OSF/ISD Project Portfolio Management Framework
January 17, 2011
Contents
Purpose Project Management Framework & Toolkit
Portfolio List High Level and Detail Milestone Plan Monthly Scorecard Monthly Status Metrics Gathered File Locations Policy Statements
2
OSF/ISD Project Portfolio Methodology
Portfolio Management Identify, prioritize, and authorize projects
Project Management Framework Basic roadmap to successful project achievement Method to achieve the benefits ISD expects from its
investment in an IT project
Monitor & Control Performed to observe project execution so that
potential problems can be identified and corrective action can be taken to control the execution of the project
Performed in order to meet performance objectives in each phase of a project
3
OSF/ISD Project Portfolio Management Framework
Project Management Process Groups Defined1
InitiationConcept Planning Execution Close
Identifies a projectidea, potentialbenefits and initial scope
Identifies a projectidea, potentialbenefits and initial scope
Defines andauthorizes a
project or projectphase
Defines andauthorizes a
project or projectphase
Defines objectives and plans the
course of actionrequired to attain
the objectives
Defines objectives and plans the
course of actionrequired to attain
the objectives
Integrates peopleand other
resources to carry out the plan
Integrates peopleand other
resources to carry out the plan
Formalizes acceptance and brings project to an orderly close
Formalizes acceptance and brings project to an orderly close
Project Management Process Group Deliverables2
InitiationConcept Planning (1) Execution Close
Updated PortfolioList
Updated PortfolioList
High Level Plan (+-50%),
Updated Portfolioand Scorecard
High Level Plan (+-50%),
Updated Portfolioand Scorecard
Detail Plan (+-10%),
Updated Portfolioand Scorecard
Detail Plan (+-10%),
Updated Portfolioand Scorecard
Updated Scorecard,
(Monthly Status -CORE)
Updated Scorecard,
(Monthly Status -CORE)
Metrics GatheredMetrics Gathered
(1) If planning phase cost is greater than $15,000 a detail plan and monthly status for the planning phase will be required
Project Management Process Group Responsibilities3
InitiationConcept Planning Execution Close
Managers updateportfolio list.CIO/CTO
move projects to Initiation
Managers updateportfolio list.CIO/CTO
move projects to Initiation
Project lead completes deliverables
Core ExecutiveBoard or CIO/CTO move projects to
Planning
Project lead completes deliverables
Core ExecutiveBoard or CIO/CTO move projects to
Planning
Project lead completes deliverables
Core ExecutiveBoard or CIO/CTO
move projects to Execution
Project lead completes deliverables
Core ExecutiveBoard or CIO/CTO
move projects to Execution
Project lead updates the Scorecard, (Monthly Status)Moves project to
Close
Project lead updates the Scorecard, (Monthly Status)Moves project to
Close
Project Lead records Actual Completion
Date and Cost,PMO collects andcompiles metrics
Project Lead records Actual Completion
Date and Cost,PMO collects andcompiles metrics
All Projects with a Cost of $15,000 or More Will Follow This Framework
4
PPM Framework
5
CloseUpdated Actuals
Captured Metrics
ConceptUpdated Portfolio (Cost > $15,000)
Name, Description, Initial Benefit, Initial Scope
PlanningUpdated Portfolio-Scorecard
+/- 10% Milestone Plan
ExecutionUpdated Portfolio-Scorecard
(Monthly Status - Core)
Initiation Updated Portfolio-Scorecard
+/- 50% Milestone Plan
Concept
Propose a new project idea Define preliminary
description, benefits, scope Update Portfolio List
6
CloseUpdated Actuals
Captured Metrics
ConceptUpdated Portfolio List (Cost > $15,000)Name, Description, Initial Benefit, Initial
Scope
PlanningUpdated Scorecard
+/- 10% Milestone Plan
ExecutionUpdated Scorecard
(Monthly Status - Core)
Initiation Updated Scorecard
+/- 50% Milestone Plan
The portfolio entry in the Concept Phase is the highest level overview of the major parameters of the project.
Evaluate a New Project Idea
Concept
No work is being done Project is identified for future
(opportunity map)
7
CloseUpdated Actuals
Captured Metrics
ConceptUpdated Portfolio List (Cost > $15,000)Name, Description, Initial Benefit, Initial
Scope
PlanningUpdated Scorecard
+/- 10% Milestone Plan
ExecutionUpdated Scorecard
(Monthly Status - Core)
Initiation Updated Scorecard
+/- 50% Milestone Plan
The portfolio entry in the Concept Phase is the highest level overview of the major parameters of the project.
Evaluate a New Project Idea
Initiation
Research initial scope – what the project must deliver
Estimate initial costs, time schedule, and resource commitments
Identify initial issues and constraints
Develop the High Level Plan Update Portfolio & Scorecard
8
The project in the Initiation Phase is researched to a +/- 50% estimate. No resources are assigned.
Define the Project
CloseUpdated Actuals
Captured Metrics
ConceptUpdated Portfolio (Cost > $15,000)
Name, Description, Initial Benefit, Initial Scope
PlanningUpdated Scorecard
+/- 10% Milestone Plan
ExecutionUpdated Scorecard
(Monthly Status - Core)
Initiation Updated Scorecard
+/- 50% Milestone Plan
Initiation
Budgetary numbers are created during budgeting cycle
High level estimates are created to make sure management wants to proceed
Time spent in this phase is minimal
9
The project in the Initiation Phase is researched to a +/- 50% estimate. No resources are assigned.
Define the Project
CloseUpdated Actuals
Captured Metrics
ConceptUpdated Portfolio (Cost > $15,000)
Name, Description, Initial Benefit, Initial Scope
PlanningUpdated Scorecard
+/- 10% Milestone Plan
ExecutionUpdated Scorecard
(Monthly Status - Core)
Initiation Updated Scorecard
+/- 50% Milestone Plan
Planning
Identify, analyze and review options and alternatives
Plan and estimate the work and costs involved
Balance scope, schedule and costs to deliver the requirements
Assess risk, plan and mitigate Document issues and
constraints Develop the Detail Plan Update Portfolio & Scorecard
10
The project in the Planning Phase is planned to a +/- 10% detailed estimate. Resources are planning, estimating, analyzing, assessing, documenting.
Plan the Project
CloseUpdated Actuals
Captured Metrics
ConceptUpdated Portfolio (Cost > $15,000)
Name, Description, Initial Benefit, Initial Scope
PlanningUpdated Scorecard
+/- 10% Milestone Plan
ExecutionUpdated Scorecard
(Monthly Status - Core)
Initiation Updated Scorecard
+/- 50% Milestone Plan
Planning
Significant time and resources are expended in this phase
RFP’s are in this phase Fit-Gaps are in this phase You must have a committed plan
and resources to leave this phase You must have signed contracts,
requisitions etc to leave this phase You must have agreement on how
the project will be paid for Combining Planning and Execution
is not a best practice When you leave this phase you are
accountable for cost and budget The movement from planning to
execution needs to be clear In most cases the planning phase is
not a project
11
The project in the Planning Phase is planned to a +/- 10% detailed estimate. Resources are planning, estimating, analyzing, assessing, documenting.
Plan the Project
CloseUpdated Actuals
Captured Metrics
ConceptUpdated Portfolio (Cost > $15,000)
Name, Description, Initial Benefit, Initial Scope
PlanningUpdated Scorecard
+/- 10% Milestone Plan
ExecutionUpdated Scorecard
(Monthly Status - Core)
Initiation Updated Scorecard
+/- 50% Milestone Plan
Execution
12
Resources are performing the work to create and deploy the project deliverables outlined by the detail milestone plan.
Create and Implement the Project Deliverables
CloseUpdated Actuals
Captured Metrics
ConceptUpdated Portfolio (Cost > $15,000)
Name, Description, Initial Benefit, Initial Scope
PlanningUpdated Scorecard
+/- 10% Milestone Plan
ExecutionUpdated Scorecard(Monthly Status - Core)
Initiation Updated Scorecard
+/- 50% Milestone Plan
Design, develop, configure, test, review, verify, assess, deploy and document project deliverables
Monitor schedule, costs and deliverable progress
Manage and control the work, costs and changes
Communicate progress, issues and resolution
Approve deliverable readiness Release, transfer deliverables
to customers Obtain feedback and sign-offs Update Portfolio & Scorecard Report status
Execution
13
Resources are performing the work to create and deploy the project deliverables outlined by the detail milestone plan.
Create and Implement the Project Deliverables
CloseUpdated Actuals
Captured Metrics
ConceptUpdated Portfolio (Cost > $15,000)
Name, Description, Initial Benefit, Initial Scope
PlanningUpdated Scorecard
+/- 10% Milestone Plan
ExecutionUpdated Scorecard(Monthly Status - Core)
Initiation Updated Scorecard
+/- 50% Milestone Plan
If you are making changes to a development environment you are in this phase
If you are making changes to a production environment you are in this phase
If you are paying external contractors you may be in this phase (a few projects will pay external contractors for the planning phase)
Close
14
Resources are released to other projects or operational demand.
CloseUpdated Actuals
Captured Metrics
ConceptUpdated Portfolio (Cost > $15,000)
Name, Description, Initial Benefit, Initial Scope
PlanningUpdated Scorecard
+/- 10% Milestone Plan
ExecutionUpdated Scorecard
(Monthly Status - Core)
Initiation Updated Scorecard
+/- 50% Milestone Plan
Complete the Project
Close the project Update Portfolio & Scorecard Update Closed Scorecard
Comments Actual Completion Date Actual Cost Project Closing Statements
Capture information for metrics
Portfolio List
Portfolio List – A Comprehensive List of Proposed and Current Projects
Assistance Service Request via the OSF Service Desk
By Department
Drop Down List
Total Baseline Cost Either +-50% or +-10% Cost Breakout by Category
15
High Level Plan / Detail Plan
Milestone Plan +- 50% in Initiation +- 10% in Planning
Includes all project costs listed +- 50% in Initiation +- 10% in Planning
Project ID, Name & Brief Description
High Level Plan – Developed in Initiating, required to move to PlanningDetail Plan – Refined in Planning, required to move to Execution if cost > $15,000
16
Project NameProject
Manager
Current Project Phase
Health Ind Schedule
Project Phase Start
Date
Project Phase
Baseline Completion
Project Phase Target
Completion
Health Ind
BudgetBaseline Cost Target Cost Comments
Backfill Developers for Production support and Enhancments
Fred Cantrell
Execution G 6/15/2009 12/18/2009 6/30/2010 G $213,200.00 $213,200.00 1011 hrs / 49% has been billed.755 hrs / 36% has been submitted or worked & not billed yet.314 hrs still available for new work.Looks like we will still stretch it through June.
Time and Labor Pilot Alex Galley Execution 3/1/2009 7/31/2010 7/31/2010 $1,529,766.00 $1,529,766.00
Commitment Accounting- Rollout
Michael Grisser
Execution G 9/1/2009 6/30/2010 6/30/2010 G $489,380.00 $489,380.00 Group F went live as of 04/17/2010 with an effective date of 04/01/2010. Group H kickoff was in March. Rollout plan is progressing as scheduled. Plan is on target
Grants/Projects/Contract A/R Billing ODOT/OESC
Kim/Alex Execution 7/1/2009 7/31/2010 7/31/2010 $2,998,740.00 $2,008,680.00
T&L Manager Self Service ODOT Pilot
Kim/Alex Execution G 3/1/2010 7/31/2010 7/31/2010 G $202,200.00 $202,200.00 Self Service for non Agile Assets personnel to coincide with roll out of Projects.
PeopleSoft Extract Staging Environment
Lisa McKeithan
Execution G 1/14/2010 6/18/2010 6/18/2010 G $153,440.00 $153,440.00 Development and testing continues.
Inventory Pilot Department of Mental Health
Execution G 4/15/2010 7/31/2010 7/31/2010 G $106,600.00 $106,600.00 Convert and implement Peoplesoft Inventory for 7 DMH warehouses
AP Workflow Michael Grisser
Execution G 5/3/2010 7/16/2010 7/16/2010 G $207,520.00 $207,520.00 To create processes utilizing imaging and Peoplesoft Control Groups with the ability to approve via workflow and to perform batch approvals by OSF prior to paycycle execution
Higher education Interface Lisa McKeithan
Execution G 4/1/2010 10/31/2011 10/31/2011 G $924,577.00 $875,560.00 External cost = $624,554. Dev = $151,300; Test = $96,754; Backfill = $376,500; Wrapping up SOW6 with Innovativ to get testers on-site. Met with OU on 4/14 to get commitment of their resources.
Monthly Scorecard
Scorecard – Reviewed Monthly in CORE Executive Board or ISD Project Review
Health Indicator Schedule Green – Within 10% of schedule Yellow – Within 20% of schedule Red – Over 20% of schedule
Portfolio List Information
Health Indicator Budget Green – Within 10% of budget Yellow – Within 20% of budget Red – Over 20% of budget
From HL/DL Plan – Changes only when Project Phase changes
Targets change when baselines are missed
Dates the Current Project Phase will start and finish .
17
Monthly Status
18
Monthly Status – Required when Planning costs are > $15,000 and for specific CORE projects.The CTO determines what status reports will be included in a monthly review presentation.
Project Management Framework
Project Management Framework and supporting documentation I:\Function\PMO\PortfolioManagement
2009 April Training Budget CORE Accessibility Documents CORE Advisory Group Data – Financials CORE Advisory Group Data – HCM CORE Partners Meeting Data CORE WIP Framework Templates Legislative Status Reports Milestone Plans Monthly Review Presentations Monthly Review Staging Monthly Status Reports Opportunity Maps & Vision Docs Portfolio-Scorecard Lists Project Metrics Projects Completed Resource Files
19
Policy Statements Projects required to follow the ISD Project Management Framework:
projects with a cost > $15,000, and Inside and Outside cable plant projects (i.e.: fiber in the ground)/(infrastructure).
Status Reports are required for certain CORE projects in Execution or for projects where the Planning Phase costs are > $15,000.
Managers enter concepts on the portfolio list and the PMO assigns a project ID Portfolio, scorecard and priorities are reviewed in the monthly Shared Business or
Technical Service Project Review meetings. Movement from Concept to the Initiation Phase is verbally approved by the CIO or CTO. Initiation Phase deliverables are +/- 50% High Level Plan and Scorecard. Completed deliverables from Initiation Phase puts project in consideration for movement
to the Planning Phase by CIO/CTO. Planning Phase deliverables are +/- 10% Detail Plan and Scorecard. Projects estimated less than $15K at end of Initiation Phase may be considered by
CIO/CTO for direct movement to the Execution Phase. New Target Dates and Costs must be established when the project will not meet its Phase
Completion Date and Cost. Managers record Actual Completion Date and Cost in the Closed Scorecard Comments
column after transitioning to the Close Phase. Managers are encouraged to record an end of project lessons learned narrative in the
Closed Scorecard Comments column. The PMO collects Completed Project Actual Completion Dates and Costs (provided by
managers on the Closed Scorecard) and compiles Completed Project metric reports. Shared Business Services Project review will be held on last Wednesday of the month. Shared Technical Services Project review will be held on last Tuesday of the month.
20