7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
1/36
Accepted Manuscript
Title: Optimal design and planning of heap leaching process.application to copper oxide leaching
Author: Jorcy Y. Trujillo Luis A. Cisternas Edelmira D.
Galvez Mario E. Mellado
PII: S0263-8762(13)00323-7
DOI: http://dx.doi.org/doi:10.1016/j.cherd.2013.07.027
Reference: CHERD 1328
To appear in:
Received date: 18-7-2012
Revised date: 9-6-2013
Accepted date: 25-7-2013
Please cite this article as: Trujillo, J.Y., Cisternas, L.A., Galvez, E.D., Mellado,
M.E., OPTIMAL DESIGN AND PLANNING OF HEAP LEACHING PROCESS.
APPLICATION TO COPPER OXIDE LEACHING, Chemical Engineering Research
and Design (2013), http://dx.doi.org/10.1016/j.cherd.2013.07.027
This is a PDF file of an unedited manuscript that has been accepted for publication.
As a service to our customers we are providing this early version of the manuscript.The manuscript will undergo copyediting, typesetting, and review of the resulting proof
before it is published in its final form. Please note that during the production process
errors may be discovered which could affect the content, and all legal disclaimers that
apply to the journal pertain.
http://dx.doi.org/doi:10.1016/j.cherd.2013.07.027http://dx.doi.org/10.1016/j.cherd.2013.07.027http://dx.doi.org/10.1016/j.cherd.2013.07.027http://dx.doi.org/doi:10.1016/j.cherd.2013.07.0277/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
2/36
Page 1 of 35
Accepted
Manus
cript
1
OPTIMAL DESIGN AND PLANNING OF HEAP
LEACHING PROCESS. APPLICATION TO COPPER
OXIDE LEACHING
Jorcy Y. Trujillo3, Luis A. Cisternas2,31, Edelmira D. Glvez1,2, Mario E.
Mellado2
1Department of Metallurgical Engineering, Universidad Catlica del Norte, Antofagasta,
Chile2Centro de Investigacin Cientfico Tecnolgico para la Minera (CICITEM), Antofagasta,
Chile3Department of Chemical Engineering, Universidad de Antofagasta, Antofagasta, Chile
Submitted to: Chemical Engineering Research and Design
Date: July 12, 2012
ABSTRACT
Although the process of heap leaching is an established technology for treating minerals,
such as copper, gold, silver, uranium and saltpeter, as well as remediating soil, no studies to
date have investigated process optimization. This work presents a methodology for the
design and planning of heap leaching systems to optimize the process. This methodology
consists of the creation of a superstructure that represents a set of alternatives to search for
the optimal solution; from this superstructure, a mixed integer nonlinear programming
(MINLP) model was generated, and a BARON-GAMS solver was used to find the optimal
solution. This method was applied to the extraction of copper from systems with one, two
and three heaps, and the effects of copper price, ore grade and other variables were
analyzed for each system. From the results, it can be concluded that this methodology can
be used to optimize heap leaching processes, including planning and design issues.
1Corresponding author: L.A.Cisternas, e-mail: [email protected]
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
3/36
Page 2 of 35
Accepted
Manus
cript
2
Keywords: Heap leaching, process design, process optimization
NOMENCLATURE
Sets
process unit}.
, heap leaching unit}.
, unit of solvent extraction}.
, species to be extracted}
Variables and Parameters
Area of heap. [m2]
Recovery constants for disjunction model.
Acid consumption constants for disjunction model.
Costs. [MUS$]
Cost of building a heap . [MUS$/cycle]
Total fixed cost of heapj. [MUS$/cycle]
Acid consumption at infinite time. [kg/ton]
Acid consumption of heapj. [kg/ton]
Initial acid consumption. [kg/ton]
Acid consumption of heapj. [kg/cycle]
Total acid consumption. [kg/cycle]
Variable cost of heapj. [MUS$/ton]
Operational cost before leaching of heapj. [MUS$/ton]
Operational cost after leaching. [MUS$/ton]
Linear availability of species in heap . [ton/m]
Planning time horizon. [days]
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
4/36
Page 3 of 35
Accepted
Manus
cript
3
Income. [MUS$]
Mass flow from process unit to of species . [ton/cycle]
Input mass flow to process unit of species . [ton/cycle]
Output mass flow from process unit of species . [ton/cycle]
Molecular weight of acid. [ton/ton-mol]
Molecular weight of species k. [ton/ton-mol]
Mass of mineral loaded on heap of species . [ton]
Constant in the big M method.
Number of cycles.
Production of species . [ton/cycle]
Price of species . [MUS$/ton]
Price of acid. [MUS$/kg]
Volumetric flow from process unit to . [m3/cycle]
Output volumetric flow from the SX unit. [m3/cycle]
Recovery from heap of species . [%]
Recovery of species in disjunctive model. [%]
Recovery at infinite time. [%]
Cycle time of the heap system. [days]
End time of leaching of heap . [days]
Profits. [MUS$]
Weight factor for incomeI.
Weight factor for cost C.
Concentration of stream from process unit to of species . [ton/m3]
Concentration of output stream from the SX unit of species . [ton/m3]
Binary variable of the cycle times.
Disjunctive binary variable.
Height of heap. [m]
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
5/36
Page 4 of 35
Accepted
Manus
cript
4
Greek letters
Recovery constants for Mellado et al. (2011) model.
Acid consumption constant for the analytical model.
Ore density. [ton/m3]
Grade of species k in the ore. [%]
Superscript
Lower bound .
Upper bound.
Subscript
Disjunctive.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
6/36
Page 5 of 35
Accepted
Manus
cript
5
1. INTRODUCTION
Heap leaching is a hydrometallurgical process that is widely used in the mining industry, in
which low-grade metals, such as copper, gold, silver and uranium, are extracted; the
process also has new applications in the treatment of non-metallic minerals, such as
saltpeter (Valencia et al., 2008), and soil remediation (Carlsson et al., 2005). Several
studies have been performed with the goal of improving the leaching process; these works
include searching for the ideal operational conditions to achieve better extraction of metals.
However, most modeling-based research has focused on the search for models based on
first principles (Dixon and Hendrix, 1993a; Dixon and Hendrix, 1993b) and semi-empirical
models (Mellado et al., 2009; Mellado et al., 2011). An analysis of the relationship between
the operational time and costs and the identification of an optimal operation time and heap
size have been performed (Padilla et al., 2008); however, despite the importance of heap
operations, no previous studies have analyzed the optimization of the entire system.
Heap leaching is a mineral processing technology in which piles of ore (crushed or run-of-
mine rock) are leached with various chemical solutions to extract valuable minerals. Large
tonnages are involved, and metal is recovered over a long period. As shown in Figure 1, a
barren solution is pumped to the pile surface and sprayed, and as it percolates downward,the extraction of metal begins. Usually an aqueous cyanide solution is used for precious
metals, and an aqueous sulfuric acid solution is used for copper ores. The metal is
recovered from the pregnant solution by a recovery process that depends on the metal to be
extracted. For example, solvent extraction (SX) followed by electrowinning is used for
copper, and activated carbon or precipitation with zinc are used for gold (Gupta and
Mukherjee, 1990). In this work, an SX process was considered as the recovery process. The
barren solution from the recovery process is recirculated to the heap system. A heap system
can include several heaps, and several irrigation networks can be used.
Figure 1: Hydrometallurgical process based on heap leaching
The objective of this research was to develop a methodology that allows design and
planning to simultaneously find the optimal operational conditions, such as recovery and
leach time, and the optimal design parameters, such as heap height. The methodology is
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
7/36
Page 6 of 35
Accepted
Manus
cript
6
based on a superstructure that represents the flowsheet alternatives and a mathematical
model that is solved through a mixed integer nonlinear programming (MINLP) approach.
The development of the model with its superstructure and corresponding equations is
provided in section 2; the application of the model to systems with one, two and three heaps
is provided in section 3, with the corresponding characteristics and sensitivity analysis.
Finally, the last section includes the conclusions.
2. MATHEMATICAL MODEL
The design and planning of heap leaching systems is a coupled problem. Padilla et al.
(2008) studied the economic optimization of this process by analyzing variables such as the
leaching time and heap height in a copper mineral treatment plant and found that the design
(heap height) and operational planning (leaching time) are coupled problems from an
economic standpoint because these variables affect both the recovery and operational
capacity of the leaching process.
The purpose of this work is to develop a methodology to design and plan heap leach
systems. To accomplish this goal, a superstructure representing a set of flowsheet
alternatives to look for the optimum solution was constructed, based on which amathematical model was developed using mass balances and their corresponding
operational conditions to obtain a model that can determine the values of variables and
parameters affecting the process. The resulting model corresponds to an MINLP.
The superstructure was built based on heap leaching and solvent extraction units. The
schematic in Figure 2 represents these units, where represents a process unit. In this
superstructure, a mixer is used at the input of the unit (square) and a divider is used at the
output of the unit (triangle) to represent the set of connection possibilities between the
different units. The rectangle in the middle of the figure represents the unit itself, either a
heap leaching or SX unit. This type of representation has been used in other problems, e.g.,
water networks (Castro and Teles, 2013) and reactor networks (Silva and Salcedo, 2011).
Figure 2: Process units used in the modeling
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
8/36
Page 7 of 35
Accepted
Manus
cript
7
To develop the mathematical model, the following sets are defined. First, the set of units is
defined as is a process unit}, following which the subsetsJ , heap
leaching unit} and , solvent extraction unit} are defined. The set of
species to be extracted is represented as .
To perform the corresponding balances, the following assumptions were considered. a) The
evaporative water losses are compensated for with fresh water so that the water losses and
fresh water flow rates are null. The water balance and the cost of water losses were not
considered because these balances and costs depend on weather conditions, heap irrigation
technology, and evaporation losses/evaporation mitigation technologies in solution pools.
b) The heaps are considered to be in a series, where heap has been operated longer than
heap . c) During solvent extraction, the output concentration of the valuable species is
assumed to be known and constant, . This concentration is assumed constant and known
because it depends on downstream operations, in this case from the electrowinning stage.
Additionally, it is assumed that this stage is ideal and does not represent entrainment of
solution or loss of valuable species. d) A constant density is assumed in the dissolutions.
2.1 Mass Balances
Mass balance in j heaps
Equation 1 shows the mass balance of species in heapj in the liquid phase as a function
of the input and output mass flow rates and the recovery in the heap:
(1)
where is the output mass flow of species in heap , [ton/cycle], and represents
the recovery of the valuable species in the leaching heap process, which depends on the
leaching time and the height of the heap , along with other variables. The term
, [%/cycle] is included in equation 1 because the heaps operate in series,
and the recovery of the heap j, , begins where the recovery of the heapj-1, , ends.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
9/36
Page 8 of 35
Accepted
Manus
cript
8
can be calculated using an adequate model, for example, the model proposed by
Lizama et al. (2005) for bioleaching, Mellado et al. (2011) for low grade ores, or Glvez et
al. (2012 ) for Caliche ores. Note that ; therefore, the superscript represents the
input solution of heap , the superscript o represents the output solution of heap and
represents the mass of the valuable species in heap , given by the following:
(2)
In equation 2, is the linear availability of species , [ton/m] which corresponds to the
area of the heap multiplied by the density of the ore with a corresponding ore
grade .
The balance of acid consumption is given by equation (3), where the first term represents
the consumption of acid in heap j, and the second term is the credit for the recovery of acid
in the electrowinning stage.
(3)
where is the acid consumption of heapj by cycle [kg/ton of ore cycle] andMWk is the
molecular weight of species k.
The total acid consumption is the sum of the acid consumption for each heap, that is,
(4)
Mass balance in the mixers and dividers in unit
For the mixers and dividers, the mass balance per component was performed based on the
input and output mass flows rates of the different process units. There is a mixer and a
divider on each process unit.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
10/36
Page 9 of 35
Accepted
Manus
cript
9
(5)
(6)
Mass balance in SX
The mass balance for species in the solvent extraction process unit was performed based
on the production of the valuable species [ton/cycle], and the input and output mass
flows to the process unit, as shown in the following equation:
(7)
2.2 Planning and operation constraints
To design and plan the heap leaching process, certain restrictions must be considered. First,
the number of cycles throughout the planned time horizon must be obtained as follows:
(8)
where is the planned time horizon [days], is the number of cycles and represents the
cycle time. A cycle consists of all operation phases of a heap, e.g., if a plant uses two heaps,
the cycle consists of the operation of both heaps. The time horizon is the length of time
used to evaluate the alternatives over the same period of time. The cycle time is the period
required to complete one cycle of heap operation. In this work it is assumed that
overlapping operation is used, this is, simultaneous heaps can be operated. Then, the cycle
time is the maximal operation time between all heap units, calculated as follows:
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
11/36
Page 10 of 35
Accepted
Manus
cript
10
(9)
Note that if a non-overlapping operation is used, then the cycle time is the sum of the
operation times of all heap units.
Heap starts and finishes the operation at times and , respectively. Equation (9) can
be written as a disjunction expression:
(10)
In this work, equation (10), the disjunctive expression for the cycle time, is represented by
the big M method (Biegler et al. 1997) as follows:
(11)
(12)
(13)
(14)
where , is a binary variable that represents the selection of the heap with the maximal
operation time. Here, the constraint in equation (12) only allows one choice of . M is a
large parameter introduced in the right side of equations (11), (13) and (14), which renders
the inequalities redundant if and enforced if .
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
12/36
Page 11 of 35
Accepted
Manus
cript
11
The following operational bounds must be considered to achieve satisfactory results. These
restrictions include lower and upper bounds in the mass flows, the height of the heap, the
recovery, the number of cycles and the cycle time as follows:
(15)
(16)
(17)
(18)
(19)
(20)
(21)
where . Then, based on equation (17), a good value of M in equations (11), (13) and
(14) is tUP.
2.3 Specifications
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
13/36
Page 12 of 35
Accepted
Manus
cript
12
In the following discussion, the expressions to calculate some bounds and parameters are
given. First, the model uses the mass flow rates of species k; however, in industry,
concentration and volumetric flow rates are used. The relationship between these variables
is as follows:
(22)
where represents the concentration of species in mass per volume [ton/m3] in the
stream moving from process unit to unit , and represents the volumetric flow rate
from process unit to [m3/cycle]. Because is the maximal flow of species , this
parameter can be calculated as the sum of the output flows of all of the SX units as follows:
(23)
In addition, from equation (22), the balance for the solvent extraction unit as a function of
the mass flows is given by
(24)
where corresponds to the output volumetric flow rate from the SX unit and ,
corresponds to the concentration of species at the output of the SX unit.
2.4 Objective Function
The expression to be maximized is an economic optimization that must be simultaneously
maximized in terms of income and minimized in terms of costs. The income is represented
as the total production multiplied by the price, and the cost is the number of cycles
produced multiplied by the cost of each heap over the time horizon.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
14/36
Page 13 of 35
Accepted
Manus
cript
13
A possible expression is represented in equation (25), where is the income; represents
the costs; and are weight factors; and represents the profits when .
Income, cost and profits can give different optimal solutions (Novak Pintari and Kravanja,
2006), and therefore different weight factor values can be analyzed.
Maximize (25)
The income, [MUS$], can be represented in terms of production, the number of cycles,
the price of the species to be extracted and the post-leaching cost
[MUS$/ton of metal], which includes the cost of the purification process (e.g., solvent
extraction or ion exchange) and the product recovery process (e.g., electrowinning or
crystallization), and represents the cost after the leaching is performed. The income is given
by
(26)
In addition, the cost, [MUS$], is given by the number of cycles, the cost of building and
operating heap , and acid consumption, as shown in the following equation:
(27)
where is the acid price in [MUS$/kg].
Then, the cost of building and operating heap [MUS$/cycle], is defined as a function
of the different costs of the heap leaching system according to the following expression:
(28)
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
15/36
Page 14 of 35
Accepted
Manus
cript
14
where represents the total fixed cost, including the cost per square meter and per cycle
in the process; is the variable cost per ton of ore and per cycle [MUS$/ton of ore cycle]
in the process that includes the power, water consumption, land preparation, maintenance
and labor; and is the cost before leaching per ton of ore and per cycle in the
process [MUS$/ton of ore cycle], including costs such as mine operation, crushing and
agglomeration.
2.5 Recovery Expressions
In this work, two methods are used to express the recovery of copper, but different models
can be used depending on the leaching technology and the leached ore. First, a disjunctive
expression is used to approximate the recovery using straight lines, and an analytical model
developed by Mellado et al. (2011) is then used. The disjunctive expression is written in the
following manner:
(29)
The recovery is expressed by straight lines for different time ranges and heap heights.
The disjunctive expression of recovery in equation (29) is expressed using the Convex Hull
method (Biegler et al. 1997):
(30)
(31)
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
16/36
Page 15 of 35
Accepted
Manus
cript
15
(32)
(33)
(34)
(35)
where are constants used to approximate the recovery from the straight line
equation, is the binary variable, and and indicate the lower and upper bounds of
the operation time for each disjunction, respectively.
Mellado et al. (2011) developed an empirical knowledge-based model, which considers two
time and size kinetics scales and includes variables such as particle radius, heap height,
irrigation rate and porosities. Here, only the heap height and leaching time are considered
as variables, keeping other variables constant. Then, the analytical expression proposed by
Mellado et al. (2011) can be written as follows:
(36)
Where represents the recovery at t= infinity, which is a function of the height of the
heap as follows:
(37)
The parameters of equations (29) and (37) are shown in Table 1.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
17/36
Page 16 of 35
Accepted
Manus
cript
16
Table 1: Parameters considered in the analytical model by Mellado et al. (2011) for copper
recovery and the analytical model (eq. 39) for acid consumption.
Figure 3 shows the graphic representation of equations (27) and (34) for the disjunctive
model and the model by Mellado et al. (2011).
Similarly as for copper recovery, two ways of expressing the acid consumption were used.
First, a disjunction expression based on straight lines for different time ranges and heap
heights was used, and then an analytical model was used. The disjunctive expression is
written as follows:
(38)
The disjunctive expression for acid consumption in equation (38) is expressed using the
Convex Hull method (Biegler et al. 1997):
(39)
(40)
where are constants.
The analytical model is
(41)
The parameters of equations 39 and 41 are given in Table 1.
The disjunctive model of acid consumption (Eqs. 39 and 40) is used together with the
disjunctive model of copper recovery (Eqs. 30 to 35). In the same way, the analytical model
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
18/36
Page 17 of 35
Accepted
Manus
cript
17
of acid consumption, Eq. 41, is used together with the analytical model of Mellado et al.
(2011), Eq. 36.
3. CASE STUDIES
This section illustrates the application of the model for the copper heap leaching process in
systems of one, two and three heaps to analyze the effects of variables such as copper price,
heap size, ore grade, acid price and variable cost on the process. The case studies consider a
heap of 200,000 m2 with an ore grade of 0.9% copper. The copper price is assumed to be
7,700 US$/ton. A time horizon of 360 days was used to analyze, design, and plan the
leaching system. Other ore characteristics and heap costs are indicated in Table 2, and they
are shared by all examples. The costs used in this work are those normally observed in the
context of copper production in Chile and were updated from the work of Schmidt (2001).
Table 2: Parameters considered in the case studies.
We must consider that the variable cost, the pre-leaching cost and the total cost in systems
with two and three heaps apply only to the first heap. In other words, the costs of heaps two
and three are zero because the heaps operate in series and because their costs have been
considered in the first heap; furthermore, it is assumed that the operational cost of heaps
two and three can be neglected.
In the following sections, the three studied cases are shown, which were implemented in
GAMS and solved by BARON using an AMD Athlon II Dual-Core M300 2.00 GHz
processor. In all studied cases only one parameter was changed, while all other parameters
were kept constant and equal to the values in table 2.
Figure 3: Recovery as a function of time with heap heights of 6 and 9 m.
3.1 One-heap leaching system
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
19/36
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
20/36
Page 19 of 35
Accepted
Manus
cript
19
Table 4: Cycle time fluctuations based on the ore grade and different leaching systems
using the disjunctive model (DM) and Mellado et al. (2011) model.
Table 5: Recovery fluctuations as a function of the ore grade for the different leaching
systems using the disjunctive model (DM) and Mellado et al. (2011) model (M). NC=Does
not converge.
The effect of the variable cost (assuming constant expenses for acid consumption),
including expenses for power, water consumption, ore transportation, maintenance and
labor, is significant. If the variable cost is increased, the cycle time and recovery increase
proportionally, and profits and income decrease. Figure 5 shows the effect of the variable
cost on the cycle time (Figure 5a) and recovery (Figure 5b), calculated for both the
disjunctive model and the Mellado et al. (2011) model. Additionally, the second and third
columns in Table 6 show the profits for both models.
Figure 5 Fluctuations in cycle times (a) and recovery (b) at 0.005, 0.01 and 0.02
kUS$/ton of ore.
Table 6: Profit fluctuations based on the variable cost and different leaching systems using
the disjunctive model (DM) and Mellado et al. (2011) model.
The effect of the acid price was studied separately from other variable costs. When the
effect of the acid price on the system is analyzed, an impact on the cost and profit is
observed: cost increases and profit decreases as the acid price increases. Nevertheless, no
change in the height of the heap is observed (9 m for the disjunctive model and 9.5 m for
the Mellado et al. model, for all values of acid price). For cycle time and recoveries, nochanges are observed for disjunctive model. On the other hand, cycle time and recoveries
increase as acid price increases for the Mellado et al. model. More details are given in table
7.
Table 7: Effect of acid price for the Disjunction and Mellado et al. models.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
21/36
Page 20 of 35
Accepted
Manus
cript
20
3.2 Two- and three-heap leaching systems
The models are applied to a system formed by two- and three-heap leaching units to
compare its behavior to the single heap system and to observe the effect of parameters such
as copper price, heap area, ore grade, acid price and variable cost. The results obtained in
these systems show a trend similar to that obtained for the single heap leaching system. For
example, when the copper price increases, the profits increase in systems with one, two and
three heaps. Table 3 shows some of the results obtained for the three systems based on the
effect of the copper price, using the disjunctive model and the model by Mellado et al.
(2011).
In addition to the copper price, the variation of profits with other parameters is important to
characterize. Table 6 shows some of the results obtained for the three systems based on the
effect of the variable cost for the disjunctive and Mellado et al. (2011) models; the results
show that in a system with more than one heap, the profits are higher with each additional
heap; this is true for most cases, except for the Mellado model with three heaps.
As in the single heap system, if the ore grade is increased the cycle time decreases, and,
therefore, the number of cycles increases; the only difference in these cases is the shorter
leaching time. With more heap leaching units in a system, the leaching time in each heap is
shorter. Table 4 shows the results obtained for the three systems based on the cycle times
using both the disjunctive model and the Mellado et al. (2011) model. As shown in Tables
3, 4 and 5, there are convergence problems in both models.
Table 4 shows that for a two-heap system and an ore grade of 0.5%, the cycle time for each
heap is 40 and 49 days, and the entire two-heap system operates for approximately 80 and
98 days, for the disjunctive model and the Mellado et al. model, respectively. These values
are similar to the values for a one-heap system.
In addition, the recovery decreases as the ore grade increases in the different systems. Table
5 shows the results obtained for the three systems based on the ore grade for the disjunctive
model and the model by Mellado et al. (2011).
As shown in Table 5, in all systems, the recovery is low. For example, the recovery in heap
two for the two-heap system with an ore grade of 0.9% is 44 and 42% for the disjunctive
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
22/36
Page 21 of 35
Accepted
Manus
cript
21
model and the Mellado et al. model, respectively. To analyze this situation, a minimal
recovery value of 70% to 90% was assigned to the model. The results of this test indicate
that the model obtains high recoveries; however, there are variations in the cycle time and
profits. The cycle times increase significantly, and the profits decrease compared to the
results shown in Table 5. Therefore, in some cases the maximal recovery is not necessarily
the best measure of operational efficiency, based on economic considerations.
As in the single heap system, if the acid price is increased the cost increases, and therefore
the profit decreases. Table 8 shows the results obtained for the three systems using both the
disjunctive model and the Mellado et al. (2011) model. It can be observed that the number
of heaps has a greater effect than the acid price on the total leaching time and recoveries. Inboth models, leaching times and recoveries are approximately constant with the acid price.
Table 8. Effect of acid price for the disjunction model and Mellado et al. (2011) model.
NC=Does not converge.
In all of the systems, the heap height calculated using the disjunctive model was 9 m, the
maximal height allowed. With the Mellado et al. (2011) model, the maximal height allowed
in the model was obtained, which was not affected by parameters such as the copper price
and ore grade. However, a test showed that if the upper bound of the height is increased in
the Mellado et al. (2011) model, the optimal height obtained is below the upper bound
because if the heap height is increased, the recovery decreases.
Finally, Figure 6 shows the effect of the weight factors on the income and costs calculated
with the Mellado et al. (2011) model. The values in the graph indicate the weight factors
. The point indicates the minimal cost, and as a result, the
minimal income. Additionally, indicates the maximal income, and as a
result, the maximal cost. The income increases significantly as the income weight factor
increases until . For an income weight between 0.5 and 0.6, the cost increases but
the income is almost constant. Then, for between 0.6 and 0.7, the income increases as
the income weight factor increases; however, the cost also increases.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
23/36
Page 22 of 35
Accepted
Manus
cript
22
As shown in these studies, parameters such as copper price, ore grade and variable cost
have an important effect on the profit as well as on some process variables. In addition, the
results of the disjunctive and Mellado et al. (2011) models are generally similar. The results
of the Mellado et al. (2011) model are slightly better than those of the disjunctive model
because the disjunctive model is an approximation to the Mellado model, and the
disjunctive model underestimates the recovery. However, the Mellado et al. (2011) model
has more convergence problems than does the disjunctive model.
Convergence problems and local optima can be attributed to the fact that the model is a
mixed integer nonlinear programming problem; it is nonconvex due to exponential terms
(recovery in the Mellado et al., 2011 model) and bilinear terms in the mass balance (e.g.,equations 1 and 2). To solve these problems, linearization (Quesada and Grossmann, 1995)
and discretization (Pham et. al, 2009) techniques can be used. This may explain why the
disjunctive model presents fewer convergence problems compared to the Mellado model.
The disjunctive model is a linearization of the latter. For bilinear expressions, the
discretization approach can be used.
Figure 6 Income and cost fluctuations based on the weight functions and .
4. CONCLUSIONS
In this work, a method has been developed to plan and design a heap leaching system. Two
models were used to calculate the recovery, one based on disjunction and the other based
on the model by Mellado et al. (2011). The developed mathematical model is a MINLP.
As determined in the copper leaching cases that were studied, one of the primary variablesaffecting the profit of the process is the copper price, as expected. Additionally, certain
other variables are shown to be important, such as the ore grade, acid price and the variable
cost, as they significantly affect the operation planning and the profit. The cycle time and
recovery decrease, but the profit increases with increasing ore grade. In addition, the cycle
time and recovery increase, but the profit decreases with increases in variable costs. The
cycle time decreases in systems with more than one heap. Moreover, the use of more than
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
24/36
Page 23 of 35
Accepted
Manus
cript
23
one heap allows better control of the irrigation rate in each heap. These results show that as
the number of heaps increases, there is more flexibility in planning and a greater production
capacity.
This study has shown that the design (heap height) and planning of a heap leaching
operation are coupled problems from an economic perspective, and therefore, these
variables must be included in the model. This coupling occurs because these are interactive
factors, and these variables affect both the recovery and the capacity of the operation in the
heap leaching process.
In addition, the results of the analytical model by Mellado et al. (2011) show higher
precision and convergence than those obtained using the disjunctive model, despite the fact
that the trend in the results is similar. Additionally, the CPU time required to obtain results
is less for the Mellado et al. (2011) model than for the disjunctive model. Because the
system converges to local optima, there is room for improvement in the computing
algorithm.
Finally, this study should be considered as a new step in the development of methodologiesfor the design and planning of heap leaching systems, and future studies must include the
effect of other variables, such as the particle size, irrigation rate and acid concentration, to
predict the optimal operational conditions.
Acknowledgments
The authors wish to thank CONICYT for its support through the Fondecyt Project 1090406
and 1090592.
REFERENCES
Biegler, L. T., Grossmann, I. E., & Westerberg, A. W., (1997). Systematic methods of
chemical process design. NJ: Prentice Hall.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
25/36
Page 24 of 35
Accepted
Manus
cript
24
Carlsson, E., Buchel, G., (2005). Screening of residual contamination at a former uranium
heap leaching site. Thuringia.,Germany Chemie der Erde, 65S1, 7595.
Castro, P.M., Teles, J.P. (2013). Comparison of global optimization algorithms for the
design of water-using networks. Computers & Chemical Engineering 52, 249 261
Dixon, D.G. and Hendrix, J.L., (1993a). A Mathematical model for heap leaching of one or
more solid reactants from porous ore pellets. Metallurgical Transactions, 24B, 157-168.
Dixon, D.G. and Hendrix, J.L., (1993b). General model for leaching of one or more solid
reactants from porous ore pellets. Metallurgical Transactions, 24B, 157-168.
Glvez, E.D., Moreno, L., Mellado, M.E., Ordez, J.I., Cisternas, L.A. (2012). Heap
leaching of caliche minerals: Phenomenological and analytical models Some
comparisons, Minerals Engineering, 33, 46-53
Gupta C.K., Mukherjee T.K. (1990). Hydrometallurgy in Extraction Processes, Vol I, CRC
Press.
Lizama, H.M., Harlamovs, J.R., McKay, D.J., Dai, Z. (2005). Heap leaching kinetics are
proportional to the irrigation rate divided by heap height. Minerals Engineering, 18, 623-
630.
Mellado, M.E., Casanova, M.P., Cisternas, L.A., Glvez E.D. (2011). On scalable
analytical models for heap leaching. Computers and Chemical Engineering, 35, 220-225.
Mellado, M.E., Cisternas, L.A., Glvez E.D. (2009). An analytical model approach to heap
leaching. Hydrometallurgy. 95, 33-38.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
26/36
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
27/36
Page 26 of 35
Accepted
Manus
cript
26
Table 1: Parameters considered in the analytical model of Mellado et al. (2011) for copper
recovery and analytical model (eq. 39) for acid consumption.
Parameters
Copper recovery model (Eq. 36)Recovery Constant
Recovery Constant
Infinite Recovery Constant
Infinite Recovery Constant 1
Infinite Recovery Constant 0.03
Acid consumption model (Eq. 39)
Acid consumption constant 0.0125Acid consumption constant 1
Infinite acid consumption 70.96 kg/ton ore
Initial acid consumption 25 kg/ton ore
Table 2: Parameters considered in the case studies.
Parameters ValuesApparent ore density
Ore grade
Time horizon
Price of copper
Area of heap
Price of acid 0.162 [kUS$/ton of acid]
Post leaching cost, 0.16675 [MUS$/ton of copper]
Pre leaching cost, 0.006074 [MUS$/ton of ore]
Variable cost, 0.0028554[MUS$/ton of ore]
Total fixed cost, 0.00095 [MUS$]
Copper mass flow rate at the output of SX 3,500
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
28/36
Page 27 of 35
Accepted
Manus
cript
27
Table 3: Variation of profits based on the copper price and the different leaching systems
using the disjunctive model (DM) and Mellado et al. (2011) model. NC=Does not
converge.
Profits[MUS$]
One Heap Two Heaps Three HeapsCopper
Price[MUS$/ton]DM Mellado DM Mellado DM Mellado
0.0055 174.8 181.6 603.0 663.7 NC NC0.0077 344.0 369.2 907.6 1,001.9 1,032.0 NC0.0099 513.2 566.5 1,212.3 1,340.6 1,539.5 NC
Table 4: Variation of the cycle times based on the ore grade and different leaching systems
using the disjunctive model (DM) and Mellado et al. (2011) model. NC=Does not
converge.
Cycle time[Days]
One Heap Two Heaps Three HeapsOre grade[%]
DM Mellado DM Mellado DM Mellado
0.5 80 97 40 49 NC 420.9 80 65 40 31 27 221.3 40 55 31 28 NC NC
Table 5: Variation of recovery as a function of the ore grade for the different leaching
systems using the disjunctive model (DM) and Mellado et al. (2011) model (M). NC=Does
not converge.
Recovery %
One Heap Two Heaps Three Heaps
Heap 1 Heap 1 Heap 2 Heap 1 Heap 2 Heap 3
Ore
grade[%]
DM M DM M DM M DM M DM M DM M
0.5 62 68 20 22 44 45 22 NC 46 NC 62 NC
0.9 62 55 20 19 44 42 22 NC 46 NC 62 NC
1.3 38 49 20 19 44 42 13 NC 38 NC 50 NC
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
29/36
Page 28 of 35
Accepted
Manus
cript
28
Table 6: Variation of profits based on the variable cost and different leaching systems using
the disjunctive model (DM) and Mellado et al. (2011) model.
Profits[MUS$]One Heap Two Heaps Three Heaps
Variable Cost
[kUS$/ton]DM Mellado DM Mellado DM Mellado
0.005 400.1 446.2 799.3 892.4 1,198.3 1,198.30.01 330.2 351.5 479.4 703.0 990.7 1.054.50.02 192.5 203.3 385.1 406.5 462.7 303.2
Table 7: Effect of acid price for Disjunction and Mellado et al. models.
Acid Price [kUS$/ton of acid]
0.11 0.162 0.21 0.11 0.162 0.21
Disjunction Model Mellado et al. Model
Heap height 9.00 9.00 9.00 9.50 9.50 9.50
Leaching cycles 4.50 4.50 4.50 5.81 5.53 5.31
Profits [MUS $] 379,458 344,004 311,278 411,925 369,118 330,635
Recovery [%] 62 62 62 53 55 56
Cycle time [days] 80.00 80.00 80.00 61.99 65.09 67.81
Income [MUS$] 579,241 579,241 579,241 673,520 662,199 652,159
Table 8. Effect of acid price for the disjunction model and Mellado et al. (2011) model.
NC=Does not converge.
DM Mellado et al.
Acid Price One Heap Two Heaps Three Heaps One Heap Two Heaps Three Heaps
[kUS$/ton] Profits[MUS$]
0.11 379.5 926.0 1,138.4 411.9 1,022.8 NC
0.162 344.0 907.6 1,032.0 369.1 1,002.0 NC
0.210 311.3 890.7 933.8 330.6 982.8 NC
Total Leaching Time [Days]
0.11 80.0 50.8 80.0 62.0 45.5 NC
0.162 80.0 50.8 80 65.1 45.5 NC
0.210 80.0 50.8 80.0 67.8 45.5 NC
Total Recovery [%]
0.11 62 44 62 53 42 NC
0.162 62 44 62 55 42 NC
0.210 62 44 62 56 42 NC
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
30/36
Page 29 of 35
Accepted
Manus
cript
29
Figure 1: Hydrometallurgy process based on heap leaching
Mine Ore
Recovery Process
Pregnantsolution
Heaps
Spent
Ore
Barrensolution
Metal
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
31/36
Page 30 of 35
Accepted
Manus
cript
30
Figure 2: Process units used in the modeling
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
32/36
Page 31 of 35
Accepted
Manus
cript
31
Figure 3: Recovery as a function of time with heap heights of 6 and 9 m.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
33/36
Page 32 of 35
Accepted
Manus
cript
32
Figure 4: Variation of profits for ore grades of 0.5, 0.9 and 1.3%.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
34/36
Page 33 of 35
Accepted
Manus
cript
33
a)
b)
Figure 5: Variation of cycle times (a) and recovery (b) at 0.005, 0.01 and 0.02 kUS$/ton of
ore.
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
35/36
Page 34 of 35
Accepted
Manus
cript
34
Figure 6: Variation of income and costs based on the weight functions and .
7/27/2019 Optimal Design and Planning of Heap Leaching Process. Application to Copper Oxide Leaching
36/36
Accepted
Manus
cript
35
This work presents a methodology for the design and planning of heap leaching systems.
The method used a superstructure that represents a set of alternatives to search for the
solution.
A MINLP model was generated and a BARON-GAMS solver was used to find the optimal
solution
It can be concluded that this method can be used to optimize heap leaching planning and
design.