YUCCAMOUNTAIN
PROJECT
Organization and Rationale ofLicense Application Plan
Presented to:NRC/DOE Technical ExchangeLicense Application Plan
Presented by:Carol Hanlon, VA License Application Plan LeadYucca Mountain Site Characterization Office
September 16, 1998 U.S. Department of EnergyOffice of Civilian Radioactive
Waste Management
License Application PlanViability Assessment Volume 4
PURPOSE OF THE LICENSE APPLICATION PLAN(Civilian Radioactive Waste Management Program Plan)
* To identify remaining scientific investigationsand engineering information needed tocomplete the License Application
* To identify costs associated with securing thisinformation
LONG-TERM GOAL* Submitting a docketable License Application
to the Nuclear Regulatory Commission
HanlonO91798.pptl1 25/NRC/Sep98 2
License Application PlanViability Assessment Volume 4
CONSIDERATIONS* Opportunity to assess adequacy of revised
approach to site characterization and design* Draw on available models and data describing
the natural system, repository, and wastepackage design
* Draw on Total System Performance Assessment* Draw on strategy for evaluating waste
containment and isolation (Repository SafetyStrategy)
* Performance confirmation program continuingduring construction and operation to furtherreduce performance uncertainties
Hanlon0917l98.pptll 25INRCISepY8 3
License Application Planin the Viability Assessment
Volume 4Site
Investigations(Volume 1)
Design(Volume 2)
Rationale forWork Needed toComplete LicenseApplication (§ 2.0)
Postclosure Safety Case* Elements of Postclosure Safety Case, Repository Safety Strategy* Description of Principal Factors* Prioritization of Principal Factors* Design Options* Technical WorkPreclosure Safety Case
* Development of PreclosureRadiological Safety Case
* Use of Demonstrated Technologyand Accepted Design Criteria
* Information NeedsDesign Decisions* Criticality* Approach to Closure* Design Alternatives
Technical WorkPlans (§ 3.0 )
Site Investigations* Geologic Framework* Unsaturated Zone* Saturated Zone* Thermal Testing* Near-Field EnvironmentalCoupled Processes
Design* Subsurface* Waste Package, Surface
Performance Assessment* Model Abstractions* TSPA Analyses* Design Support
SupportActivities
(§5.0) IU U
Costs forLicense
Application(§ 6.0)
I I~~~M
Schedule forLicense
Application(§ 7.0)Performance
Assessment(Volume 3)
0I
I Statutory Activities: EIS, Environmental Compliance, Site SuitabilityEvaluation, Site Recommendation, License Application (§ 4.0) I
HanlonO91 798.ppt/1 25/N RC/Sep98 4
License Application PlanViability Assessment Volume 4
CONTENTS OF LA PLAN
Overview1 - Introduction2 - Rationale for technical work needed to
complete the License Application3 - Technical Work Plans4 - Statutory and Regulatory Activities5 - Support Activities6 - Costs7 - Schedule8 - ReferenceAppendix A - Glossary
HanlonO91798.ppt/1 25/NRC/Sep98 5
License Application PlanViability Assessment Volume 4
SECTION 2: RATIONALE FOR TECHNICALWORK NEEDED TO COMPLETE THE
LICENSE APPLICATION PLAN| 2.1 Overview l
2.2 | Rationale for Technical Work 1 2.3 [ Rationale for Technical 1 2.4 | Rationale for Additional INeeded to Complete thePostclosure Safety Case
* Postclosure Safety Case
* Repository Safety Strategy
* Principal Factors of the
Repository Safety Strategy
* Conditional Prioritization of
Principal Factors
* Performance of Design
Options
* Summary of Technical Work
Work Needed toComplete the PreclosureRadiological Safety Case
e Preclosure Radiological
Safety Case
* Use of Demonstrated
Technology and
Acceptable Design
Criteria
* Information Needs
Technical Work toSupport Design Decisions
* Technical Work toAddress Criticality
Issues
* Technical Work toAddress Approaches toRepository Safety andClosure
* Technical Work toEvaluate DesignAlternatives
HanlonO91798.pptl1 25/NRC/Sep98 6
License Application PlanViability Assessment Volume 4
2.2 POSTCLOSURE SAFETY CASE
* In the License Application, the postclosureSafety Case will provide the basis fordetermining whether or not a repository atYucca Mountain will meet compliance standardswith reasonable assurance
* The License Application Plan defines 5elements of the Postclosure Safety Case toprovide a framework for needed data andanalyses
* The License Application Plan also summarizestechnical work to address each element
HanlonO91798.pptll 25/NRC/Sep98 7
License Application PlanViability Assessment Volume 4
2.2 POSTCLOSURE SAFETY CASE(CONTINUED)
Postclosure Safety Case elements
1 - Assessment of expected performance2 - Design margin and defense-in-depth3 - Consideration of disruptive processes and events4 - Insights from natural and man-made analogues5 - A Performance Confirmation Plan
HanlonO91 798.ppt/l 25/NRC/Sep98 8
License Application PlanViability Assessment Volume 4
PRINCIPAL FACTORS
* 19 factors important to postclosure performance,termed principal factors, have been identified inperformance assessment sensitivity studies for theVA base case with the reference design
* DOE has identified and prioritized its remainingtechnical work related to postclosure repositoryperformance based on:
- The relative importance of each factor- The degree of confidence in the current representation of
each factor in the performance assessment models- The confidence that could be obtained by the time of LA
submittal through further testing and analysisHanionO91798.ppt/1 25/NRC/Sep98 9
I [-RepositorySafety Strategy
License Application PlanRationale
............ &a
TSPA-VA
CRWMProgram
Plan(1996)
CongressionalDirection
RegulatoryRequirements
PostclosureSafety Case* Postclosure Safety Case* Repository Safety Strategy* Principal factors of the
Repository Safety Strategy* Conditional Prioritization
of Principal Factors* Performance of Design Options
* Summary of Technical WorkAvailableModels& Data
InformationNeeded
Priorities ofInformation
Needed
WorkActivities
GOAL:
DocketableLicense
Application
OperationalConsiderations,
and DesignBasis Events
PreclosureSafety Case* Development of the Preclosure
Radiological Safety Case* Use of demonstrated
technology andaccepted design criteria
* Information needs forSite Recommendationand License Application
HanlonO9 1798.ppt1 25/NRC/Sep98 10
License Application PlanViability Assessment Volume 4
2.3 PRECLOSURE RADIOLOGICAL SAFETY CASE* Comprises the body of evidence necessary to
demonstrate protection of worker and publichealth and safety while waste is being emplacedand monitored, before the repository ispermanently closed
* Based on comprehensive safety analysisidentifying facility operations and wasteemplacement scenarios which evaluate:1 - Design Basis Events2 - Safety classification of structures, systems, and components3 - Verification of system design for compliance with requirements4 - Use of demonstrated technology and accepted design criteria
HanionO91798.ppt/125/NRC/Sep98 I 1
License Application PlanViability Assessment Volume 4
2.4 RATIONALE FOR ADDITIONAL TECHNICALWORK TO SUPPORT DESIGN DECISIONS
* Technical work needed to support designdecisions
* Conduct evaluations leading to selection ofinitial design for Site Recommendation andLicense Application
HanionO91798.ppt1 25/NRC/Sep98 12
License Application PlanViability Assessment Volume 4
SECTION 3: TECHNICAL WORK PLANS
3.1 [ Site Investigations 1 3.2 | Design 1 3.3 [ Performance Assessment 1
* Geologic Framework andDisruptive Events (Table 3-1)
* Unsaturated Zone ProcessesGroup (Table 3-2)
* Saturated Zone Processes(Table 3-3)
* Thermal Testing
* Near-field Environment andCoupled Processes
* Performance Confirmation
* Management, Int. and FieldSupport
* Subsurface Design
* Waste Package
* Surface
* Model Abstractions
* Total System PerformanceAssessment Analyses
* Design Support
HanlonO91798.ppt/125/NRC/Sep98 1 3
License Application PlanViability Assessment Volume 4SECTION 4: STATUTORY AND
REGULATORY ACTIVITIES
* Environmental Impact Statement andEnvironmental Compliance
* Site Recommendation
* Licensing- Licensing Activities- License Application Status and Schedule- Nuclear Regulatory Commission Interaction and
Key Technical issues
HanlonO91798.ppt/1 25/NRC/Sep98 14
License Application PlanViability Assessment Volume 4
SECTION 5: SUPPORT ACTIVITIES
* Field Construction and Operation- Land Area, Facilities- Surface Testing Facilities- Exploratory Studies Facility- General Services
* Other Support Activities- Information Technology- Systems Engineering- Quality Assurance Program
HanlonO91798.ppt/1 25/NRC/Sep98 1 5
License Application PlanViability Assessment Volume 4
SECTION 6: COSTS* Viability Assessment to License Application
SECTION 7: SCHEDULE* Work described as necessary for License
Application in Sections 2 & 3* Statutory Milestones in the CRWM Program Plan
were used to derive Project Summary Schedule* Project Summary Schedule forms the basis for
costs shown in Section 6 and Schedule shown inSection 7
* These activities are being used to revise theMulti-Year Plan
HanionO9 I 798.ppt1 25/NRC/Sep98 16
License Application PlanViability Assessment Volume 4
CONSIDERATION OF KEY TECHNICAL ISSUES
Throughout Viability Assessment - KeyTechnical Issues have been correlated withspecific discussions, when appropriateVolumes:- 1. Site Description- 2. Design- 3. TSPA-VA- 4. License Application Plan
HanlonO91l798.ppt/l 25/NRC/Sep98 17
License Application PlanViability Assessment Volume 4
CONSIDERATION OF KEY TECHNICAL ISSUES(CONTINUED)
Volume 4- Technical Work - Activities correlated with
specific Key Technical Issues
- Section 4-3-3 Nuclear Regulatory CommissionInteraction and Key Technical Issues
- Table 4-2 Location of Information Related toKey Technical Issues in Viability AssessmentVol. 1-4
HanionO91798.pptfl125/NRC/Sep98 18
License Application PlanViability Assessment Volume 4
Locations of Information Related to Key Technical Issues inVA Volumes 1 through 4
Key TechnicalIssue
Igneous Activity
StructuralDeformation andSeismicity
Evolution of Near-Field Environment
Container Life andSource Term
Thermal Effects onFlow
Repository Designand Thermal-Mechanical Effects
Total SystemPerformanceAssessment andIntegration
Activities Related toDevelopment of theEPA YuccaMountain StandardA
Unsaturated andSaturated ZoneFlow UnderIsothermalConditions
RadionuclideTransport *
Volume 1Sections
2.2.7
2.2.1, 2.2.7
2.2.6
Volume 2Sections
5.1.3
5.1.3, 5.1.4
2.2.6
2.2.6 3.1.2, 3.3.4,4.2.7, 4.3
4.2.2,
Volume 3Sections
2.3.2, 4.4.2
3.4.1, 4.4, 4.4.3
2.2.3, 3.4,2, 4.1.3,4.1.4, 5.2.2, 6.5.1
2.2.3, 3.2.2, 3.3,3.4, 3.5.2, 5.5.1
3.1.1, 3.2, 4.1.5,5.2
5.2.2, 6.5.1
2.1, 2.3.3, 3.5, 3.6,3.7, 3.8, 3.8.3, 4.4,6.5.3
Not Addressed
3.1.1, 3.2.3, 3.3.1,3.4.2, 3.6.1, 3.7.2,4.1.3, 4.1.4
5, 5.2.2, 6.5.1
Volume 4Sections
3.1.1, 3.3.1
3.1.1, 3.2.1, 3.2.2,3.2.3, 3.3.1, 4.3.1
3.1.2, 3.1.4, 3.1.5,3.2.1, 3.3.1
3.1.4, 3.1.5, 3.2.2,3.3.1
3.1.1, 3.1.2, 3.1.4,3.1.5, 3.2.1, 3.3.1
3.1.1, 3.1.4, 3.1.5,3.2.1, 3.2.2
3.1.1, 3.1.2, 3.1.3,3.1.4, 3.1.5, 3.2.2,3.3.1
Not Addressed
A NRC has indicated no issueresolution status report will bedeveloped for this key technicalissue.
* Issue resolution status reportis not yet available. Subissuestatements are expected tochange when issue resolutionstatus report is issued.
Not Addressed
2.2.2, 2.2.3, 2.2.4,2.2.5
2.2.5, 2.2.6
Not Addressed
3.1.13.3.1
, 3.1.2, 3.1.3,
3.1.1, 3.1.2, 3.1.3,3.1.4, 3.1.5, 3.2.2,3.3.1
HanlonO9 1798.ppt/1 25/NRC/Sep98 19
License Application PlanViability Assessment Volume 4
CONCLUSIONS
* To ensure that we are able to meet our goal ofsubmitting a docketable License Application to theNRC, the License Application plan presents acomprehensive safety case and a detailed rationalefor needed additional work
* Technical work remaining to be completed for thePostclosure Safety Case receives the strongestemphasis
* Regulatory, statutory, and other activities aredeveloped with lesser detail
* Consideration of Key Technical Issues are includedthroughout the License Application Plan, as well asthroughout the Viability Assessment
HanlonO91 798.ppt/1 25/NRC/Sep98 20
License Application PlanViability Assessment Volume 4
CONCLUSIONS(CONTINUED)
* DOE believes that the License Application Planhas met the requirements of Congress and theCRWM Program Plan by identifying andprioritizing remaining scientific work,engineering, and other work necessary to submita docketable License Application
HanlonO91l798.ppt/l 25/NRC/Sep98 21
License Application PlanViability Assessment Volume 4
SUBSEQUENT PRESENTATIONS
Jean Younker
Jack Bailey
Jean YounkerRichard SnellHolly DockeryJean Younker
April Gil
Evolution of the Postclosure RepositorySafety Strategy and Safety CasePerformance Allocation andIdentification of Needed Information
DISCUSSION & EXAMPLES OFREMAINING TECHNICAL WORKSite InvestigationDesignPerformance AssessmentStatus of Quality Controls on theTechnical ProgramRegulatory Program and Path Forward
HanlonO91798.ppt/1 25/NRC/Sep98 22