Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

Embed Size (px)

Citation preview

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    1/12

    OPTIMAL OPERATION OF KERALA GRID

    UNDER DEREGULATION

    Internal GUIDE

    JOSE THOMASDr.S.ASHOK

    PROFESSOR ,NIT CALICUT

    M090421EE

    External GUIDE

    Smt.Kavitha .C.K

    Asst.Exe.engineer

    S stem O erations KSEB

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    2/12

    INTRODUCTION

    Problem definition

    To develop software to aid optimal

    operational decision making of Keralagrid based on a graphical software aided

    model of grid considering all power

    transactions aspects

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    3/12

    WORK COMPLETED

    Analysed present operational decision making techniques in Load

    dispatch center Analysed the previous years load data of the state

    Kerala power system model up to 11 kV level buses(consisting of atotal of 1995 buses) formed using ETAP 6.0

    Formed cost models for all generators including the IPPs and CentralGenerations.

    Hydel generation modeled considering reservoir status andexpected inflow.

    Optimal power flow analysis conducted for peak and off peak timeslots based on forecasted load.

    Work done during the Term

    The optimal settings and results are analyzed and compared withwith load flow results for different time slots

    A mat lab program developed for real time updating of databaseduring each time slots , for the updating of dynamic modelparameters and to work as a front end to the user.

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    4/12

    ANALYSIS OF OPF RESULTS

    Active

    power

    demand

    Reactive

    power

    demand

    Active power

    loss

    Reactive

    power loss

    Total cost

    function

    value

    Lowest end

    voltage

    recorded

    Hydel/

    thermal/cent

    ral share

    Unscheduled

    interchange(

    between state

    grids)

    Actual load flow 2366 972.068 134.393 678.845 10749862

    Rs/hr

    79% 41%,

    15%,

    39%

    5%

    OPF with real power

    loss minimization

    objective

    2166.56 987.23 112.234 926.12 10855987

    Rs/hr

    75% 55%

    10%

    35%

    -6%

    OPF with cost

    minimization

    objective

    2115.78

    1060.89

    242.11

    1273.85

    8998350

    Rs/hr

    66%

    45%

    11%

    39%

    0

    OPF with dual

    objectives of cost

    minimization and

    minimization ofreactive power loss

    2203.34 978.22 149.67 931.342 10114941

    Rs/hr

    72.67% 42%

    15%

    39%

    0

    Case 1 :An off peak slot during mid summer(slot no 56 on 12-3-2011)

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    5/12

    Active

    power

    demand

    Reactive

    power

    demand

    Active power

    loss

    Reactive

    power loss

    Total cost

    function

    value

    Lowest end

    voltage

    recorded

    Hydel/

    thermal/cent

    ral share

    Unscheduled

    interchange(

    between state

    grids)

    Actual load flow 3133.98 1072.068 134.393 678.845 7657052

    Rs/hr

    75% 48%,

    21%,

    31%

    0

    OPF with real

    power loss

    minimization

    objective

    3026.34 1047.23 112.234 926.4346 7655780

    Rs/hr

    71% 50%

    22%

    31%

    0

    OPF with costminimization

    objective

    2945.937

    1260.78

    242.654

    1273.4235

    5433525Rs/hr

    62%

    55%

    13%

    32%

    0

    OPF with dual

    objectives of cost

    minimization and

    minimization of

    reactive powerloss

    2993.34 1078.3uu 149.67 931.32 6904851

    Rs/hr

    70.67% 49%

    19%

    32%

    0

    Case 2 :A peak slot during mid summer(slot no 76 on 12-3-2010)

    ANALYSIS OF OPF RESULTS

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    6/12

    ANALYSIS OF OPF RESULTS

    Active

    power

    demand

    Reactive

    power

    demand

    Active power

    loss

    Reactive

    power loss

    Total cost

    function

    value

    Lowest end

    voltage

    recorded

    Hydel/

    thermal/cent

    ral share

    Unscheduled

    interchange(

    between state

    grids)

    Actual load flow 1980.8

    9

    772.065

    8

    111.393 582.845 871200

    Rs/hr

    73.96 80 ,

    0 ,

    30

    -10

    OPF with real power

    loss minimization

    objective

    1960.76

    5

    754.23 98.12 810.12 2704800

    Rs/hr

    76.7% 60%

    10%

    32%

    -3%

    OPF with cost

    minimization

    objective

    1898.88

    7

    743.89

    195.24

    1042.85

    816785

    Rs/hr

    70.1%

    76%

    0%

    24%

    -6%

    OPF with dual

    objectives of cost

    minimization and

    minimization ofreactive power loss

    1956.34 778.22 129.67 831.342 1914231

    Rs/hr

    77.67% 74

    6

    26

    -6

    Case 3 :An off peak slot during monsoon(slot no 60 on 17-8-2010)

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    7/12

    ANALYSIS OF OPF RESULTS

    Active

    power

    demand

    Reactive

    power

    demand

    Active power

    loss

    Reactive

    power loss

    Total cost

    function

    value

    Lowest end

    voltage

    recorded

    Hydel/

    thermal/cent

    ral share

    Unscheduled

    interchange(

    between state

    grids)

    Actual load flow 2988.32 1324.234 134.393 698.845 1413324

    Rs/hr

    76% 81%,

    0%,

    24%

    -5%

    OPF with real power

    loss minimization

    objective

    2878.56 1311.23 110.234 926.12 4976062

    Rs/hr

    75% 63%

    14%

    26%

    -2%

    OPF with cost

    minimization

    objective

    2884.78

    1276.89

    198.11

    1073.85

    1364132

    Rs/hr

    70.7%

    81%

    0%

    24%

    -5

    OPF with dual

    objectives of cost

    minimization and

    minimization ofreactive power loss

    2906.34 1284.22 149.67 931.342 1423940

    Rs/hr

    72.67% 80%

    0%

    25%

    -5%

    Case 4 :peak slot during mid monsoon(based on load data on slot 70 on 17-8-2010)

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    8/12

    MATLAB PROGRAM FLOW CHART

    Read the date and slot from user

    Start

    Initiate database tool box and Connect to the ETAP

    database

    Read reservoir levels for the day from the excel file

    reservoir data and calculate expected inflow

    Read the excel file containing forecasted load data and store theload information for the particular slot update the column for

    particular slot in ETAP database

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    9/12

    Read the details of machines unavailable during the slot and substitute

    zero the in service column of corresponding database

    If peak

    slot

    Calculate the constant k for the

    type 1 &2 generator models from

    reservoir data and peak

    Read the status of running of the thermal machines for the previous

    slot and update the model

    Run developed ETAP model keralagrid.oti and run optimal power flow

    Output the optimal settings file

    Stop

    MATLAB PROGRAM FLOW CHART

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    10/12

    WORK TO BE DONE

    Model to be fine tuned to enforce all voltage

    constraints

    Graphical front end development

    Unscheduled interchange model to be

    included with forecasted frequency

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    11/12

    REFERENCES

    1] scheduling and simulation models for deregulated energymarket,ArneHaugtad,SINTEFF Energy research Norway

    2]Systematical Determination of Load Flow Cases

    for Power System Planning, G. Rechberger, H. Renner, A. Gaun2009 EEE Bucharest Power Tech Conference

    3]Scheduling of hydroelectric generations using artificial neuralnetworks, R.-H. Liang, M.Sc.Y.-Y. HSU, Ph.D.

    4] A MARKET DESIGN FOR DEVELOPING COUNTRIES B.BHUSHAN ,Central Electricity Regulatory Commission India ,atwww.srldc.org

    5] significance of Unscheduled Interchange Mechanism in the IndianElectricity Supply Industry

    S.K. Soonee, S.R. Narasimhan and V. Pandey at www. srldc.org

    6]Optimal Generation Scheduling under ABT using Forecasted Load andFrequencySurekha R Deshmukh, D J Doke, and Y P Nerkar

    IEEE conference on power systems Nov 2008

  • 7/21/2019 Optimal Operation of Kerala GRID Under Deregulation 5th Presentation

    12/12

    THANK YOU