Optimized Risk in ABC Projects SH 114 Signature Bridge Irving, Texas Matt Paggioli, Webber, LLC Sam Piland, Webber, LLC

Optimized Risk in ABC Projects

  • Upload
    others

  • View
    4

  • Download
    1

Embed Size (px)

Citation preview

Page 1: Optimized Risk in ABC Projects

Optimized Risk in ABC Projects

SH 114 Signature Bridge

Irving, Texas

Matt Paggioli, Webber, LLCSam Piland, Webber, LLC

Page 2: Optimized Risk in ABC Projects

DFWInternational

Airport

Dallas

Irving

Project Location

2

Page 3: Optimized Risk in ABC Projects

• Bid Date: June 7, 2017

• Completion Date: December 2020

• Client: TxDOT, Dallas District

• Project Award Amount: $39,547,700

SH 114 Signature Bridge

• Scope of Work: Five new bridges over SH 114

• Three vehicular bridges over main lanes and frontage roads

• Two pedestrian bridges over main lanes

• Aesthetic steel truss supported by cable-stay system and

pylons

• New exit ramps and frontage roads

3

Page 4: Optimized Risk in ABC Projects

Project Specifics

• Three vehicular bridges over tolled express lanes, main lanes and frontage roads

• Super structure designed with standard prestressed concrete U-beams and slab

• Two pedestrian bridges over tolled express lanes and main lanes

• Super structure designed as post-tensioned continuous box girder sections utilizing cast-in-place construction methods

4

Page 5: Optimized Risk in ABC Projects

TxDOT requested to open the new tolled express lanes early, but how?

• Webber proposed an ABC method to eliminate the shoring necessary for the pedestrian bridge box girder spans to be cast-in-place and allow the early opening.

• Webber had concerns for additional costs that the original pricing of the work would not cover the proposed ABC method.

So why ABC for this Project?

5

Page 6: Optimized Risk in ABC Projects

City of Irving PropertyLeased to TxDOTApproximately 80 Ac.

• Redesign of post tensioned box girder spans

• Approval process

• Casting location

• Erection of box sections

• Optional traffic routes

• Frontage Road access requirements

• Previous experience

Considerations

6

Page 7: Optimized Risk in ABC Projects

1. Safety Measures• Engineering controls• Traffic control

2. Multiple Professional Engineers (7 Firms) working on the design• DECON – Hired by Webber for multiple design scopes

• Redesign box girders• Geotechnical report on casting yard and travel path• Overhang design

• Mammoet – Heavy lift contractor used in house engineering staff to design the lifts• Webber – Coordinate design and review with in-house engineering services• Toroja – Independent final review of complete design package• TxDOT – Bridge Division review of complete redesign package• PERI Formworks – Design and manufacture of formwork• Structural Technologies (VSL) – Design and install of post tensioned system

3. Survey Control

Risk Management Strategies

7

Page 8: Optimized Risk in ABC Projects

Shoring occupying express lanes for 8 months to cast all four spans

Express Lane

Risk Management Strategies

8

Page 9: Optimized Risk in ABC Projects

• First ABC method considered. Cast box girder spans on existing newly constructed bridge and utilize sliding jack method for moving to final location• Ruled out due to risk associated with excessive loading on newly constructed bridge

Precast Box Girder SpansFirst Option Considered

9

Page 10: Optimized Risk in ABC Projects

• Post tensioned box girder spans cast off site on the ground with steel lifting girders in place

Precast Box Girder SpansSecond Option Considered

10

Page 11: Optimized Risk in ABC Projects

11

• Staging area location and transporting route

Precast Box Girder SpansSecond Option Considered

11

Page 12: Optimized Risk in ABC Projects

Precast Box Girder SpansReinforcing Section Views

12

Page 13: Optimized Risk in ABC Projects

Precast Box Girder Span Forming System

13

Page 14: Optimized Risk in ABC Projects

Precast Box Girder SpansPost Tension Tendon Location

14

Page 15: Optimized Risk in ABC Projects

Precast Box Girder SpansClosure Pour At Center Bents

15

Page 16: Optimized Risk in ABC Projects

Gantry Arrangement for Lifting Box Girder Spans

16

Page 17: Optimized Risk in ABC Projects

Precast Box Girder SpansTransport Plan

17

Page 18: Optimized Risk in ABC Projects

18

Precast Box Girder SpansPouring Top Phase

18

Page 19: Optimized Risk in ABC Projects

19

Completion of Casting Precast Box Girder Spans at Staging Area

19

Page 20: Optimized Risk in ABC Projects

Precast Box Girder SpanLifted and Loaded on SPMT

20

Page 21: Optimized Risk in ABC Projects

Precast Box Girder SpanTransported with SPMT

21

Page 22: Optimized Risk in ABC Projects

22

Precast Box Girder SpanAdjustments with SPMT

22

Page 23: Optimized Risk in ABC Projects

23

Precast Box Girder SpanBeing Set in Place

23

Page 24: Optimized Risk in ABC Projects

24

Precast Box Girder SpanInstalled

24

Page 25: Optimized Risk in ABC Projects

https://youtu.be/JxlxVwU21xQ

Transporting and Installation with SPMT

25

Page 26: Optimized Risk in ABC Projects

Thank You

26

Page 27: Optimized Risk in ABC Projects

Questions?

27