............................................................................................................ 1-4 1.4 External Check.............................................................................................................................. 1-6 1.5 Requirements for Commissioning Engineers ................................................................................. 1-7 1.6 Commissioning Items.................................................................................................................... 1-8
OptiX OSN 7500 Commissioning Guide Figures
T2-040439-20060320-C-1.50 Huawei Technologies Proprietary iii
Figures
Figure 1-2 Connection points position of OptiX OSN 7500................................................................. 1-4
OptiX OSN 7500 Commissioning Guide Tables
T2-040439-20060320-C-1.50 Huawei Technologies Proprietary v
Tables
Table 1-1 Organisation of chapter 1 .................................................................................................... 1-1
Table 1-2 Instruments and tools for commissioning............................................................................. 1-2
Table 1-3 Numbering and functions referred to the connection points.................................................. 1-5
Table 1-4 Testing items....................................................................................................................... 1-8
OptiX OSN 7500 Commissioning Guide 1 Preparations for Equipment Commissioning
T2-040439-20060320-C-1.50 Huawei Technologies Proprietary 1-1
1 Preparations for Equipment Commissioning
This chapter describes the preparations for commissioning. Table 1-1 shows the organisation of this chapter.
Table 1-1 Organisation of chapter 1
Section Describes the
1.1 Instruments and Tools Instruments and tools needed.
1.2 Engineering Information Engineering documents needed.
1.3 Connection Points Position Connection points position.
1.4 External Check External environment required.
1.5 Requirements for Commissioning Engineers
Requirements for commissioning engineers.
1.6 Commissioning Items Commissioning items.
1 Preparations for Equipment Commissioning OptiX OSN 7500
Commissioning Guide
1-2 Huawei Technologies Proprietary T2-040439-20060320-C-1.50
1.1 Instruments and Tools Table 1-2 shows the instruments and tools for commissioning.
Table 1-2 Instruments and tools for commissioning
Name Used for
SDH analyser Testing multiplex section switching time, frequency deviation and jitter at optical or electrical interfaces, and so on.
Optical power meter
Testing the actual received optical power, receiver sensitivity, and receiver overload at optical interfaces.
Fixed attenuator Attenuating strong optical power received at optical interfaces to avoid damage.
Laptop computer NE commissioning and Ethernet indexes test.
Multimetre Testing voltage, resistance, current intensity.
Fibre jumper Transfer during optical power test of optical interfaces at the ODF side.
BER tester Testing bit errors at electrical interfaces.
Adjustable attenuator
Testing receiver overload at optical interfaces and testing receiver sensitivity.
Data analyser Testing Ethernet services.
ATM analyser Testing ATM services.
OptiX OSN 7500 Commissioning Guide 1 Preparations for Equipment Commissioning
T2-040439-20060320-C-1.50 Huawei Technologies Proprietary 1-3
1.2 Engineering Information Engineering information includes:
Networking diagram IP address allocation diagram Board layout of each NE Fibre and cable connection table Timeslot allocation diagram Board level protection information Clock tracing diagram Orderwire diagram
1 Preparations for Equipment Commissioning OptiX OSN 7500
Commissioning Guide
1-4 Huawei Technologies Proprietary T2-040439-20060320-C-1.50
1.3 Connection Points Position
GSCC
GXCS
PIU
EOW AUX
Processing board
Interface board
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
19 20 2221 23 24 25 26 27 28 29 30 31 33 3432 35 36 37 38
SL64 SL16 SL4 SLT1 SL1SLH1 SEP1
EU08 OU08 TSB8
SPQ4
MU04 D34S
PL3APQ1
D75S
EGT2 EGS2EFS0
EFF8ETF8 ETS8
EMR0 ADL4LWX MR2A BPA
3
16
17
28
26
20
5 4 13 6 14 12 15 12
2122
23
24
25
27
32
30
29
31
3334
3536
37
121111111098764543221
19
18
Figure 1-1 Connection points position of OptiX OSN 7500
OptiX OSN 7500 Commissioning Guide 1 Preparations for Equipment Commissioning
T2-040439-20060320-C-1.50 Huawei Technologies Proprietary 1-5
Table 1-3 Numbering and functions referred to the connection points
Access Point Number (Note)
Position Function Description Connection Type
1 T2SL64 Optical stm-64 connections LC
2 N1SL16, N2SL16 Optical stm-16 connections LC
3 N1SL4, N2SL4, ADL4 Optical stm-4 connections LC
4 N1SL1, N2SL1, N1SLT1, N1OU08, N2OU08
Optical stm-1 connections LC
5 N1SEP1 140 Mbit/s and STM-1 Electrical Connections
SMB
6 N1PL3A, N1D34S 34 and 45 Mbit/s Electrical Connections
SMB
7 N1LWX 10 Mbit/s to 2.5 Mbit/s Optical Connection at WDM side
LC
8 N1LWX 10 Mbit/s to 2.5 Mbit/s Optical Connection at client side
LC
9 N1MR2A Adding/Dropping and Multiplexing Any Adjacent Two Channels Connections
LC
10 N1BPA Optical booster amplifier connections LC
11 N1EGT2, N2EGS2, N2EMR0
Optical 1000Base-SX and 1000Base-LX Connections
LC
12 N1EFT8, N1EFS4, N1ETS8, N2EMR0
Fast Ethernet access connections RJ-45
13 N1MU04 140 Mbit/s and STM-1 Electrical Connections (access unit)
SMB
14 N1D75S 2 Mbit/s Electrical Connections 2mmHM (75 ohm)
15 N1EFF8 Optical fast Ethernet access connections
LC
16 N2GSCC Reset button Button
17 N2GSCC Alarm cut switch Button
18 T1PIU 50 w power output connections Common socket4 pin
19 T1PIU -48 v power access connections DB3
20 T1EOW 75-ohm clock connections 1 SMB
21 T1EOW 120-ohm clock connection 2 RJ-45
1 Preparations for Equipment Commissioning OptiX OSN 7500
Commissioning Guide
1-6 Huawei Technologies Proprietary T2-040439-20060320-C-1.50
Access Point Number (Note)
Position Function Description Connection Type
22 T1AUX Extended subrack connection RJ-45
23 T1EOW Orderwire connection RJ-45
24 T1EOW Outgoing subnet orderwire connections
RJ-45
25 T1EOW OAM connection RJ-45
26 T1EOW Serial signal connections RJ-45
27 T1EOW COM commissioning Connection RJ-45
28 T1EOW T2000 connection RJ-45
29 T1AUX 75-ohm clock connections 3 SMB
30 T1AUX 120-ohm clock connection 4 RJ-45
31 T1AUX F&f Connection RJ-45
32 T1AUX F1 connection RJ-45
33 T1AUX Cabinet alarm indicator output connection
RJ-45
34 T1AUX Cabinet alarm indicator input concatenation connection
RJ-45
35 T1AUX Alarm concatenation connection RJ-45
36 T1AUX Alarm output connection RJ-45
37 T1AUX Alarm input connection RJ-45 Note: The number in the first column is corresponding to the number in the ring in Figure 1-1.
1.4 External Check Confirm the following items in advance.
The hardware installation check is complete. The T2000 is ready. The T2000-local craft terminal (T2000-LCT) is ready in the laptop. All equipment on each NE has active and standby power supplies. Check
whether alarms need to be output. The interface impedance (75 ohms or 120 ohms) of the DDF on each NE is the
same as that of tributary boards and tributary interface boards. Clock protection is provided. The setting of the clock board is correct. To
achieve clock protection switching, it is required to provide synchronisation
OptiX OSN 7500 Commissioning Guide 1 Preparations for Equipment Commissioning
T2-040439-20060320-C-1.50 Huawei Technologies Proprietary 1-7
state message bit (SSMB) in the 2 Mbit/s clock signal and the location of that message.
1.5 Requirements for Commissioning Engineers Before using this manual, commissioning engineers should have received training on optical equipment commissioning and be skillful at using various test tools. The requirements are as follows.
Be familiar with the fundamentals of SDH, PDH, Ethernet, and ATM. Be familiar with the equipment. Be skillful at using the T2000 for service configuration. Be skillful at using the LCT for service configuration. Be skillful at using test tools (for SDH, PDH, Ethernet, and ATM).
1 Preparations for Equipment Commissioning OptiX OSN 7500
Commissioning Guide
1-8 Huawei Technologies Proprietary T2-040439-20060320-C-1.50
1.6 Commissioning Items Table 1-4 lists the testing items.
Table 1-4 Testing items
Item Sub-item
Checking hardware
Testing and powering on cabinet
Testing subrack functions
Accessing the equipment through the NM
Testing the RESET button
Testing the centralised alarm processing system
Testing the software version
Configuring service for testing
Testing optical or electrical interface indexes
Testing the electrical interfaces connection
Testing the fibre jumper connection
Testing the TPS of electrical interface
Testing the active/standby board switching
Testing bit errors on an NE
Testing the intra-station ECC
Backing up the NE database
Testing NE restarting after power failure
NE commissioning
End of commissioning
OptiX OSN 7500 Commissioning Guide 1 Preparations for Equipment Commissioning
T2-040439-20060320-C-1.50 Huawei Technologies Proprietary 1-9
Item Sub-item
Testing network-wide fibre connection
Testing ECC routing
Checking the network-wide software version
Testing service channel availability
Testing Ethernet services
Testing self-healing protection switching
Testing clock protection switching
Testing orderwire
Testing network-wide BER
Other tests
Configuring the services
Network commissioning
T2000 function verification
ContentsFiguresTables1 Preparations for Equipment Commissioning1.1 Instruments and Tools1.2 Engineering Information1.3 Connection Points Position1.4 External Check1.5 Requirements for Commissioning Engineers1.6 Commissioning Items