Orlando-Orange County Expressway Authority Project Development Process

Orlando-Orange County Expressway Authority Project Development Process

Embed Size (px)

DESCRIPTION

Project Development Process Planning Long Range Master Plan Five-Year Work Plan

Citation preview

Page 1: Orlando-Orange County Expressway Authority Project Development Process

Orlando-Orange County Expressway Authority

Project Development Process

Page 2: Orlando-Orange County Expressway Authority Project Development Process

Project Development Process

• Planning• Project Development & Environment

Assessment• Design• Finance• Right-of-way• Permitting• Bidding / Construction

Page 3: Orlando-Orange County Expressway Authority Project Development Process

Project Development Process

Planning

Long Range Master Plan

Five-Year Work Plan

Page 4: Orlando-Orange County Expressway Authority Project Development Process

Transportation Planning

• Planning Process Coordination– State and Local/Regional Agencies– Regional Transportation Authorities– Metropolitan Planning Organization

• Elected Officials: Policy Board• Technical Committee: Professional Staff• Citizens Committee: Appointed Membership

– General Public• Public Involvement Meetings, Published

Materials

Page 5: Orlando-Orange County Expressway Authority Project Development Process

Transportation Planning

• Long Range Plan/Master Plan– 20 to 25 year horizon– Updated every 5 years– Begin with existing roadway systems– Evaluate policy strategies– Coordinated with regional planning (MetroPlan)– Identify corridors which need improvements – Identify priorities and general staging approach– Provide input to OOCEA’s implementation

phases and short range planning

Page 6: Orlando-Orange County Expressway Authority Project Development Process

Transportation Planning

• Short Range Plan– Updated annually– 5-Year Work Plan– Identifies and assigns funding sources

Page 7: Orlando-Orange County Expressway Authority Project Development Process

Five-Year Work Plan Planning Process

Renewal &Replacement Projects

Does NotMeet

Criteria

Intelligent Transportation Systems Projects

Updated Revenue Projections

Master PlanProjects

Draft Five-YearWork Plan

Financial Analysis

Final Five-YearWork Plan

Board AdoptsWork Plan

Page 8: Orlando-Orange County Expressway Authority Project Development Process

Project Development Process

Planning

Corridor Planning & Development

Page 9: Orlando-Orange County Expressway Authority Project Development Process

SR 429 Part A ScheduleNew Limited-Access Road (11 miles)

PD&E

Project Activities Year 1 Year 2 Year 3 Year 4 Year 5 Year 618

Page 10: Orlando-Orange County Expressway Authority Project Development Process

Project Development & Environment

• Steps in the process– Identify and map existing environmental

features• Social (cultural, neighborhood, recreational)• Natural (wetlands, habitats, hydrologic)• Physical (air, noise, water quality)

– Develop and refine traffic forecasts

Page 11: Orlando-Orange County Expressway Authority Project Development Process

Project Development & Environment

• Steps in the process (continued)– Identify and evaluate potential corridors for

improvements: Opportunities and Constraints– Select the optimum corridor– Develop design concept

alternatives/alignments– Document positive and negative impacts– Select preferred design alignment

Page 12: Orlando-Orange County Expressway Authority Project Development Process

Project Development & Environment

• Public involvement & Coordination activities: Ongoing throughout the project– Corridor and alternative concept workshops– Public hearing– Newsletters– Direct mailouts– Press releases– Internet web sites– State and local agency coordination– Environmental Advisory Group (EAG)

Coordination

Page 13: Orlando-Orange County Expressway Authority Project Development Process

Project Development & Environment

• Documents prepared:– Public Involvement Plan– Location Hydraulics Report– Utility Impact Report– Cultural Resources Report– Wetland Evaluation Report– Geotechnical Report– Air Quality Report– Noise Study Report– Biological Assessment Report– Contamination Screening Report– Permit Coordination Report– Preliminary Engineering Report– State Environmental Report

Page 14: Orlando-Orange County Expressway Authority Project Development Process

Project Development Process

Planning

Corridor Planning & Development

Design

Page 15: Orlando-Orange County Expressway Authority Project Development Process

PD&E

Final Design

Project Activities18

14

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6

SR 429 Part A ScheduleNew Limited-Access Road (11 miles)

Page 16: Orlando-Orange County Expressway Authority Project Development Process

Design

• Detailed data collection– Aerial mapping– Design and right-of-way surveys– Geotechnical (soils) surveys– Existing and proposed utility locations– Wetland limits delineated

Page 17: Orlando-Orange County Expressway Authority Project Development Process

Design

• Prepare construction plans– Roadway, bridges, and misc. structures– Drainage and permitting documents– Traffic signal plans– Maintenance of traffic plans– Utility coordination plans– Signing and pavement marking– Toll facilities– Roadway lighting– Landscaping treatments– Fiber optic network

Page 18: Orlando-Orange County Expressway Authority Project Development Process

Design

• Plans, specifications, estimates (PSE)– Specifications

• FDOT Technical Specifications• Supplemental specifications

– Estimates• Quantity calculations• Unit prices

Page 19: Orlando-Orange County Expressway Authority Project Development Process

Project Development Process

Planning

Corridor Planning & Development

Design

Financing

Page 20: Orlando-Orange County Expressway Authority Project Development Process

Financing/Bond Sale

• Select Underwriters• Prepare Local & State Agreements• Prepare Finance Plan• Prepare Engineer’s Report• Prepare Traffic & Earnings Report• Preliminary Official Statement• Prepare Bond Documents• Obtain Ratings & Insurance• Execute Bond Purchase

Page 21: Orlando-Orange County Expressway Authority Project Development Process

Project Development Process

Planning

Corridor Planning & Development

Design

Right of Way Financing

Page 22: Orlando-Orange County Expressway Authority Project Development Process

PD&E

Final Design

Right-of-way

Project Activities18

14

18

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6

SR 429 Part A ScheduleNew Limited-Access Road (11 miles)

Page 23: Orlando-Orange County Expressway Authority Project Development Process

Right-of-way

• Right-of-way Team involved in the design process

• Acquisition process typically begins at 60% roadway plans

• Appraisal• Acquisition

– Negotiated– Condemnation

Page 24: Orlando-Orange County Expressway Authority Project Development Process

Project Development Process

Planning

Corridor Planning & Development

Design

PermittingFinancingRight of Way

Page 25: Orlando-Orange County Expressway Authority Project Development Process

PD&E

Final Design

Right-of-way

Permitting

Project Activities18

14

18

9

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6

SR 429 Part A ScheduleNew Limited-Access Road (11 miles)

Page 26: Orlando-Orange County Expressway Authority Project Development Process

Permitting

• Coordination continues from PD&E and Environmental Advisory Group activities

• Pre-application meetings at start of design• Application prepared/submitted at 60%

roadway plans and 100% drainage design, proceeding parallel with remaining design activities

Page 27: Orlando-Orange County Expressway Authority Project Development Process

Permitting

• Requires activities at numerous levels– Federal – State– Regional and Local

Page 28: Orlando-Orange County Expressway Authority Project Development Process

Permitting

• Federal agency requirements– US Army Corps of Engineers (ACOE)

• Nationwide & Individual wetland impact• Wetland Mitigation • No net loss of wetlands

– US Environmental Protection Agency• NPDES: Non-Point Discharge Elimination

System

Page 29: Orlando-Orange County Expressway Authority Project Development Process

Permitting

• State of Florida agency requirements– FDEP Environmental Resource Permit

• Includes Management and Storage of Surface Water

• Dredge and fill• Wetland Mitigation

– Florida Game and Freshwater Fish Commission• Wildlife impact on species of concern

Page 30: Orlando-Orange County Expressway Authority Project Development Process

Permitting

• Regional & Local Government requirements– Water management districts

• Environmental Resource Permit• Drainage• Wetland and wildlife impacts

– Local governments• Drainage Criteria• Wetland and wildlife impacts

Page 31: Orlando-Orange County Expressway Authority Project Development Process

Permitting

• Wetland Mitigation Options• Creation: Replace and Maintain• Mitigation “banking”: Public or Private• Beltway Mitigation Bill

Page 32: Orlando-Orange County Expressway Authority Project Development Process

Project Development Process

Planning

Corridor Planning & Development

Design

PermittingRight of Way

Construction

Financing

Page 33: Orlando-Orange County Expressway Authority Project Development Process

PD&E

Final Design

Right-of-way

Permitting

Bidding

Construction

Project Activities

2

18

14

18

9

24

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6

SR 429 Part A ScheduleNew Limited-Access Road (11 miles)

Page 34: Orlando-Orange County Expressway Authority Project Development Process

Bidding

• Advertisement• Distribution of plans and specs• Conduct Pre-bid meeting• Conduct bid opening• Evaluate bids and recommendation for

award

Page 35: Orlando-Orange County Expressway Authority Project Development Process

Construction• OOCEA general specifications• Refinements to FDOT Standard

Specifications– Lump sum MOT– Lump sum erosion control– Dispute Review Boards– Pre-award meeting– No time adjustments for weather– Partnering

Page 36: Orlando-Orange County Expressway Authority Project Development Process

Construction• Team

– OOCEA Staff and GEC– Construction Management Consultant– CEI’s– Materials Testing– Design Engineer (Post-design services)

• Activities– Contract administration– Review shop drawings and RFIs– Inspections– Expedited issues resolutions– Project acceptance

Page 37: Orlando-Orange County Expressway Authority Project Development Process

PD&E

Final Design

Right-of-way

Permitting

Bidding

Construction

Project Activities

2

18

14

18

9

24

Year 1 Year 2 Year 3 Year 4 Year 5 Year 6

SR 429 Part A ScheduleNew Limited-Access Road (11 miles)

Page 38: Orlando-Orange County Expressway Authority Project Development Process

Typical Project Schedule - GDOTProject Activities Pre-TIP

9 - 12

10 - 12

20 - 24

20 - 24

1 2 3 4 5

16 - 18

Right of Way

Completed LRP & TIP

Database Prep

Concept Dev./Validate

Environmental

?

28 - 30

Preliminary Plans

6 7 8 9 10

Advertise and Construction 24 - 30

Final Construction Plans

Page 39: Orlando-Orange County Expressway Authority Project Development Process

Typical Project Schedule - FDOTProject Activities Pre-TIP

18 - 24

14

12 - 242-3

1 2 3 4 5

7-9

Bidding

Completed LRP & TIP

PD&E

Construction Plans

Right-of-way

?

12 - 18

Permitting

Construction

6 7 8 9 10

Page 40: Orlando-Orange County Expressway Authority Project Development Process

Typical Project Schedule - NCDOT

Note:1) Timeline is for a typical 15-mi new location project2) Project Identification consists of the development of an ‘internal’ Draft environmental document.

Project Activities Pre-TIP

36

18

3yrs2-3

1 2 3 4 5

6-9

Bidding

Project Identification

Enviro. Documentation

Construction Plans

Right-of-way

?

18

Permitting

Construction

6 7 8 9 10

Page 41: Orlando-Orange County Expressway Authority Project Development Process

Typical Project Schedule - ALDOT

Note:1) Timeline is for a typical 10-mile widening project2) TIP revised on continual basis

Project Activities Pre-TIP

12

18

2-3yrs

2-3

1 2 3 4 5

6-9

Bidding

Project Id. & TIP

Prel. Eng./ Env. Doc.

Construction Plans

Right-of-way

12-24

18

Permitting

Construction

6 7 8 9 10

Page 42: Orlando-Orange County Expressway Authority Project Development Process

Project Activities Pre-TIP 1 2 3 4 5

12 - 24R/W and Utility Relo

Project Authorization ?

6 7 8 9

Acquire Permits12 - 24

10

Location/Envir Studies18 - 24

6Advanced Plng Report

24 - 36Survey and Design

Construction & Close Out 24

11 12

Contract Letting 3

18 - 36

Typical Project Schedule - TDOT

Page 43: Orlando-Orange County Expressway Authority Project Development Process

Typical Project Schedule - VDOTProject Activities Pre-TIP 1 2 3 4 5

6Complete Quantities

Project Authorization ?

Note:1) Timeline is for a typical 15-mi new location project2) Project Identification consists of the development of an ‘internal’ Draft environmental document.3) H indicates formal public hearing

6 7 8 9

R/W Acq., Utility Adj. & Plans 16

10

Preliminary Design30

26Location Study & CTBApproval H

12Final Design H

Construction 24+

11 12

Advertise and Bid Construction 6

Page 44: Orlando-Orange County Expressway Authority Project Development Process

Typical Project Schedule – Ohio DOTProject Activities Pre-TIP

9

5

249

1 2 3 4 5

12

Select Design Consult.

Project Identification

Select Env. Consultant

Pre. Alt. Studies

Feasible Alt. Studies

?

20

Select Preferred Alt.

Prepare Contract Plans

6 7 8 9 10

Clear ROW12

Process Plans & Bid Job5