Federal Aviation Administration 1

Optimization of Airspace and Procedures

in the Metroplex

To: Project Update By: Rob Henry, SoCal D&I Integration Manager

Jose Gonzalez, SoCal NATCA D&I Lead

Federal AviationAdministration

SoCal Metroplex Project UpdateApril 27, 2017 Chart Update

April 12, 2017

1

Federal AviationAdministration 2

Agenda • Metroplex Actions to Date• Legal Challenges• Community Engagement Activities• April 27 Procedures• Open Bridge, Briefing and Telcon Schedule• SCT Frequency Relocation for Metroplex • LAX RWY 07L/25R RSA and Construction Project• Traffic Management Initiatives for April 27• Air Traffic Training Update• Potential Community Issues• Post Implementation Procedure Amendments

Federal AviationAdministration 3

Activity Date Complete SIDs STARs Apchs T-Rte Airports Involved

FONSI/ROD 9/2/16

Phase 1 Implementation 11/10/16 5 8 33 0BUR, CRQ, LAX, LGB, ONT, PSP, SAN, SBA, SDM, SMO and SNA

Phase 1A Implementation 1/5/17 1 1 0 0 LGB, SLC and SNA

Phase 2 Implementation 3/2/17 37 20 6 1BUR, CRQ, LAS, LAX.

LGB, NTD, ONT, PHX. PSP, SAN, SBA, SMO and SNA

Phase 3 Implementation 4/27/17 13 17 12 0 BUR, LAX, LGB, ONT, SNA and VNY

Phase 3A Implementation 5/25/17 4 LAX

Post and Beyond 6/22/17 1 LAX DIRBY STAR

Metroplex Related to RSA 8/17/17 27 LAX

Milestones and Procedure Count

Federal AviationAdministration 4

Legal Action PendingCurrent as of March 28

• Culver City• Proposed solution being reviewed by Metroplex Team as of March 15

• Steve Murray - Citizen of Culver City• No proposal to date

• Santa Monica Canyon - Taber Law Firm provided mitigation• Response prepared by Metroplex Team

• Benedict Canyon - Taber Law Firm provided mitigation• Response prepared by Metroplex Team

• Proposed action(s) grouped together and deferred for 180 days • County of Orange – County provided mitigation-awaiting April 27, 2017 implementation• Newport Beach - Remy Law Firm provided mitigation• Laguna Beach - City provided mitigation

• Donald Vaughn - Citizen of San Diego - provided mitigation

Federal AviationAdministration 5

Community EngagementMeeting Date and Location Action Complete

Internet Based Webinar #1 JAN 18, 2017, 6:00 PM PST (LAX and SMO)Internet Based Webinar #2 JAN 18, 2017, 8:00 PM PST (LAX, BUR, VNY, SBA, CMA and NTD)Internet Based Webinar #3 JAN 19, 2017, 6:00 PM PST (SNA. LGB, FUL, TOA and SLI)Internet Based Webinar #4 JAN 19, 2017, 8:00 PM PST (SAN, CRQ, SDM, NZY, ONT and PSP)Community Informational Briefing #1 JAN 23, 2017, 3:00 PM Vets Memorial Building – Multipurpose Rm , Culver CityCommunity Informational Briefing #2 JAN 24, 2017, 5:00 PM Langley Senior Center – Monterey Park, CACommunity Informational Briefing #3 JAN 25, 2017 5:00 PM Palisades Charter High School - Pacific Palisades, CA Community Informational Briefing #4 JAN 26, 2017 5:00 PM Torrance Cultural Art Center - Torrance, CACommunity Informational Briefing #5 JAN 30, 2017 5:00 PM Burbank Community Services Bldg - Burbank, CACommunity Informational Briefing #6 JAN 31, 2017 5:00 PM City of La Habra Community Center – La Habra, CACommunity Informational Briefing #7 FEB 1, 2017 5:00 PM Oasis Senior Center – Corona Del Mar, CACommunity Informational Briefing #8 FEB 2, 2017 5:00 PM Solana Vista Elementary School - Solana Beach, CACommunity Informational Briefing #9 FEB 7, 2017 5:00 PM Ontario Arpt Administrative Building - Ontario, CACommunity Informational Briefing #10 FEB 8. 2017 5:00 PM Long Beach School for Adults - Long Beach, CA

• The FAA conducted public information meetings and webinars to further inform people about the procedures changes• The FAA also utilized public press releases on Facebook, Twitter, Instagram and the Metroplex website• The workshops are open forum with looped videos, poster boards of procedures and subject matter experts available

for questions and answers • There remains a great amount of concern and frustration reference legacy noise and the assertion that procedures

have already been implemented

Federal AviationAdministration 6

Forty Procedures April 27, 2017 BUR_SMO_VNY THRNE ONE ARRIVAL (RNAV)

LAX_SMO BOGET ONE ARRIVAL (RNAV SMO RNAV (GPS) Y RWY 03, ORIG (CAT A-D)

LAX CHATY FOUR DEPARTURE (Conventional)

LGB BAUBB1 ARRIVAL (RNAV) SMO RNAV (GPS) Z RWY 03, ORIG (CAT A/B only)

LAX DARRK ONE DEPARTURE (RNAV) LGB PCIFC ONE ARRIVAL (RNAV) SMO RNAV (GPS) RY21LAX GOATZ ONE ARRIVAL (RNAV) LGB TOPMM ONE DEPARTURE (RNAV) SNA FINZZ ONE DEPARTURE (RNAV) LAX HUULL ONE ARRIVAL (RNAV) LGB_SNA_FUL_SLI_TOA HAWWC1 ONE

DEPARTURE (RNAV) SNA HHERO ONE DEPARTURE (RNAV)

LAX ILS or LOC RWY 24L, AMDT 27 ONT EAGLZ ONE ARRIVAL (RNAV) SNA HOBOW ONE DEPARTURE (RNAV)

LAX RNAV (GPS) Y RWY 24L, AMDT 5 ONT GLRNO ONE ARRIVAL (RNAV) SNA MIKAA ONE DEPARTURE (RNAV) LAX RNAV (RNP) Z RWY 24L, AMDT 2 ONT KARLB ONE ARRIVAL (RNAV) SNA OHSEA ONE ARRIVAL (RNAV)LAX SMO ZUUMA ONE ARRIVAL (RNAV) ONT RNAV (RNP) RWY 8L, AMDT 1 SNA TILLT ONE ARRIVAL (RNAV) LAX SNSTT ONE ARRIVAL (RNAV) ONT RNAV (RNP) Z RWY 26L, AMDT 1 VNY HARYS ONE DEPARTURE (RNAV) LAX TRTON ONE DEPARTURE (RNAV) ONT RNAV (RNP) Z RWY 26R, AMDT 1 VNY ROSCOE ONE DEPARTURE

(RNAV) (PROPS) LAX WNNDY ONE DEPARTURE (RNAV) ONT RNAV (RNP) Z RWY 8R, ORIG VNY WLKKR ONE DEPARTURE (RNAV) LAX_HHR RYDRR ONE ARRIVAL (RNAV) ONT SCBBY ONE ARRIVAL (RNAV) LAX_HHR IRNMN ONE ARRIVAL (RNAV) ONT ZIGGY SIX ARRIVAL (Conventional)

Federal AviationAdministration 7

Flight InspectionsApril 27 Metroplex Procedures

• Waiting on LAX ILS Runway 25R Procedures due to construction• All other Flight Inspections are complete

Federal AviationAdministration 8

Facilities Impacted April 27, 2017 Chart Date

• Enroute Facilities Affected:• ZLA, ZOA, ZLC, ZDV and ZAB

• Terminal Facilities Affected:• SCT, LAX, SNA, BUR, VNY, LGB, FUL, TOA, ONT, PSP,

SLI and SMO

Federal AviationAdministration 9

Outreach Materials Provided For April 27, 2017• The Metroplex Team will participate in the April 5, 2017 Flight Dispatcher telcon• A SID/STAR Parameters spreadsheet will be provided with detailed information about how the

Southern California Metroplex SIDs and STARs will be used• Includes which SID/STAR to file by transition, altitude, and time of day

• Segmented route rules spreadsheet:• Provides dispatchers with segmented route rules extending beyond SID or STAR transition fixes• Adherence to these routes will provide maximum opportunity to be “cleared as filed”

Federal AviationAdministration 10

Open Bridge and Briefing Schedule

x Open Conference Bridgeo (888) 335-6670 Passcode

153783o 24/7 starting April 27 2017

0001 PDTo April 27 2017 0100 PDT

Weather and Implementation Status Briefing

x Headquarters Conference Callso April 27 and 28 2017

• 0300 PDT• 0600 PDT• 1000 PDT• 1700 PDT

o April 29 and 30 2017• 0600 PDT

Federal AviationAdministration 11

Industry Briefing Schedulevia GoToMeeting

• April 27, 2017 0700 PDTo (571) 317-3122o Passcode 534-821-189

• April 27, 2017 1700 PDTo (872) 240-3212o Passcode 733-098-133

• April 28, 2017 0700 PDTo (669) 224-3412o Passcode 781-676-269

• April 28, 2017 1700 PDTo (872) 240-3412o Passcode 307-508-901

• April 29, 0800 PDTo (571) 317-3112o Passcode 997-762-693

Federal AviationAdministration 12

Remote Communications Air/Ground (RCAG) Site• A new Remote Communications

Air/Ground (RCAG) site was established to resolve poor communications within the SCT NORR sector• 127.0 MHz at REI was moved to

a new leased site at PaivikaRidge

• As of March 22, the site is operating in the 30 Initial Operating Capacity (IOC) period

• A new frequency (133.85) was established at the QX7 RCAG Site to resolve the MAVR controller being able to communicate with aircraft coming from the HEMT position• As of March 22, the site is

operating in the 30 IOC period

NORR

MAVR HEMT133.85

127.0

Federal AviationAdministration 13

LAX Runway 07L/25R Construction Project(1 of 2)

• LAX Runway 07L/25R will close for approximately 45 days beginning in mid-April• When returned to service on/about May 25, available length

will be limited by the RSA project on the west end of the runway

• Available use during the RSA project:• Runway 25R Departures: Available for departures that can accept the reduced

length• Runway 25R Arrivals: Available for arrivals without the benefit of ground based

NAVAIDS• Likely used as a contingency for side-step and/or visual approach

• Runway 07L will be available for departures that can accept the reduced length• No arrivals will be allowed

Federal AviationAdministration 14

LAX Runway 07L/25R Construction Project(2 of 2)

Federal AviationAdministration 15

LAX Runway 07L/25R Construction Impact(1 of 3)

• April 27, 2017 SIAP charts related to Runway 07L/25R will slip to May 25, 2017 chart date

• The LEENA STAR has been an interim solution to route Cargo and General Aviation/Corporate turbo jet aircraft destined to the south ramp for parking from north of LAX and will be used during construction

• The Metroplex LAX DIRBY STAR was designed specifically to manage arrivals from north of LAX and will permanently replace the use of the LEENA STAR on June 22, 2017

Federal AviationAdministration 16

LAX Runway 07L/25R Construction Impact(2 of 3)

• Arrival and Departure delays may exceed 30 minutes during IMC and/or east operations • The following Airport Acceptance Rates (AAR) and Airport Departure Rates (ADR) have been

coordinated for the LAX Runway 07L/25R construction project

.

RY07L/25R Closed Wx Arrival RYs Departure RYs AAR/ADR Throughput

Favoring Arrivals VMC 24R, 25L (5 MIT) 24L, 25L 60, 59 119*

Surface Volume VMC 24R, 25L (7 MIT) 24L, 25L 52, 65 117*

Favoring Arrivals IMC 24R, 25L (5 MIT) 24L, 25L 58, 57 115*

Surface Volume IMC 24R, 25L (7 MIT) 24L, 25L 50, 63 113*

East Traffic VMC 06L, 07R (7 MIT) 06R, 07R 48, 48 96*

East Traffic IMC 06L, 07R (7 MIT) 06R, 07R 46, 45 91*

Lower AAR possible during Cat III or A380 operations

Federal AviationAdministration 17

LAX Runway 07L/25R Construction Impact(3 of 3)

• Traffic Management Initiatives (TMI) can include Ground Delay Program (GDP), Ground Stops, Call for Release, Metering and miles-in-trail (MIT)

• MIT from ZLC/ZAB/ZDV as needed• Used to fine tune delivery and support TBFM

• MIT from ZOA as needed• Used to fine tune delivery and support TBFM

• Time Based Flow Metering • Preferred method of delivery over miles-in-trail

• Departure MIT as needed• All TMIs will be continuously evaluated and will be lowered or removed when there

is confidence that procedures, airspace and automation are working as designed

Federal AviationAdministration 18

SoCal Metroplex Related TM Initiatives(1 of 2)

• LAX GDP daily for arrivals between 1500-0600Z or as needed• U.S. and Canada

• First week West: 50-52 AAR , East: 46-48 • Second week West: 54-56 AAR , East: 46-48 • MIT implemented as needed to fine tune delivery and support TBFM• LAX to SFO and SFO to LAX departures to depart within EDCT during

weekend SFO construction times• All TMIs will be continuously evaluated and will be lowered or removed

when there is confidence that procedures, airspace and automation are working as designed

Federal AviationAdministration 19

SoCal Metroplex Related TM Initiatives(2 of 2)

• ZLA will implement two Airspace Flow Programs (AFP) 1500z –0600z daily for steady delivery of traffic through Areas A & B• Includes all ZLA traffic except • LAX arrivals• ZLA departures• SBA, SMX and BFL arrivals from ZOA

• Airspace Flow Programs (AFP) 1500z – 0600z for PSP/UDD/TRM arrivals from the East• The AFP will balance increased traffic for Stagecoach weekend and new SCT sectors• All three airports treated as one*Note-Reroute option through BTY corridor will avoid AFP delays

Federal AviationAdministration 20

AFP Placement

Federal AviationAdministration 21

SCT/ZLA Overall TM Initiatives• All SCT departures:

• 3-10 minutes-in-trail per airport per corridor will be implemented as needed to manage sector capacity

• Increased departure delays for other terminal airports may be needed to avoid additional delays to LAX departures

• Nightly telcon with ATCSCC and Industry to discuss next days operations and planning at 1730L PST

• End of Shift Summary for lessons learned

Federal AviationAdministration 22

Playbook Routes

• PHX arrivals from ZSE and ZOA originating west of RNO including STS and SMF via BTY.J92.BLD..PRFUM..WOTRO.BRUSR1.PHX• Excludes SFO, OAK, SJC, MRY and FAT• First 4 days or as needed

• Limited ability for reroutes to assist with fix balancing will be managed tactically

Federal AviationAdministration 23

TRAINING-LOA/SOP/NOTAMS/NOTICES STATUS

Federal AviationAdministration 24

ZLA Documents StatusAs of March 23

Facility Type StatusJCF LOA Sent to JCFNATCF LOA Final reviewNTTR LOA Telcon with NTTR/ ZLC in final reviewZAB LOA In final reviewZOA LOA ZOA is letter holder: waiting for document reviewZLA FSOP Incorporating Issues identified in March 2 chart cycleSCT LOA Pending changes from meeting week of March 21BFL LOA Draft out for commentsLEENA – PHASE 3 FIX NOTICE Current Notice expires May 15

DIRBY will replace LEENA when published

Federal AviationAdministration 25

SCT Documents StatusAs of April 10

Facility Type StatusNTD LOA In ProcessTOA LOA Page Change In ProcessSNA LOA Page Change In ProcessJCF LOA Page Change In ProcessONT In ProcessLGB SOP Update In ProcessDARKK-TRTON-EXERT (ZLA FIXIT)

In Process (telcon 4/12)

ZLA LOA In ProcessSCT SOP 75 % complete

Federal AviationAdministration 26

Status of ZLA TrainingUpdated April 10, 2017

Area Percentage Complete Training Notes

Area A 79.2 %

Area B 62.9 %

Area C 58.8 %

Area D Briefings only

Area E 56.8 %

Area F Briefings only

Federal AviationAdministration 27

Status of SCT TrainingUpdated April 10, 2017

Area Percentage Complete Training Notes

LAA (Arrivals) 0 % Begins APR 15, 2017

BUR (Burbank) 0 % Begins APR 12, 2017

EMP (Empire) 95 %

COA (Coast) 50 %

DEL (Del Rey) 50 %

SAN (San Diego) N/A

District ATCTs Briefings Only 15 days prior to APR 27, 2017

Federal AviationAdministration 28

POTENIAL COMMUNITY AND PROCEDURE ISSUES

Federal AviationAdministration 29

SNA OHSEA ONE ARRIVAL (RNAV)and SNA TILLT ONE ARRIVAL (RNAV)

• The plaintiff(s) from the Orange County area are reviewing the current and future STARs with no specific challenge until after the procedures are charted• The OHSEA and TILLT

STARS are identical after STYFF waypoint

Federal AviationAdministration 30

LAX IRNMN HUULL & RYDR STAR

• The plaintiff has proposed a change to theses STARs on the north downwind arrival flow to LAX

• The proposals have been reviewed by the Design Team and a response prepared for review by legal counsel

Federal AviationAdministration 31

SNA Runway 20R - PIGGN SID(1 of 2)

• SNA departs Runway 20R over 95 % • Communities immediately south of

SNA and in/near Dana Point have expressed dissatisfaction over legacy and forecast noise issues

• The March 2, 2017 SNA PIGGN SID was designed to address community concerns and make the procedure easier to fly

DanaPoint

Federal AviationAdministration 32

SNA Runway 20R - PIGGN SID(2 of 2)

• Following a commitment to evaluate the south flow SIDs at SNA, the Metroplex Team reviewed track data after the March 2, 2017 implementation

• It appears that departures are remaining within route centerline tolerance but are consistently east of course

• The Team is working with Industry, MITRE and ATAC to determine the cause of this anomaly

• One possibility is the procedure was coded with a DME from a NAVAID that may provide a MagVar inconsistent with the intended design

• Solutions are pending further evaluation

• The Metroplex Team is also evaluating a design to provide a curved path through the Newport Bay area to address community noise concerns

• The curved SID would be one of the first of it’s kind in the NAS

PIGGN SID Tracks

Curved SID Concept

Federal AviationAdministration 33

LGB TOPMM SID Issue - April 27 Chart Date

• A final agreement was completed to amend LGB TOPMM SID due to potential conflictions with local VFR pattern traffic and noise abatement procedure

• Departing IFR traffic must climb to 1500 AGL to provide positive separation from VFR traffic in the local pattern• The April 27 procedures will be implemented as a test

for the first day with LGB ATCT to observe location of departure turns

• On April 28 the ATCT will assign a heading and altitude for the initial departure phase of flight

• A decision will be made as to how subsequent daily operations will be managed

• The October 12, 2017 chart date will be updated with a revised altitude and heading

RWY 07L/25R

RWY 07R/25L

Federal AviationAdministration 34

SNA Runway 02L SID

• The SNA Runway 02L HOBOW SID will be implemented on April 27 with a TF-TF procedure design• North flow is used less than 5 % of the time

• Industry has accepted the design; however there are numerous segments where a departure rolls wings-level and then banks for the next turn in a short distance• The Design Team is exploring two curved

SID options in collaboration with Industry partners to improve SID design and as a location for data gathering to validate the curved SID premise

Federal AviationAdministration 35

POST MARCH 2, 2017 PROCEDURE AMENDMENTS

Federal AviationAdministration 36

SoCal Metroplex Design Team Meeting

• A Design Team meeting was conducted at ZLA March 21-23, 2017• SoCal Metroplex has limited procedure production slots for October 2017 • The Metroplex procedures in the table below will be modified to correct design

issues on October 12, 2017 except for the PSP SIZLR STAR• These changes were designed in collaboration with Industry partners

SAN COMIX STAR CRQ/NFG LEGOZ STAR

LGB/SNA DSNEE STAR

LGB/SNA ROOBY STAR

SAN TOPGN STAR ONT GLRNO STAR ONT KARLB STAR LAX TUSTI SID

SAN ECHHO SID SAN MMOTO SID NZY/SDM CHASR STAR

SNA TILLT STAR

SNA HHERO SID SANTA MONICA ONE SID

LGB TOPMM SID PSP/TRM/UDD SIZLR STAR (AUG 17, 2017)

Federal AviationAdministration 37

Questions?

Federal AviationAdministration 38

APRIL 27, 2017 PROCEDURESGRAPHICS

Federal AviationAdministration 39

BUR_SMO_VNY THRNE ONE ARRIVAL (RNAV)

Federal AviationAdministration 40

LAX CHATY FOUR DEPARTURE (Conventional)

Federal AviationAdministration 41

LAX DARRK ONE DEPARTURE (RNAV)

Federal AviationAdministration 42

LAX GOATZ ONE ARRIVAL (RNAV)

Federal AviationAdministration 43

LAX HUULL ONE ARRIVAL (RNAV)

Federal AviationAdministration 44

LAX SMO ZUUMA ONE ARRIVAL (RNAV)

Federal AviationAdministration 45

LAX SNSTT ONE ARRIVAL (RNAV)

Federal AviationAdministration 46

LAX TRTON ONE DEPARTURE (RNAV)

Federal AviationAdministration 47

LAX WNNDY ONE DEPARTURE (RNAV)

Federal AviationAdministration 48

LAX_HHR RYDRR ONE ARRIVAL (RNAV)

Federal AviationAdministration 49

LAX_HHR IRNMN ONE ARRIVAL (RNAV)

Federal AviationAdministration 50

LAX_SMO BOGET ONE ARRIVAL (RNAV)

Federal AviationAdministration 51

LGB BAUBB1 ARRIVAL (RNAV)

Federal AviationAdministration 52

LGB PCIFC ONE ARRIVAL (RNAV)

Federal AviationAdministration 53

LGB TOPMM ONE DEPARTURE (RNAV)

Federal AviationAdministration 54

LGB_SNA_FUL_SLI_TOA HAWWC1 ONE DEPARTURE (RNAV)

Federal AviationAdministration 55

ONT EAGLZ ONE ARRIVAL (RNAV)

Federal AviationAdministration 56

ONT GLRNO ONE ARRIVAL (RNAV)

Federal AviationAdministration 57

ONT KARLB ONE ARRIVAL (RNAV)

Federal AviationAdministration 58

ONT SCBBY ONE ARRIVAL (RNAV)

Federal AviationAdministration 59

ONT ZIGGY SIX ARRIVAL (Conventional)

Federal AviationAdministration 60

SNA FINZZ ONE DEPARTURE (RNAV)

Federal AviationAdministration 61

SNA HHERO ONE DEPARTURE (RNAV)

Federal AviationAdministration 62

SNA HOBOW ONE DEPARTURE (RNAV)

Federal AviationAdministration 63

SNA MIKAA ONE DEPARTURE (RNAV)

Federal AviationAdministration 64

SNA OHSEA ONE ARRIVAL (RNAV)

Federal AviationAdministration 65

SNA TILLT ONE ARRIVAL (RNAV)

Federal AviationAdministration 66

VNY HARYS ONE DEPARTURE (RNAV)

Federal AviationAdministration 67

VNY ROSCOE ONE DEPARTURE (RNAV) (PROPS)

Federal AviationAdministration 68

VNY WLKKR ONE DEPARTURE (RNAV)

Federal AviationAdministration 69

SNA DSNEE 1 STARSNA ROOBY 1 STAR